Text of the determination
Case No: 269311 Determination Page 1 of 15
Case number: 269311
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim - Flood
12 September 2012
Background
1. The Applicants‟ home and contents were insured under a classic home
insurance policy forming part of a business insurance package issued by the
Financial Services Provider (FSP). The policy insured the property for
accidental damage, burglary and theft. Damage caused by flood was limited
to $20,000 for all damage arising from the one event.
2. On 14 January 2011 the Applicants‟ home in Charlton, Victoria was
inundated by water.
3. The FSP considered the damage was caused by flood water and settled the
claim by payment of $20,000 in accordance with the terms of the policy.
4. The Applicants contend the inundation was from stormwater surface runoff
and argue the policy should respond to their claim in full.
Summary of Applicants’ position
5. The Applicants are represented by a law firm. Any reference to the
Applicants in this determination will include their representative.
6. The Applicants submit that the FSP failed to clearly inform them that storm
cover was not included in the policy issued to them and no such information
is included in the policy. In this regard, the Applicants refer to Section 35 of
the Insurance Contracts Act 1984 (the Act).
7. The Applicants rely on hydrological reports dated November 2011 and
March 2012 commissioned by their representative to argue the inundation
was caused by local runoff of stormwater.
Summary of FSP’s position
8. The FSP relies on hydrological reports 31 January 2011, 19 July 2011 and 5
July 2012 commissioned by it to argue the inundation was flood water as
defined by the policy.
Determination
Case No: 269311 Determination Page 2 of 15
9. The FSP relies on the following policy terms::
“ General definitions applying to words We use in this Plan
…
Flood means the escape or release of water from the normal confines of a
pond, lake, reservoir, canal dam or uncovered watercourse.
…
What you are insured against
This policy insures You against accidental damage, burglary and theft
occurring during the Period of Insurance.
…
What is not insured
This policy does not insure You against:
1 damage directly caused by:
…
Flood, except as described under the Additional benefit “Flood
cover”
…
Additional benefits
…
Flood cover
If “Building” is shown on the certificate of insurance, We pay up to $20,000 for
damage to Your Home directly caused by Flood during the Period of
Insurance arising from any one event.
I f “Contents” is shown on the certificate of insurance, We pay up to $10,000
for damage to Contents in Your Home directly caused by Flood during the
Period of Insurance arising from any one event.
We pay up to $20,000 for all damage to Your Home and Contents at any one
location arising out of the one event.
Issues
10. Whether the FSP complied with Section 35 of the Act to clearly inform the
Applicants of the relevant terms of the policy.
11. Whether the damage to the Applicants‟ home was caused by flood as
defined by the policy.
Reasons for decision
12. Due to the complex nature of this dispute, FOS has considered it appropriate
to refer this dispute directly to the Panel in accordance with the Operational
Guidelines to the FOS Terms of Reference. The dispute has not been the
Case No: 269311 Determination Page 3 of 15
subject of a FOS Recommendation and has proceeded direct to
Determination.
13. The decision had been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in insurance industry matters and a
representative with extensive experience in consumer claims.
14. There has been an exchange of material between the parties. Each party
therefore is aware of the issues and has had the opportunity to respond.
15. Prior to arriving at a determination, the Panel has read and considered all
the material submitted by the parties to FOS.
16. The Panel has been provided with copies of the various hydrological reports
obtained by the FSP and the Applicants. As these documents have been
exchanged it is not intended to recite the details of these reports in full in this
determination. The Panel will, however, summarise the reports in relation to
the information relevant to the issues disputed in this matter.
17. The evidence in relation to the source of this water is divided. The Panel
accepts that the authors of the reports were highly compete nt professionals
and well qualified to assess and report on the likely source of water which
inundated Charlton.
18. It is difficult for the Panel to resolve a dispute where two expert witnesses
provide substantially opposed versions based on the same technical data.
However, the Panel is reinforced by the observations of the FOS personnel
who visited the area and discussed the event with the policyholder.
19. The FSP seeks to rely on a clause in the policy to deny the claim and
therefore has the burden to establish on the balance of probability the policy
exclusion.
20. In the event the Panel is not persuaded by either expert‟s report, as a matter
of law the dispute will be determined against the party with the burden of
proof, there being uncontradicted evidence of severe storms and the
presence of storm water runoff.
1 st Hydrologist report commissioned by FSP (WT) 31/1/11
Local flooding
The town historically floods from two directions in a north-south plane
with an area remaining flood free through the centre of the town along
the St Arnaud – Charlton Road (also titled Armstrong Street).
