Home / Financial Firm (Unknown - Insurer) / Determination 271600

Determination 271600

Cyclone roof and building repair settlement; loss of rent; handling delays

FirmFinancial Firm (Unknown - Insurer)
Decided2013-08-01
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded—
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

After cyclone damage, the FSP's appointed builder performed substandard roof repairs and the FSP insisted on signed releases before paying building and loss of rent amounts. AFCA ordered revised scopes, repairs authorised, loss of rent and interest paid, and $1,500 for non-financial loss.

The FSP is responsible for the defective work of the repairer it appointed, and it cannot condition undisputed payments on a signed release absent a policy requirement.

Issues

Subjects and remedies

natural disasterthird party authoritypay claimpay interestpay non financial lossreassess claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 271600 Determination Page 1 of 17 Case number: 271600 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim Amount/Quality of Repairs 29 May 2013 Background 1. The Applicant (and her husband co-insured) held a landlord insurance policy with the Financial Services Provider (FSP) providing cover for a rental location comprising of three units. The policy provided a building sum insured of $325,000, a contents sum insured of $15,000 and a rent default sum insured of $3,000. An excess of $300 applies to each claim for building and/or contents and an excess of 7 days for rent default. 2. On 3 February 2011 the insured property was damaged by Cyclone Yasi and the Applicant lodged a claim with the FSP for the damage sustained. Quotations for repairs were obtained by the FSP and the Applicant and the FSP authorised repairs to the building to its appointed builder, PJ. 3. The repairs undertaken by PJ were deemed to be inadequate and incomplete and subsequently further inspections of the property were conducted by the FSP‟s appointed experts. 4. The FSP has attempted to settle the claim by way of a cash settlement however the settlement offer has been rejected by the Applicant for a number of reasons. 5. The Applicant complains about the delays in handling the claim caused by the FSP and its appointed experts and disputes the settlement being offered. Summary of Applicant’s position 6. The Applicant says there were delays experienced throughout the claims handling process. 7. The roof repairs authorised by the FSP were completed to a sub-standard level which was confirmed by an expert appointed by the FSP after she lodged a complaint about the standard of repairs. 8. As a result of the sub-standard roof repairs, further damage has occurred at the property and this additional damage needs to also be attended to. Determination Case No: 271600 Determination Page 2 of 17 9. The FSP has insisted she sign releases to cash settle her for the roof repairs and other repairs however she expects the FSP to arrange the replacement or repairs to the roof given the FSP authorised the original repairs. 10. There were issues and delays in settling the contents aspect of her claim. 11. The FSP has not paid any loss of rent payments to date despite the Applicant having provided all information she can to support her loss of rent claim. 12. The Applicant says she wants the roof repaired and a settlement for other building repairs to reflect the additional damage and any increase in cost. She also seeks a settlement for her loss of rent claim. Summary of FSP’s position 13. The FSP says that it did not delay any aspect of the claim during its handling process. It says that the Applicant caused numerous delays in failing to keep or arrange appointments with various experts and her failure to accept offers made to her in settlement of the various aspects of her claim. 14. The FSP acknowledges that the repairs authorised to the roof of the Applicant‟s property were sub -standard however the Applicant delayed sending through quotations for the rectification work and then failed to allow its builder access to the property to provide an alternative quotation. 15. Settlement offers for the building repairs, roof repairs and other aspects of the claim have all been made to the Applicant however the Applicant has failed to sign releases for the building and roof repairs to allow settlement to take place. 16. The Applicant has failed to supply sufficient documentation in support of her loss of rent claim and therefore, the FSP is unable to consider this aspect of the claim until that documentation has been received. 17. The FSP has been in a position to settle the building aspect of the claim since 7 October 2011 and the roof repairs since May 2011. It has been attempting to assist the Applicant with her claim since it was made in February 2011. 