Failure to genuinely consider financial hardship request

FirmFinancial Firm (Unknown - Credit)
Decided2013-08-13
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$1,726
Non-financial loss$200
Amount claimed—
SourceAFCA PDF

Summary

A borrower in arrears after a house fire and later a work injury sought hardship assistance on his home loan. AFCA found the FSP did not genuinely consider a December 2011 to January 2012 request, ordering a $1,726.27 legal fee refund and $200 for distress, but declined to vary the contract.

Under section 25.2 of the Code of Banking Practice the FSP must genuinely consider hardship requests, including new unforeseen events, and communicate reasons relevant to the customer's situation.

Issues

Subjects and remedies

financial hardshiphome or building damagepay non financial lossrefund fees or charges

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Case No: «reference_id» Determination Page 1 of 14 Case number: 271353 Credit - Consumer Credit - Home Loans - Financial Difficulty - Decline of Financial Difficulty Request 10 July 2013 Background 1. This dispute has not been the subject of a Financial Ombudsman Service (FOS) Recommendation, and has proceeded directly to a Determination. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because the Applicant is suffering financial difficulty in relation to the facilities that are the subject matter of this dispute. 2. The dispute concerns financial difficulty the Applicant has been experiencing in relation to his home loan with the FSP (the Facility). The Facility was initially drawn in November 2007 for $313,500 and is secured by a mortgage over a residential property (the Security Property). 3. The outstanding balance of the Facility as of 10 July 2013 is $430,578.03 including arrears of $51,343.97. No payments have been made on the Facility since 20 September 2012. 4. The FSP commenced legal proceedings and these proceedings are on hold while FOS is considering the dispute. FOS dispute 99916 5. The Applicant first lodged a hardship dispute with the FOS on 22 October 2008 with dispute number 99916. FOS held a Telephone Conciliation Conference (TCC) on 17 June 2009 and the Applicant agreed to a settlement on 20 August 2009 which included the capitalisation of $25,612.82 in arrears under the Facility (Settlement Agreement). 6. When the Applicant didn't meet the payments required under the Agreement, the FSP instituted legal proceedings against him in November 2009. He approached FOS again in December 2009, and FOS wrote to him to say that any issues he had should be addressed in the legal proceedings. Deed of Settlement 7. In November 2010, the Applicant entered into a Deed of Settlement (the Deed) with the FSP in relation to the legal proceedings. Under the Deed, the Determination Case No:271353 Determination Page 2 of 14 FSP agreed not to proceed with the legal action and to capitalise arrears of approximately $25,000 if the Applicant made monthly repayments of $2,500 for the remainder of the Facility term. Under the Deed, if the Applicant defaulted on the payments within three years, the FSP could reinstate the proceedings and judgment would be entered against him. 8. The Applicant lodged the current dispute with FOS on 30 January 2012. He said that extenuating circumstances meant that he had been unable to comply with the terms of the Deed since early 2011. He had been unable to make payments because a fire has destroyed some of his house, followed by a flood which caused damage to his property, and then a motor vehicle accident which left him unable to work. 9. On 31 July 2012, I decided that these events appeared to constitute exceptional circumstances sufficient to warrant an investigation of both parties’ claims as a part of a jurisdictional decision under paragraph 5.2 of FOS’ Terms of Reference (TOR). The FSP elected to allow the dispute to be considered under paragraph 4.4 of the TOR instead of proceeding to a jurisdictional decision on the issue. 10. As the parties entered into a Settlement Agreement to finalise dispute 99916, I will not be forming a view on any of the events that occurred before the Settlement Agreement, and subsequent Deed, were entered into. This dispute concerns only the assistance provided to the Applicant in response to his request for assistance with his financial difficulty since January 2011, the date from which the Applicant says he has been unable to comply with the Deed because a new event of financial difficulty occurred. Summary of Applicant’s Position 11. The Applicant has been experiencing financial difficulty since January 2011. He sought financial hardship assistance from the FSP on a number of occasions from November 2011 onwards; however he says that the FSP has failed to assist him. 12. After a fire at his home in January 2011, the Applicant says he was effectively homeless until November 2011. He was then injured in a workplace accident in November 2011, but was unable to make a claim due to the parent company of his employer closing down before his entitlements could be paid. 13. The Applicant accepts that he needs to sell the Property but wants the opportunity to self it himself. He says that it is valued a lot more than what the FSP would sell it for. Summary of FSP’s Position Case No:271353 Determination Page 3 of 14 14. The FSP says it has previously provided assistance in the form of capitalising $33,467.59 in arrears on 25 January 2011 and paying outstanding rates on the Security Property of $7,360.87 in March 2011. It assessed and declined an application for further assistance on 8 December 2011 as it formed the view that the Applicant could afford, but was not making, repayments. 