Home / Financial Firm (Unknown - Insurer) / Determination 273609

Determination 273609

Settlement amount for rainwater damage to home: building repairs, contents, accommodation and cleaning

FirmFinancial Firm (Unknown - Insurer)
Decided2013-01-09
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$145,074
Non-financial loss—
Amount claimed$191,686
SourceAFCA PDF

Summary

After rainwater entered the Applicants' home through tarpaulins, the FSP offered $124,816.65 based on its builder's quote, and the builder would not do the work for that price. AFCA ordered payment of building repairs at the Applicants' builder's quote, increased contents and cleaning amounts, actual alternative accommodation costs, and interest.

Because the FSP's own contractor would not undertake the repair work at its quoted price, AFCA reviewed the competing quotes and fixed building repairs at the Applicants' builder's quote, with the FSP responsible for drying and cleaning once the claim was lodged.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 273609 Determination Page 1 of 12 Case number: 273609 General Insurance - Domestic Insurance - Home Building - Home Contents - FSP Decision - Claim Amount - Rainwater Ingress 11 December 2012 Background 1. The Applicants held a home building and contents insurance policy with the Financial Services Provider (FSP) from 4 May 2011 and the policy was current at the time of loss. 2. The Applicants lodged a claim with the FSP for severe accidental damage sustained to the property on 5 September 2011 due to an unforseen event. 3. The FSP denied liability to this claim on the grounds the damage was not covered by a defined event stipulated in the policy. 4. On 26 September 2011, the property sustained rainwater damage when rainwater water entered the property via tarpaulins installed (by the FSP’s builder when he inspected the property damage sustained in relation to the first claim as above). 5. The FSP accepted the Applicants’ second claim and offered $124,816.65 as the full and final settlement of the claim. 6. The Applicants expect $191,686 as settlement towards the loss that has been currently identified. Summary of Applicants ’ position 7. The Applicants are unhappy with the FSP’s offer of settlement for building repairs and believe the offer of settlement is inadequate to reinstate the part of the property that sustained rainwater damage. 8. The Applicants’ claim is below:  Building repairs - $116,784;  Alternative accommodation - $27,000;  Contents claim - $29,720  Carpets - $8,473;  Independent estimate of costs - $450; Determination Case No: 273609 Determination Page 2 of 12  Storage removal and return - $2,679;  Cleaning and disinfecting - $1,280;  Reinstatement of pool - $300;  Allowance for goods discarded - $5,000 and  Unknown damaged contents in boxes. Summary of FSP’s position 9. The FSP’s offer of settlement for building repair is based on its builder C’s and engineer M’s assessment. 10. The Applicants have not challenged the scope of works presented by the FSP. 11. The Applicants’ quote from builder R is based on the FSP’s scope of works and does not provide a breakdown of the total cost. 12. The estimation from estimator L is excessive and cannot be relied upon. The FSP is not required to reimburse the cost of obtaining this estimation. 13. The Applicants’ home was inhabitable as a result of the first claim and as such, it is not required to reimburse the Applicants for alternative accommodation. 14. Nevertheless, in good faith, the FSP offered alternative accommodation for the repair period relating to storm damage of 7 weeks amounting to $12,250. 15. The FSP is not liable to reimburse the Applicants for cleaning and disinfecting the property due to spread of mould spores as this was a result of the delay caused by the Applicants in sorting water damaged contents. 16. The FSP’s offer of settlement is below: a. Building repairs - $74,885; b. Alternative accommodation - $12,250; c. Contents claim - $25,530; d. Discarded items - $1,500; e. Carpets - $8,473; and f. Storage removal and return - $2,679; 17. The FSP relies on the following policy provisions: “ Storm, rainwater or wind ... Under Listed Events, we will cover your buildings or contents for loss or damage as a result of storm, rainwater or wind. Case No: 273609 Determination Page 3 of 12 ... Alternative accommodation ... If your buildings or contents suffer loss or damage and you are unable to live in your home as a result, we will cover the costs of alternative accommodation for up to 12 months. The loss or damage must occur as a result of an incident we have agreed to cover. If you have buildings insurance, we will • pay an amount that is equal to the weekly rental value of your buildings before the incident occurred • pay the reasonable costs of alternative accommodation