Landlords claimed loss of rent, agent's fees and utility costs after a kitchen fire. The FSP paid six weeks of loss of rent. AFCA ordered a further 12 weeks of loss of rent plus the electricity and gas costs with interest, but refused the later rent and the agent's fee.
The policy covers loss of rent while the building is uninhabitable during repairs, and does not extend to rent lost after repairs where the tenants' departure was not shown to be caused by the insured event.
Issues
- Claim denial primary · upheld
“FSP paid six weeks of loss of rent; Panel finds repairs took 18 weeks and orders a further 12 weeks at $330 per week.”
- Claim amount dispute secondary · upheld
“Panel orders the FSP to indemnify the full electricity bill and gas expenses for the repair period, being $279.45.”
- Delay secondary · not upheld
“No evidence the tenants vacated because of repair delays, so loss of rent beyond the repair period is refused.”
Subjects and remedies
home or building damagepay claimpay interest
Text of the determination
Case No: 271268 Determination Page 1 of 8
Case number: 271268
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
7 August 2012
Background
1. The Applicants held a Home Building Insurance Policy (the Policy) with the
Financial Service Provider (FSP), subject to a $500 excess.
2. On 9 December 2010, the Applicants contacted the FSP to lodge a claim for
fire damage to the kitchen, caused by the tenants who were residing at the
property.
3. The FSP first assessed the property on 14 December 2010. The repairs
were authorised on 22 February 2011. Repairs commenced on 26 June
2011 and were completed around 3 October 2011.
4. The tenants vacated the Applicants‟ property at the end of their lease, in
April 2011.
5. The Applicants say the tenants vacated the property due to the FSP‟s delay
in completing repairs. The Applicants claim for loss of rent from 6/4/2011 to
22/12/2011 and agents ‟ fees. The Applicants also claim for gas and
electricity costs for the period when repairs were being undertaken.
6. The FSP agreed to pay for 6 weeks of loss of rent plus electricity usage. The
remainder of the claim has been denied on the basis that the repairs were
delayed by the Applicants.
Summary of Applicants ’ position
7. The FSP has taken 9 months to repair the kitchen, despite the Applicants
repeatedly requesting the FSP to arrange to have repairs started, so as not
to inconvenience the tenants.
8. The FSP disconnected the power from the main switch for one part of the
house, including the formal sitting and dining areas and part of the kitchen.
The tenants were unable to pull up the electric shutters in these areas and
had to keep the lights switched on during the day as it was dark otherwise.
Determination
Case No: 271268 Determination Page 2 of 8
9. The tenants were unable to live comfortably without a complete kitchen and
without power to a part of the house. They therefore chose to vacate the
property upon expiration of their lease, in April 2011. They had previously
resided at the property for 2 years.
10. The Applicants say they contacted the FSP and the repairers on several
occasions since December 2010 to have repairs commenced and lodged a
complaint in regards to the delays in February 2011.
11. The colours and material to be used for the kitchen were picked by the
Applicants in February 2011. Appliances were chosen and paid for by the
Applicants in June and July 2011 and were delivered on 15 July 2011.
12. The repairers eventually used kitchen handles and tiles that were easily
available to them, not those chosen by the Applicants.
13. The repairs were completed and keys returned to the Applicants at the end
of November 2011, which is when they could readvertise the property for
new tenants. The Applicants say repairs took 27 weeks to be completed.
14. The FSP‟s delay has caused the Applicants menta l stress and financial loss.
15. The Applicants claim for loss of rent from the time the tenants vacated on 6
April 2011 until the time new tenants moved in to the property on 22
December 2011, at $330 per week.
16. The Applicants also claim for the real estate a gent‟s letting fee of one weeks
rent and electricity and gas charges after the tenants vacated. The
Applicants say there was no one living in the house when repairers started
work and they required electricity and gas connections to complete repairs
and test appliances. No one else used these services and these costs would
not have been incurred had repairs been completed when tenants were still
at the property.
Summary of FSP’s position
17. The FSP has paid the Applicants loss of rent for the reasonable time it would
have taken to complete repairs, being 6 weeks. The repairer has confirmed
that repairs could have been completed within 30 working days, if not for
delays caused by the Applicants.
18. The FSP says the tenants vacated the property in April 2011 as their lease
had expired and not due to the incomplete repairs. The Applicants have
provided no evidence to the contrary.
19. Further, after make safe works were completed 5 days after the fire, the
tenants were still able to use the kitchen for cooking. They continued to
reside at the property for 5 months after the fire, before vacating.
Case No: 271268 Determination Page 3 of 8
20. The delays in commencing and completing repairs were due to the
Applicants and not the repairer. Repairs were authorised in February 2011
but the Applicants had requested the repairers hold off commencing repairs
until the tenants had vacated the premises.
21. The repairers also advise that repairs were delayed due to the Applicants‟
busy work schedules, which made it difficult for appointments to be
arranged.
22. Repairs commenced on 27 June 2011 and were completed on 3 October
2011, with delays experienced throughout the repair process due to the
Applicants, as they had to choose doors, handles, kitchen colours and
appliances. The FSP says there were delays in having the appliances
delivered and items manufactured.
