Text of the determination
Case No: 271600 Determination Page 1 of 17
Case number: 271600
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim Amount/Quality of Repairs
29 May 2013
Background
1. The Applicant (and her husband co-insured) held a landlord insurance policy
with the Financial Services Provider (FSP) providing cover for a rental
location comprising of three units. The policy provided a building sum
insured of $325,000, a contents sum insured of $15,000 and a rent default
sum insured of $3,000. An excess of $300 applies to each claim for building
and/or contents and an excess of 7 days for rent default.
2. On 3 February 2011 the insured property was damaged by Cyclone Yasi and
the Applicant lodged a claim with the FSP for the damage sustained.
Quotations for repairs were obtained by the FSP and the Applicant and the
FSP authorised repairs to the building to its appointed builder, PJ.
3. The repairs undertaken by PJ were deemed to be inadequate and
incomplete and subsequently further inspections of the property were
conducted by the FSP‟s appointed experts.
4. The FSP has attempted to settle the claim by way of a cash settlement
however the settlement offer has been rejected by the Applicant for a
number of reasons.
5. The Applicant complains about the delays in handling the claim caused by
the FSP and its appointed experts and disputes the settlement being offered.
Summary of Applicant’s position
6. The Applicant says there were delays experienced throughout the claims
handling process.
7. The roof repairs authorised by the FSP were completed to a sub-standard
level which was confirmed by an expert appointed by the FSP after she
lodged a complaint about the standard of repairs.
8. As a result of the sub-standard roof repairs, further damage has occurred at
the property and this additional damage needs to also be attended to.
Determination
Case No: 271600 Determination Page 2 of 17
9. The FSP has insisted she sign releases to cash settle her for the roof repairs
and other repairs however she expects the FSP to arrange the replacement
or repairs to the roof given the FSP authorised the original repairs.
10. There were issues and delays in settling the contents aspect of her claim.
11. The FSP has not paid any loss of rent payments to date despite the
Applicant having provided all information she can to support her loss of rent
claim.
12. The Applicant says she wants the roof repaired and a settlement for other
building repairs to reflect the additional damage and any increase in cost.
She also seeks a settlement for her loss of rent claim.
Summary of FSP’s position
13. The FSP says that it did not delay any aspect of the claim during its handling
process. It says that the Applicant caused numerous delays in failing to keep
or arrange appointments with various experts and her failure to accept offers
made to her in settlement of the various aspects of her claim.
14. The FSP acknowledges that the repairs authorised to the roof of the
Applicant‟s property were sub -standard however the Applicant delayed
sending through quotations for the rectification work and then failed to allow
its builder access to the property to provide an alternative quotation.
15. Settlement offers for the building repairs, roof repairs and other aspects of
the claim have all been made to the Applicant however the Applicant has
failed to sign releases for the building and roof repairs to allow settlement to
take place.
16. The Applicant has failed to supply sufficient documentation in support of her
loss of rent claim and therefore, the FSP is unable to consider this aspect of
the claim until that documentation has been received.
17. The FSP has been in a position to settle the building aspect of the claim
since 7 October 2011 and the roof repairs since May 2011. It has been
attempting to assist the Applicant with her claim since it was made in
February 2011.
18. The FSP relies on the following [policy/contract provisions etc]:
“ How we will settle your claim
There are two methods of settling your claim.
The method for settling Building claims is selected by you and is shown on the
Schedule.
...
Method of settlement
Section 1 – Building
Case No: 271600 Determination Page 3 of 17
Reinstatement or Replacement Value
We will pay the Cost of rebuilding or repairing any damaged part of your
Building to the same condition as when it was new. ”
(Page 8)
“ Loss of rent
If your Building is damaged by an Occurrence you are covered for under
Section 1 and the Building cannot be lived in, we will pay for your loss of Rent
for the period of time required to reinstate or repair your Building, for up to 12
months from the date of damage, or up to 20% of the Sum Insured on the
Building, whichever is the lesser.
Payment for Loss of Rent is in addition to the Sum Insured.
If the Building is unoccupied at the time of Occurrence, we will not pay for loss
of Rent.”
(Page 10)
“ When we may reduce or refuse to pay a claim
We may reduce or refuse to pay a claim if:
1. ...
2. you fail to provide assistance, information or proof in support your
claim; ...”
