Text of the determination
Case No: 271009 Determination Page 1 of 9
Case number: 271009
Investments - Managed Investments - Mixed Asset Fund/s - Disclosure -
Misleading product/service information
20 November 2013
Summary
Description
The Applicant seeks compensation for deductions made by the
Financial Services Provider (FSP) for fees and costs following his early
withdrawal from a managed investment scheme.
The Applicant contended that:
i. the product ’ s Product Disclosure Statement (PDS) was defective
and misleading in respect to the nature of its capital guarantee and
the early withdrawal fee and other costs
ii. the early withdrawal fee was exorbitant
iii. there was no evidence on how it was calculated, and
iv. he was not liable to pay the fees and costs.
The FSP denied liability and relied on the PDS that provided that the
investment was capital guaranteed upon maturity and set out the basis
upon which the early withdrawal fee and costs were calculated. It
contended that the early withdrawal fee was calculated in accordance
with the PDS.
Basis for Determination
The PDS adequately disclosed both the capital protection limit and the
early withdrawal fee.
The amount of the early withdrawal fee was not excessive.
Determination
The FSP was not liable to pay compensation to the Applicant.
Determination
Case No: 271009 Determination Page 2 of 9
Background
1. This dispute is about the early withdrawal fee charged to the Applicant by the
FSP, the responsible entity for a managed investment scheme (S scheme),
following the Applicant’s withdrawal of his investment from the S scheme.
The investment was capital protected if held to maturity but fees were
payable upon early withdrawal.
2. The Applicant invested $500,000 in the scheme in mid 2009 upon the advice
of an authorised representative of Company U. The investment was 100%
funded by a loan from Company L. The Applicant agreed to be bound by the
terms of the S scheme’s PDS. He applied for early withdrawal from the S
scheme in November 2011.
3. The withdrawal application was finalised on or about 23 November 2011.
The proceeds available to pay Company L (net of monthly fees, including a
fee for November 2011) totalled $511,088.73. This did not include accrued
income of $5,074.04 or returns for November 2011, paid to Company L in
January 2012).
4. However, before the funds were paid to Company L, the FSP deducted an
early withdrawal fee of $48,650. As a result, only $462,438.73 was paid to
Company L to reduce the margin loan (including accumulated interest),
leaving the Applicant with a shortfall.
5. The Applicant alleges the PDS was misleading and deceptive in its
description of both the capital protection feature and the early withdrawal
fee. He also challenges the correctness of the early withdrawal fee. 1
6. The FSP denied liability and contended that the PDS was not defective or
misleading and deceptive.
The Applicant position
7. The Appli cant’s initial position is contained in the Recommendation.
The FSP position
8. The FSP’s initial position is contained in the Recommendation.
1 The Applicant also lodged a dispute against Company L, which resolved by agreement between the
parties, and a dispute against Company U, which did not proceed.
Case No: 271009 Determination Page 3 of 9
Conclusions in Recommendation
9. A FOS Legal Counsel provided the parties with a Recommendation on the
issues in dispute. The Recommendation was in favour of the FSP. A copy of
the Recommendation is attached to this Determination.
10. The Recommendation was not accepted by the Applicant.
Further submissions
11. The Applicant, in not accepting the Recommendation, provided the following
submission dated 26 August 2013:
“ [The Applicant] does not accept the recommendation and requests that the
matter proceed to a Determination.
The recommendation has failed entirely to recognise that [the FSP] [has]
admitted in their correspondence that they were never in a position to
determine the break costs and consequently could not and did not have the
capacity to advise [the Applicant] or his advisor of the break costs at the time
when he was considering entering into the investment.
The fact that [the FSP] provided information at the time when [the Applicant]
was in a position when he had no option other than to break the investment is
irrelevant. Your recommendation is therefore based on an irrelevant
consideration.
In addition, your subjective conclusion that [the Applicant] would still have
made the investment is not based on any evidence or fact and is your
personal opinion. However, that is also the basis of your conclusion and
therefore the conclusion is invalid.
You have not explained why you took so long to reach a conclusion. Was this
because you were under pressure from your colleagues to find in favour of
[the FSP] when you personally recognised that you should recommend in
favour of [the Applicant]?