for your pets up to 20 per cent of the buildings sum insured, as listed on your schedule. ... How we settle a buildings claim 1 We will decide how we will settle your claim If your buildings suffer loss or damage, we will decide whether to • repair • rebuild, or • pay you the cost to repair or rebuild that part of your buildings that suffered loss or damage. ... How we settle a contents or valuable items claim ... If we decide to replace your contents or valuable items We will replace the item with the nearest equivalent new item. ... Your responsibilities when you are making a claim When you make a claim, you must meet a number of responsibilities. You must • be truthful and frank in any statement you make in connection with a claim • take safe and reasonable steps to prevent any further loss, damage or liability occurring ... • keep all damaged buildings or contents so we can inspect them if required ... • not repair or replace any damage d buildings or contents without our consent.” Case No: 273609 Determination Page 4 of 12 Issue 18. Whether the FSP’s offer of settlement is fair, reasonable and in accordance with the terms and conditions of the policy. Reasons for decision 19. Due to the nature of this dispute, FOS has considered it appropriate to expedite it in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 20. This decision has been made by a Panel consisting of an Ombudsman, an insurance representative appointed by the Financial Ombudsman Service Board, and a consumer representative appointed by the Financial Ombudsman Service Board. 21. The Panel is satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 22. There is no dispute the Applicants ’ claim falls within the general provisions of the policy and the issue remains whether the FSP’s offer of settlement is fair and reasonable and is in accordance with the terms and conditions of the policy. 23. The Applicants do not dispute receipt of the policy documents and the Panel is satisfied in these circumstances that the FSP has met its obligations to clearly inform the Applicants of the terms and conditions of the policy. 24. The Panel notes that the Applicants accept the FSP’s denial of their first claim and its offer of settlement for the carpets and storage under the second claim and therefore, these will not form part of this Determination. Building Repairs 25. The FSP says the Applicants have not raised any issues regarding inadequacies in its scope of works which required attention and was related to rainwater damage and the Panel is satisfied that the Applicants accept the FSP’s final scope of works. 26. The FSP’s initial offer of settlement based on its builder’s quote was $70,784.37 and subsequent to receiving an estimate from L, the FSP allowed the following additional expenses:  Electrical Distribution Board - $2,000;  Internal Scaffold hire - $1,000; and  Bin hire - $1,000. Case No: 273609 Determination Page 5 of 12 27. The FSP’s current offer of settlement towards building repairs is $74,984.37. 28. The Panel notes the Applicants have presented the quotes (based on the FSP’s scope of works) below:  Estimation by L - $153,772;  Quote by Builder R - $116,784; and  Quote by Builder A - $121,550. 29. The Applicants say that when they inquired of C whether it could undertake the repairs as per the quote it presented to the FSP, C had refused to accept the work and confirmed that it would only undertake repairs directly authorised by the FSP. 30. The Applicants’ response in this regard was exchanged with the FSP and it has not forwarded any comments on this matter. 31. The Services’ Case Manager has contacted C in this regard and its customer service representative confirmed that it would not undertake any work request from private individuals and it would only take direct requests from the insurance companies. This policy applies to private individuals, even if the request is based on a quote supplied by C to the respective insurance company (FSP). 32. As a result the Applicants are placed in a disadvantageous position where the FSP’s offer of settlement (based on C’s quote) is inadequate for their own builder R to attend to the necessary repair works and on the other hand the FSP’s builder C would not undertake the repairs either. 