Home / Financial Firm (Unknown - Insurer) / Determination 274018

Determination 274018

Building settlement amount - deduction for pre-existing wear and tear after cyclone

FirmFinancial Firm (Unknown - Insurer)
Decided2012-10-31
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$289,277
SourceAFCA PDF

Summary

After a cyclone damaged a home, the applicants rejected the FSP's $254,276.66 settlement and sought the full rebuild cost plus $35,000. AFCA found the applicants not entitled to full rebuild cost and the FSP's offer fair after deducting pre-existing wear and betterment.

The PDS allows settlement limited to cyclone-related repairs with a deduction for wear, tear, maintenance and betterment, and the FSP's offer reflected that method.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 274018 Determination Page 1 of 9 Case number: 274018 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 31 October 2012 Background 1. The Applicants hold a household insurance policy with the Financial Services Provider (FSP) which was current at the date of loss. 2. The policy provided building cover for $391,000, contents cover for $149,000 and specified contents items in the home cover for $7,000. The applicable policy excess is $300. 3. The Applicants lodged a claim with the FSP for cyclone damage which occurred at their home on 3 February 2011. The FSP subsequently accepted the Applicants contents claim and provided settlement for contents accordingly. 4. After assessments of the building were undertaken by the FSP and Applicants’ appoin ted builders, a dispute arose regarding items the FSP deemed to be maintenance/wear and tear issues and not damaged by the cyclone. 5. The FSP has offered settlement to the Applicants based on building reports and quotations obtained however this settlement has been rejected by the Applicants. Summary of Applicants ’ position 6. The Applicants are represented. For the sake of clarity and brevity, the Panel will refer hereafter to the Applicants and their representative as “the Applicants”. 7. The Applicants say the FSP failed to assess the damage caused to their home by the cyclone in a timely manner. They say the FSP has delayed and confused the settlement process by treating the damage to the property as repairable when it is not economically feasible to repair the home building. 8. The Applicants say the proposed settlement offered by the FSP attributes the loss as 43% due to pre-existing wear and tear/maintenance issues and only 57% to cyclone damage Determination Case No: 274018 Determination Page 2 of 9 9. The Applicants say the FSP has failed and refused to provide details of the pre-existing wear and tear and maintenance issues sufficient to attribute the loss in the percentages detailed. 10. The Applicants say the FSP has failed and refused to properly review its decision. 11. The Applicants seek to have the FSP pay the proposed settlement amount already offered of $254,276.66, on a without prejudice basis, and pay immediately a further amount of $35,000 for the demolition, certification and design costs for the building, as per the quotation provided by the Applicants from CB. In addition, the Applicants seek to have the FSP source three quotations for the repairs of the pre-existing damage alleged by the FSP and then pay the full cost of rebuilding the property, less the average of these three quotations. Summary of FSP’s position 12. The FSP says it has accepted the Applicants’ claim for cyclone related damage, acknowledging the property did suffer cyclone damage, and has settled the Applicants’ contents claim accordingly. These issues are not in dispute. 13. The FSP says it appointed builders, engineers, assessors and experts to inspect the property to provide an opinion on the damage caused and a scope of works to enable quotations for repairs to be completed. As a result of the inspections undertaken by these experts, a number of maintenance items, wear and tear and pre-existing damage were found at the Applicants’ premises. 14. The FSP says it received a quotation for the rebuilding of the property supplied by the Applicants’ builder ; however this quotation was prepared prior to the inspection of the property by any engineers or experts to enable an accurate scope of works to be provided. On receipt of the accurate scope of works relating to cyclone damage only, this was provided to the Applicants ’ builder to offer them an opportunity to p rovide a quotation, however they did not provide a quotation. 15. The FSP says the quotations it received for the scope of works were assessed and determined to be accurate. The most competitive quotation was used to calculate settlement. In addition, an allowance for variations in costs/materials etc was added, as recommended by its experts, of 20% of the quoted repair cost. 16. The FSP says its offer was based on its experts’ advice on the condition of the property and accurate quotations provided to it by its nominated builders. A generous allowance was also provided for variations in costs/materials etc. Case No: 274018 Determination Page 3 of 9 17. The FSP says it is not required to contribute anything towards maintenance, wear and tear or pre-existing damage to the property as these items are excluded from the policy coverage. 