Home / Financial Firm (Unknown - Insurer) / Determination 272998

Determination 272998

Claim for retaining wall declined under exclusions for storm erosion, earth movement and upgrades

FirmFinancial Firm (Unknown - Insurer)
Decided2013-04-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$8,580
SourceAFCA PDF

Summary

The applicants claimed $8,580 for a retaining wall after storm-related soil erosion affected their home. The FSP denied the claim and AFCA agreed the works were an upgrade and excluded for storm erosion and earth movement.

The policy covers repair or replacement to prior condition rather than improvements, and expressly excludes storm damage in the nature of erosion or earth movement.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 272998 Determination Page 1 of 6 Case number: 272998 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion/condition 29 April 2013 Background 1. This is a review of a Recommendation by the Service’s Case Manager dated 25 February 2013. The Applicants have rejected the Recommendation and in accordance with the requirements of the Terms of Reference, the matter has been referred to me for Determination. 2. The relevant background, summaries of the parties’ position and issue to be determined are set out in paragraphs 1 to 8 of the Recommendation and I will restate same. “1. The Applicants hold a home insurance policy with the Financial Services Provider (FSP) for their residential property. The policy was incepted on 29 May 2007. 2. On 14 June 2011, the Applicants lodged a claim under the policy for damage caused by storm, citing the date of the loss as being on or around 20 May 2011. The damage was predominantly due to soil eroding and scouring at or around the north eastern side of the property. This claim related to a previous claim lodged by the Applicants which was subsequently withdrawn. 3. The FSP denied the claim on a number of bases, namely that there was no loss or damage sustained due to an insured event or alternatively, that the claim falls within a policy exclusion. 4. The Applicants have disputed this. Summary of Applicants’ position 5. The Applicants submit the following in substantiating their position: a. The damage resulted from a massive storm that impacted the Gap in May 2008. As their property is built on a hillside, a massive amount of rainwater runoff cascaded to their home which resulted in significant soil being deposited against the wall of their downstairs bedroom and two stumps holding their laundry area being badly exposed. b. They have experienced continuing problems since then with future soil erosion from stormwater runoff. In particular, the bottom bedroom has a build up of soil erosion plus an added problem of white ant infestation. This has been exacerbated by the severe weather events experienced in Brisbane in 2011. Determination Case No: 272998 Determination Page 2 of 6 c. Prior to the severe storm in 2008, the existing plumbing and drainage of the site dealt with the relevant runoff. However, this has now been compromised as a result of the severe storm in 2008. 6. Based on these series of events, the Applicants are seeking reimbursement for the costs involved in the supply and installation of a retaining wall. A quotation has been provided in this regard totalling $8,580. Summary of FSP’s position 7. The FSP relies on an engineer’s report (NJA), a builder’s report (MK) and the following policy provisions to substantiate its position: “ Exclusions … We do not insure you for any loss or damage that is caused by or arises from:  …  wear and tear, gradual deterioration, or fading  …  settling, expansion, shrinkage or any earth movement other than earthquake. … We will insure your building and contents at the site against loss or damage caused by the following events if they occur during your period of insurance. … Storm … We won’t cover  loss or damage to: - retaining walls, paths, driveways or landscaping …  loss or damage caused by or resulting from: - landslide, subsidence, erosion or any earth movement (other than earthquake).” Issue 8. Whether the FSP is entitled to deny the A pplicants’ claim.” Reasons for Decision 3. There has been a full exchange of information and each party has had the opportunity to address the issues that have been raised. Case No: 272998 Determination Page 3 of 6 4. I have read all of the exchanged material and I have considered the parties’ submissions including the Applicants further submission dated 11 March 2013. 5. In making his Recommendation, the Service’s Case Manager set out his reasons in paragraphs 10 to 23 and I will restate same. “10. I note that according to the policy terms and conditions, the FSP is obliged to do the following when a claimable loss has occurred: “We may choose to repair:  the reasonable cost of repair, or  the reasonable costs of replacement to new condition with property of the same size and specification or with items as near to original as is currently possible, or  a cash amount. If we agree to pay cash, we will pay the amount it would reasonably cost to repair or replace the property. Where a building is not being replaced, the amount we will pay will be less a reasonable deduction for depreciation due to wear and tear and age of the property.” 11. Accordingly, when you consider this provision in conjunction with the description of what events the policy covers, it is evident that the intention of the contract is to repair or replace a damaged item to the condition it was in prior to the loss. It is not intended to pay for the costs involved in improving or enhancing any area of the property that suffered loss or damage, even if such costs are reasonable and necessary. 12. In light of this, I will now consider the available expert evidence and the Applicants’ claim in further detail. In relation to the latter, I note the Applicants’ claim is limited to the cost of installing a retaining wall, which includes the installation of an agricultural pipe. Consideration of the available evidence 13. Both parties have provided an engineer’s report (the Applicants provided one by SCE) and the FSP has also provided a report from builder MK. The latter was involved in the Applicants’ withdr awn claim. 