(Page 18)
Issues
19. Whether the FSP has correctly offered settlement for the roof repairs.
20. Whether the FSP has correctly offered settlement for the building repairs, in
addition to the roof repairs.
21. Whether the Applicant is entitled to a loss of rent payment.
22. Whether the FSP caused any undue delays in the claims handling process.
23. Whether the Applicant is entitled to compensation.
Reasons for decision
24. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
25. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in insurance industry matters and a
representative with extensive experience in consumer claims.
Case No: 271600 Determination Page 4 of 17
26. The Panel is satisfied there has been a full exchange of material between
the parties and that each party has had the opportunity of clarifying the
issues that arise from the material.
27. It is common knowledge that Cyclone Yasi crossed the coast of Queensland,
approximately 138km south of Cairns, at approximately 1.00am on 3
February 2011. The adverse weather associated with the cyclone and the
resultant damage was widespread.
28. There is agreement between the parties in this instance that the Applicant‟s
property was in the path of the cyclone and that it suffered cyclone damage.
This dispute relates to the damaged roof at the Applicant‟s property,
subsequent repairs undertaken by the FSP‟s appointed builder, PJ, the
settlement offered by the FSP, an outstanding claim for loss of rent and the
complaint by the Applicant regarding unacceptable delays in the processing
of the claim.
29. The Panel notes that the FSP has now settled the outstanding contents
claim the Applicant had and therefore, the Applicant‟s contents claim will not
be discussed in this Determination.
Timeline
30. To assist in reviewing the issues of this dispute, the Panel has confirmed the
following time line of events, specifically relating to the roof repairs, based on
information contained within the FSP‟s Notice of Response (NOR) and
associated material:
a) Date of event – 3 February 2011
b) FSP appoints an assessor, CR – 12 February 2011
c) CR attends Applicant‟s property – 16 March 2011
d) CR provides report to FSP – 28 March 2011
e) Applicant was requested to obtain quotations for roof repairs
f) Applicant provides quotations for roof repairs – one is undated, one is
dated 17 March 2011
g) Repairs to roof repairer, PJ, authorised by FSP – 3 May 2011
h) Applicant notifies CR that she wishes to discuss issues regarding
building (not clear if this relates to roof repairs or quotations for other
building repairs) by telephone – 10 June 2011
i) Applicant informs CR that roof repairs have not been completed
adequately or up to standard by telephone – 21 June 2011
j) Engineer, IC, appointed to inspect roof and investigate Applicant‟s
complaint – 27 June 2011
k) IC attends to inspect property – 26 August 2001
l) IC report to FSP confirming poor standard of roof repairs and providing
a Scope of Works (SOW) to rectify – 6 September 2011
Case No: 271600 Determination Page 5 of 17
m) SOW sent to Applicant requesting Applicant to obtain two written
quotations for rectification works – 8 September 2011
n) Applicant advises FSP via CR (email) that she cannot obtain
quotations as no builder wants to undertake rectification works, and
requests FSP to arrange quotations – 3 October 2011
o) Applicant is offered cash settlement of $33,000 via a release for roof
repairs based on PJ‟s original quotation for repairs of $33,300 – no
indication as to when this offer was originally made
p) Applicant obtains quotation for roof rectification – 23 January 2012
q) Applicant provides quotation to FSP and is ack nowledged as being
received by FSP – 9 March 2012
r) CR acknowledges receiving advice from FSP to obtain a second
quotation for roof repairs in its report dated 17 April 2012 – no advice
as to when request was made by FSP or builder appointed to quote
s) CR provides copy of quotation from its appointed builder, JL, dated 13
April 2012, to FSP – 17 April 2012
t) NOR sent to FOS by FSP advises second quotation has not been
received as Applicant has not provided second quotation or allowed
access to property to allow a second quotation to be provided – 2 May
2012
31. During the course of the claim the Applicant supplied quotations for building
works, in addition to roof repairs, which the Applicant contends could not be
completed until the roof repairs had been finalised. This has not been
disputed by the FSP.
32. The Applicant also says that due to the failed roof repairs and the FSP‟s
failure to rectify the repairs, additional damage has been caused to the
building which may incur additional costs.
33. The Panel is of the opinion that as the building repairs referred to involve
internal repairs, it would be reasonable to assume that these repairs could
not be completed until the roof repairs had been finalised.
34. The Panel notes that the timeline provided above is not supported by the
Applicant on all issues.