18. The FSP relies on the following [policy/contract provisions etc]: “ How we will settle your claim There are two methods of settling your claim. The method for settling Building claims is selected by you and is shown on the Schedule. ... Method of settlement Section 1 – Building Case No: 271600 Determination Page 3 of 17 Reinstatement or Replacement Value We will pay the Cost of rebuilding or repairing any damaged part of your Building to the same condition as when it was new. ” (Page 8) “ Loss of rent If your Building is damaged by an Occurrence you are covered for under Section 1 and the Building cannot be lived in, we will pay for your loss of Rent for the period of time required to reinstate or repair your Building, for up to 12 months from the date of damage, or up to 20% of the Sum Insured on the Building, whichever is the lesser. Payment for Loss of Rent is in addition to the Sum Insured. If the Building is unoccupied at the time of Occurrence, we will not pay for loss of Rent.” (Page 10) “ When we may reduce or refuse to pay a claim We may reduce or refuse to pay a claim if: 1. ... 2. you fail to provide assistance, information or proof in support your claim; ...” (Page 18) Issues 19. Whether the FSP has correctly offered settlement for the roof repairs. 20. Whether the FSP has correctly offered settlement for the building repairs, in addition to the roof repairs. 21. Whether the Applicant is entitled to a loss of rent payment. 22. Whether the FSP caused any undue delays in the claims handling process. 23. Whether the Applicant is entitled to compensation. Reasons for decision 24. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 25. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. Case No: 271600 Determination Page 4 of 17 26. The Panel is satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. 27. It is common knowledge that Cyclone Yasi crossed the coast of Queensland, approximately 138km south of Cairns, at approximately 1.00am on 3 February 2011. The adverse weather associated with the cyclone and the resultant damage was widespread. 28. There is agreement between the parties in this instance that the Applicant‟s property was in the path of the cyclone and that it suffered cyclone damage. This dispute relates to the damaged roof at the Applicant‟s property, subsequent repairs undertaken by the FSP‟s appointed builder, PJ, the settlement offered by the FSP, an outstanding claim for loss of rent and the complaint by the Applicant regarding unacceptable delays in the processing of the claim. 29. The Panel notes that the FSP has now settled the outstanding contents claim the Applicant had and therefore, the Applicant‟s contents claim will not be discussed in this Determination. Timeline 30. To assist in reviewing the issues of this dispute, the Panel has confirmed the following time line of events, specifically relating to the roof repairs, based on information contained within the FSP‟s Notice of Response (NOR) and associated material: a) Date of event – 3 February 2011 b) FSP appoints an assessor, CR – 12 February 2011 c) CR attends Applicant‟s property – 16 March 2011 d) CR provides report to FSP – 28 March 2011 e) Applicant was requested to obtain quotations for roof repairs f) Applicant provides quotations for roof repairs – one is undated, one is dated 17 March 2011 g) Repairs to roof repairer, PJ, authorised by FSP – 3 May 2011 h) Applicant notifies CR that she wishes to discuss issues regarding building (not clear if this relates to roof repairs or quotations for other building repairs) by telephone – 10 June 2011 i) Applicant informs CR that roof repairs have not been completed adequately or up to standard by telephone – 21 June 2011 j) Engineer, IC, appointed to inspect roof and investigate Applicant‟s complaint – 27 June 2011 k) IC attends to inspect property – 26 August 2001 l) IC report to FSP confirming poor standard of roof repairs and providing a Scope of Works (SOW) to rectify – 6 September 2011 Case No: 271600 Determination Page 5 of 17 m) SOW sent to Applicant requesting Applicant to obtain two written quotations for rectification works – 8 September 2011 n) Applicant advises FSP via CR (email) that she cannot obtain quotations as no builder wants to undertake rectification works, and requests FSP to arrange quotations – 3 October 2011 o) Applicant is offered cash settlement of $33,000 via a release for roof repairs based on PJ‟s original quotation for repairs of $33,300 – no indication as to when this offer was originally made p) Applicant obtains quotation for roof rectification – 23 January 2012 q) Applicant provides quotation to FSP and is ack nowledged as being received by FSP – 9 March 2012 r) CR acknowledges receiving advice from FSP to obtain a second quotation for roof repairs in its report dated 17 April 2012 – no advice as to when request was made by FSP or builder appointed to quote s) CR provides copy of quotation from its appointed builder, JL, dated 13 April 2012, to FSP – 17 April 2012 t) NOR sent to FOS by FSP advises second quotation has not been received as Applicant has not provided second quotation or allowed access to property to allow a second quotation to be provided – 2 May 2012 31. During the course of the claim the Applicant supplied quotations for building works, in addition to roof repairs, which the Applicant contends could not be completed until the roof repairs had been finalised. This has not been disputed by the FSP. 32. The Applicant also says that due to the failed roof repairs and the FSP‟s failure to rectify the repairs, additional damage has been caused to the building which may incur additional costs. 