14. NJA provided the following relevant comments: “ General outline of damage Significant scour had occurred around the perimeters of two of the three concrete footings to the steel support posts along at the top of the embankment on the northern side of the sub- floor area. … Discussions and conclusions The surface water drainage provisions outside the line of the top of the sub-floor embankment have clearly proved grossly inadequate to prevent surface water entry into the sub-floor area in the course of heavy rainfall events. The paved area outside the northern wall of the house is relatively flat, and there is no kerb installed to prevent the overflow of surface water onto the top of the embankment. Case No: 272998 Determination Page 4 of 6 Given the susceptibility of the earth bank in the sub-floor area to scour, and the location of the house footings along the top of the embankment, we believe that the paved area outside the northern side of the house should have been formed in such a manner as to direct surface water away from the house and beyond the north-eastern corner of the house without entering the sub-floor area. The scour-affected pier footings do not appear to have suffered any movement to date, however their lateral stability will have been reduced to some extent by the scouring. The depths of the footings are unknown, however they are founded on materials which have remained stable to date. Given the nature of the house construction and the poor external drainage conditions there is clearly the potential of ongoing scour of the embankment, and we consider that the construction of the proposed retaining wall appears to be a wise precaution. … It does not appear at this stage that the house has been structurally damaged by the effects of the surface water ingress, however the balance of the unretained bank remains susceptible to scouring damage and therefore to possible resultant footing instability.” 15. SCE’s report was dated 12 October 2012 and contained the following of relevance: “ Observations The nature of the slope is significant and towards the parklands located to the rear right hand (South-East) corner of the site. The drainage on site is adequate to the right and poor to the left. At the time of the inspection a section of the boulder retaining wall had failed resulting in debris and boulders in close proximity to the external face of the dwelling. The primary water source appears to be from the rear left property. Substantial erosion and scouring of the earth bank material around the chain wire fence along the rear boundary. An overland flow open drain or similar was in place on the adjoining property above this fence line at the time of the inspection. … Conclusion The failure of the retaining wall and resultant water damage to the dwelling is likely to a combination of factors which include:  Numerous storm events over years effecting the left face of the dwelling.  The overland stormwater which has been directed to the dwelling and scoured the earth batter over the retaining walls.  The channel on the adjoining property directing excess stormwater into the site.  Inadequate retaining wall design and installation. Case No: 272998 Determination Page 5 of 6 The statement was made by [W] insurance that the erosion has been the result of “deterioration, expansion and earth movement which are exclusions under the Policy” rather than an “insurable storm event”. It should be verified within the insurance policy as o these condition being an implied or explicit condition of the policy.”(sic) 16. MK’s report was dated 25 August 2009 and contained the following of relevance: “Upon our inspection we have noted that the soil surrounding the footings to this elevation is eroding away from the footings and collapsing into the lower level exterior wall of the dwelling. This is due to the defective design and construction of the dwelling as the soil has been cut to accommodate for the dwelling to be constructed into the land as it is a very steep block however no means of retaining the soil or making a rainwater run off course has been put in place to divert rainwater away from the subflo or area or footings.” 17. Upon reviewing all of the available expert evidence, it is clear they are consistent in a number of relevant factors. In particular, they all acknowledge that there was inadequate drainage to this area of the property. Although the Applicants have submitted that the volume of rainfall in May 2008 was such that no amount of drainage or retaining wall would have been able to cope, this is not corroborated by any of the experts. 18. For instance, none of the experts state that the drainage measures installed on the property previously were adequate and/or compromised as a result of the storm in May 2008. Instead, they all expressly acknowledge there is inadequate drainage to this area of the property which requires to be redressed. In particul ar, according to the Applicants’ own engineer (SCE), one of the factors he accepted as causing the failure of the previous retaining wall was “inadequate retaining wall design and installation”. 19. In addition, the costs sought by the Applicants regarding the construction of the retaining wall, which includes an agricultural pipe, is consistent with the experts’ recommendation that this is a necessary measure to protect the property from potential structural damage. 20. Accordingly, based on the available evidence , I accept the FSP’s position that the costs being sought by the Applicants is with respect to a modification to the site that constitutes an upgrade. This in particular is corroborated by the fact that the costs being sought by the Applicants are not to repair or replace any existing structure. 21. Although I accept that these works appear to be both necessary and reasonable, it is not a loss covered by the policy. This is mainly due to the fact that the basis for constructing the structure is to rectify inadequate drainage measures that existed at the property throughout the Applicants’ ownership as opposed to repairing or replacing a structure that suffered loss or damage as a result of an insured event. 22. Further and in the alternative, even if I accept the costs were necessary to replace the previous retaining wall that failed, the claim would still not be payable as damage to a retaining wall caused by storm is specifically not covered by the policy. Case No: 272998 Determination Page 6 of 6 23. As a result, I am not satisfied the Applicants’ claim is payable under the terms and conditions of the policy. ” 6. I agree with the Case Manager’ s reasons and with his recommended outcome. 7. I note that the Case Manager set out in detail the essence of the Applicants ’ expert report and in particular, I refer to the report by “ SCE ” quoted in paragraph 15 of the Case Manager’s reasons. 8. In deciding this matter, I am particularly influenced by the aetiology of the storm events referred to in support of the application. The first of those events occurred in May 2008 with subsequent future soil erosion events caused by later storms. 9. In their further submission dated 11 March 2013, the Applicants state that the claim is confined to damages to their property, apparently including the retaining wall, and not for a new levee retaining wall. 10. I note that the Applicants ’ expert (SCE) accepted the failure of the original retaining wall was caused by “inadequate retaining wall design and insulation”. 11. I agree with the Case Manager’s reasoning and with his recommended outcome. I particularly note that the costs that were necessary to replace the original retaining wall are excluded under the policy because damage to a retaining wall caused by a storm is excluded by the policy. 12. Further, and significantly, the policy excludes “storm dama ge in the nature of erosion or any earth movement”. 13. Whilst I empathise with the Applicants in their predicament, I am satisfied that the Applicants’ claim is not covered under the terms and conditions of the policy. Determination 14. The FSP is entitled to deny the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.