18. The FSP relies on the following policy provisions of the applicable Product Disclosure Statement (PDS): “ Settling your claim If your certificate of insurance shows that you have home insurance we will cover your home for loss or damage as a result of an insured event occurring during the period of insurance. We may choose at our option to:  rebuild or repair your home as new; or  pay you the cost to us of rebuilding or repairing your home as new including any additional costs (relating only to that part of the home that was damaged) necessary to comply with government or local government laws existing at the time of the damage occurring, provided that at the time of the original construction the laws and by-laws prevailing then were complied with; or  pay you the home sum insured; or  settle, when allowance for wear and tear or lack of maintenance of the property is to be made, as explained in “Claims settlement other than on an as new basis” on page 26.” “ Claims settlement other than on an as new basis The amount we pay for rebuilding or repairing damage will be reduced from an as new basis to an amount that would place you in the same position you were in immediately before the loss or damage occurred with due allowance for age, wear, tear and where applicable, lack of maintenance of the property in the following circumstances:  where the home was not in a sound condition or well maintained at the time of the loss or damage occurring;  ...” 19. The Panel notes the letter to the Applicants on 27 October 2011 refers to an incorrect PDS which was released around January 2011. As the Applicants’ policy had a cover period of 15 February 2010 to 15 February 2011 covering the time of loss the PDS referred to could not be the applicable document. Issues 20. Whether the Applicants are entitled to receive from the FSP the full cost of rebuilding their residence. 21. Whether the Applicants are entitled to receive payments from the FSP for demolition, certification and design costs for rebuilding their home from the FSP. Case No: 274018 Determination Page 4 of 9 22. Whether the FSP is required to provide quotations for the maintenance, wear and tear and pre-existing items as requested by the Applicants. Reasons for decision 23. This decision has been made by a Panel consisting of an Ombudsman, an industry representative and a consumer representative. 24. The Panel is satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. 25. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 26. The FSP is obliged to indemnify the Applicants for any loss they incur during the period of insurance, as a result of an insured event, in accordance with the policy terms and conditions as set out in the FSP’s applicable PDS, current at the time of the loss. 27. In this case, it has been clearly established that the Applicants held a current policy of insurance with the FSP at the time of the loss and that the event giving rise to the reported damage was an insured event (cyclone). The issues giving rise to this dispute revolve around the settlement being offered by the FSP and the method of calculating that settlement. 28. The FSP’s position appears to be, on the face of it, quite simple, in that it is prepared to indemnify the Applicants for their loss as a result of the cyclone damage their property suffered, but it is not obliged to provide any contribution towards areas of damage not caused by the cyclone. The FSP has relied on its experts’ evidence which indicates the Applicants’ property had a number of areas exhibiting signs of normal wear and tear, pre-existing damage and an apparent lack of maintenance. 29. The Applicants say that the FSP has not provided detailed information regarding the maintenance/wear and tear/pre -existing damage to their property, nor has the FSP provided costs associated with rectification of these items. 30. The Panel notes that copies of all reports from all of the FSP’s experts have been provided to the Applicants. This is not denied by the Applicants and these various reports, quotations and photographs have been referred to by the Applicants in their correspondence to the FSP and to FOS. 31. The initial inspection of the property was made by the FSP’s internal loss adjuster on or around 14 February 2011, which is the date of his report. The adjuster advised the following in his report: Case No: 274018 Determination Page 5 of 9 “During the cyclone the wind has blown a very large tee on to the roof of our insureds (sic) home, the impact has badly damaged the roof, veranda and front wall of the home. A section of the tree has crashed through the roof over the lounge room, study area and main bedroom, sending debris, timber and rain into both rooms. ... Nature/Extent of Damage: Building: Refer scope of works from [BC.” (sic) 32. From documents presented by the FSP it appears the FSP appointed a building consultant, BC, to attend with its internal loss adjuster on or around 14 February 2011. BC’s report of 15 February 2011 provides the following: “ Overview Of Loss Damage has been sustained to: The tree has impacted diagonally across the front right corner of the house with the top of the trunk going over the middle towards the left rear corner and as a result of the impact all of the external walls have been forced outwards at the top and the front wall pushed down through the floor into the subfloor area and engineer will be required to determine if restoration is viable given the age of the dwelling.” 