33. The Panel is of the opinion that as the building repairs referred to involve internal repairs, it would be reasonable to assume that these repairs could not be completed until the roof repairs had been finalised. 34. The Panel notes that the timeline provided above is not supported by the Applicant on all issues. Method of Settlement 35. The FSP says that in accordance with the terms and conditions of the policy, it chooses the option of settlement, whether repairs are authorised or a cash settlement made. It relies on the following wording of its PDS: “ Method of settlement Section 1 – Building ... We will at our option either: Case No: 271600 Determination Page 6 of 17 1. pay you the Indemnity Value of the damaged part of the Building; or 2. repair or replace the damaged part of the Building.” (Page 8) 36. The Panel has reviewed the PDS and relevant section quoted by the FSP and notes that the FSP has failed to recognise its own policy provisions. Namely, on the same page (page 8) of the wording, it states: “ How we will settle your claim There are two methods of setting your claim. The method for settling Building claims is selected by you and is shown on the Schedule.” 37. The Panel notes the Applicant‟s Schedule shows she has a “Replacement Value” policy. Page 8 of the PDS continues: “ Method of settlement Section 1 – Building Reinstatement or Replacement Value We will pay the Cost of rebuilding or repairing any damaged part of your Building to the same condition as when it was new. ... Indemnity Value We will at our option either: 1. pay you the Indemnity Value of the damaged part of the Building; or 2. repair or replace the damaged part of the Building.” 38. The FSP has quite clearly misquoted its own PDS and used a condition detailed under the Indemnity Value settlement method, when attempting to settle the Applicant‟s claim under her Replacement Value po licy. 39. It is the opinion of the Panel that the FSP therefore does not have the option of choosing the method of settlement, nor does it have the option of cash settling any aspect of the Applicant‟s claim for the indemnity value of the repairs/replacement. Any settlement, whether authorising repairs or cash settling the Applicant, must be to a value of repairs/replacement to place the Applicant‟s property into a condition as it was when it was new. Roof Repairs 40. The Applicant provided two quotations for repairs to the roof and the FSP authorised repairs based on one of these quotations to PJ on 3 May 2011. 41. On 17 May 2011 the Applicant advised that she did not wish to have PJ complete the work however on the same day, changed her mind and agreed to allow PJ to start repairs. Case No: 271600 Determination Page 7 of 17 42. The Applicant says PJ advised her repairs would begin on 23 May 2011 and would take seven days to complete, meaning that repairs would be completed by 31 May 2011. She says she made several complaints to the FSP after repairs were started by PJ, as repairs were not completed within seven days; PJ did not return to the site for approximately five weeks after this time, he left the site untidy and with items lying on the ground, as well as on the roof, causing some items to rust and that the repairs he had done were not acceptable. 43. On the advice of the Applicant‟s complaint, the FSP says it appointed an Engineer, IC, to attend the Applicant‟s property and provide a report on the quality and standard of repairs. It says the Applicant failed to make and keep appointments with IC which caused a delay in IC‟s inspection and subsequent report. In any event, IC‟s report confirmed that the repairs completed by PJ were sub-standard and required rectification. 44. IC‟s report, in part says: “ 3.3 INCOMPLETE WORKS Repair works required to bring the house back to its pre-damaged condition: 3.3.1. Painting - ... 4. CONCLUSION AND SUMMARY OF REPAIR We are of the opinion that the roof sheeting, flashings, downpipe spreaders, roof frame repairs, roof frame tie down and gutter installation have all been carried out to a standard which is below that of industry standard and in our opinion the workmanship presents as defective building work. We believe for the purposes of the Queensland Building Services Authority Act (BSA), the defective works present as both category one and category two defects in accordance with their policy. In our opinion if the matter were to be put to the BSA that the time frames for both category one and two defects would be deemed „withi n time‟ for BSA to order rectification of the works. Generally we are of the opinion that all flashings, cappings, and Dektites be removed and replaced. Eaves gutters will require re- adjustment to achieve suitable falls. If an engineer deems that tie downs are inadequate, then we believe all roof sheeting will also enquire removal to facilitate repair of those components. At this stage we are of the opinion that will be necessary, as such this will reflect in our scope of works.” 