Text of the determination
Case No: 270400 Determination Page 1 of 8
Case number: 270400
General Insurance - Small Business/Farm Insurance - Contractors All Risk -
FSP Decision - Denial of claim-No policy or contract
17 January 2013
Background
1. The Applicant held a Contract Works and Legal Liability policy of insurance
with the Financial Services Provider (FSP). The policy commencement date
was 9 April 2010 and it renewed on 9 April 2011. The policy covers
construction risks up to $2,000,000 and was subject to an excess of $1,000
per claim. The policy also covers public liability for $10,000,000 subject to an
excess of $2,500.
2. On 7 April 2011 the Applicant lodged a claim with the FSP for theft and
damage of items in a newly constructed property.
3. The FSP assessed the claim and determined that the policy cover had
ceased because the policy only covers the period of construction up to the
completion of the Contract Works.
4. The Applicant disputes the declinature on the basis that the construction had
not ceased and accordingly the policy should still be on foot.
Summary of Applicant’s position
5. The Applicant has enclosed a copy of his renewal document for the policy.
The renewal commences on 9 April 2011 at 4 .00pm and expires on 9 April
2012 at 4.00pm.
6. The Applicant has enclosed a copy of the tender dated 2 February 2010.The
Panel notes the tender includes documentation involving the following
items:
Electric hot water heaters
Hot and cold water point and drainage point for future dishwasher in the
kitchen of each dwelling.
Floor finishings such as carpet.
7. The Applicant notes that at 6.45am on 8 March 2011 it was discovered that a
block of townhouses under construction had been broken into and items
stolen. The property was also vandalised. The matter was reported to the
police and the Applicant confirms that approximately $117,955.12 worth of
Determination
Case No: 270400 Determination Page 2 of 8
losses occurred. The Applicant has provided an itemised list confirming the
basis of these calculations and that the figure is GST inclusive.
8. The Applicant says that the Occupation Certification dated 21 February 2011
was obtained for the building to proceed to sale. However, the construction
was not finalised. The Applicant had also not received final payment for the
works or completed other „finish offs‟. The Applicant submits that the contract
between the developer and the Applicant was still on-going.
9. The Applicant states that he contacted the developer on 29 April 2011 to
advise the works had been completed and final payment was owed. The
developer came out to complete the final inspection on 10 May 2011 and
then issued a list of defects dated 19 May 2011. The final cheque for the
matter was banked on 11 May 2011. The Applicant contends that until the
final cheque is received, the Applicant was still liable for the construction of
the building, liability of the building and insurance of the building.
10. The Applicant submits that the definition of minor defects is a defect that is
not likely to resolve in the failure of a unit or product that does not reduce the
usability of its intended purposes (eg: dripping taps, touch up paint, burned
light bulbs and cleaning). The installation of hot water heaters, flooring,
basement copper work and light fittings constitute an uncompleted contract
with the developer, not minor works.
11. The Applicant maintains that until a contract is finalised by completion of
outstanding works and final payment, the builder holds full responsibility for
the building until the contract has been fulfilled by both parties.
12. The Applicant notes the insurance policy does not state that the building
insurance is terminated by outstanding works and the final payment.
13. The Applicant is dissatisfied with the FSP taking 9 months to reject the claim
despite having relevant documentation for over 6 months.
14. The Applicant seeks indemnity for the claim.
Summary of FS P’s position
15. The FSP relies on the following policy terms and conditions:
“Period of Insurance shall mean both of the following periods:
1. Construction period being the period commencing on the date
specified in the Schedule and expiring:
(a) at the time of practical completion of the contract Works, being
when the Contract Works are complete except for minor omissions
and minor defect which do not prevent the Contract Works from being
reasonably capable of being used for their intended purpose; or
(b) with respect to any separable portion of the Contract Works at the
time it is taken over or taken into use (whichever is the earlier) by the
Principal; or
(c) on the Expiry Date specified in the schedule
Case No: 270400 Determination Page 3 of 8
Whichever occurs first.
...
Section A – Material Damage
The liability of the Company under Items 1, 2 and 3 of Section A of this Policy
as specified in the Schedule shall not exceed the Sum(s) Insured stated in the
Schedule in respect of each Item, subject to the application of the Deductible.
Should more than one Deductible under Section A apply for any claim arising
from or attributable to one source or original cause, such Deductibles shall not
be aggregated and only the highest applicable Deductible under Section A
shall apply.
1. Construction Period
The Company will indemnify the Persons Insured against unforeseen physical
loss of or damage to the Contract Works provided such loss or damage is not
hereafter excluded and occurs at the Contract Site (or elsewhere as set out in
the Schedule) during the Constructi on Period.”
16. The FSP relies on its assessor report dated 31 May 2011. The Panel notes
the following from this report:
The date of loss occurred between the “pm” of Monday 7 March 2011
and 6.45am on 8 March 2011.
The construction activities on the site commenced in April 2010 and the
Final Occupation Certificate was issued on 21 February 2011.