33. The Panel accepts the FSP is entitled to choose the method of the claim settlement. Nevertheless, in the circumstances, due the reasons explained above, the Panel has no choice but to review the quotes submitted by the Applicants’ builders R and A. 34. The Panel notes that Builder R’s quote appears economical, was based on the FSP’s scope works but without a cost break -up. However, when compared to builder A’s quote, it appears reasonab le. 35. Thereby, in the absence of any further quotes from the FSP from a builder who is willing to undertake the work for the price quoted by C, the Panel is satisfied that the FSP should pay $116,784 (based on R’s quote) towards building repairs. Alternative Accommodation 36. The FSP says the Applicants’ initial claim as denied by the FSP, was what rendered the property uninhabitable and as such it is not required to make any contribution towards alternative accommodation related to the second claim as the Applicants were not prejudiced, in that regard by the occurrence of the second claim. Case No: 273609 Determination Page 6 of 12 37. The FSP, in good faith, offered settlement for alternative accommodation for the estimated repair period of storm related damage of 7 weeks. 38. The Applicants say they are unable to return home due to the FSP’s various delays and expect reimbursement as follows:  38 weeks @ $250/week - 38 weeks; and  10 weeks @ $250/day - 10 weeks for the repair period. 39. The Case Manager has contacted the Applicants to confirm whether they were living at the premises when the second incident occurred and the female Applicant has confirmed they did not get an opportunity to move in due to the occurrence of the second event (rain water ingress). 40. She said an independent engineer appointed by them to revie w the FSP’s denial of the first claim indicated that the ground floor of the property was safe and habitable. 41. Upon the Case Manager’s request, the Applicants have provided their engineer’s report dated 14 October 2011 which describes the initial damage sustained to the property and the safety instructions to be followed to keep the children away from the damage and debris. 42. The report indicates the property could be reinstated to its pre-event condition. However it does not indicate the property was habitable. This may be due to the fact, at the time of his inspection, the other parts of the property had sustained water damage. 43. On the other hand the FSP has not provided any expert evidence (other than the loss assessor’s comment) that the Applicants’ propert y was uninhabitable after the first incident. 44. Based on the Applicants’ engineer’s report, the Panel does not agree with the FSP’s view that they may have been able to occupy the ground floor of the property after attending to the cleanup of the rubble and essential safety repairs. 45. However, the Panel is of the opinion that the above progress would not have taken more than a maximum of two months and believes the Applicants would have been able to occupy their property from 5 November 2011. 46. The Panel does not understand the FSP’s recent response in which it says the offer for alternative accommodation was withdrawn when the Applicants decided to take the dispute to the Service. 47. In the FSP ’s submission to the Service dated 12 June 2012, it maintained its offer of settlement of $12,250 for alternative accommodation. 48. An agreement was made at a later date for the Applicants to accept the entitlement of $112,566.65, however, there is no evidence this offer was ever withdrawn. Case No: 273609 Determination Page 7 of 12 49. In any event, the Panel is of the view that the FSP is bound to consider a period of alternative accommodation beyond two months from the initial claim on 5 September 2011. 50. The Panel also understands the Applicants were unable to organise repairs to the property as the offer of settlement towards building repairs was inadequate. 51. Therefore the Panel is satisfied that it is fair in all the circumstances that the FSP should pay alternative accommodation expenses from 5 November 2011 until the storm damage repairs have been completed in accordance with the entitlement under the policy as below: “ pay an amount that is equal to the weekly rental value of your buildings before the incident occurred ... up to 20 per cent of the buildings sum insured, as listed on your schedule. ” 52. The FSP pay the Applicants’, upon submission of evidence, the actual cost of alternative accommodation, from 5 November 2011until the repairs relating to storm damage are completed for up to 12 months in accordance with the terms of the policy. Damaged Contents 53. In regards to the loss of contents, the Applicants’ claim and the FSP’s offer of settlement is below: The Applicants’ Claim The FSP’s offer C's Room $11,705 $11,275 J's Room $3,070 $3,070 S's Room $4,395 $4,215 Z's Room $60 $60 Curtains $3,000 $3,000 Downstairs $9,370 $3,470 54. The FSP has recently informed the Service that it has decided to accept the Applicants’ claim for the damaged lounge (The Applicants claimed $4,500 under downstairs). It has organised a store voucher to the amount of $4,874 in this regard. 