Denial of retaining wall collapse claim due to faulty design or construction

FirmFinancial Firm (Unknown - Insurer)
Decided2012-10-11
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$80,000
SourceAFCA PDF

Summary

A body corporate's driveway retaining wall collapsed after prolonged heavy rain, and the FSP denied the rectification claim on the basis of faulty design and construction. AFCA found the defective construction was the proximate cause, the excluded faulty design or construction defeated the claim, and no payment was ordered.

Expert evidence established that the wall was defectively constructed, and under the concurrent causes principle, the excluded cause meant the policy did not respond to any part of the claim.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 274706 Determination Page 1 of 7 Case number: 274706 General Insurance - Domestic Insurance - Residential Strata Title - FSP Decision - Denial of claim 10 October 2012 Background 1. The Applicant in this matter is a body corporate comprising of 39 units. The Applicant‟s property is insured under a strata title insurance policy issued by the Financial Services Provider (FSP) for $8,661,452. 2. On 6 December 2011 a driveway retaining wall collapsed. The FSP denied a claim under the policy for rectification of the retaining wall on the ground the primary cause for the collapse was defects in its design and construction. 3. The Applicant contends that the proximate cause of loss was the torrential downpours immediately prior to the collapse. 4. The FSP submits that in the event that excessive rainfall caused the collapse, storm damage to retaining walls is specifically excluded from cover provided by the policy. Alternatively exclusions apply to rainwater damage to the exterior of the building not caused by a sudden event a nd from gradually developing flaws and earth movement. Summary of Applicant’s position 5. The retaining wall collapsed after eight months of torrential rain. Despite the FSP declining the claim on the ground of faulty construction, the wall was designed by an engineer and approved by the council‟s engineer. 6. An engineer has confirmed the life of a crib wall is about 55 years. Their wall was only 24 years old at the time of the collapse after the ongoing torrential rain. 7. The FSP is not taking into consideration the weather conditions preceding the collapse of the crib wall. 8. The Applicant‟s appointed engineer PT reported that prolonged rainfall experienced in the 12 months prior to the failure was one of the reasons for the collapse. The report further refers to a 6.4m trench that goes 0.9m under the level of the crib wall and to the back fill from this trench (which is a utilities trench). This meets the wall at right angles at the point of failure. Determination Case No: 274706 Determination Page 2 of 7 Accordingly the FSP should seek compensation from the contractors responsible for the trench. 9. They insured against unforseen happenings such as the weather conditions that were not normal. 10. Three factors contributed the wall failure being:  Poor construction methods,  Unusually high rainfall for 12 months prior to the collapse, and  The utilities trench placed at right angles to the part of the wall that fractured and the back fill that came from the trench and became saturated by the preceding rains. 11. The fair way of settling the claim is to pro rata the total cost of rebuilding the wall as follows:  Cost to rebuild the wall $120,000  Divide by 3 $ 40,000  Multiply by 2 $ 80,000 Summary of FSP’s position 12. The FSP relies substantially on loss adjuster C‟s and engineer NA‟s reports obtained by it. 13. The loss adjuster reported residents discovered damage to the wall in November. The wall subsequently collapsed on 26 December. 14. The engineer reported persistent and high rainfall for three months had progressively increased the moisture content of the soil. Had the wall been properly constructed it would have coped with the change in moisture content. 15. The FSP contends the wall collapsed as it was not adequately supported. The exclusion relative to faulty design therefore applies. 16. Further the policy does not cover storm damage to walls that should be built to withstand weather conditions and as the evidence has established the swelling of the wall was progressive the claim is not covered by application of the exclusion applying to gradual deterioration or developing flaws. 17. The FSP relies on the following policy provisions: “ Exclusions We do not insure you against loss or damage caused directly or indirectly by or arising out of: ... 9. storm, hail or wind damage to: Case No: 274706 Determination Page 3 of 7 (a) retaining walls; ... 12. error or omission in design, plan, specifications, failure of design, faulty materials or faulty workmanship. ... We do not insure you for: ... (d) ... gradual deterioration or developing flaws....” Issue 18. What was the proximate cause of the loss. 19. Whether the FSP was entitled to deny liability for the claim. Reasons for decision 20. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the complex nature of the issues. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 21. This decision has been made by a Panel comprised of an Ombudsman, an insurance representative appointed by the Financial Ombudsman Service Board, and a consumer representative appointed by the Financial Ombudsman Service Board. 22. There has been an exchange of material between the parties. Each party therefore is aware of the issues and has had the opportunity to comment. 