15. The FSP is of the view that the Applicant is unwilling or incapable of committing to the promised payment arrangements and that his financial difficulties are not short term. In spite of this, on 2 August 2012 and 3 October 2012, the FSP did offer the Applicant a period of 90 days to voluntarily sell the Security Property. 16. It has suspended all collection activity and has not charged any default interest on the Facility since the FOS dispute was lodged, over twelve months ago. The Applicant has only made sporadic payments in that time, insufficient to meet the monthly repayments. The FSP views the capitalisation of the current arrears, approximately $40,000, would only worsen the Applicants’ financial position , and delay the inevitable sale of the Security Property, which it sees as the only way the Facility will be repaid. Issues 17. Whether the FSP has given genuine considera tion to the Applicant’s request for assistance in relation to his financial difficulty. 18. If not, whether the Applicant is entitled to any compensation. 19. Whether I should exercise my power to vary the Facility contract. Reasons for Decision Financial difficulty 20. I consider that under section 25.2 of the Code of Banking Practice (CBP) an FSP has an obligation to give genuine consideration to a customer’s request for assistance, where the customer is in financial difficulty. 21. I also expect a customer to be willing to work with their financial services provider, and to propose a realistic repayment plan that will result in the repayment of the debt within a reasonable timeframe. 22. The Applicant has made several requests for assistance from January 2011 onwards. I have outlined below a brief chronology of events. History of key events Case No:271353 Determination Page 4 of 14 23. The Applicant’s home, the Security Property, was affected by a fire in January 2011, only two months after he signed the Deed. The account statements show that, in accordance with the terms of the Deed, the FSP capitalised arrears of $33,467.59 on 25 January 2011. 24. For his part, the Applicant was supposed to resume repayments of $2,500 per month from 25 December 2010 under the term s of the Deed. The FSP’s contact notes show, however, that he called on 28 January 2011 to say that the “had a fire in the house and had lost his job”. He asked for, and was granted, an extension of time to pay the December 2010 and January 2011 payments. The FSP’s notes show that the arrears were cleared by a payment of $2,900 on 28 February 2011. 25. The Applicant was unable to make the March 2011 repayment and his spouse called the FSP on 15 March 2011 to seek further hardship assistance. She said that they were living in a caravan and “chasing insurance [agent] regarding [the] contents claim”. 26. The FSP representative advised them to complete a hardship application and submit it for the FSP’s consideration. A few days later , the FSP received and paid an overdue rates notice for $7,360.87 to stop any recovery action that the local council might take in relation to the Security Property. 27. The FSP’s contact notes do not show that the Applicant returned the hardship application. He made three repayments in April 2011 and the arrears, by 19 May 2011, had been reduced to $54.92. 28. The FSP’s contact notes show that it tried multiple times to contact the Applicant from June 2011 to October 2011. The repayments were sporadic during this period, with no payment being made in June 2011, $3,000 being paid on 8 July 2011 followed by weekly payment of $750 for three weeks and then no payments in August 2011. 29. By the time the FSP was able to speak to the Applicant, on 18 October 2011, the Applicant’s spouse said that they were s till trying to recover from the January 2011 fire at their home. She told the FSP that they were expecting compensation from the insurance claim and, once received, they could repay the arrears. 30. In the meantime, the Applicant committed to making repayments of $750 per week which he said he could afford as he had recently found a new job. They told the FSP that they would be applying for hardship assistance as the new job indicated a positive change in their circumstances. It would appear that the FSP sent a hardship application for the Applicant to complete at this time. 31. When the hardship application had not been returned by 8 November 2011, the FSP called the Applicant on this date and his spouse said they had faxed the application back already. They were advised to resend it and to call the hardship team to make sure it had been received . The Applicant’s spouse Case No:271353 Determination Page 5 of 14 told the FSP in this call that they were expecting the compensation claim to be paid at the end of January 2012. 32. The FSP’s notes from 15 November 2011 show that the hardship application had still not been received. T he FSP’s solicitors noted , on that date, that the FSP was entitled to serve a default notice on the Applicant as the arrears were $2,822.23 and the Applicant had breached the Deed by defaulting on repayments within a three year period. The FSP decided not to progress to a default notice, however, as it noted, on 23 November 2011, that the account was only “2.3 payme nts past due and hardship [application ] to be submitted”. 