45. The FSP arranged for IC to prepare a SOW and this was sent to the Applicant on 8 September 2011 with a request that she obtain two quotations for the rectification work. 46. The Applicant did not supply quotations and accordingly, the FSP offered the Applicant an amount of $33,000 ba sed on PJ‟s original quote of $33,300, less the $300 policy excess. A review of the settlements made to the Case No: 271600 Determination Page 8 of 17 Applicant indicate that a $300 excess may have already been deducted from the Applicant‟s contents claim. 47. The Applicant emailed the FSP on 3 October 2011 to explain that she was having difficulty in having a builder attend her property to provide a quotation and requested that the FSP or IC attend to arranging quotations given that the original repairs had been authorised by the FSP. The FSP advised t he Applicant that it would cash settle her for the roof repairs based on the original quotation supplied by PJ. 48. The FSP‟s file notes indicate that this decision was made “because insured stated numerous times could not obtain quotes we decided to settle o n original qte $33k”. This tends to support the Applicant‟s advice, despite the FSP‟s lack of file notes to indicate that the Applicant had contacted it on “numerous” occasions to advise of the difficulties she was having. 49. The Panel must note at this point that IC had provided his opinion and report, on what was required to bring the property back to its pre-loss condition. This is not in accordance with the terms and conditions of the policy and the Panel is of the opinion that the SOW must be reviewed to ensure that the works required will bring the property up to a condition as it was, when new. 50. In addition, the FSP‟s file notes and emails to the Applicant clearly indicate that it is only responsible for rectifying the repairs completed by PJ and to repair the cyclone damage to the roof. It clearly indicates to the Applicant that it is not responsible for any additional damage to other property that PJ may have caused whilst completing the works. 51. The Panel disagrees on this point and notes that as the FSP appointed PJ to effect repairs to the Applicant‟s property, it assumes responsibility for the actions of PJ and therefore is responsible for ensuring that in addition to rectification of the original roof repairs, any other damage caused by PJ is also rectified by the new roof repairer. Building Repairs 52. The FSP has accepted a quotation for other building repairs provided to it by the Applicant. It offered settlement to the Applicant based on this quotation and the Panel is of the opinion that the offer is reasonable. 53. The Applicant says she did not want to sign the release form for these monies as she could not have the work completed until the roof repairs had been rectified. 54. The Panel is of the opinion that this is a reasonable approach, given that if the internal building components are repaired prior to the roof being repaired, and further water entry or other damage occurs, the internal building repairs would be quite pointless. Case No: 271600 Determination Page 9 of 17 55. The Panel has reviewed the FSP‟s PDS and can find nothing precluding it from paying the sum of money offered to the Applicant without a signed release. It is the opinion of the Panel that the FSP should have paid these monies to the Applicant. 56. The FSP provided a release which clearly states that the payment of the amount offered a nd the Applicant‟s agreement to accept same means that she would have “... no further claim against [the FSP] in respect of [the] occurrence .” In light of the Applicant‟s concerns, the Panel is of the opinion that the FSP‟s actions in insisting the Applica nt sign the release before releasing payment, is not fair in all the circumstances. Loss of Rent 57. The FSP says that the Applicant has been requested to supply copies of current bond documents, lease agreements and rental ledgers to confirm that each of the insured units at the property were occupied at the time of loss. It says further that occupancy needs to be confirmed as no cover exists for loss of rent if the relevant unit or units were unoccupied at the time of the event. 58. In its letter to the Applicant in September 2011 it explained to the Applicant that there was a note contained within the policy schedule that suggested Unit 1 of the property was being occupied by the Applicant. The Panel has reviewed the policy schedule provided and can see no such note. As such, the Panel does not consider this to be a consideration when calculating a loss of rent claim. 59. The Panel accepts that the FSP is entitled to seek clarification of amounts claimed and occupancy of the units pursuant to the terms and conditions of the policy. It is noted however that the Applicant has provided copies of tenancy agreements for all three units, a letter from a real estate agent for one unit (confirming occupancy by the tenant at the time of the event, his departure date due to cyclone damage to the property and his weekly rent payment) and a copy of a ledger for another unit showing rent payments made by the tenant on a regular basis. 60. The third unit was tenanted by the Applicant‟s daughter and as such, no records of rent payments have been able to be produced as the Applicant says that rent was paid in cash to her, by her daughter. 