33. Attached to this first report from BC are a number of photographs clearly showing the tree still on top of the Applicants ’ home. 34. Based on the advice provid ed in BC’s report, the FSP appointed a building engineer to undertake an inspection of the Applicants’ property to comment on any safety issues and to summarise the main engineering issues. The engineer attended the property on 26 February 2011 and his report dated 1 March 2011 identified the following safety issues: “ Safety Issues Identified and Recommended Emergency Make Safe  Sidewalls have come away the top. We recommend that timber struts be put into place from top of wall to bottom of verandah post.  Props to ceiling joists to timber floor to support collapsed roof. Props to be placed over floor joist over supporting concrete stump.  Piece of timber hanging by electrical cord at front door to be removed. ...” The engineer further provided the following summary on the main engineering issues: “ General Engineering Observations  A large tree near the house has fallen landing on the font right hand section of the verandah and house causing significant damage and water ingress.  At the time of the inspection, tarps had been fitted to prevent further water ingress. Case No: 274018 Determination Page 6 of 9  The existing floor appeared dry and minor signs of swelling.  Over 50% of the roof has been extensively damaged and the front external wall from the door to the right hand side bay window has been damaged.  Due to the force of the impact and lack of ceiling horizontal tie from left to right, the sidewalls have been pushed outwards at the top. Apart from this, all walls and floor framing appeared to be structurally sound.  The existing solar power panels installed on the rear of the roof are undamaged and are to be removed prior to rectification works. We understand the owner will undertake this task soon.  The entire existing roof sheeting is to be removed. All roof framing to be removed, with the existing rafters cut at the external wall so that the rafters remain over the veranda. Any damaged veranda rafters to be replaced with salvaged timber from the main section of the roof.  Ceiling joists and VJ ceiling lining to be removed over the main section of the residence.  Front-pitched veranda over the entry is to be removed and veranda rafters supported by right hand side front wall to also be removed.  Front wall, including front entry door, to right hand side bay window to be removed. Supporting bearer to be replaced as necessary if damaged. Timber stud wall to be reinstated with VJ MDF internal lining wan weatherboard lining externally. Note that the remaining walls will need to have studs installed, by removing existing belt rail, and cladding externally with weatherboards in order to match rectification of front wall as well as to accommodate tie down rods of wall frame.  Reinstate main section of roof with timber trusses at 900 CRS and hardwood timber or steel battens. Roof to be colorbond corrugated roof sheeting and ceiling to be VJ MDF lining painted and sealed both sides.  All remaining VJ walls to sanded and gap sealed and repainted.  Kitchen joinery water damaged to be replaced.  Some existing concrete stumps have cracked and will be replaced. We noted 3 stumps were cracked at time of inspection, including one stump under the front right hand side corner of the house.  All works are to be to current Australian Standard Codes and relevant BCA clauses.” (sic) 35. A scope of works was prepared by BC and the engineer’s report was used as a basis of what work was required. The FSP says the engineer was not involved in determining what areas of required repairs related to cyclone damage and what area of damage related to wear and tear issues. This was determined by the assessors based on the builder’s advice and observations regarding wear and tear/maintenance issues. 36. The wear and tear/maintenance issues were identified by all of the builders who were requested to provide a quotation for repairs and they indicated they were not prepared to carry out the cyclone related repairs without attending to the other repairs required at the property. The other repairs Case No: 274018 Determination Page 7 of 9 related to wear and tear/maintenance items and/or pre -existing damage all of which did not form part of the cyclone damage. 37. The Applicants’ builder’s quotation and proposed repair work included the comment under “Note”, that: “[BC]’s Scope of Works and Engineers report missed several structural issues which have been included in the overall cost of this provided quote. Clarification can be provided if required by contacting ...” (sic) 38. The FSP attempted to obtain clarification of the quotation from the Applicants’ builder, however no response was received. The Panel realises the Applicants’ builder’s quotation includes items which have been identified by the FSP and its experts as not having been damaged by cyclone, for example the concrete subfloor posts (5). The quotation does not specify rooms requiring repairs or specific measurements or areas referred to. Accordingly, the Panel cannot distinguish what repairs the Applicants’ builder has quoted on which relate solely to cyclone damage and what repairs are related to non-cyclone damage. 39. Whilst the Panel accepts the quotation from the Applicants’ b uilder covers all repairs required to be completed at the property, the Panel cannot accept that all repairs quoted are related to cyclone damage in light of the overwhelming evidence provided by the FSP that there was pre -existing wear and tear/maintenance issues at the property. 40. Despite the FSP’s efforts to clarify the quotation with the Applicants’ builder in an effort to resolve the settlement dispute, the information sought was not forthcoming. The Panel cannot, therefore, accept that quotation is either accurate or useful for the purposes of determining a fair and reasonable settlement. 