Home / Financial Firm (Unknown - Insurer) / Determination 274886
Determination 274886
Denial of wall and ceiling cracking claim from water leak and subsidence
Summary
The applicant claimed for wall cracking after a water pipe leak under his home and the FSP denied it. The Panel found drought-related subsidence and footing inadequacy were a significant cause, so the FSP is not liable beyond the floorboard damage it already agreed to pay.
Where one cause within the policy and another excluded concur and neither is clearly dominant, the Wayne Tank principle means the policy does not respond.
Issues
- Claim denial primary · not upheld
“Considerable contribution to the damage arose from excluded perils such as drought-related subsidence, so the policy does not respond under the concurrent causes principle.”
- Inadequate claim investigation secondary · not upheld
“Applicant's engineer's 70 percent attribution to the leak lacked detail and did not displace the FSP engineer's evidence.”
Subjects and remedies
home or building damageno remedy
Text of the determination
Case No: 274886 Determination Page 1 of 5
Case number: 274886
General Insurance - Domestic Insurance – Home Building - FSP Decision -
Denial of claim
28 September 2012
Background
1. The Applicant is insured under a Home Building Defined Events policy
underwritten by the Financial Services Provider (FSP)
2. The Applicant advised the FSP of a claim on 13 th September 2007. A water
pipe under the kitchen concrete slab had been leaking and a considerable
volume of water had leaked under the house over an extended period of
time, possibly up to 90 days. The leaking pipe had been repaired, but the
walls of the house were cracking and showed evidence of the house moving
on its foundations.
3. The FSP employed an independent consultant engineer to inspect the
damage to the insured premises. The engineer concluded that damage was
not caused by the leaking pipe, but was as a result of the foundations
settling caused by shrinkage of the clay soil following an extreme and
extended period of drought.
4. The FSP has denied the claim on the basis that the Applicant has failed to
prove a loss under the policy.
5. The FSP also offers a second reason for denial, being the operation of an
exclusion, which states:
“We will not cover
loss, damage injury or death that occurs as a result of
......wear, tear, rust, corrosion, deterioration or corrosion
......atmospheric conditions or extreme temperature
......subsidence or landslide unless it happens immediately after an
earthquake
......tree roots”
Determination
Case No: 274886 Determination Page 2 of 5
Summary of Applicant’s position
6. The Applicant advises that the effect of such a large volume of water
(approximately 63,000 litres) flowing under the house has not been
appropriately considered by the FSP and its consultant engineer. The slope
of the land is such that if the water flowed under the house, it would flow
from the back to the front under the full extent of the building.
7. The Applic ant maintains that floor level measurements taken by the FSP’s
consultant engineer in 2007 show evidence of heaving indicating volumetric
change in soil due to wetting. Subsequent measurements taken in 2011
show the floor levels settling indicating volumetric change in soil due to
drying.
8. The Applicant employed its own consultant engineer who inspected the
house on 29 August 2011. The Applicant’s consultant engineer
acknowledged the difficulties arising from not having seen the building in
2007 but concludes:
“My inspection of the house walls shows more than normal house cracking
even in these recent conditions of drought. Whilst there are shrubs in the front
yard and whilst there has been water restrictions in Adelaide the degree of
movement in this dwelling is unusual. I would inspect at least 40 houses
annually with regard to wall cracking and the degree of cracking in this house
is unusual even with the drought conditions.
It is my opinion that the water mains leak affected the footings and walls to the
dwelling and the consequences are more than that which has been allowed in
the (FSP’s Engineer’s) report. It is my estimate that over 70% of the current
cracking to the front rooms of the house are as a result of the earlier 2007
water leak.”
Summary of FS P’s position
9. The FSP advises that in their view the Applicant has failed to prove a loss
under the policy and reminds us that the onus of proof rests upon the
Applicant to prove that the damage was caused by water leaking from a
pipe.
10. The FSP’s consultant engineer inspected the insured property in 2007 and
again in 2011 and has issued four reports detailing the damage. In 2007 the
FSP’s engineer advised that in his opinion the wall cracking was due to:
“Severe soil drying and hence shrinkage caused by the p rolonged 2006-07
drought, the worst ever recorded in this state.
