Determination 270400

Denial of claim - policy construction period ceased

FirmFinancial Firm (Unknown - Insurer)
Decided2013-01-17
ProductGeneral Insurance · Other general
OutcomeFor the complainant
Amount awarded$103,978
Non-financial loss—
Amount claimed$117,955
SourceAFCA PDF

Summary

The applicant's newly built townhouses were stolen from and vandalised in March 2011 during a construction-period claim under a contract works policy. The FSP declined on the basis the construction period had ended at the Occupation Certificate date; AFCA found the period had not ended and ordered cash settlement of $103,977.56 plus statutory interest.

The policy's Construction Period runs until practical completion of the Contract Works, which includes outstanding works and final payment, and cannot be read down on the basis of a Certificate of Occupancy.

Issues

Subjects and remedies

theft or burglarypay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 270400 Determination Page 1 of 8 Case number: 270400 General Insurance - Small Business/Farm Insurance - Contractors All Risk - FSP Decision - Denial of claim-No policy or contract 17 January 2013 Background 1. The Applicant held a Contract Works and Legal Liability policy of insurance with the Financial Services Provider (FSP). The policy commencement date was 9 April 2010 and it renewed on 9 April 2011. The policy covers construction risks up to $2,000,000 and was subject to an excess of $1,000 per claim. The policy also covers public liability for $10,000,000 subject to an excess of $2,500. 2. On 7 April 2011 the Applicant lodged a claim with the FSP for theft and damage of items in a newly constructed property. 3. The FSP assessed the claim and determined that the policy cover had ceased because the policy only covers the period of construction up to the completion of the Contract Works. 4. The Applicant disputes the declinature on the basis that the construction had not ceased and accordingly the policy should still be on foot. Summary of Applicant’s position 5. The Applicant has enclosed a copy of his renewal document for the policy. The renewal commences on 9 April 2011 at 4 .00pm and expires on 9 April 2012 at 4.00pm. 6. The Applicant has enclosed a copy of the tender dated 2 February 2010.The Panel notes the tender includes documentation involving the following items:  Electric hot water heaters  Hot and cold water point and drainage point for future dishwasher in the kitchen of each dwelling.  Floor finishings such as carpet. 7. The Applicant notes that at 6.45am on 8 March 2011 it was discovered that a block of townhouses under construction had been broken into and items stolen. The property was also vandalised. The matter was reported to the police and the Applicant confirms that approximately $117,955.12 worth of Determination Case No: 270400 Determination Page 2 of 8 losses occurred. The Applicant has provided an itemised list confirming the basis of these calculations and that the figure is GST inclusive. 8. The Applicant says that the Occupation Certification dated 21 February 2011 was obtained for the building to proceed to sale. However, the construction was not finalised. The Applicant had also not received final payment for the works or completed other „finish offs‟. The Applicant submits that the contract between the developer and the Applicant was still on-going. 9. The Applicant states that he contacted the developer on 29 April 2011 to advise the works had been completed and final payment was owed. The developer came out to complete the final inspection on 10 May 2011 and then issued a list of defects dated 19 May 2011. The final cheque for the matter was banked on 11 May 2011. The Applicant contends that until the final cheque is received, the Applicant was still liable for the construction of the building, liability of the building and insurance of the building. 10. The Applicant submits that the definition of minor defects is a defect that is not likely to resolve in the failure of a unit or product that does not reduce the usability of its intended purposes (eg: dripping taps, touch up paint, burned light bulbs and cleaning). The installation of hot water heaters, flooring, basement copper work and light fittings constitute an uncompleted contract with the developer, not minor works. 11. The Applicant maintains that until a contract is finalised by completion of outstanding works and final payment, the builder holds full responsibility for the building until the contract has been fulfilled by both parties. 12. The Applicant notes the insurance policy does not state that the building insurance is terminated by outstanding works and the final payment. 13. The Applicant is dissatisfied with the FSP taking 9 months to reject the claim despite having relevant documentation for over 6 months. 14. The Applicant seeks indemnity for the claim. Summary of FS P’s position 15. The FSP relies on the following policy terms and conditions: “Period of Insurance shall mean both of the following periods: 1. Construction period being the period commencing on the date specified in the Schedule and expiring: (a) at the time of practical completion of the contract Works, being when the Contract Works are complete except for minor omissions and minor defect which do not prevent the Contract Works from being reasonably capable of being used for their intended purpose; or (b) with respect to any separable portion of the Contract Works at the time it is taken over or taken into use (whichever is the earlier) by the Principal; or (c) on the Expiry Date specified in the schedule Case No: 270400 Determination Page 3 of 8 Whichever occurs first. ... Section A – Material Damage The liability of the Company under Items 1, 2 and 3 of Section A of this Policy as specified in the Schedule shall not exceed the Sum(s) Insured stated in the Schedule in respect of each Item, subject to the application of the Deductible. Should more than one Deductible under Section A apply for any claim arising from or attributable to one source or original cause, such Deductibles shall not be aggregated and only the highest applicable Deductible under Section A shall apply. 1. Construction Period The Company will indemnify the Persons Insured against unforeseen physical loss of or damage to the Contract Works provided such loss or damage is not hereafter excluded and occurs at the Contract Site (or elsewhere as set out in the Schedule) during the Constructi on Period.” 