23. The Applicants are not entitled to loss of rent after the repairs were
completed.
24. The FSP says the repairers did not require a gas connection to complete
repairs and the gas charges are therefore denied. The FSP agrees to pay a
part of the electricity cost subject to the Applicants providing an itemised bill
so the FSP can determine the exact usage costs.
25. The FSP relies on the following policy provisions:
“ We pay for loss of rent
We will pay for the loss of rent incurred by you while your landlord building is
being rebuilt or repaired if:
Your landlord building has been damaged or lost by an insured event,
and
We agree your landlord building is no longer habitable, and
Your tenant was paying rent due under a current rental agreement
with you for at least for consecutive weeks proceeding the date the
damage or loss occurred.
We also pay loss of rent if:
We agree that access to your landlord building is prevented by
accidental damage or loss to other property near your landlord
building,
And
Your tenant was paying rent due under a current rental agreement
with you for at least four consecutive weeks proceeding the date the
damage or loss occurred.
Our payment will be actual loss of rent incurred by you during the reasonable
period up to 12 months required to repair or rebuild your landlord building or
to restore access to your landlord building and it is otherwise habitable. ”
Case No: 271268 Determination Page 4 of 8
Issues
26. Whether the Applicant is entitled to additional payments for loss of rent.
27. Whether the Applicant is entitled to:
a. Agents fees
b. Gas expenses
c. Electricity expenses
Reasons for decision
28. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with clause 8.6 of the FOS Terms of Reference. This
is due to the circumstances and quantum of the dispute. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
29. I am satisfied that a full exchange of information has take n place between
each party and that each party has had the opportunity to address any
issues raised.
30. Based on the evidence, the parties agree on the following:
a. The Applicants had a valid Policy at the time of the event
b. The kitchen was damaged by an insured event
c. The home was considered uninhabitable while repairs were being
undertaken
d. There were considerable delays between the date of loss and when
repairs were completed.
31. According to the terms of the Policy, the Applicants are entitled to loss of
rent payments for the period the home was being repaired, if it is established
that the loss was caused by an insured event, the building was no longer
habitable and the tenants were paying rent for four consecutive weeks prior
to the date of loss.
32. The loss occurred in December 2010, when the tenants were living at the
property and paying rent. The tenants had been at the property for 2 years.
The fire in the kitchen is an insured event under the Policy. According to the
repairer, the property was inhabitable while kitchen repairs were being
undertaken.
33. Accordingly, it is clear that the Applicants have an entitlement for loss of rent
payments under the Policy.
34. What is in dispute is the length of this entitlement and the cause of the
delays.
Case No: 271268 Determination Page 5 of 8
Loss of Rent
35. The FSP says that the total repair period was from 27 June 2011 to 3
October 2011. The repairer says the property was unliveable for a period of
6 weeks, from 11 July 2011 to 31 August 2011. Loss of rent has been paid
for this 6 week period.
36. The Applicants say repairs were not complete until the end of November
2011, when the keys to the property were returned to them by the repairer.
The Applicants say that further unrepaired damage was discovered after 3
October 2011, which the repairers had to rectify.
37. The Applicants say the property was unable to be placed on the market until
repairs were completed and the keys were returned.
38. Having considered all the correspondence and claim notes provided, I note
the following:
a. In an email dated 20 February 2011, the repairer advises the FSP:
Repairs were authorised on 22 February 2011
The Applicants advised not to proceed with repairs until tenants had
vacated the property
The repairer met with the Applicants at the property on 16 June
2011
Stripping and demolition of the kitchen commenced on 27 June
2011
Stone top was installed on 21 August 2011
Appliances were installed on 1 September 2011 following some
delays
Tiling was completed on 29 September 2011, following delays by
the Applicants who had no time to look for tiles and left it up to the
repairer
Repairer had meeting with Applicants on 3 October 2011 to finalise
repairs.
b. Claim notes dated 28 October 2011 indicates that a claims
representative contacted the repairer, who advised:
Kitchen was pulled out on 11 July 2011 and replaced on 31 August
2011.
The house was unliveable during this 6 week period.
c. The Applicant states:
They selected stone top and cabinets in February 2011 from a
factory next door to the repairer, to minimise delay.
Tiles, handles and stone were selected prior to tenants vacating
premises.
Case No: 271268 Determination Page 6 of 8
Repairers did not end up using the handles and tiles chosen by the
Applicants as they were not available at Bunnings. Handles and
tiles were chosen by the repairer based on what was available to
him.
Repairs commenced on 27 June 2011
Appliances were delivered on 15 July 2011. Appliances were
chosen from a supplier in Thomastown, who knew the repairer and
would supply them quicker.
During the inspection on 3 October 2011, the Applicants pointed out
some repairs which were incomplete. The repairer kept the keys to
the premises to complete this additional work. Paint work was
completed after this.
Keys were returned to the Applicants at the end of November 2011.
Keys were immediately handed to the real estate agent to advertise
the property for new tenants.
