Determination 274549

Partial denial of cyclone damage claim to commercial premises

FirmFinancial Firm (Unknown - Insurer)
Decided2012-10-09
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Commercial premises damaged by Cyclone Yasi were partly denied by the FSP as pre-existing or maintenance damage. AFCA found the roof, flashing and sub-floor column damage cyclone-related and ordered it accepted and settled under the PDS, while the rear stairs and guttering remained the applicants' cost.

The FSP did not prove the exclusions for the roof damage, whereas the stairs and guttering were shown to be pre-existing and excluded.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 274549 Determination Page 1 of 8 Case number: 274549 General Insurance - Small Business/Farm Insurance - Commercial Property - FSP Decision - Claim Amount 27 September 2012 Background 1. The Applicants hold a Business Property Smart Choice Insurance Policy with the Financial Services Provider (FSP) covering their tenanted business premises in Innisfail, Queensland. The policy commenced on 22 March 2010 and was current at the time of the reported loss. 2. The building has a sum insured of $761,000 and an applicable policy excess of $500. 3. On 2 February 2011, the property was damaged when Cyclone Yasi hit the area. A claim was lodged by the Applicants on 4 March 2011, with the FSP. 4. The FSP requested quotations for repairs from the Applicants and on receiving these, the FSP appointed its own builder and engineer to attend to inspect the property. 5. Based on the FSP’s appointed engineer, some maintenance and pre - existing damage to the property was identified and subsequently excluded from the settlement offer made to the Applicants. 6. The Applicants say the amount offered will not repair the cyclone related damage and they do not understand what areas require maintenance. The FSP has maintained its decision to provide only settlement on those aspects of damage it believes are related to cyclone damage. Summary of Applicants ’ position 7. The Applicants say that when taking out the insurance with the FSP they were not aware of some of the maintenance issues the FSP is now claiming existed. 8. The FSP had a building survey completed at the time the policy commenced and at this time none of the maintenance issues now being claimed by the FSP regarding the roof were advised to them. Determination Case No: 274549 Determination Page 2 of 8 9. The FSP is denying the roof damage caused by the cyclone but their builder has identified areas in the roof and the roof sheeting which they believe are cyclone dama ge related. Further, the FSP’s appointed builder never viewed the area as the roof was under tarpaulins at the time of the inspection. 10. The FSP has not adequately informed them of what constitutes maintenance or pre-existing damage to enable them to attend to those repairs. 11. They accept the roof guttering at the premise was a pre -existing problem and accept they must attend to its repairs. 12. The Applicants say they want another inspection of the premises to take place in order to properly identify all of the cyclone related damage. Summary of FSP’s position 13. It has admitted the claim under the relevant insurance policy and has accepted some of the claimed damage as being cyclone related. 14. Its engineer has assessed the building and identified those areas which have been damaged by cyclone. The engineer has also identified areas of maintenance or pre-existing problems at the property. 15. It has provided all relevant scope of works and quotations it obtained in assessing the Applicants’ damaged building and will not be a ppointing anyone further to provide any further assessment. 16. The Applicants are responsible for attending to the maintenance and pre- existing damage at their own cost and it will not be responsible for any further damage and/or claims which may result, should this damage not be attended to. 17. It on the following policy provisions of its Product Disclosure Statement (PDS): “ Section 1: Fire and Defined Events/Accidental Damage This Section insures You for loss or damage to the building, arising from a defined event during Your Period of Insurance. If You lease out Your building, Your landlord’s fixtures and fittings, including floor coverings are insured as part of Your building. Defined events Defined events include happenings such as fire, lightning, storm, impact and malicious damage. Please refer to Part C, pages 24 to 27, for details of what is covered and what is not covered under each defined event. Defined events are number 1 to 8 for easy reference. ” (Page 9) “ 9. Precautions and Inspection You must: Case No: 274549 Determination Page 3 of 8 (a) take all necessary steps to ensure that the Insured Property is kept in a good state of repair and maintenance and free of waste material and rubbish; (b) take all necessary steps to ensure that only competent employees and contractors are engaged by You; (c) take all reasonable precautions and action to enforce observances by all appropriate persons of all proper safeguards to prevent, avoid or minimise any loss, destruction, damage, Personal Injury or liability; (d) ensure compliance with all Statutes relating to safety of persons or property or the operation, inspection or maintenance of any property; and (e) allow Our representative to inspect or examine: (i) the Insured Property; (ii) the buildings or structures in which the Insured Property is contained; and (iii) Your operations.” (Page 18) “ 8. Storm and/or Tempest, Water and Other Liquid Storm and/or Tempest, Water and Other liquid as defined in (a), (b), (c), (d) and (e) below. (a) Rainwater Rainwater – Water in the form of rain falling from the sky on to the Premises or the building in which the Premises is situated until such time as it reaches the ground. (b) Run-off Run-off – Rainwater that has accumulated directly on and flowed across normally dry ground. Run-off includes Rainwater that has overflowed from the following:- (i) public roadside gutters, channels and drains that are normally dry. (ii) Swimming pools, spars or saunas. Run-off does not include Flood or Water from the Sea. ... (d) Storm and/or Tempest Storm and/or Tempest – a violent atmospheric disturbance accompanied by high wind, rain, snow or hail, but does not mean persistent bad weather, heavy rain or persistent rain by itself.” (Pages 25 and 26) “ Exclusions Applicable to Defined Event 8 1. We will not be liable for destruction or damage caused by: (d) erosion, collapse, subsidence, landslide or mudslide or any other earth movement; ... Case No: 274549 Determination Page 4 of 8 (h) Water entering the Premises as a result of: (i) structural defects; (ii) faulty design; (iii) faulty workmanship; or (iv) lack of maintenance by You. 2. We will not be liable for destruction of or damage to: ... (b) Insured Property whilst in the open air unless it comprises or forms part of a permanent structure designed to function without the protection of walls or roofs;” (Pages 26 and 27) Issues 18. Whether the FSP has adequately assessed the damage claimed b y the Applicants. 19. Whether the Applicants are entitled to any further settlement towards cyclone related damage as part of their claim. Reasons for decision 20. This decision has been made by a Panel consisting of an Ombudsman, an industry representative and a consumer representative. 21. The Panel is satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. 22. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. Experts 23. The Panel has considered the opinions of the FSP’s appointed experts, including an engineer (R), and the opinions expressed by the Applicants’ appointed builders. 24. R has provided a clear indication of cyclone damage he could view at the Applicants’ premises. R has not identified t he specific causes or rectification work required for the maintenance and pre-existing damage identified by him at the Applicants’ premises. This is based on the instructions he received from the FSP which was simply to identify all cyclone related damage. Case No: 274549 Determination Page 5 of 8 25. As such R has provided his report on what he considered to be maintenance related or pre-existing damage but he has not advised as to why he believed this to be the case. The Panel is of the opinion this has caused some confusion for the Applicants. Building Surveyor’s report 26. After taking out the policy of insurance with the FSP, the Applicants, in accordance with the terms and conditions of their policy, permitted an inspection of the premises, , by building surveyor (I), appointed by the FSP. 27. I inspected the premises in April 2010, and provided a report on the property. The report provides details of I’s inspection and noted its concerns with risk at the premise from an insurance perspective. 28. Based on the information provided by I, the FSP issued a letter to the Applicants advising of items they must attend to within 60 days. This letter was sent via email to the Applicants representative, S, on 20 April 2010. 29. The letter requested the Applicants to not only attend to the items within 60 days, but to also to advise the FSP once the items had been attended to. The items included having the rear stairs inspected by an engineer or council inspector and the obtaining of a certificate of compliance for safety. It also identified that repairs to columns in the sub-floor area needed to be attended to. There is no reference to any roof related issues and no mention of any damage to those sub-floor columns/posts which had already been subject to repairs. 30. The Panel notes that although the FSP requested the Applicants to attend to a variety of matters within 60 days, it did not advised the Applicants of any possible ramifications if the items were not completed within 60 days, i.e.: limitation or cancellation of cover etc. However, the Panel notes the relevant policy wording does clearly identify circumstances where claims will not be paid. Roof damage 31. The Panel has reviewed R’s report and notes that there seems to be no consideration or comment regarding the fact that the Applicants’ premise had previously been subject to a cyclone event in 2006. This is something that was confirmed by the building surveyor appointed by the FSP at the time the policy was taken out. 32. The surveyor inspected the property in April 2010 and did not notice or report on any pre-existing damage to the roof or guttering. Indeed, the surveyor, under the heading “Condition of Property“, reported “Roof and Guttering - Acceptable and new”. 33. The Panel finds it difficult to understand why Case No: 274549 Determination Page 6 of 8 34. R in its report stated there was no evidence of structural roofing members being damaged or lifting and the condition of the sheeting was reported as being good. Accordingly, the Panel is at a loss to understand what R is inferring by its comment “Evidence of prior repair attempts were also noted. We believe that this is a pre-existing condition and not attributed to cyclone Yasi.” 35. R fails to explain what “prior repair attempts” were noted and it does not appear to have asked the Applicants or anyone else when these alleged previous repairs were done. The only explanation by way of support for the comment is “Refer to Photos 3 & 4”. The Panel has examined the photographs and notes they show ceiling damage caused by water and in the foreground of photo four there is a spray can which appears to read “leak sealer”. 36. The Panel concludes that to make any assumptions based on the paucity of comment from R and the supplied photographs tendered as providing proof of these previous repairs, would be speculative. 