It is readily apparent from this recommendation that while FOS readily make
adverse decisions against advisors whom they dislike, they will do everything
to protect the large entities who provide the flawed products that in fact are
the root cause of the losses.
No doubt FOS is unable to realise that if product providers ensured that their
products were designed appropriately and delivered as promised then
investors would not suffer losses and the concept of advice being appropriate
for an investor would be generally irrelevant. That is, even if advice to a
sophisticated investor is “appropriate” does not mean that products should
have inherent defects that result in losses.”
Case No: 271009 Determination Page 4 of 9
12. On 12 September 2013 the Applicant further submitted:
“ I would also wish to clarif y some points as it appears to me that the main
point of my argument has been completely missed.
1) Early termination fee, ref the below
I cannot comprehend that the FSP cannot offer a “realistic estimate”. How
could they possible know how they would make money from the product
without having a very clear picture of the full financial model and cost
elements of the below items
Also in regard to the inability to offer a realistic estimate, how can they say
that but also respond with
Clearly they had full knowledge of
a. My monthly fees
b. The costs were … committed….upon establishment of the
product”. I am assuming that the “product” was established prior to
the PDS being produced thus they did know the costs
I am sure that the FPS is perfectly capable and under disclosure requirements
bound to supply a realistic range of the percentage say 8-10%. However had
they done so I am sure that the product would have far fewer investors.
Frankly I cannot comprehend that the FOS would believe or indeed
support this statement.
2) The termination fee being available on the website is completely
irrelevant to this discussion due to the fact there is no disclosure of the
website until such time as investment in the scheme is made.
3) Your statement
Case No: 271009 Determination Page 5 of 9
I was in a position of financial stress and unable to meet the >$6,000 per
month running costs of this investment (fees + interest), it was keep going or
feed my family, I chose to feed my family.
There was no “willing” whatsoever.
My knowledge of the break fee at this time is irrelevant to my complaint. My
acceptance was forced by my circumstances. The relevant timing for
providing information about the quantum and impact of the break costs was
prior to investment. [The FSP] failed to do that and have acknowledged that in
writing to FOS. Consequently, FOS must take that admission into account and
must acknowledge that [the FSP’s] failure to disclose information which they
clearly must have been able to estimate has caused my loss.” [sic]
13. On 23 September 2013 the Applicant’s submissions w ere forwarded to the
FSP for comment. The FSP responded on 11 October 2013 as follows:
“ We refer to your letter of 23 September 2013 in which you advise that [the
Applicant] has advised FOS that he do es not accept the Recommendation
previously made by the Financial Ombudsman Service (FOS) and that
accordingly the dispute will be progressed for a Determination to be made.
[The FSP] wishes to provide the following statements in respect of comments
made by [the Applicant] in his email to FOS dated 12 September 2013
regarding the disclosure of the early withdrawal fee and [the FSP’s]
obligations regarding disclosure.
[The Applicant] states that he assumes the product was established prior to
the Product Disclosure Statement being produced.
This is in fact not the case. While the Separately Managed Accounts (ARSN
***530) was in operation, the [named product] that [the Applicant] invested in
was only established after all applications for that particular application date
were received. This is consistent with the explanation provided for the term
“Offer Period” on page 11 of the PDS, which states that the [named product]
may not proceed if a minimum investment amount was not obtained and that
once a client's Account is established, it may be held in cash until the
Investment Date, which may be up to 30 days following the end of the Offer
Period.
As stated in our letter of 16 March 2012, the first part of the strategy
implemented by [the Bank] to provide capital protection is effected by the
purchase of an over-the-counter European put option entered into at the
Investment Date with an exercise date that is the end of the Capital Protected
Period or Maturity. The Investment Date is defined in the PDS as the “date
(sic) the application moneys from the Offer Period is invested in the [FSP]
[named product] Index Model Portfolio”.
[The Applicant] also notes that [the FSP] should have been in a position to
provide a realistic range of the percentage of the early withdrawal fee and that
he believes [the FSP] were bound to do so under disclosure requirements.