61. The Panel is somewhat confused over the FSP‟s suggestion in its initial NOR that this information had not been supplied. From the Panel‟s review of the material, this information appears to have been supplied sometime around November 2011, and some of the information had been provided in September 2011. 62. The Panel is therefore satisfied that the Applicant supplied all information and documentation that was available to her in support of her loss of rent claim. Case No: 271600 Determination Page 10 of 17 63. The Panel is of the opinion that the information she provided was more than adequate to enable the FSP to settle this aspect of the claim, at the very least partially from the time of loss to the time it received the documentation. Any further loss of rent payment could and ought to have been paid to the Applicant as repairs were undertaken. 64. On this issue, the Panel notes the General Conditions of the FSP‟s PDS. The relevant section reads: “ Progress payments We will not unreasonably withhold progress payments. We will pay progress payments on claims at intervals to be approved by us following receipt of our interim report from our loss adjuster or representative.” 65. The FSP considered that the information provided by the Applicant to support her loss of rent claim was not adequate. At one point, after receiving the documentation, it informed the Applicant that she had failed to provide any documentation and this is reiterated in its NOR. 66. The Panel is of the opinion that the documentation provided by the Applicant for at least two of the units, was sufficient, and as such, a progress payment for loss of rent should have been paid. To withhold such a payment would be considered unfair in the circumstances. 67. The FSP says there is a lack of evidence to confirm the amount of rent paid by one tenant, J, due to there being different amounts recorded on the rent ledger as being paid. It also suggests that the lease agreement is not current as it was from 15 September 2009 to 14 March 2010. 68. The Panel has reviewed this rent ledger and is satisfied that the amounts appear to generally be $250 per week or payments of multiples of $250. Based on the Panel‟s calculations, it appears J may have been behind in her rental payments however, this does not exclude the Applicant from claiming loss of rent. 69. Given that there is sufficient evidence to show that a second tenant‟s weekly rent is $250 and that the Applicant has verbally advised that her daughter was paying her $250 a week for rent, the Panel is of the opinion that on the balance of probabilities, J was also paying $250 per week. 70. The Applicant has advised that J was on an ongoing lease and did not sign a new agreement. The Panel is satisfied that situations like this exist where tenants are not required to have an agreement in place for an ongoing arrangement. The rental ledger shows that J was paying rent at the property, with her last payment being on 28 January 2011, just a few days prior to the cyclone event. 71. The Applic ant has not supplied any documentation to support her daughter‟s rent payments. The Applicant says her daughter paid her cash and therefore no records were kept. The Panel accepts that this is not unreasonable in situations where family members have a tena nt/landlord relationship. Case No: 271600 Determination Page 11 of 17 However, the onus still rests with the Applicant to demonstrate that she was receiving rent from her daughter. 72. The Panel notes that the FOS Case Manager requested copies of bank statements of the Applicant‟s daughter to show the w ithdrawal of money from her account on a regular basis to demonstrate that some of her money could have been paid to the Applicant for rent, as advised by the Applicant. However to date, the Applicant has not supplied any further information in this regard. Claim Handling Delays 73. Having reviewed all of the material provided by both parties the Panel is of the opinion that delays were encountered in the claims process for a number of reasons. 74. The FSP has suggested that the majority of delays have been caused by the Applicant‟s consistent calls and emails requesting updates on the claim, the Applicant‟s failure to keep or make appointments with builders and experts and the Applicant‟s failure to acknowledge email communications either in a timely manner or at all. 75. The Applicant says that the FSP has contributed to these delays by failing to acknowledge, via CR, that she had made complaints regarding the quality of the roof repairs. She also says that the FSP‟s engineer, IC, has contributed to the delays as both IC and the Applicant were both having difficulty in arranging a mutually agreeable time to meet on site due to both parties being on leave or unavailable at the “right” time. 76. The Panel accepts that there have been delays caused by all parties involved in t his matter. However what is concerning is the FSP‟s failure to take a more pro-active approach in handling the roof repair aspect of the claim. 