Home / Financial Firm (Unknown - Insurer) / Determination 274706
Determination 274706
Denial of retaining wall collapse claim due to faulty design or construction
Summary
A body corporate's driveway retaining wall collapsed after prolonged heavy rain, and the FSP denied the rectification claim on the basis of faulty design and construction. AFCA found the defective construction was the proximate cause, the excluded faulty design or construction defeated the claim, and no payment was ordered.
Expert evidence established that the wall was defectively constructed, and under the concurrent causes principle, the excluded cause meant the policy did not respond to any part of the claim.
Issues
- Claim denial primary · not upheld
“The Panel concludes that the proximate cause of the loss was faulty design or construction of the retaining wall, so the policy exclusion applies to defeat the claim.”
- Product terms interpretation secondary · not upheld
“Where concurrent causes include an excluded cause, the exclusion is dominant and the claim fails, even if storm contributed.”
Subjects and remedies
home or building damagenatural disasterno remedy
Text of the determination
Case No: 274706 Determination Page 1 of 7
Case number: 274706
General Insurance - Domestic Insurance - Residential Strata Title - FSP
Decision - Denial of claim
10 October 2012
Background
1. The Applicant in this matter is a body corporate comprising of 39 units. The
Applicant‟s property is insured under a strata title insurance policy issued by
the Financial Services Provider (FSP) for $8,661,452.
2. On 6 December 2011 a driveway retaining wall collapsed. The FSP denied a
claim under the policy for rectification of the retaining wall on the ground the
primary cause for the collapse was defects in its design and construction.
3. The Applicant contends that the proximate cause of loss was the torrential
downpours immediately prior to the collapse.
4. The FSP submits that in the event that excessive rainfall caused the
collapse, storm damage to retaining walls is specifically excluded from cover
provided by the policy. Alternatively exclusions apply to rainwater damage to
the exterior of the building not caused by a sudden event a nd from gradually
developing flaws and earth movement.
Summary of Applicant’s position
5. The retaining wall collapsed after eight months of torrential rain. Despite the
FSP declining the claim on the ground of faulty construction, the wall was
designed by an engineer and approved by the council‟s engineer.
6. An engineer has confirmed the life of a crib wall is about 55 years. Their wall
was only 24 years old at the time of the collapse after the ongoing torrential
rain.
7. The FSP is not taking into consideration the weather conditions preceding
the collapse of the crib wall.
8. The Applicant‟s appointed engineer PT reported that prolonged rainfall
experienced in the 12 months prior to the failure was one of the reasons for
the collapse. The report further refers to a 6.4m trench that goes 0.9m under
the level of the crib wall and to the back fill from this trench (which is a
utilities trench). This meets the wall at right angles at the point of failure.
Determination
Case No: 274706 Determination Page 2 of 7
Accordingly the FSP should seek compensation from the contractors
responsible for the trench.
9. They insured against unforseen happenings such as the weather conditions
that were not normal.
10. Three factors contributed the wall failure being:
Poor construction methods,
Unusually high rainfall for 12 months prior to the collapse, and
The utilities trench placed at right angles to the part of the wall that
fractured and the back fill that came from the trench and became
saturated by the preceding rains.
11. The fair way of settling the claim is to pro rata the total cost of rebuilding the
wall as follows:
Cost to rebuild the wall $120,000
Divide by 3 $ 40,000
Multiply by 2 $ 80,000
Summary of FSP’s position
12. The FSP relies substantially on loss adjuster C‟s and engineer NA‟s reports
obtained by it.
13. The loss adjuster reported residents discovered damage to the wall in
November. The wall subsequently collapsed on 26 December.
14. The engineer reported persistent and high rainfall for three months had
progressively increased the moisture content of the soil. Had the wall been
properly constructed it would have coped with the change in moisture
content.
15. The FSP contends the wall collapsed as it was not adequately supported.
The exclusion relative to faulty design therefore applies.
16. Further the policy does not cover storm damage to walls that should be built
to withstand weather conditions and as the evidence has established the
swelling of the wall was progressive the claim is not covered by application
of the exclusion applying to gradual deterioration or developing flaws.
17. The FSP relies on the following policy provisions:
“ Exclusions
We do not insure you against loss or damage caused directly or indirectly by
or arising out of:
...
9. storm, hail or wind damage to:
Case No: 274706 Determination Page 3 of 7
(a) retaining walls;
...
12. error or omission in design, plan, specifications, failure of design,
faulty materials or faulty workmanship.
...
We do not insure you for:
...