33. The hardship application was finally received on 5 December 2011, dated 2 December 2011 (the 2 December 2011 Hardship Application). By this time, the arrears were $8,610.53 and the Applicant requested that the arrears be capitalised. He said he could make repayments of $750 per week and could resume normal repayments in February/March 2013. He said he had been in a truck accident but he had been cleared to return to work on 5 December 2012. He stated his income to be $5,822.48 and his monthly expenses to be $3,880. 34. The FSP declined the 2 December 2011 Hardship Application. Its ’ contact notes from 8 December 2011 state that assistance was declined “in view of LVR and broken promises to pay”. LVR refers to the Loan to Value Ratio. 35. In the FSP’s letter to the A pplicant dated 8 December 2011, it said that its reasons for declining the Applications were that it did not “reasonably expect that [the Applicant] will be in a position to meet [his] financial obligations now and in the future”. 36. In a later submission, dated 3 October 2012, the FSP said that it actually declined the Applicant’s 2 December 2011 Hardship Application because his income and expenses showed that he had servicing capacity and yet he had not made repayments as required. It pointed to the fact that, in retrospect, even though the Applicant had been cleared to return to work he did not resume repayments as promised. 37. After being advised that assistance had been declined, the Applican t’s spouse told the FSP on 16 December 2011 that she wanted to make an arrangement to avoid a notice of default being issued on the account. 38. She told the FSP that the insurer had not paid the full value of their home contents ’ claim following the fire, and that they had lodged a FOS dispute about this issue. She expected this issue would take three to six months to resolve. She also advised the FSP that the Applicant had been off work for four to five weeks but would return on 19 December 2011, at which time he would resume weekly repayments of $750 to $800. 39. The FSP made an arrangement with the Applic ant’s spouse on 17 December 2011 for the Applicant to pay a $3,000 lump sum within 28 days as well as resuming weekly payments of $800 from 30 December 2011. The Case No:271353 Determination Page 6 of 14 Applicant did not pay the $3,000 but made payments of $800 on 28 December 2011, 5 January 2012, 13 January 2012 and 20 January 2012. 40. When the FSP next spoke to the Applicant, on 18 January 2012, he said he was still waiting on the $3,000 from a Work Cover action and expected it in the middle of February 2012. He also said that he was expecting to return to work at the end of February 2012. The FSP representative advised him that they would note what he had said, but while the account was in arrears there was still a risk of further action being taken. 41. This is, in fact, what did happen. The Applicant made the payment of $800 on 20 January 2012, but the FSP proceeded to refer the account to its legal department on 24 January 2012. It decided to list the matter for hearing on the basis that the Applicant had breached the Deed rather than issue a notice of default and follow the recovery process. The matter was listed for hearing on 16 February 2012 but was adjourned by the FSP once the FOS dispute was lodged on 30 January 2012. 42. In his FOS dispute form, the Applicant requested repayments to be suspended for a period of three months to allow him to continue the weekly repayments and “catch up on the loan to date” (the 30 January 2012 Proposal).The FSP responded, on 14 February 2012, stating that loan balance had increased from $313,500 to $394,089.41 since it was drawn, and the LVR was now 111%, based on the valuation completed in 2006. It also said it had complied with its obligations to provide assistance to the Applicant. 43. Several months were then spent with FOS taking submissions and forming a view on whether FOS should consider the issues raised by the Applicant in his dispute, given he had signed the Deed on 20 November 2010. As stated earlier, the FSP consented to FOS considering the dispute under paragraph 4.4 of the TOR and FOS proceeded to investigate the issues relating to the events that occurred after the Deed was signed. 44. In addition to the submissions about whether FOS should investigate the dispute, the Applicant also requested, on 24 May 2012, a three months “freeze” on the Facility, in which time he prom ised to catch up on the arrears (the 24 May 2012 Proposal). He said he could resume repayments of $800 per week after the three month period. He also submitted that the Security Property was now worth $689,500, based on its insured value, and he said he was seeking independent valuations to confirm this. 45. The FSP declined this proposal on 2 August 2012. It offered the Applicant until 31 August 2012 to repay the arrears, which were $26,822.75 at that time. It said that if the arrears were not cleared in that time it would allow the Applicant to provide a Listing Agreement by 14 September 2012 and, once received, a further 90 days to obtain an unconditional contract of sale for the Security Property. It also agreed to work with the Applicant to negotiate a repayment arrangement