[The FSP] has previously addressed why we believe we have complied with
our disclosure obligations.
Case No: 271009 Determination Page 6 of 9
[The FSP] remains of the firm view that the PDS is 'clear, concise and
effective' in that it discloses all relevant information in a way that promotes
understanding of the product. The PDS includes all of the information
prescribed in the Corporations Act 2001, associated regulations and ASIC
guidance, including Regulatory Guide 168: Disclosure: Product Disclosure
Statements (and other disclosure obligations) ('ASIC RG 168').
In relation to [the Applicant’s] statement that [the FSP] should have been able
to provide a realistic range, [the FSP] has previously set out its reasons for
not disclosing a range for the Early Withdrawal Fee in the PDS in our
submissions dated 16 March 2012 and 16 August 2012 respectively. For
clarity, [the FSP] wishes to restate that the purchase price of the put option
acquired to provide capital protection as part of the Static Strategy was not
known until the Investment Date (after all application monies had been
received) and that such price was heavily dependent on market volatility at
the time of purchase and reflects the market risk that that the counterparty
expected over the 7 year term to Maturity at the time of purchase.
Given that the calculation of the Early Withdrawal Fee charged to an investor
is dependent in part on the sale proceeds of the put option which, as outlined
above, was not purchased by [the Bank] until the Investment Date, it was not
possible for [the FSP] to disclose in the PDS at the time of issue a realistic or
meaningful range of the Early Withdrawal Fee before the put option was
actually purchased.
In addition to the sale proceeds of the put option, the Early Withdrawal Fee at
any time is also dependent upon a number of variable factors including [the
Bank's] break costs, market volatility, interest rates and the value of the
securities in an investor's portfolio.
Accordingly, for the reasons outlined above, it was not practicable or
reasonable for [the FSP] to accurately set out in the PDS at the time of issue
a range of the Early Withdrawal Fees that may be charged to investors for the
whole of the seven year capital protection period. For this reason, investors
had access to the actual early withdrawal fee which would have been levied
had they sought to withdraw from the [named product], calculated daily in
arrears.
In the closing paragraph of his email dated 12 September 2013, [the
Applicant] states “The relevant timing for providing information about the
quantum and impact of the break costs was prior to investment. [The FSP]
failed to do that and have acknowledged that in writing to FOS ."
In relation to the bolded text, [the FSP] reiterates, for the reasons provided
above, and in previous correspondence, that we have not failed to disclose
the required information in relation to the withdrawal fee (the break costs) and
have not acknowledged any such failing to FOS, in writing or otherwise.” [sic]
Case No: 271009 Determination Page 7 of 9
Ombudsman’s consideration
14. I have independently decided this case on its merits, having regard to the
relevant law, good industry practice, codes of practice and previous FOS
decisions. I have taken into account all the material submitted by the parties,
both before and after the Recommendation. I am satisfied that the
documentation I have relied on has been provided to both parties.
15. I have carefully considered the FOS Legal Counsel’s Recommendation,
together with the pa rties’ further submissions.
16. I am satisfied that the Legal Counsel’ s Recommendation contains an
accurate summary of the background to this dispute, the parties’ positions,
the issues to be determined, any applicable paragraphs of the Terms of
Reference and relevant law.
17. I note that the Applicant has made comments in respect of FOS’s impartiality
and implied that there was a bias in favour of larger FOS members. I point
out that FOS is an independent ASIC approved external dispute resolution
scheme charged with the obligation to resolve matters in accordance with its
Terms of Reference. It is transparent in its decision-making and does not
show a bias in favour of any party to a dispute before it.
18. Having considered all the material, I agree with the Legal Counsel’ s reasons
for the Recommendation and the recommended outcome. The
Recommendation relevantly discusses the disclosure made in the PDS of
the limit of capital protection and early withdrawal fee and the related use of
the FSP’s website. It also addre sses whether the early withdrawal fee was
excessive in a discussion of the FSP’s Constitution and PDS.
19. The Applicant has essentially challenged the operation of the S scheme in
respect of early withdrawals from the scheme despite the fact that he had
access to the Constitution, PDS and a financial planner to advise him upon
the investment before it was made.