39. I note that the repairer provides conflicting information in regards to when
repairs commenced and were completed. The period the repairer estimates
the premises was unliveable for is inconsistent with the repair timeline
provided in the email dated 20 February 2011. While he says the property
was unliveable from 11 July 2011, he also says the demolition began on 27
June 2011.
40. Neither the repairer nor the FSP provides any information in relation to the
additional repair works that had to be undertaken after 3 October 2011.
41. Based on the evidence, I am satisfied that the repair period commenced on
27 June 2011 but was not complete until sometime after 3 October 2011,
taking into account the additional repair works that had to be completed.
42. The Applicant says the repairs were completed and keys were returned to
them at the end of November 2011 but no exact date of finalisation has been
provided by either party. Accordingly, I consider it fair in all the
circumstances to estimate that all repairs would have concluded by early
November 2011, being the midway point between the dates offered by either
party.
43. The repairer attributes some of the repair time to delays by the Applicant in
selecting parts and Appliances. However, based on the invoices provided by
the Applicants I am satisfied that the Appliances were delivered on 15 July
2011 and were available to the repairer at the time of repairs.
44. While the FSP calculates that the time of repairs was 6 weeks, based on the
evidence, I am satisfied that the repair period was from 27 June 2011 to 1
November 2011, being 18 weeks.
45. Noting that the FSP has paid the Applicant for loss of rent for 6 weeks, I
consider it fair in the circumstances that the FSP indemnify the Applicant for
Case No: 271268 Determination Page 7 of 8
an additional 12 weeks of loss of rent, at $330 per week, for the time taken
to complete the repairs.
46. Due to the nature of the repairs, including installation of the kitchen and
cooking appliances, painting and tiling, I do not consider that the property
would have been „liveable‟ and in a condition to be re-let, until all repairs had
been completed.
Other Expenses
47. The Applicant says that the tenants vacated due to the FSP‟s delay in
commencing repairs. The claim notes indicate that the Applicants were
contacting the FSP on a regular basis since the date of loss, to follow up on
the progress of repairs . Claim notes also refer to the Applicants‟ expressing
concerns regarding the delay in repairs and the inconvenience to the
tenants.
48. I also note that the FSP was actively managing the claim at this time and
delays caused by the availability of contractors during the Christmas period
are beyond the control of the FSP.
49. There is insufficient explanation as to why repairs did not commence
between when the repairs were authorised and when repairs commenced,
except for the repairer ‟s advice that the Applicants requested waiting until
the tenants had vacated and a reference to the Applicants being unwell.
50. I note the Applicants claim that they frequently contacted the FSP before the
tenants vacated, requesting that the repairs commence. But at other points
of their submissions they do appear to indicate that they asked the repairers
to carry out repairs after the tenants vacated. Whilst I am inclined to accept
the Applicants‟ version of events I cannot conclude that they have
established that the tenants vacated due to the absence of repairs.
51. There is also no evidence to establish that the tenants vacated the property
due to the lack of repairs, either by way of a statement from the tenant or
any claim notes to the effect, at the time the tenants vacated the property.
Due to the lack of such evidence, I accept that there is a possibility that the
tenants would have chosen to vacate at the end of the lease period
regardless of the state of the repairs.
52. Accordingly, I do not consider that the FSP is liable to pay for the loss of rent
for the period outside the time taken to complete the repairs.
53. I also do not consider that the FSP is liable to pay the agen t‟s cost for re-
letting the premises. This is not an expense covered under the Policy and
there is insufficient evidence to attribute this cost to the FSP‟s actions.
Case No: 271268 Determination Page 8 of 8
Gas and Electricity Expenses
54. The FSP has agreed to pay for electricity usage during the time of repairs.
The FSP refuses to pay for the connection fees noting that this would have
been incurred by the Applicants in any event.
55. However, noting that the connection was only activated during the period of
29 June 2011 to 30 September 2011 for the purposes of conducting the
repairs, it is fair in all the circumstances that the FSP indemnifies the
Applicants for the complete electricity bill. This is a cost directly associated
with the repairs and would not have been incurred by the Applicant but for
the repairs.
56. The FSP denies the claim for gas expenses noting that repairers did not use
the gas connection during repairs. The Applicant advises that the gas
service had to be activated for the purpose of testing the Appliances upon
completion of repairs. The gas bills indicate that the service was connected
from 30 June 2011 to 14 September 2011, which is the period of repairs.
57. For the reasons noted above, it is fair in the circumstances that the FSP
indemnify the Applicants for the gas expenses, as this is also a cost
associated with the repairs and would not have been incurred otherwise.
Determination
58. On the basis of the available information I determine :
a. The FSP must pay the Applicants an additional 12 weeks of loss of rent
at the rate of $330 per week, being $3,960.
b. The FSP must pay the Applicants the costs of the gas and electricity
bills incurred during the period of repairs, being $279.45.
c. The FSP must pay interest on the above payments, at the appropriate
rate, from 20 February 2012 when the IDR Decision was made, until
the date of payment.
d. The FSP must make payment as per this Determination, within 14 days
of acceptance of the Determination.