Method of Settlement
35. The FSP says that in accordance with the terms and conditions of the policy,
it chooses the option of settlement, whether repairs are authorised or a cash
settlement made. It relies on the following wording of its PDS:
“ Method of settlement
Section 1 – Building
...
We will at our option either:
Case No: 271600 Determination Page 6 of 17
1. pay you the Indemnity Value of the damaged part of the Building;
or
2. repair or replace the damaged part of the Building.”
(Page 8)
36. The Panel has reviewed the PDS and relevant section quoted by the FSP
and notes that the FSP has failed to recognise its own policy provisions.
Namely, on the same page (page 8) of the wording, it states:
“ How we will settle your claim
There are two methods of setting your claim.
The method for settling Building claims is selected by you and is shown on the
Schedule.”
37. The Panel notes the Applicant‟s Schedule shows she has a “Replacement
Value” policy. Page 8 of the PDS continues:
“ Method of settlement
Section 1 – Building
Reinstatement or Replacement Value
We will pay the Cost of rebuilding or repairing any damaged part of your
Building to the same condition as when it was new.
...
Indemnity Value
We will at our option either:
1. pay you the Indemnity Value of the damaged part of the Building;
or
2. repair or replace the damaged part of the Building.”
38. The FSP has quite clearly misquoted its own PDS and used a condition
detailed under the Indemnity Value settlement method, when attempting to
settle the Applicant‟s claim under her Replacement Value po licy.
39. It is the opinion of the Panel that the FSP therefore does not have the option
of choosing the method of settlement, nor does it have the option of cash
settling any aspect of the Applicant‟s claim for the indemnity value of the
repairs/replacement. Any settlement, whether authorising repairs or cash
settling the Applicant, must be to a value of repairs/replacement to place the
Applicant‟s property into a condition as it was when it was new.
Roof Repairs
40. The Applicant provided two quotations for repairs to the roof and the FSP
authorised repairs based on one of these quotations to PJ on 3 May 2011.
41. On 17 May 2011 the Applicant advised that she did not wish to have PJ
complete the work however on the same day, changed her mind and agreed
to allow PJ to start repairs.
Case No: 271600 Determination Page 7 of 17
42. The Applicant says PJ advised her repairs would begin on 23 May 2011 and
would take seven days to complete, meaning that repairs would be
completed by 31 May 2011. She says she made several complaints to the
FSP after repairs were started by PJ, as repairs were not completed within
seven days; PJ did not return to the site for approximately five weeks after
this time, he left the site untidy and with items lying on the ground, as well as
on the roof, causing some items to rust and that the repairs he had done
were not acceptable.
43. On the advice of the Applicant‟s complaint, the FSP says it appointed an
Engineer, IC, to attend the Applicant‟s property and provide a report on the
quality and standard of repairs. It says the Applicant failed to make and keep
appointments with IC which caused a delay in IC‟s inspection and
subsequent report. In any event, IC‟s report confirmed that the repairs
completed by PJ were sub-standard and required rectification.
44. IC‟s report, in part says:
“ 3.3 INCOMPLETE WORKS
Repair works required to bring the house back to its pre-damaged
condition:
3.3.1. Painting - ...
4. CONCLUSION AND SUMMARY OF REPAIR
We are of the opinion that the roof sheeting, flashings, downpipe
spreaders, roof frame repairs, roof frame tie down and gutter
installation have all been carried out to a standard which is below that
of industry standard and in our opinion the workmanship presents as
defective building work.
We believe for the purposes of the Queensland Building Services
Authority Act (BSA), the defective works present as both category one
and category two defects in accordance with their policy.
In our opinion if the matter were to be put to the BSA that the time
frames for both category one and two defects would be deemed „withi n
time‟ for BSA to order rectification of the works.
Generally we are of the opinion that all flashings, cappings, and
Dektites be removed and replaced. Eaves gutters will require re-
adjustment to achieve suitable falls.
If an engineer deems that tie downs are inadequate, then we believe
all roof sheeting will also enquire removal to facilitate repair of those
components. At this stage we are of the opinion that will be
necessary, as such this will reflect in our scope of works.”
45. The FSP arranged for IC to prepare a SOW and this was sent to the
Applicant on 8 September 2011 with a request that she obtain two
quotations for the rectification work.