20. If the Applicant or his adviser was dissatisfied with the disclosures made in
the PDS in relation to the basis for calculations of the break costs, the
investment could have been assessed as unsuitable and it need not have
been made.
21. The Applicant, upon making the application to invest in the S Scheme,
signed the application form in which he declared he agreed to be bound by
the PDS’s terms and conditi ons.
22. The PDS defined the extent of the “capital protected” period and made it
apparent to investors that the capital protection only applied if the investment
was held to maturity. It made it clear that withdrawals made prior to the
maturity would not rece ive capital protection. Further, the Applicant’s
adviser’s SOA given prior to the investment said:
“partial withdrawals are not allowed and capital protection does not apply on
early withdrawals.”
Case No: 271009 Determination Page 8 of 9
23. I am satisfied that the Applicant was aware of the limited nature of the capital
protection that applied to the investment at the time he made the investment.
24. The PDS also explained that an early withdrawal fee was payable upon
withdrawal made prior to the maturity of the investment. The PDS contains a
descripti on of the fee under the heading “Fees and other costs”. It sets out
the basis upon which the fee is calculated and draws attention to the fact
that as the fee can be variable due to certain market factors, the current fee
was available on the FSP’s website.
25. The Applicant has challenged the placement of the fees on the website
rather than disclosing a range of such fees in the PDS. The FSP argues that
it would not be realistic to do this. I agree with paragraph 29 of the
Recommendation, in which it was said:
“ As the amount of the fee reflects the cost of unwinding the capital protection,
it will necessarily vary over time and could not be disclosed in advance as a
flat percentage. In those circumstances, the explanation in the PDS is
adequate when combined wi th the reference to the FSP’s website for the
percentage amount of the current early withdrawal fee. ”
26. I am satisfied that the Applicant had been put on notice of the basis upon
which the early withdrawal fee was to be calculated and had access to the
curr ent fees on the FSP’s website.
27. The Applicant has argued that he did not willingly make the early withdrawal
reliant on the FSP’s website but as a consequence of the financial pressure
that he was under at the time. I understand the Applicant’s predicament but
am satisfied that this was not as a result of any failure of disclosure by the
FSP at the time the investment was made.
28. The Recommendation has explored in detail the issue of the excessive
nature of the withdrawal fee. FOS, under its Terms of Reference, cannot
consider a dispute about the level of fees in the absence of non-disclosure or
misrepresentation, incorrect application of the fee and the breach of a legal
obligation by the FSP. I find, from an examination of the documentation, that
there had been disclosure of the fee and that there was no
misrepresentation.
29. The Recommendation discusses the application of the Constitution together
with the PDS in respect of the entitlement to charge a withdrawal fee and
liability to pay such fee to the Bank. I agree with the Legal Counsel’s
analysis and conclusions.
30. I also confirm the Recommendation’s conclusion on other matters in
paragraph 56:
“ As I have concluded that the PDS adequately disclosed both the capital
protection and the early withdrawal fee, and that the amount of the early
withdrawal fee was not excessive, and no compensation should be paid, I do
not need to consider whether it would be the FSP, or its successor as
Responsible Entity, who would have to pay any compensation. ”
Case No: 271009 Determination Page 9 of 9
Determination
31. I determine in favour of the FSP.
Case No: 271009 Recommendation Page 1 of 9
Case number: 271009
Investments - Managed Investments - Mixed Asset Fund/s - Disclosure -
Misleading product/service information
07 August 2013
Background
32. The Financial Service Provider (FSP) was the responsible entity for the S
managed investment scheme (S scheme) until 7 December 2012, when it
was replaced by an unrelated company.
33. Relevantly, the S scheme provided separate accounts for each investor. In
this case, the underlying investment (the subject of its own Product
Disclosure Statement or PDS) provided exposure to “top 20” shares, and
was capital guaranteed if held to maturity (that is, seven years after the
investment was made).
34. The capital guarantee feature was secured by contracts (including options
contracts) between the FSP and a third party (“the Bank”). The Applicant
was not a party to those contracts.