55. Further, the FSP’s offer of settlement is based on the adjustments made by the loss assessor as follows:  $150 for light fittings was reduced to $120 per light fitting;  $100 for repairs to corroded skates was adjusted to $70;  $350 for the replacement of books in [S]s Room was reduced to $300;  $1,000 for an antique chair was reduced to $600; and Case No: 273609 Determination Page 8 of 12  $100 skates from S’s room not allowed. 56. The Applicants have accepted the adjustments made towards the light fittings and a skate from S’s room amounting to $100 and reject the adjustment made towards the antique chair, books and corroded skate. 57. The Panel notes the FSP has presented no evidence nor reasons as how and why these adjustments were made but simply says the loss assessor had discussed this with the Applicants. 58. The policy covers replaced items on new for old basis and thereby, the Panel is of the view that the FSP should pay the amounts as claimed by the Applicants as it has not sought any quotes for the replacement cost of the items which are in dispute. 59. The FSP should increase the contents settlement by $480 in this regard. Damaged items in boxes 60. In regards to the damaged, damp or mouldy items which may have been packed into the boxes with the undamaged items, the Applicants say: “It took [FSP] 6 weeks to send in the restoration crew and it wasn’t until their third visit that they were able to do the job as they were not given all the information. When they did start they said and I had this clarified twice by them and I rang the assessor to confirm that they had been told to pack everything in boxes, wet, dry mouldy or otherwise and put the boxes downstairs on the white carpet. The restoration crew were so shocked at these instructions that they even rang to confirm and that is definitely what they were told to do. We also know from the little that we did see that things that were not on the list were discarded and because of circumstance described above we have know way of knowing how much until we have our house back and can unpack it all.” 61. Further, the Panel is also aware that (loss assessor’s report dated 5 December 2011) the loss assessor contacted the FSP regarding cleaning damp items but was instructed by the FSP to continue boxing the items. It appears as a result of this instruction W may have packed water damaged and undamaged items together in the same boxes. 62. These items are yet to be identified and the Panel is of the view that these items should be assessed further when the boxes are re-opened and the FSP would be liable for any water damaged or mould damaged items. Undamaged Contents Discarded by W 63. It appears W may have discarded some of the Applicants’ undamaged contents whilst discarding damaged ones. Case No: 273609 Determination Page 9 of 12 64. The FSP requested the Applicants to list these items and the Applicants initially claimed for $460 for the items and then requested the FSP to pay $5,000 as they believed that W may have discarded contents close to this value. 65. In the absence of the Applicants’ inability to list these items, the Panel considers the current offer of settlement of $1,500 to be reasonable. 66. The Panel understands the Applicants’ comments that they would never know the missing items until the boxes are unpacked. 67. The Panel suggests the loss assessor to be present when the boxes are opened so that the matters in dispute in relation to the items stored in the boxes could be investigated and assessed further. Cleaning and Disinfecting 68. The FSP refers to the Applicants’ solicitor’s letter dated 7 October 2011 which states: “To minimise our clients’ loss and to mitigate their damages they will take action to protect their premises and also commence remedial work” 69. The FSP says the spread of mould spores was caused by the Applicants not sorting out the water damaged debris in due time and as a result it is not liable to indemnify them for this expense. 70. The Applicants say the FSP should clean and disinfect the entire house after completion of repairs as the mould had appeared during the six weeks delay in the FSP appointing W. 71. Further, members of W had dumped mouldy debris over the internal balustrade into the wheel barrow in the ground floor without due care. Each time a cloud of mould spores had scattered throughout the unaffected areas of the house. 72. The Panel notes the loss assessor in his various reports requested the FSP, and not the Applicants, should attend to issues relating to dampness to prevent further damage as follows: “ 29/09/2011 Subject to acceptance of liability, we recommend that the following steps of action be undertaken:  Appointment of two panel builders to provide alternative quotations for building repairs.  Appointment of Restoration Company to remove all contents from the front of the property to rear of property (Including cleaning where necessary).  