77. The FSP in its NOR has suggested that the Applicant contacted CR on 17 May 2011 advising that she no longer wished to use PJ to do the roof repairs and that it was not until 10 June 2011 that she contacted CR again to advise she was happy with PJ to proceed. This is in fact incorrect. CR‟s contemporaneous file notes indicate that the Applicant called CR twice on 17 May 2011. Firstly she advised she no longer wished PJ to proceed and in her second call, less than 30 minutes later, she advised she did wish PJ to proceed. 78. On 10 June 2011 CR‟s contemporaneous notes show an email sent to CR by the Applicant indicating she had issues regarding the building which she wished to discuss with CR. These contemporaneous file notes tend to support the Applicant‟s advice that PJ informed her he would be on site to start repairs by 23 May 2011 and that work would be finished in seve n days. 79. The FSP further says that it did not become aware of issues with the roof repairs or the Applicant‟s complaint regarding the quality of repairs until 21 Case No: 271600 Determination Page 12 of 17 June 2011. The FSP says the Applicant complained about repairs at this time despite the fact repairs were not completed. 80. The Panel is confused over this point. The Applicant has clearly indicated that PJ told her repairs would be completed in seven days and this information has not been disputed by the FSP. This would effectively mean that repairs should have been completed by 31 May 2011. However, the FSP is acknowledging that as of 21 June 2011, when the Applicant contacted CR to complain about the roof repairs and almost a month after repairs should have been completed, repairs had still not been completed. This is evidenced by CR‟s contemporaneo us notes which read: “[Applicant‟s daughter] called – she complained at length over the roof repairs – she seems to think that workmanship is not up to standard – she has taken pictures of same – I tried to advise that works are not complete – advised we h ave had other claims with this roofer and have had no complaints.” 81. The FSP has suggested that the Applicant refused PJ access to the site to complete repairs. However there is no evidence to support this in the form of contemporaneous notes or emails etc. The Panel is therefore satisfied that the FSP has failed to act in a timely manner in dealing with the Applicant‟s concerns regarding the quality of the roof repairs. 82. The FSP has further suggested that the Applicant failed to keep appointments with the engineer appointed by the FSP, IC, or failed to contact IC to arrange an appointed. The Applicant on this point says that due to availability problems for both herself and IC, a suitable appointment could not be arranged until August 2011. 83. The Panel is of the opinion, that on the balance of probabilities, the Applicant has made several attempts to complain about the quality of the roof repairs up to and including 21 June 2011. Based on the material before the Panel, there is no evidence to support the FSP‟s advice that the Applicant has failed to keep appointments. The Panel is therefore satisfied that delays in IC‟s attendance at the Applicant‟s property was due to availability issues on the part of IC and the Applicant. 84. The FSP has suggested that further delays were experienced due to the Applicant failing to respond to countless offers of settlement in relation to roof repairs and building repairs. It says it sent release forms for the Applicant to sign for both aspects and that it has been willing to settle the building repairs since 7 October 2011. It says it has been willing to settle the roof repairs aspect of the claim since May 2012. 85. The Panel‟s opinions on the building repairs and roof repairs have been detailed earlier in this Determination and there is no need to repeat that information. 86. The FSP has insisted that the Applicant must sign a release form in order to obtain monies for the building and roof repairs. These releases contain the phrase: Case No: 271600 Determination Page 13 of 17 “... and on payment of the above WE shall have no furt her claim against [the FSP] in respect of this occurrence.” 87. The Applicant‟s reluctance or refusal to sign these releases for whatever reason does not preclude the FSP from making payment. There is no provision within the FSP‟s PDS that requires the Applica nt to sign such a release. There is also credence in the Applicant‟s advice that until the roof repairs were completed satisfactorily, building repairs could not commence. Why then should or would she accept the offer made for building repairs until she was satisfied that the roof repairs had been satisfactorily resolved? 88. The Panel is of the opinion that the Applicant has therefore not caused any delays in accepting the sums offered. Rather she had lodged a complaint with the FSP and eventually FOS which she has yet to have resolved. 89. The FSP has also relied upon a Statutory Declaration from the handler of the Applicant‟s claim who declares that the Applicant and her daughter (as the Applicant‟s representative regarding this claim) contacted her on numerous occasions and for lengthy periods of time to seek updates on her claim and to query various aspects of her claim. She also says that numerous emails were also received from the Applicant and her daughter and that the Applicant had two other claims at different properties for the same event. 