Home / Financial Firm (Unknown - Insurer) / Determination 271598
Determination 271598
Claim amount
Summary
The applicant's heritage-listed investment property was damaged by water ingress, and the insurer denied most of the claim before cash settling $17,200 net of excess. AFCA ordered the insurer to provide a breakdown of its settlement costings substantiated by a builder's quote, and found loss of rent was not covered.
The insurer must substantiate the cost of the repairs it accepted with appropriate quotes, as the policy pays the cost to repair the home.
Issues
- Claim amount dispute primary · upheld“the Panel is not satisfied the FSP has satisfactorily established the cost to it for the repairs it has accepted.”
- Claim denial secondary · not upheld“The Panel determines the FSP was entitled to deny liability for loss of rent.”
Subjects and remedies
home or building damagenatural disasterprovide documents
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 271598 Determination Page 1 of 8
Case number: 271598
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim-Exclusion/ condition
25 October 2012
Background
1. The Applicant is insured with the Financial Services Provider (FSP) under a
home building insurance policy for an investment property. The policy
provides cover for loss or damage caused by an event covered by the policy.
The relevant period of insurance is 26 August 2010 to 26 August 2011
during which the building was insured for the sum of $250,000.
2. The Applicant also owned the adjacent property which was insured with the
FSP.
3. On 20 January 2010 the Applicant contacted the FSP to advise the property
had sustained damage as a result of a storm event. The date of loss was
reported as 27 November 2010. The description of loss recorded by the FSP
onto its records was :
“Storm and heavy rain caused gutters and valley in roof to overflow and flood
inside, affect power and tiles on floor are lifting”
4. The FSP arranged for the property to be inspected which was conducted by
a building consultant. The inspection did not take place until 8 March 2011.
Cyclone Yasi impacted the region in early February 2011.
5. Following receipt of the building consultant’s report the FSP wrote to the
Applicant on 24 March 2011 advising the claim was not one for acceptance:
“As the damage to your property occurred as a result of defective and faulty
workmanship and was not the result of water entering your home through a
storm created opening:”
6. The Applicant was dissatisfied with the FSP’s decision to deny his claim and
raised issues with it. The FSP arranged for the property to be reinspected on
30 March 2011 and a scope of works obtained. The reinspection identified
some damage was possibly associated with Cyclone Yasi. The scope of
works detailed repairs costs at approximately $12,000.
7. On 1 July 2011 the FSP cash settled the Applicant for the amount of $18,200
less the policy excess of $1,000 following further consideration of further
costs sought by him.
Determination
Case No: 271598 Determination Page 2 of 8
8. On 1 February 2012 the Applicant lodged his dispute with the Service.
Summary of Applicant’s position
9. He asked the FSP for a copy of the scope of works and costings for the
settlement but was not provided with this information.
10. There has been maladministration on behalf of the FSP as it failed to provide
correct costings or carry out its duties towards him in a responsible manner.
11. No reports were obtained relating to electrical works, footings, roof, kitchen
or bathroom.
12. He has been given a council order for the removal or demolition of the
house.
13. The matter should be resolved with payment of the building sum insured less
the amount already paid plus payment for loss of income.
14. He will accept $220,000 as settlement.
Summary of FSP’s position
15. The Applicant was provided with the scope of works.
16. He was not provided with quotes from other builders as they are classed as
Commercial-in-Confidence.
17. The scope of works completed is accurate. It says the Applicant has failed to
provide evidence to show the scope of works is incorrect.
18. The Applicant was cash settled on 1 July 2011. It does not know why the
Applicant has failed to address the building issues and rent the property out
again.
19. No supporting evidence has been provided by the Applicant to show the
building is structurally unsound and/or under a Council order to demolish or
remove it.
20. The onus is on the Applicant to establish that all the damage claimed has
arisen as a result of an insured event but he has failed to do so.
21. The weight of evidence shows an accurate and detailed inspection has been
completed of the Applicant’s house and the correct claims decision and
settlement amount has been made in relation to the claim.
22. The FSP relies on the following policy provisions:
“ Damage caused by weather ...
Case No: 271598 Determination Page 3 of 8
What is covered What is not covered
Storm Loss or damage:
...
caused by rain or wind entering the
home unless it enters through an
opening in the windows, walls or roof
made by the storm;
...
When you are not covered – general exclusions
These general exclusions apply to all sections of your policy. We will not pay
for loss or damage or the incurring of a legal liability caused by:
Exclusions When you are not covered
...
defective or faulty workmanship the inherent defect or defective
workmanship, design or manufacture
...
failing to take care of the home or
contents
failure to maintain the home and its
contents in good condition
...
wear, tear, rust, mould wear, tear, rust, corrosion, rot,
mould, action of light or atmospheric
or climatic conditions including
damage caused by wind, rain or sand
happening over an extended period
of time.