Heavy rain fell in the area between 10 and 14 January. The largest fall
was recorded at 9.00am on Friday 14 January.
The township‟s most intense rainfall fell on the morning of 11 and early
morning on 13 January.
Case No: 269311 Determination Page 4 of 15
The Avoca River peak flood level of 8.05m was reached early morning
on 15 January being at least 2 days after the most intense rainfall.
2 nd Hydrologist report commissioned by FSP (WT) 19 July 2011
Local flooding
Historically the town floods on both sides east and west with an area
remaining flood free through the centre of town along the St Arnaud-
Charlton Road.
Heavy rain fell in the area between 10 and 14 January. The largest fall
was recorded at 9.00am on Friday 14 January.
The most intense rainfall fell on the morning of 11 January and early
morning on 13 January as shown on charts (figure 7.4).
The peak flood level of 8.05m was reached early morning on 15
January being at least 2 days after the most intense rainfa ll.
The Yeungroon creek catchment responded more quickly on Thursday
[13 January] and Friday [14 January]. At about 8.00am [14 January]
Yeungroon Creek reached its peak.
At this time most of the town remained out of the main flood extent with
some local runoff pooling at shallow depths through town.
Flow depths in Yeungroon Creek were not expected to impact
anywhere west of Kaye Street.
Waters from Yeungroon Creek east of Kaye Street would have been up
to 150mm deep on the east side of Kaye Street and between 0.5m and
1m deep further to the east between there and Back St Arnaud Road.
After this, flows in Yeungroon Creek began to subside and the Avoca
River increased.
From around 5.00pm [14 January] local reports say the river began to
rise rapidly.
From about 6.00pm houses in the town were inundated with the river
peaking in the early hours of Saturday morning [15 January].
The general method of flooding for properties in Charlton was via
overflows of the Avoca Rover and Yeungroon systems. The Avoca
River peaked at 8.05m resulting in widespread flooding of the town and
inundation of multiple properties. A large portion of the town flooded
about 12 hours after the last significant rainfall.
Any flooding after lunchtime [14 January] can be directly attributable to
the Avoca River flooding as Yeungroon Creek had peaked earlier that
morning.
Ceiling damage is associated with the storm event.
Floor inundation that occurred east of Armstrong Street early on 14
January can be attributed to storm water flooding.
Case No: 269311 Determination Page 5 of 15
Fl ooding at Applicants’ site
The Applicants‟ home is located in the southern half of the township.
A site inspection was carried out and discussions were held with the
Applicants.
Water entered No 33 Menzies Street at 7.00pm on 14 January. The
Applicants agree with this timing for their property
Water initially entering the home was clear becoming muddier later in
the event.
This end of town may have experienced up to 150mm of flood depth
from the Yeungroon Creek earlier that day.
A large scour hole was formed at the rear of the property indicating
high velocities experienced in the area.
Based on hydrologic modelling of the site the following was ascertained.
The main flood wave from the Avoca River broke out south of the town
reaching the town late on the afternoon of 14 January.
The predominant method of flooding of this property was from the
Avoca River flows reaching the property late on the afternoon of 14
January.
Some flooding up to 150mm may have been experienced on site earlier
than the Avoca flows. This flooding was associated with a breakout
from the Yeungroon Creek.
3 rd Hydrologist report commissioned by FSP (WT) 5 July 2011
Between Yeungroon Creek and the Avoca River are two unnamed
tributaries or drainage lines; one crossing Charlton – St Arnaud Road
(referred to in the report as „Charlton - St Arnaud Road tributary‟ ) that
joins the Avoca River upstream of the town, the other flows through the
town under the Calder Highway (referred to in the report as „Calder
Highway tributary‟ ) and enters the Avoca River downstream of railway
line.
River levels at Charlton began to rise steeply from about midday on 12
January continuing to rise throughout the afternoon and reaching a
Minor flood level of 5 metres at 4.00am on 13 January. Moderate flood
level was reached at 8.45 pm on 13 January and Major flood level was
reached at 5.15pm on 14 January.
The river at Charlton peaked at 1.15am on 15 January.
The recorded water level can be used to indicate when water came
directly from the Avoca River in the channel at Charlton, it will not
provide any inundation of timing of flows across Charlton from any
breakouts upstream from Yeungroon Creek or tributaries.
Locally derived stormwater flows would not have caused significant
flooding in Charlton after about 7.00am or 8.00am on 14 January.