on any shortfall debt remaining after the sale. Case No:271353 Determination Page 7 of 14 46. The Applicant did not respond to this offer and on 3 October 2012, the FSP said it would not agree to any further extension of time to achieve a voluntary sale if an unconditional contract of sale was not obtained within the proposed 90 day period. The Applicant has not responded to FOS or the FSP. He told FOS on 29 April 2013 that the Security Property has been valued by him but that he had not, as yet, listed it for sale. 47. The account statements show that the Applicant made payments of $800 in July 2012, $500 in August 2012, and three payments of $1,000 in September 2012. The last payment received on the Facility was $1,000 on 20 September 2012. The account is currently $51,343.97 in arrears. The Applicant has not provided a Statement of Financial Position (SOFP) as requested by FOS on 28 August 2012. In a conversation with FOS on 29 April 2013, the Applicant said there had been some health and family issues which resulted in them losing track of the payments in recent months. He requested a further period of time to sell the Security Property himself. Analysis 48. I am satisfied that the FSP gave genuine consideration to the Applicant’s requests for assistance from 28 January 2011 until 15 November 2011 and from 30 January 2012 until the current date. 49. I am not, however, satisfied that the FSP genuinely considered the Applicant’s financial difficulty from 2 December 2011 until 30 January 2012. My reasons for this are as follows: 28 January 2011 until 15 November 2011 50. The FSP met its obligations to try to assist the Applicant to overcome his financial difficulty for the period from 28 January 2011 until 15 November 2011. The reasons for this are as follows: The FSP granted him an extension of time on 28 January 2011 to pay the December 2010 and January 2011 payments The FSP sent the Applicant a hardship application to complete after being advised on 15 March 2011 that he was waiting for an insurance claim to be paid, but this was not returned by the Applicant The FSP paid outstanding rates on the Security Property on 18 March 2011 to stop any further enforcement of that debt against the Security Property The FSP sent the Applicant a hardship application to complete on 18 October 2011 after the Applicant’s spouse said that they had experienced a positive change in their circumstances On 15 November 2011, the FSP allowed the Applicant further time to return the hardship application rather than issuing a default notice. 51. The information provided by the Applicant in conversations with the FSP during this period indicated that his difficulties were not likely to be long term Case No:271353 Determination Page 8 of 14 in nature, however his repayments were sporadic. He had indicated to the FSP that he had resumed working after losing his job earlier in the year which suggested that, once the insurance claims were resolved, he would be able to resume his repayments and continue to service the Facility. 52. The FSP was entitled to request information from the Applicant about his financial situation in order to make an assessment of what options were available to him, and by asking for this information on 15 March 2011 and 18 October 2011 the FSP demonstrated genuine consideration of his situation. 53. The Applicant missed a few payments in this period, and the FSP was entitled to enforce the debt under the Deed. It did not do so however, and by paying his overdue rates and allowing him further time to submit a hardship application, the FSP gave him an opportunity to overcome the issues that had resulted from the January 2011 fire at his home and loss of his job. 2 December 2011 until 30 January 2011 54. I am not, however, satisfied that the FSP genuinely considered the Applicant’s financial difficulty from 2 December 2011 until 30 January 2012. My reasons for this are as follows: Although the FSP received the 2 December 2011 Hardship Application an d made a decision to decline the Applicant’s request to consolidate the arrears, it did not effectively communicate the reasons for declining assistance in the letter dated 8 December 2011. In this letter it said its reasons for declining assistance were based on its view that the Applicant could not improve his financial situation sufficient to repay the arrears. However, the actual reasons for declining the Application appear to have been its view that the Applicant could afford to repay the arrears but had failed to do so, and its concern about the LVR position. By not communicating the actual reasons for declining the Application and clearly stating how these reasons were referable to the Applicant’s situation, the FSP’s response left the Applicant with no clear idea as to why his hardship request had been declined. It follows then, that the Applicant was not afforded an opportunity to address the FSP’s concerns. I am also of the view that the FSP failed to take into account the Applicant’s statement in his 2 December 2011 Hardship Application that he had experienced a recent, unexpected event of hardship caused by the truck accident, which resulted in him being out of work. At that point, he said that his hardship appeared to be short term, and that he believed he would be able to resume full repayments after a short period of assistance, that is, after February/March 2012. I consider