(d) ... gradual deterioration or developing flaws....”
Issue
18. What was the proximate cause of the loss.
19. Whether the FSP was entitled to deny liability for the claim.
Reasons for decision
20. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is because of the complex nature of the issues. This dispute
has not been the subject of a FOS Recommendation and has proceeded
directly to Determination.
21. This decision has been made by a Panel comprised of an Ombudsman, an
insurance representative appointed by the Financial Ombudsman Service
Board, and a consumer representative appointed by the Financial
Ombudsman Service Board.
22. There has been an exchange of material between the parties. Each party
therefore is aware of the issues and has had the opportunity to comment.
23. Prior to arriving at a determination the Panel has read and considered all the
material submitted by the parties to FOS.
24. As there has been an exchange of material between the parties it is not
intended to recite the detail of the various expert reports in this
determination. However the relevant sections will be summarised.
25. The property manager of the body corporate first commissioned a consultant
structural engineering report from “SB” dated 13 January 2011. The report
contains the following:
The property manager and several unit owners indicated the
progression of the wall bulging was slow but consistent.
About 8m-10m of the crib retaining wall failed as a result of an internal
disruption of the support line of the arrangement at the interchange
between structural member lengths around 2.7m up from the base.
Case No: 274706 Determination Page 4 of 7
There is an anomalous situation created in the original construction of
the wall that has in recent years developed into a (partial) failure
mechanism due to mechanical changes in the retained soil margin in
the vicinity.
The structural members (stretchers and headers) used in the system
were unreinforced, the outcome of which was the breaking off of many
of the stretcher units at the outer tip (adjacent to the header recess)
under prolonged overstress conditions.
26. A report from consulting engineer NA dated 10 March 2011 and
commissioned by the FSP contains the following;
Based on Bureau of Meteorology records there was persistent and
unusually high rainfall in the Miami area over the three month period
leading up to the collapse.
Given the substantial catchment behind the top of the wall this rainfall
can be anticipated to have progressively increased the moisture
content in the retained clay embankment materials to unusually high
levels in the days before the collapse.
Had the wall been adequately designed and constructed this should not
have initiated the collapse of the wall.
The key to the failure suggested by [engineer SB] is the absence of the
intermediate row of stretcher units installed beneath the rear of the line
of the upper section of the wall and extending down to the foundation
level.
Had these stretcher units been installed then the upper header units in
the lower section of the wall would not have failed in the manner
outlined by engineer SB.
The absence of the header units would be a clear defect in the design
and/or construction of the retaining wall.
The report concluded (in part)
“The persistent and unusually high rainfall in the area over the three month
period leading up to the collapsed can be anticipated to have progressively
increased the moisture content in the retained clay embankment materials to
unusually high levels in the days prior to the occurrence of the collapse,
however if the wall had been adequately designed and constructed this
should not have initiated the collapse.
... The absence of these units has led to the structural failure of the upper
header units in the lower section of the wall and then to the progressive
collapse of the wall. Had the stretcher units been installed then the failure
should not have occurred.
...
Despite the apparent inadequacies in the design/construction of the wall it
performed adequately for many years. It is possible the wall may have
performed adequately over its full design life despite these inherent
inadequacies, if it had never been subject to the combination of loadings
Case No: 274706 Determination Page 5 of 7
resulting in the prevailing weather conditions in the months prior to the
collapse, and heavy rains in December 2010.”
27. The Applicant‟s representative in a report dated 30 August 2011 argued that
if the back stretchers and back headers were not installed then that does not
translate as a defective design or construction at the time the wall was built.
The representative referred to and relied on technical data issued by a
co nstruction contractor and a publication in May 2008 by „CC&AA‟.
28. In his response dated 14 September 2011 to the representative‟s submission
engineer NA noted the technical data sheet referred to was not an
engineering technical document but appeared to be intended to be
interpreted by non-engineers. The document included a single paragraph
describing crib walls and did not address any of the particular technical
design issues associated with these walls.
29. Engineer NA further reviewed the Applicant‟s represe ntative‟s submissions
(report dated 21 November 2011). In essence he concluded that publication
submitted by the representative was not an engineering document setting
out designs specifications for the construction of a particular retaining wall.
30. Enginee r NA refers to a manufacturer „H‟s‟ publication titled Crib walls which
they say was published in the mid 1990‟s. This publication contains
illustrations of dual-thickness crib walls both of which show the intermediate
row of stretcher units installed beneath the upper section of the wall and
extending down to ground level. No evidence has been provided to show the
H‟s crib wall units were used in the construction of the Applicant‟s wall.