35. The Applicant applied to invest $500,000 in the S scheme on 22 June 2009,
through his adviser, an authorised representative of Company U. The
investment was funded 100% by a margin loan from Company L.
36. The declaration signed by the Applicant as part of the application included
the following statement:
“This application is made upon and subject to the terms and conditions of the
PDS dated 30/4/09 which I/we have read.
I/we agree to be bound by the Constitution as it may be amended from time to
time and by the terms and con ditions as set out by this PDS.”
37. On 12 November 2011, the Applicant emailed his adviser asking to withdraw
from the investment. He expressly confirmed in his email that he understood
his portfolio value to be $531,874.22 and there would be an early withdrawal
fee of 9.65%. He stated he would forward a signed form “with the required
date soonest ” .
38. The FSP received the Applicant’s withdrawal application on 17 November
2011 at 10.28 am 2 .
2 Letter from the FSP to the Applicant dated 19 December 2011. The Applicant has not contradicted this
statement.
Recommendation
Case No: 271009 Recommendation Page 2 of 9
39. The withdrawal application was finalised on or about 23 November 2011.
The proceeds available to pay Company L (net of monthly fees, including a
fee for November 2011) totalled $511,088.73. This did not include accrued
income of $5,074.04 or returns for November 2011, paid to Company L in
January 2012).
40. However, before the funds were paid to Company L, the FSP deducted an
early withdrawal fee of $48,650. As a result, only $462,438.73 was paid to
Company L to reduce the margin loan (including accumulated interest),
leaving the Applicant with a shortfall.
41. The Applicant alleges the Product Disclosure Statement (PDS) was
misleading and deceptive in its description of both the capital protection
feature, and the early withdrawal fee. He also challenges the correctness of
the early withdrawal fee 3 .
Summary of Applicant’s position
42. The Applicant says:
The PDS gives the impression that the investment is capital protected
over the whole if its life, because:
a) This is implied by the use of the words “Capital Protected” in the
name of the scheme.
b) The “capital protection period” is defined as the life of the
investment.
c) The fees for capital protection were levied on an ongoing basis,
which implies that the capital protection was also ongoing.
This is misleading or deceptive, as the “capital protection” only applies
on maturity.
The early with drawal fee was an “exorbitant and unfair cost”, and
without basis. It should be disallowed as a penalty.
The FSP has not provided any evidence that it incurred any expense or
actual costs as a result of the early withdrawal, or any details of how
the calculation was made or how the percentage applied was
determined. It is improper for the FSP or the Bank to claim fees for
costs that have not been incurred.
The FSP says that the early withdrawal fee is payable to the Bank.
However, there is no agreement between the Applicant and the Bank,
and therefore the Applicant does not have any obligation to pay any
amount to the Bank.
3 The Applicant also lodged a dispute against Company L, which resolved by agreement between the parties,
and a dispute against Company U, which (at the time of this Recommendation) has not proceeded.
Case No: 271009 Recommendation Page 3 of 9
The FSP has not shown the cost of unwinding the capital protection
feature was $48,650 (the amount of the early withdrawal fee).
Sum mary of FSP’s position
43. The FSP says:
When the Investment Product was established, several capital
protection strategies or mechanisms were put in place by the Bank,
which were to be managed throughout the capital protection period and
were designed to remain in place until the maturity date (July 2016).
The early withdrawal fee represents the fees the Bank charged for
terminating the underlying capital protection arrangements early. In
particular, it represents the balance of the cost of implementing,
maintaining and closing out the capital protection that would have been
recouped by the monthly capital management fee, had the investor
remained in the investment until maturity.
These costs were effectively incurred or committed to by the Bank for
the duration of the capital protected period, and allocated to all investor
accounts upon establishment of the product. That is, the cost of the
protection strategy is effectively incurred from the beginning of the
capital protection period, and not on maturity.
The calculation of the Applicant’s ear ly withdrawal fee was based on:
unamortised capital management fee and other break costs; value of
unwound Vanilla put option; and value of unwound CPPI put option.
The value of the unwound put option was affected by volatility; interest
rates; and market prices for securities in the investor’s account.