that where an unforseen new event of financial difficulty has occurred, the FSP should review any new request for assistance with fresh eyes, notwithstanding any previous agreements. This may occur after a period of financial difficulty assistance has come to an end or Case No:271353 Determination Page 9 of 14 during a period of financial difficulty assistance if the new event could not have been reasonably foreseen at the time the period of assistance commenced. If a reasonable alternative is available that will help the Applicant overcome their financial difficulty, it should not be overlooked purely because the Applicant was previously unable to maintain an agreement. In this dispute, the Applicant was unfortunate in experiencing a new event of financial hardship in November 2011, having not sufficiently recovered from the fire at the Security Property in January 2011. However, he believed at that time that the settlement of the insurance claim and a payout from Work Cover would enable him to repay the arrears and was seeking a short term arrangement of three months to be able to do so. Curiously, although the FSP declined the 2 December 2011 Hardship Application, it then agreed to a short term arrangement with his spouse to avoid further enforcement of the debt. The arrangement, to pay $3,000 within 28 days and resume weekly payments of $800, does not appear to have been confirmed in writing and it is not clear what the required time frames were for clearing the arrears under the arrangement. Although, I acknowledge that the FSP was trying to work with the Applicant at this point to delay enforcement action, it would have been preferable for the FSP to give greater consideration to the information it had before it and commit to a formal arrangement rather than a short delay on enforcement activity with an agreement to repay a lump sum, especially as the payment of the lump sum could not be guaranteed and the timefra mes were outside of the Applicant’s control. The uncertain time fame for the lump sum payment would have been clear to the FSP when the Applicant called in the middle of January 2012 to say that the payment had been delayed and would be paid in mid February 2012. However, instead of re-evaluating the options that were available at that time, the FSP proceeded to enforce the Deed. I consider that, if the FSP had genuinely considered the Applicant’s financial difficulty from 2 December 2011 until 30 January 2011, it would have provided him with a three to six month period in which to repay the arrears, either by increasing his repayments in addition to (or as an alternative to) accepting the payment of the $3,000 lump sum. At the time he applied for assistance, the available information suggested that his difficulties were short term and that he had sufficient income to make repayments. The arrears were approximately $8,000 and I see no reason why the FSP could not have arranged for him to repay these over a six month period. His SOFP suggested he could afford an additional $1,500 per month and he should have been given the opportunity to try and overcome his present financial difficulty, despite having struggled to meet previous arrangements. Case No:271353 Determination Page 10 of 14 At this time, the contact notes demonstrate that the Applicant was working with the FSP to generate options. By failing to articulate the reasons for declining his proposal to capitalise arrears or provide any reasonable alternative, the FSP did not effectively work with the Applicant. 55. I consider below whether the Applicant is entitled to any compensation for the FSP’s failure to consider his financial difficulty for this period. 30 January 2012 until current date 56. I am satisfied that the FSP has engaged with the Applicant since the dispute was lodged with FOS on 30 January 2012 until the current date. 57. Since the dispute has been with FOS, the Applicant has made two proposals to “freeze “interest and repayments for a period of three months. Although the Applicant does not specify it, I take these proposals to mean that he wanted the FSP to capitalise the repayments (including interest) for a three month period to allow him to make his normal weekly repayments of $800 and “catch” up on the arrears. The minimum monthly repayments at this time were approximately $2,500 so the $800 weekly would have covered the minimum monthly payment with approximately $500 additional to pay down the existing arrears. 58. It is not clear how the Applicant expected a three month moratorium on repayments, without the capitalisation of the existing arrears, would have allowed him to catch up on the arrears if he was only making the minimum repayments plus an additional $500 per month. When he made the 30 January 2012 proposal, the arrears on the Facility were approximately $10,000. By the time he requested this arrangement again on 24 May 2012, the arrears were approximately $20,000. 59. If the FSP had placed on “freeze” on the repayments for the three month periods proposed, without capitalising the existing arrears, the Applicant’s position would have continued to worsen as the repayment amount proposed by the Applicant was not sufficient to meet the required repayments and significantly reduce the existing arrears. 