46. The Applicant did not supply quotations and accordingly, the FSP offered the
Applicant an amount of $33,000 ba sed on PJ‟s original quote of $33,300,
less the $300 policy excess. A review of the settlements made to the
Case No: 271600 Determination Page 8 of 17
Applicant indicate that a $300 excess may have already been deducted from
the Applicant‟s contents claim.
47. The Applicant emailed the FSP on 3 October 2011 to explain that she was
having difficulty in having a builder attend her property to provide a quotation
and requested that the FSP or IC attend to arranging quotations given that
the original repairs had been authorised by the FSP. The FSP advised t he
Applicant that it would cash settle her for the roof repairs based on the
original quotation supplied by PJ.
48. The FSP‟s file notes indicate that this decision was made “because insured
stated numerous times could not obtain quotes we decided to settle o n
original qte $33k”. This tends to support the Applicant‟s advice, despite the
FSP‟s lack of file notes to indicate that the Applicant had contacted it on
“numerous” occasions to advise of the difficulties she was having.
49. The Panel must note at this point that IC had provided his opinion and
report, on what was required to bring the property back to its pre-loss
condition. This is not in accordance with the terms and conditions of the
policy and the Panel is of the opinion that the SOW must be reviewed to
ensure that the works required will bring the property up to a condition as it
was, when new.
50. In addition, the FSP‟s file notes and emails to the Applicant clearly indicate
that it is only responsible for rectifying the repairs completed by PJ and to
repair the cyclone damage to the roof. It clearly indicates to the Applicant
that it is not responsible for any additional damage to other property that PJ
may have caused whilst completing the works.
51. The Panel disagrees on this point and notes that as the FSP appointed PJ to
effect repairs to the Applicant‟s property, it assumes responsibility for the
actions of PJ and therefore is responsible for ensuring that in addition to
rectification of the original roof repairs, any other damage caused by PJ is
also rectified by the new roof repairer.
Building Repairs
52. The FSP has accepted a quotation for other building repairs provided to it by
the Applicant. It offered settlement to the Applicant based on this quotation
and the Panel is of the opinion that the offer is reasonable.
53. The Applicant says she did not want to sign the release form for these
monies as she could not have the work completed until the roof repairs had
been rectified.
54. The Panel is of the opinion that this is a reasonable approach, given that if
the internal building components are repaired prior to the roof being
repaired, and further water entry or other damage occurs, the internal
building repairs would be quite pointless.
Case No: 271600 Determination Page 9 of 17
55. The Panel has reviewed the FSP‟s PDS and can find nothing precluding it
from paying the sum of money offered to the Applicant without a signed
release. It is the opinion of the Panel that the FSP should have paid these
monies to the Applicant.
56. The FSP provided a release which clearly states that the payment of the
amount offered a nd the Applicant‟s agreement to accept same means that
she would have “... no further claim against [the FSP] in respect of [the]
occurrence .” In light of the Applicant‟s concerns, the Panel is of the opinion
that the FSP‟s actions in insisting the Applica nt sign the release before
releasing payment, is not fair in all the circumstances.
Loss of Rent
57. The FSP says that the Applicant has been requested to supply copies of
current bond documents, lease agreements and rental ledgers to confirm
that each of the insured units at the property were occupied at the time of
loss. It says further that occupancy needs to be confirmed as no cover exists
for loss of rent if the relevant unit or units were unoccupied at the time of the
event.
58. In its letter to the Applicant in September 2011 it explained to the Applicant
that there was a note contained within the policy schedule that suggested
Unit 1 of the property was being occupied by the Applicant. The Panel has
reviewed the policy schedule provided and can see no such note. As such,
the Panel does not consider this to be a consideration when calculating a
loss of rent claim.
59. The Panel accepts that the FSP is entitled to seek clarification of amounts
claimed and occupancy of the units pursuant to the terms and conditions of
the policy. It is noted however that the Applicant has provided copies of
tenancy agreements for all three units, a letter from a real estate agent for
one unit (confirming occupancy by the tenant at the time of the event, his
departure date due to cyclone damage to the property and his weekly rent
payment) and a copy of a ledger for another unit showing rent payments
made by the tenant on a regular basis.
60. The third unit was tenanted by the Applicant‟s daughter and as such, no
records of rent payments have been able to be produced as the Applicant
says that rent was paid in cash to her, by her daughter.
61. The Panel is somewhat confused over the FSP‟s suggestion in its initial
NOR that this information had not been supplied. From the Panel‟s review of
the material, this information appears to have been supplied sometime
around November 2011, and some of the information had been provided in
September 2011.