Case No: 269311 Determination Page 6 of 15
Flooding from breakouts and transfer flows from Charlton-St Arnaud tributary,
Yeungroon Creek and Avoca River.
Flows in the Calder Highway tributary and other depressions leading
into Charlton after 8.00am would be caused by overland flows resulting
from breakouts from the Charlton- St Arnaud Road tributary,
Yeungroon Creek and later from the Avoca River further upstream.
Flooding along the Calder Highway tributary accounts for much of the
flooding in the eastern part of the catchment. The Charlton – St Arnaud
Road tributary, Yeungroon Creek and the Avoca River transferred flows
across the flood plain upstream of the town causing large flows through
the tributary waterway as well as across Charlton.
Flooding directly from Avoca River
The river reached a Major flood level at about 5.00pm on 14 January.
From around 6.00pm houses in the township were inundated directly by
overflows from the Avoca River. Properties flooded by the Avoca River
would have initially been on the west and southern side then east and
south.
Hydrological report commissioned by the Applicant (PM). November 2011
Rainfall
The highest rainfall was 15mm per hour from 17:00 to 08:00 on 13
January. Rainfall rates were persistently high from 23 :00 hours on 13
January to 06:00 on 14 January. No rain fell after 08 :00 on 14 January.
The radar data for Charlton indicates the rainfall was highly
concentrated in short duration bursts. The rainfall which produced the
15mm/hour actually occurred over a period of about 12 minutes.
This situation is similar for the rainfall over night on 13-14 January.
The rainfall intensities in these bursts are much higher than the
recorded hourly rates.
Overflow from local drainage systems
Given the intensity of rainfall which was muc h more than hourly rainfall
rates overflow from local drainage systems and culverts was highly
likely. Especially given that the drainage system was already close to
capacity from earlier rainfall bursts.
The timing of overflow would correspond closely to the timing of the
rainfall.
The first possible incident of stormwater drainage overflow would have
occurred around 07:00 on 13 January. Any of the intense rainfall
periods recorded between 13 and 14 January could have been
responsible for overflow of stormwater drainage systems. The greater
probability being from midnight to 0400 on 14 January.
Case No: 269311 Determination Page 7 of 15
Direct overflow is less likely after this time.
Without augmentation from other sources stormwater drainage
overflow would be short lived.
Runoff from surrounding areas
There were two possible sources of runoff. Runoff was possible from
(the township of) Charlton which does not enter the drainage systems,
and runoff from surrounding rural areas.
During periods of heavy rainfall bursts, water would have overflowed
and contributed to surface runoff. Without augmentation from other
sources stormwater drainage overflow would have been short-lived.
It is highly likely that rainfall which fell on 13 and 14 was saturation
overland flow and would have led to inundation of Charlton on 13 and
14 before floodwater from Avoca (River) entered the town.
Water falling south and east of Armstrong and High Streets will tend to
move east with water to the west and north tending to move to the river.
Water runoff as overland flow would concentrate water in the eastern
part of Charlton.
The combination of surface runoff from the surrounding area being
directed toward east Charlton combined with periodic overflow from
drainage systems in other parts of the town would lead to inundation by
stormwater and locally derived surface water on the morning of 14
January.
That inundation from locally derived (sources) rather than Avoca River
water is further supported by the changing sediment loads of water
seen in Charlton.
Yeungroon Creek
Yeungroon Creek was a former course of the Avoca River which has
been abandoned and infilled with flood deposits over many years.
Much of its length has been infilled to the extent there is no longer a
well-defined channel. It still acts as a natural drainage line.
South of Charlton the course of the creek is marked by linear
depression and vegetation. East of Charlton and north of the Calder
Highway a more clearly defined channel begins to develop.
Clear water
When the Avoca River overtopped its banks and Charlton was
inundated by floodwater the source of that water can be clearly seen
because of its high sediment load.
The presence of clear water in Charlton suggests that prior to
inundation from the Avoca River some floodwater was sourced locally
Case No: 269311 Determination Page 8 of 15
from stormwater which fell in town or collected east of town to partially
inundate the low lying parts of town, particularly to the east.
This water would not have extended over the whole of Charlton or have
been as great a depth as the main flooding from the Avoca River.
Flooding from Avoca River
Minor flood level was reached at 04:00 on 13 January. Moderate flood
levels were reached at 20:45 on 13 January. Major flood level was
reached at 17:15 on 14 January.