16. The FSP relies on its assessor report dated 31 May 2011. The Panel notes the following from this report:  The date of loss occurred between the “pm” of Monday 7 March 2011 and 6.45am on 8 March 2011.  The construction activities on the site commenced in April 2010 and the Final Occupation Certificate was issued on 21 February 2011.  The contract for the construction is dated February 2010 and states a contract price of $2,030,000.  The police have been unable to locate any firm leads regarding the theft and vandalism.  The preliminary list of loss (excluding GST) was $81,025.27, however a reserve of $90,000 was recommended by the assessor.  The Final Occupation Certificate indicates that the residences are fit for habitation. However, the residence may not be fully completed and minor tasks still required to be undertaken. The assessor notes that items such as dishwasher, dryer and hot water systems had not been installed although these items were located within the townhouses. 17. The FSP has enclosed the Building Contract from which the Panel notes the following:  Clause 1 of the agreement requires the builder to complete the works under this contract in a workmanlike manner, supply materials necessary for the completion of the work of the kind and qua lity specified or as good building practice requires. The builder is to comply with all relevant Australian standards, laws and statutory authorities.  Clause 7 relates to the completion of work. The work must be finished free of defects and all rubbish/surplus materials removed from site. When the contractor believes the work is complete he must notify the owner in writing. The owner may then provide notice to the contractor of any items considered incomplete or defective. The contractor must complete these works and notify the owner in writing. Case No: 270400 Determination Page 4 of 8  Clause 10 provides the schedule of progress payment. The „Finish Off‟ payment was in the amount of $101,500.  Clause 13 relates to the final payment. The contracts states that: “On receipt of the final payment, the c ontract (sic) must hand over to the owner a copy of all contract documents, guarantees, instructions manuals and the like unless already provided and all keys relating to the work, together with any certificate or approval which may have been provided by any public authority relating to the work. If the works is a new dwelling or additions to an existing dwelling, the owner may not take occupancy of the work until all moneys due to the contractor are paid or written consent from the contractor is obtained.”  Clause 20 requires the contractor to effect and maintain insurance until completion of the work. 18. The FSP has enclosed the Final Occupation Certificate dated 21 February 2011. The certificate indicates that the final inspection for issuance of the Occupation certificate was satisfactory. The party which issued the certificate has certified the building is suitable for its use under the Building Code of Australia, and, all the pre-conditions of development consent have been satisfied. 19. The FSP has enclosed a letter dated 2 June 2011 from the Applicant which states that the final items for completion were:  Final completion of floor coverings  Installation of hot water heaters, dishwashers and dryers  Installation for ducting of rangehoods  Final/touch up painting  Final clean up of dwellings  Basement copper works ie. Gas  Light fittings to be installed  Basement clean up  Final building inspection by the contractor (the Applicant ) and developer) The developer was informed on 29 April 2011 the works had been completed and that final payment was required. The developer inspected the property on 10 May 2011 and provided a list of defects on 19 May 2011. The final cheque however was banked on 11 May 2011. 20. There is an enclosed schedule entitled „Telopea Site Final Inspection‟ which lists more minor issues such as the finger mark left on the wall up to the stair, no lights in bathroom, clothes hanging rail not fitted etc. Presumably this is the list provided to the Applicant on 19 May 2011. 21. The FSP‟s policy provides cover fo r unforseen loss or damage to the Contract Works during the Construction Period. The term „ Construction Period ‟ is defined by the policy as the period commencing on the date specified in the Schedule and expiring in this case, at the time of practical Case No: 270400 Determination Page 5 of 8 completion of the Contract Works. The FSP submits this is when the Contract Works are complete except for minor omissions and minor defects which do not prevent the Contract Works from being reasonably capable of being used for their intended purpose. 22. The Appl icant‟s construction company received a Final Occupancy Certificate dated 21 February 2011 for the eight town houses subject of the Contract of Works. This certificate declared the property had been completed, all preconditions of the development consent had been satisfied and that the property was suitable for use. As such, the FSP has submitted the property‟s construction had reached its practical completion on the 21 February 2011 as except for minor works and defects, the property could have been used for its intended purpose. The FSP therefore submits that the loss and damage occurred outside of the period of insurance. 23. The FSP contends that the minor works required are irrelevant as the Final Certificate of Occupancy confirms the property is suitable for use and had reached its practical completion as per the policy definition. Once the practical completion has been reached the policy bears no liability regardless of any minor omissions and minor defects which do not prevent the Contract Works from being reasonably capable of being used for their intended purpose. 24. The FSP apologises for the time taken to reach a decision in this matter. 25. The FSP notes that the Applicant has not argued he did not receive the relevant policy documents or that the terms and conditions were unclear. The FSP is therefore entitled to rely on the policy terms and conditions. Issue 26. Whether the FSP was entitled to decline the Applicant‟s claim in this matter. Reasons for decision 27. There has been an exchange of material between each party, and the Panel is satisfied each party has had an opportunity to reply to the issues raised. 