31. Engineer report dated 20 May 2012 PT commissioned by the Applicant. The
report contains the following information.
The failure of the wall was caused by;
1. The increased height of the wall with no apparent increase in the
design with the crib components below 3.5m.
2. The presence of poor backfill material in the services trench.
3. The saturation of the backfill material by the prolonged rain periods
experienced in the12 months prior to the failure, causing significant
increase in the pressure on the rear of the wall.
4. Poor detailing at the transition from the smaller top section to the
wider bottom section of the wall causing cracking and weakening of
the header components. Poor drainage to the area above the
retaining wall
Summary
32. The policy provides cover against physical loss or damage to the building
occurring during the period of insurance. It is common ground between the
parties the retaining wall of the Applicant‟s property suffered damage in
December 2010. As such the Applicant has established a prima facie claim
under the policy.
Case No: 274706 Determination Page 6 of 7
33. The FSP seeks to rely on clauses in the policy to deny the claim and
therefore has the burden of establishing on the balance of probabilities that
the terms of the relevant clauses apply to defeat the claim.
34. The evidence has established to the Panel‟s satisfaction that, based on
current building standards, the method employed in construction of the
retaining wall was defective. Both engineers considered the wall was
constructed without header units at the base of the upper level of the wall
and that this affected the integrity of the wall.
35. The Panel has given consideration to the submission by the Applicant‟s
representative in relation to the building codes at the time the wall was
constructed. However, there is no evidence to show that the construction
methods used at that time were in breach of building standards.
36. The Panel is also satisfied the two consultant engineers who carried out site
inspections were qualified to provide such expert evidence. Following a
review of the material relied on by the representative consultant NA
remained of the view that construction of the retaining wall was defective.
37. Nevertheless despite the inadequate construction method, it was considered
the wall should have performed satisfactorily for its design life being about
another 25 years.
38. The failure was in part attributed to the increased lateral loads on the wall
due to significant rainfall in the three months preceding the collapse thereby
increasing the moisture content of the backfill. In addition, the surface water
drainage impacted on the backfill materials to the extent that the loads were
transferred to the inadequate header units at the top of the lower section of
the wall.
39. It is therefore important to consider this in the context of whether the rainfall
was the proximate cause for the loss.
40. The Panel accepts the argument that it is not necessarily the last in time that
is the proximate cause but it is the dominant or effective or operative cause
that is relevant. It is a judgement of fact to determine the cause that is
proximate in efficiency. Common sense must be applied in determining this.
41. There is no doubt that the intense rainfall in the three months prior to the
collapse of the wall significantly increased the moisture content of the back
fill materials. However, according to the expert opinion the moisture content
of the back fill alone would not have caused the wall to collapse, had it been
adequately constructed.
42. The expert opinion was that the inadequate design and construction of the
wall was unable to withstand the lateral forces generated b y the moisture
content of the back fill. Had he wall been correctly constructed with stretcher
units in place, the failure would not have occurred.
Case No: 274706 Determination Page 7 of 7
43. For these reasons the Panel concludes that the proximate cause of the loss
was faulty design or construction of the retaining wall. The policy exclusion
relative to failure of design or faulty workmanship therefore applies to defeat
the claim.
44. The Panel has also considered whether the „torrential down pours‟ that fell in
the period prior to the loss could be considered to be a proximate cause.
There is no dispute between the expert engineers that the effect of the
rainfall ultimately triggered the loss, given the inadequate construction of the
wall.
45. If even the downpours were considered to be the proximate cause, such loss
would be excluded from cover, as retaining walls are specifically excluded
from cover.
46. In any event it is established law that when two or more concurrent causes
are considered to be responsible for the loss and one cause is covered by
the policy and the other is excluded, the exclusion clause is dominant and
the claim fails. Hence if both the storm and the faulty design/construction of
the wall are considered to have equally contributed to the loss, the claim will
fail. This is known as the “Wayne Tank” principle.
47. On the basis that there were two or more proximate causes the Applicant
has proposed a pro-rata settlement to allow for the competing causes for the
failure. However as noted in paragraph 46 above, once where there are two
or more proximate causes and one use is excluded from cover, the policy
does not respond to any part of the claim.
48. After careful analysis of the material the Panel considers the FSP has
discharged the onus that rests with it to show the policy terms apply to
defeat the claim.
Determination
49. Based on the available information the Panel determines that the FSP was
entitled to deny the claim for rectification of the damaged retaining wall.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.