90. The Panel is of the opinion that given the Applicant was not living in the same State as the damaged property that this has certainly contributed to frustrations and delays from all parties. Conclusion Roof Repairs 91. There is no dispute that the repairs completed by PJ were sub-standard. As the FSP has taken the responsibility of authorising repairs to this builder, it must also take responsibility for any problems that may occur during that repair process. 92. The Panel is of the opinion that the FSP is responsible for authorising the rectification repairs to the roof and arranging/authorising any other repairs required to the Applicant‟s property which has been damaged by PJ during the course of those repairs. Building Repairs 93. The Panel is satisfied that the amount offered for settlement by the FSP for the building repairs is reasonable. However, the FSP should have already paid the amount to the Applicant. Given the FSP should have also authorised the roof rectification repairs and did not; it follows that the FSP must also be responsible for any additional costs for the building repairs which may now be present. These repairs would relate to increases in costs and/or additional damage incurred to the property due to the roof repairs having not been completed. Case No: 271600 Determination Page 14 of 17 Loss of Rent 94. The Applicant has supplied information to the FSP to settle this aspect of the claim with the exception of monies paid by the Applicant‟s daughter, who has been confirmed as a tenant in the form of the tenancy agreement. The Panel is satisfied that this documentation is sufficient to allow the FSP to settle as least part of the loss of rent claim. The Panel is of the opinion therefore that the FSP should have settled part of the loss of rent claim from the time it received the documentation, being 6 September 2011. 95. The Panel is of the opinion that the FSP is to settle the loss of rent claim from the date of loss, being 3 February 2011, until such time that all repairs have been completed at the Applicant‟s proper ty, regardless of policy limitations. This is based on the Panel‟s opinion that the offers made by the FSP to settle the building and roof aspects of the claim, and the methods used to offer those settlements, have not been fair in all the circumstances. Claim Handling Delays 96. FOS acknowledges and accepts that during times of catastrophic weather events the resources of any FSP are stretched to cope with the unusually high influx of new claims and the additional demands of policyholders who have been displaced from their usual residences. The cyclone event the subject of the Applicant‟s claim certainly falls into this category. It is therefore reasonable to accept that some delays would occur during the claims handling process. 97. The Panel suggests that some delays in this instance have been caused by the FSP and this in turn has caused a degree of stress and anxiety for the Applicant who has, on more than one occasion, expressed that she has felt the FSP has ignored her complaints. 98. The Panel is of the opinion that the FSP‟s actions in insisting that the Applicant obtain quotations for the rectification of the poorly repaired roof which it had authorised repairs for originally, and that the Applicant would have to address the issue of damage caused by PJ directly with PJ, is far from fair to the Applicant. 99. It is quite obvious from the material that the actions of the FSP on these aspects has certainly caused a great deal of concern and stress to the Applicant and has caused further unnecessary delays which could have been avoided had the FSP authorised the necessary repairs and any other repairs for damage caused by PJ whilst he was on site. Compensation 100. The Panel has given consideration to another aspect of the matter which is of concern. FOS Terms of Reference “ 9.3 Other compensation Case No: 271600 Determination Page 15 of 17 a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute. b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non-financial loss but only where: i. an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind has occurred; or ii. in the case of a Dispute pertaining to an individual‟s privacy rights - injury has occurred to the Applicant‟s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute.” 101. The Panel has raised the relevance of paragraph 9.3(b) with the FSP. In a detailed submission the FSP argued that no award should be made to the Applicant as the Applicant has not satisfied the requirement of paragraph 9.3(b)(i). It says that the FSP has not delayed the finalising of the Applicant‟s claim. 102. The Panel does not accept the FSP‟s submission, given the facts as detailed above, regarding its handling of this claim. The Panel accepts that some delays were inevitable given the magnitude of the cyclone event and the impact this would have had on the FSP‟s resources. 103. However the Panel, for the reasons detailed above, is of the opinion that the FSP was in a position to make some payments to the Applicant and failed to do so as the Applicant refused to sign release forms. The Panel, as discussed earlier, can find no requirement within the FSP‟s PDS to suggest that any settlement is dependent on a signed release being provided. 