23. Prior to arriving at a determination the Panel has read and considered all the material submitted by the parties to FOS. 24. As there has been an exchange of material between the parties it is not intended to recite the detail of the various expert reports in this determination. However the relevant sections will be summarised. 25. The property manager of the body corporate first commissioned a consultant structural engineering report from “SB” dated 13 January 2011. The report contains the following:  The property manager and several unit owners indicated the progression of the wall bulging was slow but consistent.  About 8m-10m of the crib retaining wall failed as a result of an internal disruption of the support line of the arrangement at the interchange between structural member lengths around 2.7m up from the base. Case No: 274706 Determination Page 4 of 7  There is an anomalous situation created in the original construction of the wall that has in recent years developed into a (partial) failure mechanism due to mechanical changes in the retained soil margin in the vicinity.  The structural members (stretchers and headers) used in the system were unreinforced, the outcome of which was the breaking off of many of the stretcher units at the outer tip (adjacent to the header recess) under prolonged overstress conditions. 26. A report from consulting engineer NA dated 10 March 2011 and commissioned by the FSP contains the following;  Based on Bureau of Meteorology records there was persistent and unusually high rainfall in the Miami area over the three month period leading up to the collapse.  Given the substantial catchment behind the top of the wall this rainfall can be anticipated to have progressively increased the moisture content in the retained clay embankment materials to unusually high levels in the days before the collapse.  Had the wall been adequately designed and constructed this should not have initiated the collapse of the wall.  The key to the failure suggested by [engineer SB] is the absence of the intermediate row of stretcher units installed beneath the rear of the line of the upper section of the wall and extending down to the foundation level.  Had these stretcher units been installed then the upper header units in the lower section of the wall would not have failed in the manner outlined by engineer SB.  The absence of the header units would be a clear defect in the design and/or construction of the retaining wall. The report concluded (in part) “The persistent and unusually high rainfall in the area over the three month period leading up to the collapsed can be anticipated to have progressively increased the moisture content in the retained clay embankment materials to unusually high levels in the days prior to the occurrence of the collapse, however if the wall had been adequately designed and constructed this should not have initiated the collapse. ... The absence of these units has led to the structural failure of the upper header units in the lower section of the wall and then to the progressive collapse of the wall. Had the stretcher units been installed then the failure should not have occurred. ... Despite the apparent inadequacies in the design/construction of the wall it performed adequately for many years. It is possible the wall may have performed adequately over its full design life despite these inherent inadequacies, if it had never been subject to the combination of loadings Case No: 274706 Determination Page 5 of 7 resulting in the prevailing weather conditions in the months prior to the collapse, and heavy rains in December 2010.” 27. The Applicant‟s representative in a report dated 30 August 2011 argued that if the back stretchers and back headers were not installed then that does not translate as a defective design or construction at the time the wall was built. The representative referred to and relied on technical data issued by a co nstruction contractor and a publication in May 2008 by „CC&AA‟. 28. In his response dated 14 September 2011 to the representative‟s submission engineer NA noted the technical data sheet referred to was not an engineering technical document but appeared to be intended to be interpreted by non-engineers. The document included a single paragraph describing crib walls and did not address any of the particular technical design issues associated with these walls. 29. Engineer NA further reviewed the Applicant‟s represe ntative‟s submissions (report dated 21 November 2011). In essence he concluded that publication submitted by the representative was not an engineering document setting out designs specifications for the construction of a particular retaining wall. 30. Enginee r NA refers to a manufacturer „H‟s‟ publication titled Crib walls which they say was published in the mid 1990‟s. This publication contains illustrations of dual-thickness crib walls both of which show the intermediate row of stretcher units installed beneath the upper section of the wall and extending down to ground level. No evidence has been provided to show the H‟s crib wall units were used in the construction of the Applicant‟s wall. 31. Engineer report dated 20 May 2012 PT commissioned by the Applicant. The report contains the following information.  The failure of the wall was caused by; 1. The increased height of the wall with no apparent increase in the design with the crib components below 3.5m. 2. The presence of poor backfill material in the services trench. 