Due to the impact that prevailing, daily market conditions have on
determining the early withdrawal fee, the FSP was not able to
accurately disclose in the PDS an exact fee or a realistic estimate or
range of the early withdrawal fee. Page 20 of the PDS highlighted this
and refers to the fee being made available online.
Pages 8, 13 and 15 of the PDS clearly state that “the capital protection
only applies if the product is held until Maturity”. The PDS also c learly
sets out the implications of termination of an investor’s account prior to
maturity, and the fees and costs which will be payable. The early
withdrawal fee is disclosed a number of times in the PDS.
The early withdrawal fee was deducted from the Ap plicant’s account in
accordance with the terms set out in the PDS, and in accordance with
the Scheme’s Constitution dated 16 June 2005.
Case No: 271009 Recommendation Page 4 of 9
Issues
44. Did the PDS for the S fund accurately and adequately describe:
a) The operation and limits of the capital protection feature?
b) The early withdrawal fee?
45. If the description was inaccurate or inadequate, to what extent did the
Applicant rely on it?
46. If the above issues had been adequately disclosed, what if anything would
the Applicant have done differently, and how would his current financial
situation have been different?
47. Did the early withdrawal fee exceed the amount the FSP was allowed to
charge?
48. In December 2012, the FSP was replaced as responsible entity 4 . To what
extent does this affect its liability (if any) to compensate the Applicant in
respect of the above matters?
Reasons for Recommendation
49. Under paragraph 8.2 of the FOS Terms of Reference, I am required to
decide what is fair in the circumstances of this dispute, having regard to the
following:
legal principles;
any applicable industry codes of practice;
good industry practice; and
previous relevant decisions of FOS (though I am not bound by these).
Did the PDS accurately and adequately describe the S scheme?
50. As the issuer of the S scheme, which was on offer to retail clients, the FSP is
required to issue a Product Disclosure Statement. Further, that statement
must not be “defective”.
51. A disclosure document is “defective” if it
contains a misleading or deceptive statement, or
4 Sections 601FS and 601 FT of the Corporations Act 2001 set out the extent to which liability would
pass to the successor responsible entity rather than remaining with the FSP. Essentially, liability will
remain with the FSP only if it could not reimburse itself out of the scheme property – which will
depend on whether it was (or would be) entitled to do so under the scheme Constitution, and whether
the expense or liability was occurred in the proper performance of its duties as responsible entity
(section 601GA).
Case No: 271009 Recommendation Page 5 of 9
fails to contain information about significant features of the product
including, among other things:
a) benefits to which a holder of the product will or may become
entitled (and when and how those benefits will or may be
provided);
b) significant risks associated with the product; or
c) any amounts which will or may become payable after the
investor acquires it 5 .
52. An inaccurate or incomplete description in the PDS may also constitute
misleading or deceptive conduct in relation to a financial product 6 , or
negligent misstatement. Any of these could entitle the Applicant to
compensation if he relied on the inaccurate or incomplete information, and
suffered a loss as a result.
Capital protection
53. The investment is called “capital protected” in its t itle, and the PDS defines
the “capital protected period as the seven year term of the investment. If
considered in isolation, either of these could give the impression that the
capital protection applied over the life of the product.
54. However, at numerous points throughout the PDS it is made clear that the
capital protection only applies if the investment is held until maturity. The
clearest of these can be found in the explanation of the capital protection
strategy on page 8:
“Capital Protection only appli es to investments held until Maturity.
Withdrawals prior to the end of the Capital Protected Period will not receive
the benefit of capital protection.”
55. Other statements to the same effect can be found at pages 5-6, and in the
description of “Capital Risk” on page 13.
56. I am therefore satisfied the PDS was not defective in its description of the
capital protection, or of its limits.
Early Withdrawal fees
The PDS
57. The fact that an early withdrawal fee would be charged on withdrawals prior
to maturity is explained in the PDS both at Page 15 under the sub-heading
5 Sections 1021B to 1013D, Corporations Act 2001 . ASIC has provided guidance on how these
disclosure obligations should be met, most relevantly Regulatory Guide 168.