28. The Panel has read each party‟s submissions and materials and will only refer to the relevant submissions and materials raised. 29. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is due to the circumstances and quantum of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 30. The Panel further confirm that the parties have agreed to allow FOS to determine this dispute. Case No: 270400 Determination Page 6 of 8 31. The Panel notes the parties do not dispute the following:  The policy commenced on 9 April 2010 at 4pm.  The Final Certificate of Occupancy was issued on 21 February 2011.  The Applicant was still completing works up until approximately 29 April 2011, at which time he contacted the developer.  The works to be completed included floor coverings, installation of fixed appliances such as hot water systems, copper works (gas) and clean up.  The developer completed a final inspection on 10 May 2011 and issued a list of defects on 19 May 2011.  The Applicant did however receive the final cheque which was banked on 11 May 2011. 32. The question before the Panel is whether, at the time of the loss, the “Construction Period” as defined by the policy had ceased. 33. The Panel notes the Construction Period expires at the time of practical completion of the Contract Works (aside from minor works), any separable portion of the Contracts works at the time it is taken over or taken into use or the expiry date in the Schedule. 34. The Panel notes that the definition of Contract Works in the policy means: “...works of engineering, construction or mechanical installation or erection including formwork, falsework, temporary works, temporary buildings including all associated contents other than employees‟ personal effects, scaffolding, hoardings, Principal supplied or free-issue materials, materials for incorporation in the works, and additions and alterations to or refurbishment of pre-existing buildings or structures, all of which are carried out in their entirety within Australia during the Period of Insurance and which are described more particularly in the Schedule.” 35. The Panel notes that the issuer of the Certificate of Occupancy declared the building is suitable for its use under the Building Code of Australia, and, all the pre-conditions of development consent have been satisfied. However, the policy does not appear to refer to the Certificate of Occupancy as an indicator of practical completion of the Contract Works. The Panel considers that a Certificate of Occupancy could certainly be an indicator the „practical completion of the Contract Works‟. 36. The policy defines the Contract Works as including works of engineering, construction or mechanical installation including materials for incorporation into the works. This is considerably broader than what ma y be considered by the Certificate of Occupancy which reviews whether the building itself is suitable for occupation. The Certificate of Occupancy may be issued with works still outstanding such as carpeting, landscaping and fencing etc. However, it would appear that certain items such as sanitary and drainage fixtures should be in place. Case No: 270400 Determination Page 7 of 8 37. The Construction Period does not include minor works/defects which do not prevent the Contract Works from being reasonably capable of being used for their intended purpose. The Panel notes that the defect list provided on 19 May 2011 would certainly fall within this description. 38. The parties do not dispute that items such as the dishwasher, hot water heaters, dryers, rangehoods and floor coverings had not been installed at the time of the theft. The Panel has difficulty accepting that the practical completion of the works would not include the hot water system which would be necessary for proper habitation of the building. Further, the tender documentation actually requires such items to be installed which would suggest construction works were outstanding as at the time of the loss. In addition to this, a final payment was rendered well after the Certificate of Occupancy date and a list of minor defects were provided after this final payment. The Panel considers that the practical completion of the Contract of Works would require the completion of all works in the contract and final payments. Further, the Contract of Works allows for such minor defects, as contemplated by the Construction Period policy definition, to be rectified but these do not generally form part of the tender. 39. This leads the Panel to a conclusion that the Construction Period and Contract Works are somewhat broader than the requirements provided by the Certificate of Occupation. The definition of Construction Period contained within the policy cannot be read down on the basis of the Certificate of Occupancy. 40. Accordingly, the Panel determines on the balance of probabilities the claimed losses fall within the purview of the policy, on the basis the „Construction Period‟ envisaged by the policy had still to be satisfied as at the date of the theft. 41. In respect of quantum, the Panel notes the Applicant has provided a detailed list totalling $117,955.12 which the FSP has not challenged, albeit its assessor RK on 31 May 2011 suggested there was some discrepancy between material initially provided by the Applicant and the final claimed amount, nevertheless the assessor recommended a reserve of $90,000. Given the length of time this matter has been pending, the Panel determines pursuant to its mandate to do what is „fair in all the circumstances‟ the FSP is to cash settle the Applicant in the sum of $103,977.56 representing the midpoint between the two figures. 42. The P anel has considered the Applicant‟s complaint regarding the delay. The Panel notes this matter is quite technical and the FSP took some time to review the loss and obtain the relevant contractual documentation. The FSP has provided an apology to the Applicant for this delay but not provided a specific basis for this delay. Determination 43. On the basis of the available information the Panel determines the FSP was not entitled to decline the Applicant‟s claim. The Panel determines the FSP Case No: 270400 Determination Page 8 of 8 shall make payment of $103,977.56 plus statutory interest calculated from 9 September 2011, the date of denial until the date this Determination is satisfied. 44. The Panel notes that it does not order compensation for the delay due to the interest component already provided.