3. The saturation of the backfill material by the prolonged rain periods experienced in the12 months prior to the failure, causing significant increase in the pressure on the rear of the wall. 4. Poor detailing at the transition from the smaller top section to the wider bottom section of the wall causing cracking and weakening of the header components. Poor drainage to the area above the retaining wall Summary 32. The policy provides cover against physical loss or damage to the building occurring during the period of insurance. It is common ground between the parties the retaining wall of the Applicant‟s property suffered damage in December 2010. As such the Applicant has established a prima facie claim under the policy. Case No: 274706 Determination Page 6 of 7 33. The FSP seeks to rely on clauses in the policy to deny the claim and therefore has the burden of establishing on the balance of probabilities that the terms of the relevant clauses apply to defeat the claim. 34. The evidence has established to the Panel‟s satisfaction that, based on current building standards, the method employed in construction of the retaining wall was defective. Both engineers considered the wall was constructed without header units at the base of the upper level of the wall and that this affected the integrity of the wall. 35. The Panel has given consideration to the submission by the Applicant‟s representative in relation to the building codes at the time the wall was constructed. However, there is no evidence to show that the construction methods used at that time were in breach of building standards. 36. The Panel is also satisfied the two consultant engineers who carried out site inspections were qualified to provide such expert evidence. Following a review of the material relied on by the representative consultant NA remained of the view that construction of the retaining wall was defective. 37. Nevertheless despite the inadequate construction method, it was considered the wall should have performed satisfactorily for its design life being about another 25 years. 38. The failure was in part attributed to the increased lateral loads on the wall due to significant rainfall in the three months preceding the collapse thereby increasing the moisture content of the backfill. In addition, the surface water drainage impacted on the backfill materials to the extent that the loads were transferred to the inadequate header units at the top of the lower section of the wall. 39. It is therefore important to consider this in the context of whether the rainfall was the proximate cause for the loss. 40. The Panel accepts the argument that it is not necessarily the last in time that is the proximate cause but it is the dominant or effective or operative cause that is relevant. It is a judgement of fact to determine the cause that is proximate in efficiency. Common sense must be applied in determining this. 41. There is no doubt that the intense rainfall in the three months prior to the collapse of the wall significantly increased the moisture content of the back fill materials. However, according to the expert opinion the moisture content of the back fill alone would not have caused the wall to collapse, had it been adequately constructed. 42. The expert opinion was that the inadequate design and construction of the wall was unable to withstand the lateral forces generated b y the moisture content of the back fill. Had he wall been correctly constructed with stretcher units in place, the failure would not have occurred. Case No: 274706 Determination Page 7 of 7 43. For these reasons the Panel concludes that the proximate cause of the loss was faulty design or construction of the retaining wall. The policy exclusion relative to failure of design or faulty workmanship therefore applies to defeat the claim. 44. The Panel has also considered whether the „torrential down pours‟ that fell in the period prior to the loss could be considered to be a proximate cause. There is no dispute between the expert engineers that the effect of the rainfall ultimately triggered the loss, given the inadequate construction of the wall. 45. If even the downpours were considered to be the proximate cause, such loss would be excluded from cover, as retaining walls are specifically excluded from cover. 46. In any event it is established law that when two or more concurrent causes are considered to be responsible for the loss and one cause is covered by the policy and the other is excluded, the exclusion clause is dominant and the claim fails. Hence if both the storm and the faulty design/construction of the wall are considered to have equally contributed to the loss, the claim will fail. This is known as the “Wayne Tank” principle. 47. On the basis that there were two or more proximate causes the Applicant has proposed a pro-rata settlement to allow for the competing causes for the failure. However as noted in paragraph 46 above, once where there are two or more proximate causes and one use is excluded from cover, the policy does not respond to any part of the claim. 48. After careful analysis of the material the Panel considers the FSP has discharged the onus that rests with it to show the policy terms apply to defeat the claim. Determination 49. Based on the available information the Panel determines that the FSP was entitled to deny the claim for rectification of the damaged retaining wall.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.