6 Section 1041H Corporations Act ; see also section 12DA ASIC Act.
Case No: 271009 Recommendation Page 6 of 9
“Withdrawing your investment prior to maturity at page 20, under the heading
“Additional explanation of fees and other costs”, as follows:
An Early withdrawal Fee may be payable on amounts withdrawn … pri or to
Maturity. This fee is paid to [the Bank, which provides the capital protection for
the investment] for terminating your capital protection within the 7 year term”.
58. The description of the fee at page 19 under the heading “Fees and other
costs”, and a t page 20, confirms the fee is calculated daily by the Bank,
taking into account any costs associated with terminating the capital
protection, volatility, interest rates, and the market price for the securities in
the investor’s account.
59. The fee is calculated daily as a percentage of the withdrawal amount, and
because it varies it is not specified in the PDS. Instead, the PDS says it will
be available on the FSP’s website.
60. As the amount of the fee reflects the cost of unwinding the capital protection,
it will necessarily vary over time and could not be disclosed in advance as a
flat percentage. In those circumstances, the explanation in the PDS is
adequate when combined with the reference to the FSP’s website for the
percentage amount of the current early withdrawal fee.
The FSP’s website
61. Unlike the decision to invest, the Applicant’s decision to withdraw the
investment was also informed by the most recently available early
withdrawal figures on the FSP’s website.
62. Neither party has provided FOS with a copy o f the FSP’s website as at 12
November 2011, the date the Applicant relayed his request for early
withdrawal to his adviser. However, the figure quoted in the applicant’s 12
November 2011 email – 9.65% - is consistent with the figure the FSP says 7
was displayed from Friday 11 to Sunday 13 November 2011.
63. The web pages for the investment (on various dates which I have reviewed)
consistently state the early withdrawal fee “as at” the date of the immediately
preceding business day. The Applicant’s adviser infor med him in an email
dated 29 September that the calculation would always be “a day behind”.
64. A schedule of exit fees for the weeks leading up to 18 November 2011 show
that the exit fee fluctuated by as much as a full percentage point from one
business day to the next. However, as the Applicant was on notice that the
figures posted were a day behind, I do not consider this was misleading.
65. The applicant was willing to withdraw his investment in the awareness that
the exit fee was then 9.65% of his assets. He was also aware that this fee
was not the current withdrawal fee, which could be different.
7 16 August 1012 submission and schedule
Case No: 271009 Recommendation Page 7 of 9
66. I am satisfied that if he was aware the withdrawal fee would be 9.73% rather
than 9.65% - a difference of only 0.02% in what was a substantial fee - he
still would have proceeded with the withdrawal application.
Conclusion
67. As the PDS adequately disclosed both the capital protection feature and the
basis on which the early withdrawal fees would be charged, there is no basis
on which the FSP should compensate the Applicant for the losses arising
from any reliance on the information contained in it.
68. I therefore do not need to consider whether the Applicant relied upon the
relevant statements in the PDS, what he would have done differently if these
aspects of the investment had been disclosed in the way he says was
required, or what loss if any he suffered as a result.
69. However, without reaching any definite conclusions, I have doubts about the
Applicant’s claim that, if he had understood the limits of the capital
protection, he would instead have made no investment due to the volatility of
global markets 8 .
70. This investment could only be made through an adviser. The Applicant made
the investment through, and after receiving advice from, a financial planner.
He has provided extracts from the Statement of Advice (SOA) dated 19 June
2009 recommending the investment.
71. The pages of the SOA which have been provided suggest the investment
was recommended at least partly for its tax effectiveness – not (or at least
not primarily) for its capital protection. Further, page 37 of the SOA says:
“Partial withdrawals are not allowed and capital protection does not apply on
early withdrawal.”
72. Therefore, even if the PDS itself had not been clear enough on the limits of
the capital protection feature, the Applicant had been put on notice of those
limits by his adviser.
73. Under those circumstances, either he did not rely on the statements about
capital protection in the PDS, or any such reliance would have been
unreasonable. On either basis there would be no basis for compensation.
Did the early withdrawal fee exceed the amount the FSP was allowed to
charge?