...
General conditions
...
What you must do
You must
at your expense take all reasonable precautions to:
keep your home and contents in good condition; ”
Case No: 271598 Determination Page 4 of 8
Issues
23. Whether the FSP’s settlement payment of $18,200 less the policy excess of
$1,000 fulfils its obligations under the terms and conditions of the policy for
damage.
Reasons for decision
24. Due to the nature of the dispute, this matter has been referred to the Panel
for Determination in line with the Operational Guidelines to the Financial
Ombudsman Service’s Terms of Reference.
25. The Panel consists of an Ombudsman, a representative with extensive
experience in insurance industry matters and a representative with extensive
experience in consumer claims.
26. An exchange of the information submitted by the parties has taken place
between each party and each has had the opportunity to address any issues
raised.
27. The Panel does not intend to recite details of the information in this
Determination except where it is considered relevant.
28. The Panel notes the building, the subject of this dispute, is approximately
100 years of age and is heritage listed.
29. The Applicant referred this matter to the Service seeking settlement of the
claim in the amount of the building sum insured under the policy.
30. The Applicant has since advised the Service’s Case Manager that he is
willing to accept payment for repair works based on the quotes submitted by
him.
31. Due to the allegations by the FSP that the property had not been maintained ,
much of the material submitted by the Applicant relates to disputing this.
32. Nevertheless, the onus rests with the Applicant to show that an event which
is covered by the policy has caused the damage which he has claimed.
Once the Applicant has done this the onus then reverts to the FSP to
establish that the damage is not covered due to a policy exclusion or
condition.
33. The policy provides cover for loss or damage caused by a storm but it
excludes loss or damage caused by wind or rain entering the home unless it
enters through an opening in the windows, walls or roof made by the storm.
34. The policy also covers bursting, leaking, discharging or overflowing of liquids
from pipes and gutters which are fixed or connected to the home.
35. The initial claim was lodged for damage caused by overflowing gutters to:
Case No: 271598 Determination Page 5 of 8
family room and kitchen tiling,
bathroom tiling,
Kitchen ceiling
floor tiling
Wall cladding in family room
bedroom two flooring
36. The FSP relied on the evidence of the building consultant (DD) who deemed
the damage resulted from a gradual process of repeated incidents. It was
reported the box gutter installed was inappropriate and that tiling had been
laid directly onto the timber floor. It was also reported that water ingress
would have occurred through external doors due to the large gaps evident.
37. Accordingly, the FSP rejected the claim on the ground the damage to the
property occurred as a result of defective workmans hip and was not the
result of water entering the home through a storm made opening.
38. However, the property was subsequently reinspected following the
Applicant’s dissatisfaction with the FSP’s decision to reject the claim. The
person (PS) who did the inspection was from the same company as the
building consultant DD. It is understood PS is a loss adjuster.
39. PS in her report dated 6 April 2012 indicated the Applicant believed tiles in
kitchen, living and bathroom areas had loosened from water ingress due to
Cyclone Yasi. She also reported there was water staining to ceilings and
walls in the kitchen and living room and that the electricity supply was
isolated.
40. PS was of the opinion that although additional damage was caused to the
ceilings and walls from water ingress due to Cyclone Yasi water had been
entering in various areas over a long period of time due to poor construction.
41. PS also reported that she believed the tiles were loose prior to Cyclone Yasi
as a result of poor construction techniques due to their having been installed
directly onto the floor. Moreover, the construction of the roof had contributed
to water ingress resulting from capping not been scribed properly.
42. From the available evidence it appears water ingress has occurred via the
roof, roof gutters and underneath external doors. However, due to the FSP
simply referring to policy exclusions it remains unclear what repairs it has not
accepted.
43. A scope of works was submitted by PS’s report with the cost of repairs
estimated as $12,252.04. The FSP was of the view the scope of works was
generous.
44. The Applicant obtained his own builder’s quote which, according to the
quote, was based on a scope of works as detailed in an email from the
Case No: 271598 Determination Page 6 of 8
Applicant dated 3 June 2011. The quote was dated 16 June 2011 and was
for the amount of $77,600 including GST.
45. According to the FSP it spoke to this builder (DT) who had quoted for the
Applicant and he advised his quote included works that were not claim
related. The Applicant rightly says the FSP has no evidence of this as there
is no statement from DT. Moreover, the Applicant says he spoke to DT who
he said he could not recall making any statement.
46. Nevertheless, the Panel accepts that DT’s quote included works that were
not noted in the FSP’s obtained scope of w orks.
47. DT also quoted separately on 16 June 2011 in the amount of $45,000, which
included GST, for roof repairs. According to DT the damage quoted for was
“Roof sheets leaking at joints”. The quote makes no mention as to the cause
of damage.