The contract for the construction is dated February 2010 and states a
contract price of $2,030,000.
The police have been unable to locate any firm leads regarding the
theft and vandalism.
The preliminary list of loss (excluding GST) was $81,025.27, however a
reserve of $90,000 was recommended by the assessor.
The Final Occupation Certificate indicates that the residences are fit for
habitation. However, the residence may not be fully completed and
minor tasks still required to be undertaken. The assessor notes that
items such as dishwasher, dryer and hot water systems had not been
installed although these items were located within the townhouses.
17. The FSP has enclosed the Building Contract from which the Panel notes the
following:
Clause 1 of the agreement requires the builder to complete the works
under this contract in a workmanlike manner, supply materials
necessary for the completion of the work of the kind and qua lity
specified or as good building practice requires. The builder is to comply
with all relevant Australian standards, laws and statutory authorities.
Clause 7 relates to the completion of work. The work must be finished
free of defects and all rubbish/surplus materials removed from site.
When the contractor believes the work is complete he must notify the
owner in writing. The owner may then provide notice to the contractor
of any items considered incomplete or defective. The contractor must
complete these works and notify the owner in writing.
Case No: 270400 Determination Page 4 of 8
Clause 10 provides the schedule of progress payment. The „Finish Off‟
payment was in the amount of $101,500.
Clause 13 relates to the final payment. The contracts states that:
“On receipt of the final payment, the c ontract (sic) must hand over to the
owner a copy of all contract documents, guarantees, instructions manuals and
the like unless already provided and all keys relating to the work, together with
any certificate or approval which may have been provided by any public
authority relating to the work.
If the works is a new dwelling or additions to an existing dwelling, the owner
may not take occupancy of the work until all moneys due to the contractor are
paid or written consent from the contractor is obtained.”
Clause 20 requires the contractor to effect and maintain insurance until
completion of the work.
18. The FSP has enclosed the Final Occupation Certificate dated 21 February
2011. The certificate indicates that the final inspection for issuance of the
Occupation certificate was satisfactory. The party which issued the certificate
has certified the building is suitable for its use under the Building Code of
Australia, and, all the pre-conditions of development consent have been
satisfied.
19. The FSP has enclosed a letter dated 2 June 2011 from the Applicant which
states that the final items for completion were:
Final completion of floor coverings
Installation of hot water heaters, dishwashers and dryers
Installation for ducting of rangehoods
Final/touch up painting
Final clean up of dwellings
Basement copper works ie. Gas
Light fittings to be installed
Basement clean up
Final building inspection by the contractor (the Applicant ) and
developer)
The developer was informed on 29 April 2011 the works had been
completed and that final payment was required. The developer inspected the
property on 10 May 2011 and provided a list of defects on 19 May 2011. The
final cheque however was banked on 11 May 2011.
20. There is an enclosed schedule entitled „Telopea Site Final Inspection‟ which
lists more minor issues such as the finger mark left on the wall up to the
stair, no lights in bathroom, clothes hanging rail not fitted etc. Presumably
this is the list provided to the Applicant on 19 May 2011.
21. The FSP‟s policy provides cover fo r unforseen loss or damage to the
Contract Works during the Construction Period. The term „ Construction
Period ‟ is defined by the policy as the period commencing on the date
specified in the Schedule and expiring in this case, at the time of practical
Case No: 270400 Determination Page 5 of 8
completion of the Contract Works. The FSP submits this is when the
Contract Works are complete except for minor omissions and minor defects
which do not prevent the Contract Works from being reasonably capable of
being used for their intended purpose.
22. The Appl icant‟s construction company received a Final Occupancy
Certificate dated 21 February 2011 for the eight town houses subject of the
Contract of Works. This certificate declared the property had been
completed, all preconditions of the development consent had been satisfied
and that the property was suitable for use. As such, the FSP has submitted
the property‟s construction had reached its practical completion on the 21
February 2011 as except for minor works and defects, the property could
have been used for its intended purpose. The FSP therefore submits that the
loss and damage occurred outside of the period of insurance.
23. The FSP contends that the minor works required are irrelevant as the Final
Certificate of Occupancy confirms the property is suitable for use and had
reached its practical completion as per the policy definition. Once the
practical completion has been reached the policy bears no liability regardless
of any minor omissions and minor defects which do not prevent the Contract
Works from being reasonably capable of being used for their intended
purpose.
24. The FSP apologises for the time taken to reach a decision in this matter.
25. The FSP notes that the Applicant has not argued he did not receive the
relevant policy documents or that the terms and conditions were unclear.
The FSP is therefore entitled to rely on the policy terms and conditions.
Issue
26. Whether the FSP was entitled to decline the Applicant‟s claim in this matter.
Reasons for decision
27. There has been an exchange of material between each party, and the Panel
is satisfied each party has had an opportunity to reply to the issues raised.
28. The Panel has read each party‟s submissions and materials and will only
refer to the relevant submissions and materials raised.
29. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with clause 8.6 of the FOS Terms of Reference. This
is due to the circumstances and quantum of the dispute. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
30. The Panel further confirm that the parties have agreed to allow FOS to
determine this dispute.
Case No: 270400 Determination Page 6 of 8
31. The Panel notes the parties do not dispute the following:
The policy commenced on 9 April 2010 at 4pm.
The Final Certificate of Occupancy was issued on 21 February 2011.
The Applicant was still completing works up until approximately 29 April
2011, at which time he contacted the developer.
The works to be completed included floor coverings, installation of fixed
appliances such as hot water systems, copper works (gas) and clean
up.
The developer completed a final inspection on 10 May 2011 and issued
a list of defects on 19 May 2011.
The Applicant did however receive the final cheque which was banked
on 11 May 2011.
32. The question before the Panel is whether, at the time of the loss, the
“Construction Period” as defined by the policy had ceased.
33. The Panel notes the Construction Period expires at the time of practical
completion of the Contract Works (aside from minor works), any separable
portion of the Contracts works at the time it is taken over or taken into use or
the expiry date in the Schedule.
34. The Panel notes that the definition of Contract Works in the policy means:
“...works of engineering, construction or mechanical installation or erection
including formwork, falsework, temporary works, temporary buildings including
all associated contents other than employees‟ personal effects, scaffolding,
hoardings, Principal supplied or free-issue materials, materials for
incorporation in the works, and additions and alterations to or refurbishment of
pre-existing buildings or structures, all of which are carried out in their entirety
within Australia during the Period of Insurance and which are described more
particularly in the Schedule.”
35. The Panel notes that the issuer of the Certificate of Occupancy declared the
building is suitable for its use under the Building Code of Australia, and, all
the pre-conditions of development consent have been satisfied. However,
the policy does not appear to refer to the Certificate of Occupancy as an
indicator of practical completion of the Contract Works. The Panel considers
that a Certificate of Occupancy could certainly be an indicator the „practical
completion of the Contract Works‟.
36. The policy defines the Contract Works as including works of engineering,
construction or mechanical installation including materials for incorporation
into the works. This is considerably broader than what ma y be considered by
the Certificate of Occupancy which reviews whether the building itself is
suitable for occupation. The Certificate of Occupancy may be issued with
works still outstanding such as carpeting, landscaping and fencing etc.
However, it would appear that certain items such as sanitary and drainage
fixtures should be in place.
Case No: 270400 Determination Page 7 of 8
37. The Construction Period does not include minor works/defects which do not
prevent the Contract Works from being reasonably capable of being used for
their intended purpose. The Panel notes that the defect list provided on 19
May 2011 would certainly fall within this description.
38. The parties do not dispute that items such as the dishwasher, hot water
heaters, dryers, rangehoods and floor coverings had not been installed at
the time of the theft. The Panel has difficulty accepting that the practical
completion of the works would not include the hot water system which would
be necessary for proper habitation of the building. Further, the tender
documentation actually requires such items to be installed which would
suggest construction works were outstanding as at the time of the loss. In
addition to this, a final payment was rendered well after the Certificate of
Occupancy date and a list of minor defects were provided after this final
payment. The Panel considers that the practical completion of the Contract
of Works would require the completion of all works in the contract and final
payments. Further, the Contract of Works allows for such minor defects, as
contemplated by the Construction Period policy definition, to be rectified but
these do not generally form part of the tender.
39. This leads the Panel to a conclusion that the Construction Period and
Contract Works are somewhat broader than the requirements provided by
the Certificate of Occupation. The definition of Construction Period contained
within the policy cannot be read down on the basis of the Certificate of
Occupancy.
40. Accordingly, the Panel determines on the balance of probabilities the
claimed losses fall within the purview of the policy, on the basis the
„Construction Period‟ envisaged by the policy had still to be satisfied as at
the date of the theft.
41. In respect of quantum, the Panel notes the Applicant has provided a detailed
list totalling $117,955.12 which the FSP has not challenged, albeit its
assessor RK on 31 May 2011 suggested there was some discrepancy
between material initially provided by the Applicant and the final claimed
amount, nevertheless the assessor recommended a reserve of $90,000.
Given the length of time this matter has been pending, the Panel determines
pursuant to its mandate to do what is „fair in all the circumstances‟ the FSP is
to cash settle the Applicant in the sum of $103,977.56 representing the
midpoint between the two figures.
42. The P anel has considered the Applicant‟s complaint regarding the delay.
The Panel notes this matter is quite technical and the FSP took some time to
review the loss and obtain the relevant contractual documentation. The FSP
has provided an apology to the Applicant for this delay but not provided a
specific basis for this delay.
Determination
43. On the basis of the available information the Panel determines the FSP was
not entitled to decline the Applicant‟s claim. The Panel determines the FSP
Case No: 270400 Determination Page 8 of 8
shall make payment of $103,977.56 plus statutory interest calculated from 9
September 2011, the date of denial until the date this Determination is
satisfied.
44. The Panel notes that it does not order compensation for the delay due to the
interest component already provided.