The applicant claimed for wall cracking after a water pipe leak under his home and the FSP denied it. The Panel found drought-related subsidence and footing inadequacy were a significant cause, so the FSP is not liable beyond the floorboard damage it already agreed to pay.

Where one cause within the policy and another excluded concur and neither is clearly dominant, the Wayne Tank principle means the policy does not respond.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 274886 Determination Page 1 of 5 Case number: 274886 General Insurance - Domestic Insurance – Home Building - FSP Decision - Denial of claim 28 September 2012 Background 1. The Applicant is insured under a Home Building Defined Events policy underwritten by the Financial Services Provider (FSP) 2. The Applicant advised the FSP of a claim on 13 th September 2007. A water pipe under the kitchen concrete slab had been leaking and a considerable volume of water had leaked under the house over an extended period of time, possibly up to 90 days. The leaking pipe had been repaired, but the walls of the house were cracking and showed evidence of the house moving on its foundations. 3. The FSP employed an independent consultant engineer to inspect the damage to the insured premises. The engineer concluded that damage was not caused by the leaking pipe, but was as a result of the foundations settling caused by shrinkage of the clay soil following an extreme and extended period of drought. 4. The FSP has denied the claim on the basis that the Applicant has failed to prove a loss under the policy. 5. The FSP also offers a second reason for denial, being the operation of an exclusion, which states: “We will not cover loss, damage injury or death that occurs as a result of ......wear, tear, rust, corrosion, deterioration or corrosion ......atmospheric conditions or extreme temperature ......subsidence or landslide unless it happens immediately after an earthquake ......tree roots” Determination Case No: 274886 Determination Page 2 of 5 Summary of Applicant’s position 6. The Applicant advises that the effect of such a large volume of water (approximately 63,000 litres) flowing under the house has not been appropriately considered by the FSP and its consultant engineer. The slope of the land is such that if the water flowed under the house, it would flow from the back to the front under the full extent of the building. 7. The Applic ant maintains that floor level measurements taken by the FSP’s consultant engineer in 2007 show evidence of heaving indicating volumetric change in soil due to wetting. Subsequent measurements taken in 2011 show the floor levels settling indicating volumetric change in soil due to drying. 8. The Applicant employed its own consultant engineer who inspected the house on 29 August 2011. The Applicant’s consultant engineer acknowledged the difficulties arising from not having seen the building in 2007 but concludes: “My inspection of the house walls shows more than normal house cracking even in these recent conditions of drought. Whilst there are shrubs in the front yard and whilst there has been water restrictions in Adelaide the degree of movement in this dwelling is unusual. I would inspect at least 40 houses annually with regard to wall cracking and the degree of cracking in this house is unusual even with the drought conditions. It is my opinion that the water mains leak affected the footings and walls to the dwelling and the consequences are more than that which has been allowed in the (FSP’s Engineer’s) report. It is my estimate that over 70% of the current cracking to the front rooms of the house are as a result of the earlier 2007 water leak.” Summary of FS P’s position 9. The FSP advises that in their view the Applicant has failed to prove a loss under the policy and reminds us that the onus of proof rests upon the Applicant to prove that the damage was caused by water leaking from a pipe. 10. The FSP’s consultant engineer inspected the insured property in 2007 and again in 2011 and has issued four reports detailing the damage. In 2007 the FSP’s engineer advised that in his opinion the wall cracking was due to: “Severe soil drying and hence shrinkage caused by the p rolonged 2006-07 drought, the worst ever recorded in this state. Government watering restrictions have meant that all homeowners have been unable to water lawns and gardens with the consistency required to maintain equilibrium moisture conditions on reactive clay allotments Any trees in the near vicinity, such as street trees in this case, have survived the drought conditions and watering restrictions by extending their root systems further and deeper than in previous years with the writer’s soil testing indicating zones of drying are now extending for horizontal distances up to Case No: 274886 Determination Page 3 of 5 three or four times the height of trees in groups and to depths of 4 metres and beyond.” 11. The FSP’s consultant engineer’s report also states: “The original solid masonry portion of th is dwelling comprises the most brittle form of dwelling construction, this being render and set masonry walls supported by poorly gridded concrete strip beam footings containing minimal steel reinforcement.” 12. Then in conclusion states: “The pattern of crack ing in walls and ceilings is clearly consistent with footing settlements and not with a soil heave centred at the kitchen sink as indicated by our floor level measurements. The writer concludes that because there has been no heaving of the dwelling floors in the vicinity of the kitchen area the leaking copper water pipe has not caused, or contributed to, wall and ceiling cracking in this particular case.” 13. The FSP’s engineer in his June 2011 report reiterated the causes of the cracking contained in his previous report and made the following comment in relation to the flow of water from the leaking pipe: “In the writer’s opinion a large proportion of the leaked mains water in 2007 would have tended to accumulate most readily within and along the 1:50 grade waste drain trench which extends outwards from the kitchen sink to the external southern elevation and then down the eastern elevation to the street connection point.” 14. Without conceding that the Applicant has proven a loss under the policy, the FSP advises that even if the Applicant were able to do so, the FSP would still deny indemnity on the basis of the policy exclusion and, should it be determined that there are concurrent causes of loss, then the existence of the excluded cause will result in the policy not responding. Issues 15. Whether the Applicant has proven that its loss falls within the scope of the policy. 16. Whether a significant element of the loss is caused by an excluded peril and the impact that might have on the policy response. Reasons for decision 17. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is due to the quantum and complexity of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. Case No: 274886 Determination Page 4 of 5 18. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issued raised. 19. The reports submitted by the FSP’s engine er indicate that this building has a history of cracking and movement with some indication of possible underpinning and superficial repairs. 20. These reports also indicate that the type of footings used are inadequate for the soil conditions and it is common to find wall cracking in this type of construction and in the area where this dwelling is located. 21. Neither of these assertions are refuted by the Applicant’s engineer. 22. The report submitted by the Applicant’s engineer claims that over 70% of the cracking to the front rooms of the house are due to the water leak. However the report does not provide any detail as to how this percentage was derived nor the process of measurement used. It is unclear as to whether the 70% relates to the severity of cracking or the number of cracks. The statement appears to be an “indication only” based solely on the engineer’s observations and experience. However, in itself it infers that a significant percentage of the cracking, however measured, results from causes other than the leaking pipe. 23. Taking all of the evidence and opinions into account, at the very least it appears that subsidence and settling due to climatic conditions, drought, watering restrictions and the extraction of sub-soil water by trees will have played a significant part in causing the damage. 24. The Court of Appeal indicated in Wayne Tank and Pump Co Ltd v Employers’ Liability Assurance Corpn Ltd that: "... unless one cause is clearly more decisive than the other, it should be accepted that there are two causes of the loss and no attempt should be made to give one of them the quality of dominance” 25. On the basis of the evidence provided I am of the view a considerable contribution to the cause of damage will have arisen from perils that are excluded under this policy. 26. It is therefore unnecessary to labour over which expert’s opinion, and therefore which cause of loss, should hold sway. There is clear case law in relation to concurrent causes, so that even if it were proven that the water leak contributed to the damage it would not be sufficient to cause the policy to respond. 27. Where there are two causes of loss, one within the policy and the other excluded, the policy will not respond. Case No: 274886 Determination Page 5 of 5 Determination 28. On the basis of the available information I determine that the FSP is not liable to indemnify the Applicant for its loss beyond the extent to which it has already agreed in relation to damaged floor boards.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.