62. The Panel is therefore satisfied that the Applicant supplied all information
and documentation that was available to her in support of her loss of rent
claim.
Case No: 271600 Determination Page 10 of 17
63. The Panel is of the opinion that the information she provided was more than
adequate to enable the FSP to settle this aspect of the claim, at the very
least partially from the time of loss to the time it received the documentation.
Any further loss of rent payment could and ought to have been paid to the
Applicant as repairs were undertaken.
64. On this issue, the Panel notes the General Conditions of the FSP‟s PDS.
The relevant section reads:
“ Progress payments
We will not unreasonably withhold progress payments. We will pay progress
payments on claims at intervals to be approved by us following receipt of our
interim report from our loss adjuster or representative.”
65. The FSP considered that the information provided by the Applicant to
support her loss of rent claim was not adequate. At one point, after receiving
the documentation, it informed the Applicant that she had failed to provide
any documentation and this is reiterated in its NOR.
66. The Panel is of the opinion that the documentation provided by the Applicant
for at least two of the units, was sufficient, and as such, a progress payment
for loss of rent should have been paid. To withhold such a payment would be
considered unfair in the circumstances.
67. The FSP says there is a lack of evidence to confirm the amount of rent paid
by one tenant, J, due to there being different amounts recorded on the rent
ledger as being paid. It also suggests that the lease agreement is not current
as it was from 15 September 2009 to 14 March 2010.
68. The Panel has reviewed this rent ledger and is satisfied that the amounts
appear to generally be $250 per week or payments of multiples of $250.
Based on the Panel‟s calculations, it appears J may have been behind in her
rental payments however, this does not exclude the Applicant from claiming
loss of rent.
69. Given that there is sufficient evidence to show that a second tenant‟s weekly
rent is $250 and that the Applicant has verbally advised that her daughter
was paying her $250 a week for rent, the Panel is of the opinion that on the
balance of probabilities, J was also paying $250 per week.
70. The Applicant has advised that J was on an ongoing lease and did not sign a
new agreement. The Panel is satisfied that situations like this exist where
tenants are not required to have an agreement in place for an ongoing
arrangement. The rental ledger shows that J was paying rent at the property,
with her last payment being on 28 January 2011, just a few days prior to the
cyclone event.
71. The Applic ant has not supplied any documentation to support her daughter‟s
rent payments. The Applicant says her daughter paid her cash and therefore
no records were kept. The Panel accepts that this is not unreasonable in
situations where family members have a tena nt/landlord relationship.
Case No: 271600 Determination Page 11 of 17
However, the onus still rests with the Applicant to demonstrate that she was
receiving rent from her daughter.
72. The Panel notes that the FOS Case Manager requested copies of bank
statements of the Applicant‟s daughter to show the w ithdrawal of money
from her account on a regular basis to demonstrate that some of her money
could have been paid to the Applicant for rent, as advised by the Applicant.
However to date, the Applicant has not supplied any further information in
this regard.
Claim Handling Delays
73. Having reviewed all of the material provided by both parties the Panel is of
the opinion that delays were encountered in the claims process for a number
of reasons.
74. The FSP has suggested that the majority of delays have been caused by the
Applicant‟s consistent calls and emails requesting updates on the claim, the
Applicant‟s failure to keep or make appointments with builders and experts
and the Applicant‟s failure to acknowledge email communications either in a
timely manner or at all.
75. The Applicant says that the FSP has contributed to these delays by failing to
acknowledge, via CR, that she had made complaints regarding the quality of
the roof repairs. She also says that the FSP‟s engineer, IC, has contributed
to the delays as both IC and the Applicant were both having difficulty in
arranging a mutually agreeable time to meet on site due to both parties
being on leave or unavailable at the “right” time.
76. The Panel accepts that there have been delays caused by all parties
involved in t his matter. However what is concerning is the FSP‟s failure to
take a more pro-active approach in handling the roof repair aspect of the
claim.
77. The FSP in its NOR has suggested that the Applicant contacted CR on 17
May 2011 advising that she no longer wished to use PJ to do the roof repairs
and that it was not until 10 June 2011 that she contacted CR again to advise
she was happy with PJ to proceed. This is in fact incorrect. CR‟s
contemporaneous file notes indicate that the Applicant called CR twice on 17
May 2011. Firstly she advised she no longer wished PJ to proceed and in
her second call, less than 30 minutes later, she advised she did wish PJ to
proceed.