37. Moreover, the Panel notes that R did not inspect the property until July 2011, some five months after the cyclone event. 38. In the event that the roof pre-existing damage and repair comments made by R relate solely to its comments on the roof’s box guttering t hey are (as far as repair or replacement is concerned) of no relevance to this determination as the Applicants accept that there were pre-existing issues with the guttering and state that they will be responsible for the costs associated therewith. 39. It follows therefore that the FSP is not liable in relation to damage caused by water entering the building resulting from the poor condition of the guttering. 40. The Panel notes in regard to the roof flashing R has reported it was damaged by the cyclone and therefore forms part of the claim. 41. In contrast to R’s report the Applicants builder (J) has provided a series of photographs depicting roof bearers/beams/battens which appear to be split or lifted. It is his opinion that this is as a result of the cyclone event. 42. Based on their builder’s report, the Applicants believe the damage to the roof as claimed was damage caused by the cyclone. 43. The Panel has considered the reports and photographs made available in relation to the roof and it prefers the report of the Appli cant’s builder which asserts cyclone damage and is supported by numerous photographs depicting splitting, lifting and separation of trusses/rafters/battens, evidence which has not been refuted by the FSP. 44. In its NOR the “[The FSP] notes from the ISA repor t that the roof had been replaced approximately between March to August 2008 and had been subject to a cyclone in 2006. Whilst the quoted comment does not accord fully with the ISA report which describes the roof as “Acceptable and new” it Case No: 274549 Determination Page 7 of 8 does lend substance to the contention that the roof was not in a damaged condition prior to the cyclone. Rear stairs 45. The Applicants say the stairs at the rear of the property were in a sound condition prior to Cyclone Yasi and only required some minor repairs. 46. The Panel note R’s report and the surveyor’s report completed when the policy was taken out. Both reports refer to the poor condition of the stairs. Both reports indicate the stairs required remedial action and pose a safety hazard. 47. The Panel is of the opinion this damage was pre-existing and that the Applicants were aware of the condition of the stairs prior to Cyclone Yasi. Floor structure 48. In his report, R has identified columns within the sub-floor which have been subjected to previous repairs to combat “concrete cancer”. It is his opinion these previous repairs may have been sub-standard as he could not see any reinforcement in the concrete repairs, through a crack in the repaired area which is now present. He has therefore determined the two columns on which the repairs have cracked to be pre-existing and maintenance related issues. 49. The Panel notes the surveyor’s report which was completed on behalf of the FSP at the time the policy was taken out. This report also identifies the column repairs as having been done to combat “concrete cancer”. However, the surveyor makes no mention of there being any inadequacies in the repairs, or any cracks evident to suggest the repairs were sub-standard or not doing what they were intending to do. In fact, the surveyor commented: “On some of the concrete columns, the concrete has been exposed and the steel rod reinforcing has rusted away but generally most of the columns appear to be sound enough to carry this very heavy 3 storey complex.” And, as a comment on a photograph provided by I of the column referred to by R in his report, he says: “The concrete post of the left has been heavily repaired to rectify the cancer.” (sic) 50. Considering I’s report was done in April 2010 and the cyclone occurred in February 2011, the Panel is not convinced that this cracking to the two columns has not occurred as a result of Cyclone Yasi. Carpet 51. The FSP’s NOR states that the female Applicant advised the FSP of various areas of damage including carpet. The FSP says it advised the female Case No: 274549 Determination Page 8 of 8 Applicant that carpets were not covered as the Applicants only had building insurance. 52. This appears to be contradictory to the policy coverage under Section 1 of the policy, as detailed above (Page 9 of the PDS), which reads: “If you lease out Your building, Your landlord’s fixtures and fittings, including floor coverings are insured as part of Your building.” 53. The Panel is aware the property is leased out and as such, carpets, which are clearly a floor covering, would be covered, providing the carpets have been damaged by a defined event. In this instance, it must be established that the carpets were damaged by Cyclone Yasi and if this is the case, unless the water emanated from the defective guttering, or an effective exclusion applies, the claim for carpet must be accepted. Determination 54. On the basis of the available information the Panel is of the opinion the FSP has not proven the exclusions on which it relies upon to deny the Applicants’ claim. Therefore, the Panel determines that the FSP must accept the App licants’ claim for cyclone damage to the roof, its flashing and the two sub-floor columns and must settle the claim in accordance with its PDS. 55. The Panel is of the opinion the damage claimed to the rear stairs and guttering has been proven to be pre-existing and is therefore excluded under the policy of insurance. The costs to rectify this damage must be met by the Applicants. 56. The Panel also determines that in the event the FSP is liable for carpet damage in response to 56 above the Applicants must provide documentation for the cost to replace or repair the damaged carpet and the FSP must settle this aspect of the claim in accordance with the PDS.