48. The Applicant obtained a quote from a plumber (WB) dated 30 January 2012
for $21,960 to supply and fit iron roof only. The quote gave no indication of
why the roof needed replacement.
49. The FSP expressed concern regarding an unsigned and undated statement
from plumber WB that was submitted by the Applicant. The concern referred
to the misspelling of a word that was also misspelled, in identical way, in
another unsigned statement that was included as part of the Applicant’s
submission.
50. The FSP’s argument that the possibility of two unrelated persons misspelling
the same word in the same context is remote is noted. Notwithstanding this,
a telephone number was provided on the statement and the FSP could have
contacted WB, as it did with DT.
51. In this statement WB notes structural damage to the roof. It is unclear
however as to what is the structural damage is other than advising roof iron
has been loosened and some sheets of iron torn along with nails also having
been loosened.
52. The Panel has some problems with this evidence because when the roof
was quoted for repairs in June 2011 it was noted roof sheets leaking at
joints. There was no indication of other damage sustained to the roof such
as torn sheets.
53. Further the Panel would find it surprising that torn roof sheets would not
h ave been identified by the FSP’s appointed building consultant or the loss
adjuster when they inspected the property. Photographs of the roof included
in the reports do not show structural damage to the roof or torn iron sheets.
54. The Panel is not satisfied the Applicant has established that the roof has
been damaged by an event covered by the policy.
Case No: 271598 Determination Page 7 of 8
55. Regardless, the FSP maintained it position that the Applicant had not
substantiated that all the damage claimed was caused by an event covered
by the policy.
56. An issue that concerned the Applicant was the FSP advising the tiles were
laid directly on the floor. The Applicant says this is incorrect and has
provided photographic evidence to disprove this.
57. The Panel has considered the reports obtained by the FSP which refer to
tiles been laid directly onto floor boards however photographs provided with
PS’ s report include a photograph which is captioned to indicate cement
sheet underlay is present under the floor tiles.
58. The Panel accepts the tiles were laid onto ceme nt sheeting and not directly
to the floor. The FSP is to replace cement underlay in the areas it has
accepted to replace floor tiling.
59. In deciding the respective and conflicting opinions between the parties on
the scope of works the Panel is more heavily i nfluenced by the FSP’s
experts as the opinions of the FSP’s experts are more substantive and
provide greater detail as to the cause of the damage.
60. By contrast, the Applicant’s evidence does not show or substantiate the
cause of damage.
61. Accordingly, the Panel sees no reason that the scope of works obtained by
the FSP should not be accepted as identifying the damage for which the
FSP is liable.
62. The Panel notes the Applicant says he sought from the FSP the scope of
works and costings for the settlement. The FSP says the Applicant was
provided with the scope of works and stated he was not provided with quotes
from other builders as they are classed as Commercial-in-Confidence.
63. The Panel believes that the Applicant was not asking for quotes from other
builders but was seeking the details from the FSP as to how it arrived at its
settlement figure of $18,200 based on its further considerations subsequent
to the scope of works.
64. The Panel is of the view the Applicant is entitled to know the basis of the
FSP’s settle ment amount. Particularly as the policy entitles the FSP to pay
the Applicant the amount of the cost to the FSP to rebuild or repair the
home. This requires the FSP to obtain substantiated quotes by appropriate
persons.
65. The FSP says it accepted a scope of works prepared by the building
consultant who itemised the costing of $12,252.04. No information whatever
has been provided as to what additional repairs the amount of $18,200
covers. Thus the Panel is not satisfied the FSP has satisfactorily established
the cost to it for the repairs it has accepted. The Panel therefore stipulates
that this omission must be remedied the FSP.
Case No: 271598 Determination Page 8 of 8
Rent.
66. The Applicant is claiming for loss of rent.
67. The FSP submits the Applicant was paid for repairs to the property. There is
no indication the Applicant used any of the settlement money towards its
repair. The FSP does not know why the repairs have not been undertaken.
The FSP says the Applicant is obliged to mitigate his loss.
68. The policy provides for loss of rent if the building is rendered unfit to be lived
caused by an insured event. Although some damage has been accepted by
the FSP there is no evidence to show any insured event has caused it to be
unfit to be lived in.
69. The Panel is not satisfied a loss of rent claim extends to the Applicant in this
circumstance.
Determination
70. On the basis of the available information the Panel determines the FSP is to
provide the Applicant with a breakdown of the repairs and costings on which
its settlement of $18,200 was based substantiated by a quote from an
appropriate builder. The Panel further determines the FSP is to provide this
information to the Applicant within 14 days of receipt of this determination.
71. Once the Applicant has received the breakdown of the work and costings, he
is then in a position to challenge the costings if he wishes to do so.
72. The Panel determines the FSP was entitled to deny liability for loss of rent.