78. On 10 June 2011 CR‟s contemporaneous notes show an email sent to CR
by the Applicant indicating she had issues regarding the building which she
wished to discuss with CR. These contemporaneous file notes tend to
support the Applicant‟s advice that PJ informed her he would be on site to
start repairs by 23 May 2011 and that work would be finished in seve n days.
79. The FSP further says that it did not become aware of issues with the roof
repairs or the Applicant‟s complaint regarding the quality of repairs until 21
Case No: 271600 Determination Page 12 of 17
June 2011. The FSP says the Applicant complained about repairs at this
time despite the fact repairs were not completed.
80. The Panel is confused over this point. The Applicant has clearly indicated
that PJ told her repairs would be completed in seven days and this
information has not been disputed by the FSP. This would effectively mean
that repairs should have been completed by 31 May 2011. However, the
FSP is acknowledging that as of 21 June 2011, when the Applicant
contacted CR to complain about the roof repairs and almost a month after
repairs should have been completed, repairs had still not been completed.
This is evidenced by CR‟s contemporaneo us notes which read:
“[Applicant‟s daughter] called – she complained at length over the roof repairs
– she seems to think that workmanship is not up to standard – she has taken
pictures of same – I tried to advise that works are not complete – advised we
h ave had other claims with this roofer and have had no complaints.”
81. The FSP has suggested that the Applicant refused PJ access to the site to
complete repairs. However there is no evidence to support this in the form of
contemporaneous notes or emails etc. The Panel is therefore satisfied that
the FSP has failed to act in a timely manner in dealing with the Applicant‟s
concerns regarding the quality of the roof repairs.
82. The FSP has further suggested that the Applicant failed to keep
appointments with the engineer appointed by the FSP, IC, or failed to
contact IC to arrange an appointed. The Applicant on this point says that due
to availability problems for both herself and IC, a suitable appointment could
not be arranged until August 2011.
83. The Panel is of the opinion, that on the balance of probabilities, the Applicant
has made several attempts to complain about the quality of the roof repairs
up to and including 21 June 2011. Based on the material before the Panel,
there is no evidence to support the FSP‟s advice that the Applicant has failed
to keep appointments. The Panel is therefore satisfied that delays in IC‟s
attendance at the Applicant‟s property was due to availability issues on the
part of IC and the Applicant.
84. The FSP has suggested that further delays were experienced due to the
Applicant failing to respond to countless offers of settlement in relation to
roof repairs and building repairs. It says it sent release forms for the
Applicant to sign for both aspects and that it has been willing to settle the
building repairs since 7 October 2011. It says it has been willing to settle the
roof repairs aspect of the claim since May 2012.
85. The Panel‟s opinions on the building repairs and roof repairs have been
detailed earlier in this Determination and there is no need to repeat that
information.
86. The FSP has insisted that the Applicant must sign a release form in order to
obtain monies for the building and roof repairs. These releases contain the
phrase:
Case No: 271600 Determination Page 13 of 17
“... and on payment of the above WE shall have no furt her claim against [the
FSP] in respect of this occurrence.”
87. The Applicant‟s reluctance or refusal to sign these releases for whatever
reason does not preclude the FSP from making payment. There is no
provision within the FSP‟s PDS that requires the Applica nt to sign such a
release. There is also credence in the Applicant‟s advice that until the roof
repairs were completed satisfactorily, building repairs could not commence.
Why then should or would she accept the offer made for building repairs until
she was satisfied that the roof repairs had been satisfactorily resolved?
88. The Panel is of the opinion that the Applicant has therefore not caused any
delays in accepting the sums offered. Rather she had lodged a complaint
with the FSP and eventually FOS which she has yet to have resolved.
89. The FSP has also relied upon a Statutory Declaration from the handler of the
Applicant‟s claim who declares that the Applicant and her daughter (as the
Applicant‟s representative regarding this claim) contacted her on numerous
occasions and for lengthy periods of time to seek updates on her claim and
to query various aspects of her claim. She also says that numerous emails
were also received from the Applicant and her daughter and that the
Applicant had two other claims at different properties for the same event.
90. The Panel is of the opinion that given the Applicant was not living in the
same State as the damaged property that this has certainly contributed to
frustrations and delays from all parties.