74. FOS will not consider a dispute about the level of a fee or charge, except to
the extent there are allegations of:
non-disclosure
misrepresentation
8 Submission dated 23 January 2013 from the Applicant’s representative.
Case No: 271009 Recommendation Page 8 of 9
incorrect application of the fee or charge, or
breach of a legal obligation or duty, by the FSP. 9
75. For the reasons set out above, I am satisfied the fee was adequately
disclosed and there was no misrepresentation of how it would be calculated.
The Applicant has also alleged the fee was beyond what his contract with
the FSP (that is, the scheme constitution and the PDS) allowed. I have
considered this argument below.
The Constitution and the PDS
76. The Constitution for the S scheme, including a number of amending Deeds,
does not expressly provide for an early withdrawal fee. However, clause
10(g)(iii) allows the FSP to withdraw payments from an investor’s accounts
to settle any fees, charges, or expenses imposed on the investor’s
transactions or portfolio, or on the S scheme as a result of carrying out the
investor’s instructions. Further, clause 15.3 allows the FSP to pass on (to an
individual investor’s account) any expenses it incurs which are attributable to
that investor’s account.
77. This would include the early withdrawal fee, which is charged by the Bank to
unwind the options and capital protection provided for this investment.
78. The FSP says 10 that the fee charged by the Bank was made up of an
“Unamortised Capital Management Fee and other break costs” comprising
16.40% of the value of the portfolio, less the value of the unwound put
options (6.67% of the portfolio value).
79. While the FSP has declined to provide a copy of the break cost calculations,
because this is proprietary to the Bank 11 , it has provided copies of two put
options entered into with the Bank in respect of the S scheme, both dated 23
July 2009, which it says were current at the time. These confirm that the
Bank was entitled to charge break costs if the options were unwound to any
extent before the 20 July 2016 maturity date.
80. While the available evidence does not conclusively prove that the Bank
charged (or was entitled to charge) the FSP $48,650 by way of an early
withdrawal fee, it is consistent with that conclusion. None of the available
evidence suggests the Bank did not charge this amount.
81. The PDS does not specify a specific formula or percentage for the early
withdrawal fee. However, it says that the fee -
9 Paragraph 5.1(b)(i),(ii) of the Terms of Reference effective 1 January 2012 (Terms of Reference).
10 Email to FOS dated 20 July 2012
11 Submission dated 18 August 2012
Case No: 271009 Recommendation Page 9 of 9
“is calculated daily by [the Bank] and, as it varies, will be available
online at [the FSP’s website]”; and
“is calculated as a percentage of the amount you withdraw”.
82. While the Applicant has argued the FSP has failed to prove the fee was
properly calculated, he bears the burden of showing that the fee exceeded
what it was entitled to charge.
83. According to the schedule provided by the FSP on 16 August 2012, the early
withdrawal fee on 18 November 2011 was 9.73% of the value of the
Applicant’s portfolio at close of business 17 November 2011. According to
the FSP, this value was $ 525,915.02 (including income, but net of the FSP’s
monthly fees) or $511,088.73 (taking into account capital appreciation only).
84. The FSP has stated 12 that the early withdrawal fee of $48,650 was actually
calculated as 9.73% of the initial investment of $500,000. This is
mathematically correct.
85. Since the value of the initial investment was less than the amount withdrawn,
the early withdrawal fee was also slightly less than the PDS would have
allowed the FSP to charge (subject to not exceeding the amount actually
charged to the FSP by the Bank).
86. While this suggests a possible (very slight) internal inconsistency between
the Constitution and the PDS on how to calculate the early withdrawal fee,
the FSP has used the lower of the two possible figures. Therefore, the
Applicant has not been disadvantaged by the approach the FSP has taken.
Other matters
87. As I have concluded that the PDS adequately disclosed both the capital
protection and the early withdrawal fee, and that the amount of the early
withdrawal fee was not excessive, and no compensation should be paid, I do
not need to consider whether it would be the FSP, or its successor as
Responsible Entity, who would have to pay any compensation.
Recommendation
88. On the basis of the available information, I recommend in favour of the FSP.
12 Email to FOS dated 20 July 2012