60. This means that these proposals would not have resulted in the repayment of the existing arrears in a reasonable period. Further, if the FSP had agreed to an arrangement of this nature, and the Applicant did not make all promised repayments, he would have been in a worse financial position at the end of the arrangement. On this basis, I am satisfied that these proposals were not reasonable and the FSP was entitled to reject them. 61. For its part, since the dispute has been with FOS, the FSP has offered the Applicant time to voluntarily sell the Security Property and to enter into negotiations to assist him with the repayment of any shortfall debt. I am satisfied that the FSP made these offers, in August 2012 and October 2012, after careful consideration of the Applicant’s position, including the increasing arrears position, and that it communicated its reasons for these Case No:271353 Determination Page 11 of 14 decisions in writing to the Applicant. The Applicant has had sufficient time to respond to the FSP’s options or listing the Security Property for sale, but has failed to do so. 62. I would also note that the Applicant has not worked with the FSP to provide information to assist the FSP in generating further options. The Applicant has an obligation to work with the FSP by responding promptly to all reasonable requests for information, however he has to date failed to provide a Statement of Financial Position despite being requested to do so on several occasions. 63. This means that the FSP has been unable to assess what temporary or longer term assistance might be appropriate. The Applicant has also to date failed to provide a realistic repayment proposal that would see the debt, including arrears, repaid within a reasonable timeframe. In these circumstances, I do not consider that the FSP acted incorrectly when it declined the Applic ant’ s requests for further assistance since the dispute was lodged with FOS. Is the Applicant entitled to any compensation? Financial Loss 64. As referred to earlier, I am of the view that if the FSP genuinely considered the Applicant’s request for financial difficulty assistance on 2 December 2012, it would have provided a reasonable period, without enforcement of the debt, for him to repay the arrears through either a repayment arrangement or through a lump sum payment, or a combination of both. I view a six month period without enforcement of the debt in which the Applicant could repay the arrears through either or both of these methods, as being a reasonable arrangement based on the information available at that time. 65. If the Applicant had been afforded this opportunity he would not have been charged legal costs in the amount of $1726.27 charged to the account on 12 March 2012. I have had regard to the Invoice 297233 for the legal charges passed onto the Applicant on this date. As the charges relate to enforcement of the debt from 17 November 2011 to 25 January 2012, when the FSP should reasonably have entered into an arrangement with the Applicant to repay the arrears, I am not satisfied that the Applicant would have incurred them if the FSP had genuinely considered his position on 2 December 2012 and provided him with a reasonable period to overcome his difficulties. 66. I acknowledge that some of the Fees in Invoice 297233 were incurred for professional services charged before the FSP received the Applicant’s 2 December 2011 Hardship Application, however as the costs are not separately itemised, I have been unable to determine what portion of the total amount of $1726.27 these constitute. As such, I view a refund of the total amount of $1726.27 as reasonable in these circumstances. Case No:271353 Determination Page 12 of 14 67. The FSP should refund this charge the Applicant by refunding the charge and recalculating the Facility balance on the assumption that this charge was never applied. 68. No default interest charges were applied to the Facility for this period and the FSP is entitled to charge standard interest charges for this period. Non-financial loss 69. Claims for non-financial loss include claims for distress, inconvenience, anxiety and disappointment. 70. It is only in limited circumstances that compensation is considered for non- financial loss. An award for such damage is unlikely to be substantial. In assessing whether an award may be made for such loss or damage, I expect Applicants: To be moderately robust in the way in which they deal with a problem To take responsibility for ensuring that their financial affairs are in order in the ordinary course of the transactions concerned; To bear the ordinary and normal degree of inconvenience associated with correcting an unexpected problem; and To take reasonable steps to minimise the inconvenience suffered. 71. I have considered whether the Applicant is entitled to any compensation for the FSP’s failure to consider his financial difficult from 2 December 2011 until 30 January 2012. In assessing this, I have had regard to the fact that, by not: adequately explain why his application for assistance was deficient, which would have increased his stress and uncertainty acknowledging that his new event of financial difficulty, the truck accident, was a separate event and a further setback for him engaging with him when he called to advise on 16 January 2011 that the payment of the $3,000 lump sum would be delayed until the middle of February 2011, the FSP is likely to have caused the Applicant to suffer undue anxiety and distress. 