104. In addition, the FSP failed to arrange quotations for the rectification of its authorised roof repairer‟s work and also failed to authorise these rectification repairs once quotations had been supplied. 105. The Panel is t herefore of the view that the FSP‟s conduct of the matter has been such as to cause a good deal of physical inconvenience and time taken to resolve the matter, thus having an impact upon the Applicant‟s expectation of enjoyment and peace of mind. 106. The Panel need not set out the facts again. In the Panel‟s opinion the FSP has contributed to the Applicant‟s stress due to its actions, after a catastrophic weather event. 107. As there is no exclusion in the FSP‟s PDS precluding the Panel from awarding a compensation payment, the Panel therefore considers that the FSP should further compensate the Applicant by payment of the sum of $1,500 under this heading. Case No: 271600 Determination Page 16 of 17 Determination 108. On the basis of the available information the Panel determines that:  The Applicant‟s nominated bui lder, M, is to provide current costings for its previously submitted quotation for building repairs taking into account any changes to prices and any additional damage caused by the failed roof repairs;  The FSP is to settle the building aspect of the claim based on M‟s revised quotation;  The FSP is to have IC prepare a SOW that provides repairs to the Applicant‟s roof up to a condition as to when it was new;  RB is to provide a revised quotation on the new SOW (if any changes are made) and to show any changes in prices;  Repairs are to be authorised to RB for the roof repairs and rectification work required to reinstate the Applicant‟s roof to a condition as it was when new;  Should any additional or further claim related repairs or repairs required due to damage caused by PJ become apparent during the repair process, RB is to provide the FSP with a quotation for this work and repairs are to be authorised by the FSP within seven days of receiving the revised quotation;  The Applicant is to authorise repairs to M for the remaining building items within 14 days of the satisfactory completion of the roof repairs and the Applicant will be responsible for the monitoring of these repairs and payment of M‟s account for same;  The Applicant is to provide the FSP a copy of the final invoice submitted by M confirming the date repairs were completed and the date the invoice was paid within 7 days of repairs being completed;  The FSP is to pay loss of rent to the Applicant from 3 February 2011 for two units where rent amounts have already been quantified to the satisfaction of the Panel, as detailed above, up to the date that repairs are authorised to RB;  The FSP is to pay monthly loss of rent payments to the Applicant from the date roof repairs are authorised until completio n of all repairs for two units only;  The Applicant is to provide the FSP with copies of her daughter‟s bank statements showing regular withdrawals of monies from her account for from 1 January 2011 until the date of loss, in support of her advice that she was paying cash for the rent to her parents from the start of the lease date, being 12 January 2011;  The FSP is to pay to the Applicant, loss of rent for the unit leased by her daughter from 3 February 2011 until receipt of the Applicant‟s daughter‟s bank statements; Case No: 271600 Determination Page 17 of 17  The FSP is to pay monthly loss of rent payments to the Applicant from this date until completion of all repairs for the unit previously leased by her daughter;  The FSP will not be obliged to pay any further loss of rent for any of the units from the date of completion of all repairs, which will be confirmed by the Applicant as detailed above. 109. In addition, the FSP is to pay interest on the loss of rent aspect of the claim from 6 September 2011 until roof repairs are authorised, for two units only. The applicable interest rate is calculated pursuant to Section 57 of the Insurance Contracts Act 1984 (Cth) in the sum of 6.75% given the Applicant would have had access to these settlement amounts at the time of the original settlement of this aspect of the claim. 110. Interest is not payable on the loss of rent payable from the date roof repairs are authorised until repairs are completed, on the unit tenanted by the Applicant‟s daughter or on any additional amount quoted by M to finalise the building repairs. 111. The FSP is to make payment to the Applicant within 14 days of receipt of this Determination for:  Loss of rent on two units;  Interest on loss of rent; and  Interest on M‟s original quotation. 112. The FSP is to arrange for a revised SOW to be forwarded to RB within 7 days of receipt of this Determination and is to authorise roof repairs to RB within 14 days of receipt of the amended quotation (or confirmation that no amendment will be required). 113. Pursuant to paragraph 9.3(b)(i) of the Terms of Reference, the Panel also determines that the FSP should pay to the Applicant the sum of $1,500. This amount is to be paid to the Applicant within 14 days of receipt of this Determination.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.