Conclusion
Roof Repairs
91. There is no dispute that the repairs completed by PJ were sub-standard. As
the FSP has taken the responsibility of authorising repairs to this builder, it
must also take responsibility for any problems that may occur during that
repair process.
92. The Panel is of the opinion that the FSP is responsible for authorising the
rectification repairs to the roof and arranging/authorising any other repairs
required to the Applicant‟s property which has been damaged by PJ during
the course of those repairs.
Building Repairs
93. The Panel is satisfied that the amount offered for settlement by the FSP for
the building repairs is reasonable. However, the FSP should have already
paid the amount to the Applicant. Given the FSP should have also
authorised the roof rectification repairs and did not; it follows that the FSP
must also be responsible for any additional costs for the building repairs
which may now be present. These repairs would relate to increases in costs
and/or additional damage incurred to the property due to the roof repairs
having not been completed.
Case No: 271600 Determination Page 14 of 17
Loss of Rent
94. The Applicant has supplied information to the FSP to settle this aspect of the
claim with the exception of monies paid by the Applicant‟s daughter, who has
been confirmed as a tenant in the form of the tenancy agreement. The Panel
is satisfied that this documentation is sufficient to allow the FSP to settle as
least part of the loss of rent claim. The Panel is of the opinion therefore that
the FSP should have settled part of the loss of rent claim from the time it
received the documentation, being 6 September 2011.
95. The Panel is of the opinion that the FSP is to settle the loss of rent claim
from the date of loss, being 3 February 2011, until such time that all repairs
have been completed at the Applicant‟s proper ty, regardless of policy
limitations. This is based on the Panel‟s opinion that the offers made by the
FSP to settle the building and roof aspects of the claim, and the methods
used to offer those settlements, have not been fair in all the circumstances.
Claim Handling Delays
96. FOS acknowledges and accepts that during times of catastrophic weather
events the resources of any FSP are stretched to cope with the unusually
high influx of new claims and the additional demands of policyholders who
have been displaced from their usual residences. The cyclone event the
subject of the Applicant‟s claim certainly falls into this category. It is therefore
reasonable to accept that some delays would occur during the claims
handling process.
97. The Panel suggests that some delays in this instance have been caused by
the FSP and this in turn has caused a degree of stress and anxiety for the
Applicant who has, on more than one occasion, expressed that she has felt
the FSP has ignored her complaints.
98. The Panel is of the opinion that the FSP‟s actions in insisting that the
Applicant obtain quotations for the rectification of the poorly repaired roof
which it had authorised repairs for originally, and that the Applicant would
have to address the issue of damage caused by PJ directly with PJ, is far
from fair to the Applicant.
99. It is quite obvious from the material that the actions of the FSP on these
aspects has certainly caused a great deal of concern and stress to the
Applicant and has caused further unnecessary delays which could have
been avoided had the FSP authorised the necessary repairs and any other
repairs for damage caused by PJ whilst he was on site.
Compensation
100. The Panel has given consideration to another aspect of the matter which is
of concern.
FOS Terms of Reference
“ 9.3 Other compensation
Case No: 271600 Determination Page 15 of 17
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential
financial loss or damage up to a maximum amount of $3,000 per claim made
in the Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial loss
but only where:
i. an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant‟s expectation of
enjoyment or peace of mind has occurred; or
ii. in the case of a Dispute pertaining to an individual‟s privacy rights -
injury has occurred to the Applicant‟s feelings or humiliation has been
suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be $3,000 per
claim made in the Dispute.”
101. The Panel has raised the relevance of paragraph 9.3(b) with the FSP. In a
detailed submission the FSP argued that no award should be made to the
Applicant as the Applicant has not satisfied the requirement of paragraph
9.3(b)(i). It says that the FSP has not delayed the finalising of the Applicant‟s
claim.
102. The Panel does not accept the FSP‟s submission, given the facts as detailed
above, regarding its handling of this claim. The Panel accepts that some
delays were inevitable given the magnitude of the cyclone event and the
impact this would have had on the FSP‟s resources.
103. However the Panel, for the reasons detailed above, is of the opinion that the
FSP was in a position to make some payments to the Applicant and failed to
do so as the Applicant refused to sign release forms. The Panel, as
discussed earlier, can find no requirement within the FSP‟s PDS to suggest
that any settlement is dependent on a signed release being provided.