Installation of dehumidifiers by Restoration Company to assist in drying out and prevent any potential problems with dampness to both Case No: 273609 Determination Page 10 of 12 buildings and unaffected contents. RE-secure tarps in an attempt to prevent any further rainwater from entering the property. ...  We would then request that all damaged items be removed from the property as soon as possible while the undamaged contents be stored in a dry area of the home. ” ... “ 5/12/2011 Our First Report of 29 September 2011 requested that dehumidifiers be installed in order to prevent any possible issues with dampness to both the buildings and unaffected contents. We also suggested that a Restoration company be appointed to move all contents from the wet area of the property to the unaffected area at the rear of the property. We again requested in our Second Report of 4 October 2011 that the carpets be disposed of and dehumidifiers be installed. Note, we only received your instructions on 26 October 2011 that authorisation could be given to [W] to remove carpets from the prope rty.” 73. The facts remain that the appointment of W to remove water damaged carpets and thereafter the water damaged mattresses were delayed by the FSP. 74. The FSP also failed to follow the loss assessor’s specific instructions to fix dehumidifiers to dry the internal pats of the home. 75. Finally, the FSP does not reject the actions of the members of W who may have allowed spreading of mouldy spores into the unaffected areas of the house. 76. The Panel agrees that the Applicants should take action to mitigate the loss. However, once the claim is lodged with the FSP, the responsibilities of drying the property lies with the FSP and not the Applicants. 77. Considering the above, the Panel is satisfied that the FSP should reimburse the cost relating to cleaning and disinfecting the damaged and undamaged parts of the house amounting to $1,280. Reinstatement of the Pool 78. The Applicants say they were unable to maintain the pool when the electricity connection to the property was disconnected for a long period of time as a result of the various delays and expect the FSP to reimburse the cost of reinstating the pool. 79. The FSP says any damage to the pool was not caused by the storm incident and that is outside of the scope of cover of the policy. 80. The Panel notes that electricity connection to the property was disconnected after the first claim and was not reconnected as a result of rainwater ingress Case No: 273609 Determination Page 11 of 12 and that this action led to the Applicants’ inability to maintain the pool during this period. 81. The Applicants have not presented any evidence from their engineer that the power connection could have been made after the first event. 82. The Panel also accepts that had the second event not occurred, the Applicants pool cleaning would not have delayed further. 83. However, since the pool did not sustain any storm damage, the Panel is satisfied the cleaning of the pool is not directly related to the rainwater ingress to the property and accordingly, the FSP is not required to reimburse this expense to the Applicants. Cost of L’s Report 84. The Applicants request the FSP to pay the cost of obtaining an independent estimate by L amounting to $450. 85. The Panel is aware of the fact that the FSP did not request them to obtain such report. 86. Further, upon review of L’s report, the FSP revised its offer of settlement by $4,000 by using parts of the estimation by L. 87. However, the Panel has decided to settle the building repair claim in accordance with the Applicants’ builder R’s quote and did not utilise the information contained in L’s estimate. 88. Therefore, the FSP is not required to reimburse this expense to the Applicants. Determination 89. On the basis of the available information, the Panel determines the FSP should pay the following less any initial payments made:  Building repairs - $116,784;  Alternative accommodation – upon submission of evidence, the FSP should reimburse the cost from 5 November 2011 until storm damage repairs are completed for up to 12 months in accordance with the terms of the policy;  Contents claim - $25,510;  Cleaning and disinfecting - $1,280;  Discarded contents $1,500 until further items are identified upon opening the boxes; and  Damaged contents in boxes to be assessed when the boxes are opened. Case No: 273609 Determination Page 12 of 12 90. The FSP is not required to pay for the Independent estimate from L and the cost of pool reinstatement. 91. If the parties do not agree towards the settlement for the damaged items in boxes and items discarded by W, they may lodge a separate dispute with the Service in this regard. 92. The FSP should pay interest at the statutory rate on the balance cash settlement payable to the Applicants from 27 January 2012 until settlement.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.