72. In my view, the Applicant is entitled to an award of $200 to compensate him for non- financial loss suffered as a result of the FSP’s failure to meet its obligations during the period from 2 December 2011 to 30 January 2012. The $200 should be paid to the Facility in reduction of the debt owing. Contract variation 73. I may elect to exercise my power under clause 9.1(f) of the Terms of Reference to vary a credit contract that is regulated under the National Case No:271353 Determination Page 13 of 14 Credit Code. I may do this in circumstances where an applicant has made a reasonable request for a variation to a credit contract that will assist in overcoming their financial difficulties, and the financial services provider has refused the request. 74. When considering whether to exercise my power to vary a credit contract, I will take into account the a pplicant’s current financial circumstances, and whether the applicant can show that their financial circumstances will improve after a reasonable period of assistance such that they will be able to meet their contractual obligations after that time. Do I have the power to vary the facility contract? 75. On 1 July 2010, the National Consumer Credit Protection Act 2009 (Cth) came into effect. Pursuant to that Act, a contract that had previously been regulated by the Uniform Consumer Credit Code (UCCC) and had not been discharged prior to 1 July 2012 became regulated by the National Credit Code (NCC). The provisions of the UCCC were in operation in August 2006 when the facility was approved. 76. A credit contract was regulated under the UCCC if it was granted primarily in relation to personal, domestic or household use. Specifically, the UCCC did not apply to loans for business or investment purposes. 77. As the purpose of the facility was to enable the Applicant to purchase a residential property, I consider that the facility was originally regulated by the UCCC. As the facility remains on foot, it is now regulated by the NCC. This means that I have the power to vary the facility contract. Should I exercise my power to vary the facility contract? 78. I will only exercise my power to vary a credit contract where I am satisfied that such a variation would assist the Applicant to overcome his financial difficulty. In considering whether to vary the Facility, I also need to take into account the FSP’s response. 79. I have said above that the FSP provided the Applicant with 90 days to voluntarily sell the Security Property in August 2012 and October 2012. It is my view that this was a reasonable response in the circumstances as the Applicant has not proposed any arrangement that would result in the arrears being repaid in a reasonable period, nor provided any further information to allow the FSP to generate any other options. 80. The Applicant has not provided an up to date Statement of Financial Position, despite being requested by FOS to do so. I have not been able to form a view on what the Applicant’s current living expenses or income are. Further, I have not been provided with any information to show that the Applicant’s fina ncial position will improve in the foreseeable future such that he would then be able to service the minimum monthly payments under the Facility. Case No:271353 Determination Page 14 of 14 81. As I have not been provided with any financial information by the Applicant to show that he could repay the debt, it is my view that there is no contract variation that would reasonably be open to me to require the FSP to make. 82. It is relevant that the Applicant has not made any repayments to the Facility since September 2012 and the payments were sporadic for a year prior to this. This means that in a period of more than eighteen months the Applicant has been unable to overcome his financial difficulty and return to making full repayments and also clear the arrears. The FSP is not under an obligation to support the Applicant indefinitely and I would not compel it to do so. 83. The FSP offered the Applicant 90 days to sell the Security Property himself on 3 August 2012 and 2 October 2012 but the Applicant did not accept this offer. He is now seeking further time to sell the Security Property himself. The Applicant has had sufficient time to arrange a sale but has not done so. In the circumstances, the FSP should be permitted to take steps to sell the Security Property. Determination 84. On the basis of the available information I determine that the FSP gave genuine consideration to the Applicant’s requests for assistance from 28 January 2011 until 15 November 2011 and from 30 January 2012 until the current date. 85. I am not, however, satisfied that the FSP genuinely considered the Applicant’s financial difficulty from 2 December 2011 until 30 January 2012. If the FSP had genuinely considered his request for assistance he would not have incurred $1726.27 in legal fees and these should be refunded to the Facility, with the Facility balance recalculated to reflect the refund and any interest that was charged on these fees. 86. The Applicant should also be compensated $200 for the stress and inconvenien ce caused by the FSP’s conduct and this amount should be paid to the Facility in reduction of the debt owing. 87. It is not appropriate for me to exercise my power to vary the credit contract. 88. Upon closure of the FOS dispute file, the FSP is entitled to exercise its contractual right to recover the debt owing to it.