104. In addition, the FSP failed to arrange quotations for the rectification of its
authorised roof repairer‟s work and also failed to authorise these rectification
repairs once quotations had been supplied.
105. The Panel is t herefore of the view that the FSP‟s conduct of the matter has
been such as to cause a good deal of physical inconvenience and time taken
to resolve the matter, thus having an impact upon the Applicant‟s
expectation of enjoyment and peace of mind.
106. The Panel need not set out the facts again. In the Panel‟s opinion the FSP
has contributed to the Applicant‟s stress due to its actions, after a
catastrophic weather event.
107. As there is no exclusion in the FSP‟s PDS precluding the Panel from
awarding a compensation payment, the Panel therefore considers that the
FSP should further compensate the Applicant by payment of the sum of
$1,500 under this heading.
Case No: 271600 Determination Page 16 of 17
Determination
108. On the basis of the available information the Panel determines that:
The Applicant‟s nominated bui lder, M, is to provide current costings for
its previously submitted quotation for building repairs taking into
account any changes to prices and any additional damage caused by
the failed roof repairs;
The FSP is to settle the building aspect of the claim based on M‟s
revised quotation;
The FSP is to have IC prepare a SOW that provides repairs to the
Applicant‟s roof up to a condition as to when it was new;
RB is to provide a revised quotation on the new SOW (if any changes
are made) and to show any changes in prices;
Repairs are to be authorised to RB for the roof repairs and rectification
work required to reinstate the Applicant‟s roof to a condition as it was
when new;
Should any additional or further claim related repairs or repairs required
due to damage caused by PJ become apparent during the repair
process, RB is to provide the FSP with a quotation for this work and
repairs are to be authorised by the FSP within seven days of receiving
the revised quotation;
The Applicant is to authorise repairs to M for the remaining building
items within 14 days of the satisfactory completion of the roof repairs
and the Applicant will be responsible for the monitoring of these repairs
and payment of M‟s account for same;
The Applicant is to provide the FSP a copy of the final invoice
submitted by M confirming the date repairs were completed and the
date the invoice was paid within 7 days of repairs being completed;
The FSP is to pay loss of rent to the Applicant from 3 February 2011 for
two units where rent amounts have already been quantified to the
satisfaction of the Panel, as detailed above, up to the date that repairs
are authorised to RB;
The FSP is to pay monthly loss of rent payments to the Applicant from
the date roof repairs are authorised until completio n of all repairs for
two units only;
The Applicant is to provide the FSP with copies of her daughter‟s bank
statements showing regular withdrawals of monies from her account for
from 1 January 2011 until the date of loss, in support of her advice that
she was paying cash for the rent to her parents from the start of the
lease date, being 12 January 2011;
The FSP is to pay to the Applicant, loss of rent for the unit leased by
her daughter from 3 February 2011 until receipt of the Applicant‟s
daughter‟s bank statements;
Case No: 271600 Determination Page 17 of 17
The FSP is to pay monthly loss of rent payments to the Applicant from
this date until completion of all repairs for the unit previously leased by
her daughter;
The FSP will not be obliged to pay any further loss of rent for any of the
units from the date of completion of all repairs, which will be confirmed
by the Applicant as detailed above.
109. In addition, the FSP is to pay interest on the loss of rent aspect of the claim
from 6 September 2011 until roof repairs are authorised, for two units only.
The applicable interest rate is calculated pursuant to Section 57 of the
Insurance Contracts Act 1984 (Cth) in the sum of 6.75% given the Applicant
would have had access to these settlement amounts at the time of the
original settlement of this aspect of the claim.
110. Interest is not payable on the loss of rent payable from the date roof repairs
are authorised until repairs are completed, on the unit tenanted by the
Applicant‟s daughter or on any additional amount quoted by M to finalise the
building repairs.
111. The FSP is to make payment to the Applicant within 14 days of receipt of this
Determination for:
Loss of rent on two units;
Interest on loss of rent; and
Interest on M‟s original quotation.
112. The FSP is to arrange for a revised SOW to be forwarded to RB within 7
days of receipt of this Determination and is to authorise roof repairs to RB
within 14 days of receipt of the amended quotation (or confirmation that no
amendment will be required).
113. Pursuant to paragraph 9.3(b)(i) of the Terms of Reference, the Panel also
determines that the FSP should pay to the Applicant the sum of $1,500. This
amount is to be paid to the Applicant within 14 days of receipt of this
Determination.