41. Furthermore, the Applicants have not provided any evidence to support their opinion that the wear and tear/maintenance related issues were not present prior to the cyclone or were minimal. Photographs provided by the FSP taken some 11 days after the cyclone event show evidence of the peeling paint, poor condition of the veranda balustrade and cracks to stumps. 42. The Panel is satisfied that the Applicants’ property did in fact have pre- existing damage which was not related to cyclone damage, and which would be considered to be general wear and tear or maintenance related. It is on this basis that the Panel accepts the FSP’s submission that these items should be excluded from any settlement. 43. The Panel notes the Applicants’ comments regarding photographs provided by the FSP being taken a considerable period after the insured event. In their email to the FSP on 25 January 2011, the Applicants say: “We note that the photographs reflect significant deterioration of our clients’ home that has occurred in the 12 months since the cyclone. The photographs also show the original emergency tarpaulin put in place by the SES. Our clients cannot understand why [the FSP] failed to ensure that the building was properly protected. We are instructed that [the FSP] instructed [BC] to arrange Case No: 274018 Determination Page 8 of 9 it when our clients told them the roof was leaking. On that basis all deterioration since the cyclone is the responsibility of [the FSP].” 44. The Panel has reviewed all photographs provided by the FSP including original photographs taken on or around 14 February 2011, 11 days after the cyclone event. The Panel does not accept the Applicants’ opinion that the property has significantly deteriorated since the cyclone event and there does not appear to be any further damage to the property as a result of the FSP’s “make safe” measures. 45. The Applicants also say that CB has indicated the cost to repair the cyclone related damage at $285,000 and the repair of other items at $120,000. They say based on this, the FSP is indicating that 43% of the home is in need of maintenance for non cyclone related damage and only 57% of the damage relates to the cyclone. They say this is inaccurate and that their home was in a sound condition and well maintained prior to the cyclone event. 46. The Panel does not accept that the calculations detailed by the Applicants are correct. The Applicants did not explain how their figure was reached but appear to have used the following formula: $120,000 ÷ $285,000 = 0.421 x 100 = 42.1% (approximately) Instead of adopting the correct formula, which should be: $120,000 + $285,000 = $405000 (total cost of all repairs/rebuilding cost ex GST) $120,000 ÷ $405,000 = 0.305 x 100 = 30.5% (approximately) (Pages 47,44,42) 47. Based on the Panel’s assessment of all information regarding repairs provided by the FSP’s experts and the Applicants, and using the correct formula, the Panel is of the opinion that 30.5% of damage attributable to maintenance, wear and tear and pre-existing damage, is reasonable. 48. The FSP’s PDS is clear and unambiguous in its method of settlement where wear and tear or maintenance issues are identified, as described above. In this instance, the FSP is entitled to settle the claim based on the cost to repair only the cyclone related damage taking into consideration a reduction for wear and tear. That is, the Applicants are not entitled to receive a settlement based on “new for old” replacement or repairs. 49. The Panel is satisfied that the repairs as q uoted by the various builders will be using new products, for example, new paint to cover various areas of the home which sustained damage as a result of the cyclone. However the paint in these areas was quite obviously in a poor state of repair prior to the cyclone and the Applicants will therefore be receiving a benefit of new products/materials that were not present prior to the cyclone. Accordingly, the FSP is entitled to make an appropriate deduction from the overall quoted repair figure to allow for these types of improvements. Case No: 274018 Determination Page 9 of 9 Determination 50. On the basis of the available information the Panel determines that the Applicants are not entitled to receive the full cost of rebuilding their residence from the FSP as it has been clearly determined that the residence has not been completely destroyed. Whilst the Panel accepts that additional repairs are required in order for cyclone damage to be effected, these additional repairs involve pre-existing and non-cyclone related damage, and therefore could not be considered by the FSP as part of the claim made by the Applicants. 51. The Panel further determines that the inclusive offer of $254,276.66 made by the FSP is fair and reasonable in the circumstances. It is based on a fair and reasonable quotation provided by a qualified builder to effect repairs to the cyclone related damage only. From that quotation, a deduction has been made for depreciation, which takes into account the wear and tear/maintenance related items and any betterment or improvement the Applicants may receive from the repairs. 52. Finally, the Panel determines that other than identifying the areas of the residence which have not been damaged by the cyclone event, the FSP is not required to provide quotations for these items, as requested by the Applicants.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.