Government watering restrictions have meant that all homeowners have been
unable to water lawns and gardens with the consistency required to maintain
equilibrium moisture conditions on reactive clay allotments
Any trees in the near vicinity, such as street trees in this case, have survived
the drought conditions and watering restrictions by extending their root
systems further and deeper than in previous years with the writer’s soil testing
indicating zones of drying are now extending for horizontal distances up to
Case No: 274886 Determination Page 3 of 5
three or four times the height of trees in groups and to depths of 4 metres and
beyond.”
11. The FSP’s consultant engineer’s report also states:
“The original solid masonry portion of th is dwelling comprises the most brittle
form of dwelling construction, this being render and set masonry walls
supported by poorly gridded concrete strip beam footings containing minimal
steel reinforcement.”
12. Then in conclusion states:
“The pattern of crack ing in walls and ceilings is clearly consistent with footing
settlements and not with a soil heave centred at the kitchen sink as indicated
by our floor level measurements.
The writer concludes that because there has been no heaving of the dwelling
floors in the vicinity of the kitchen area the leaking copper water pipe has not
caused, or contributed to, wall and ceiling cracking in this particular case.”
13. The FSP’s engineer in his June 2011 report reiterated the causes of the
cracking contained in his previous report and made the following comment in
relation to the flow of water from the leaking pipe:
“In the writer’s opinion a large proportion of the leaked mains water in 2007
would have tended to accumulate most readily within and along the 1:50
grade waste drain trench which extends outwards from the kitchen sink to the
external southern elevation and then down the eastern elevation to the street
connection point.”
14. Without conceding that the Applicant has proven a loss under the policy, the
FSP advises that even if the Applicant were able to do so, the FSP would
still deny indemnity on the basis of the policy exclusion and, should it be
determined that there are concurrent causes of loss, then the existence of
the excluded cause will result in the policy not responding.
Issues
15. Whether the Applicant has proven that its loss falls within the scope of the
policy.
16. Whether a significant element of the loss is caused by an excluded peril and
the impact that might have on the policy response.
Reasons for decision
17. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with clause 8.6 of the FOS Terms of Reference. This
is due to the quantum and complexity of the dispute. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
Case No: 274886 Determination Page 4 of 5
18. I am satisfied that a full exchange of information has taken place between
each party and that each party has had the opportunity to address any
issued raised.
19. The reports submitted by the FSP’s engine er indicate that this building has a
history of cracking and movement with some indication of possible
underpinning and superficial repairs.
20. These reports also indicate that the type of footings used are inadequate for
the soil conditions and it is common to find wall cracking in this type of
construction and in the area where this dwelling is located.
21. Neither of these assertions are refuted by the Applicant’s engineer.
22. The report submitted by the Applicant’s engineer claims that over 70% of the
cracking to the front rooms of the house are due to the water leak. However
the report does not provide any detail as to how this percentage was derived
nor the process of measurement used. It is unclear as to whether the 70%
relates to the severity of cracking or the number of cracks. The statement
appears to be an “indication only” based solely on the engineer’s
observations and experience. However, in itself it infers that a significant
percentage of the cracking, however measured, results from causes other
than the leaking pipe.
23. Taking all of the evidence and opinions into account, at the very least it
appears that subsidence and settling due to climatic conditions, drought,
watering restrictions and the extraction of sub-soil water by trees will have
played a significant part in causing the damage.
24. The Court of Appeal indicated in Wayne Tank and Pump Co Ltd v
Employers’ Liability Assurance Corpn Ltd that:
"... unless one cause is clearly more decisive than the other, it should be
accepted that there are two causes of the loss and no attempt should be
made to give one of them the quality of dominance”
25. On the basis of the evidence provided I am of the view a considerable
contribution to the cause of damage will have arisen from perils that are
excluded under this policy.
26. It is therefore unnecessary to labour over which expert’s opinion, and
therefore which cause of loss, should hold sway. There is clear case law in
relation to concurrent causes, so that even if it were proven that the water
leak contributed to the damage it would not be sufficient to cause the policy
to respond.
27. Where there are two causes of loss, one within the policy and the other
excluded, the policy will not respond.
Case No: 274886 Determination Page 5 of 5
Determination
28. On the basis of the available information I determine that the FSP is not
liable to indemnify the Applicant for its loss beyond the extent to which it has
already agreed in relation to damaged floor boards.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.