Significant inundation of Charlton from the Avoca River did not begin
until late afternoon on 14 January and became more severe through
the evening and night. Some outlying parts of Charlton would have
been inundated mid-afternoon.
Summary
Depending on the exact location of properties, they will have begun to
have been inundated from the Avoca River overflow sometime in the
afternoon and early evening of 14 January.
Any inundation from runoff before this time particularly corresponding to
those time when periods of heavy rainfall occurred on 13 and early
morning on 14 January could not have been caused by inundation from
the Avoca River.
It is possible that flooding could have been caused by
stormwater/intense rainfall runoff on 13 and early on 14 January.
Inundation from stormwater accumulating in eastern and southern
Charlton is probable on the night of 13/14 and early morning/early
afternoon of 14 January.
Hydrological report commissioned by the Applicant (PM). March 2012
The report was provided following an onsite assessment of Charlton
and individual properties.
Topography and storm water drainage
The stormwater outlet in Charlton empties directly into the Avoca River.
As the level rose in the Avoca River, the stormwater outlet would be
inundated by the river water and the drainage system would have back
filled to capacity with river water preventing stormwater on the surface
from draining away.
The upper height of the stormwater outlet pipe was 4.6m relative to the
river height. This level was reached early in the morning of 13 January.
From this time onwards the stormwater drainage system in Charlton
was inundated and at full capacity and rainwater runoff would not have
been able to freely run away.
Case No: 269311 Determination Page 9 of 15
Stormwater accumulation in Charlton therefore becomes a factor from
mid morning on 13 January and onwards.
Properties on or close to High Street (Calder Highway) are more likely
to be inundated by accumulated stormwater earlier compared to
properties on the south side of Charlton (Watson and Menzies Sts).
The topography and modelling indicate properties on the east of
Charlton close to High Street were inundated by locally accumulated
stormwater. This was before the town was inundated by water from the
Avoca River.
Clear water
Sediment laden water is from the river. Water with low sediment was
unlikely to be sourced directly from the river.
In the east of Charlton the sediment water occurred at about 6pm
associated with rapid river rise.
Some homeowners reported clear water until 7-8 pm.
This is explained as the complete mixing of the two water bodies had
not yet occurred in the central higher parts of town.
Mixing of clear water and muddy water was a gradual process that took
some time.
Flooding in some houses was therefore controlled by rise in river levels
but the actual water at the site was stormwater.
Major flood level
Major flood level (7.5m) was reached at 5.15pm on 14 January. It was
this point that water began to spill into the town.
Significant inundation from flood water probably occurred sometime
after 5.15pm.
Based on eye witness reports 6pm was a reasonable estimate of the
time delay between the water reaching major flood level and the flood
moving across the town.
It is possible river banks to the west and south of the town with low
points allowed water to overflow and inundate parts of the town earlier
than this.
Summary
Stormwater would have played a major role in flooding of the town.
The stormwater drainage system would have been inundated with
rising river water before the river overtopped its banks preventing
stormwater from draining away.
Case No: 269311 Determination Page 10 of 15
Modelling indicates the east part of town was inundated independently
of the river before the western part of town was inundated directly from
the river.
Properties in the east part of town were more likely to have been
impacted by stormwater in the drain running through the eastern side of
town.
Clear water before 6.00pm was most likely to be stormwater. After this
time clear water levels may have risen because of the influence of river
water. The presence of clear water cannot be taken as an indicator of
local stormwater after 6.00pm.
Up to 20 to 45cm of inundation are the most that can be attributed to
stormwater.
The Applicants’ property
The Applicants advised:
On the morning of 14 [January] water had started to seep through
the backyard fence and into the garden.
At about 5.00pm fast moving water started entering the property
through the backyard fence.
This water was clear.
The water quickly entered the house up to 5cm when they
evacuated soon after.
There is an 8.5cm step from the slab giving a total inundation of
13.5cm when they left.
Based on this information the first phase of inundation at about 5pm
was likely to have been sourced from the local drain and consisted of
locally derived stormwater.
This probably reached a depth of 15cm and possibly 20cm.
Section 35 of the Insurance Contracts Act 1984 (he Act) – Cleary inform
21. The Applicants submit that the FSP beached Section 35 of the Act as it has
not clearly informed the Applicants that storm was not covered under the
policy.
22. Section 35 of the Act provides that, where a claim is made under a
prescribed contract and the event giving rise to the claim is a prescribed
event in relation to the contract, an insurer may not refuse to pay an amount
equal to the minimum amount of cover set out in the regulations made
pursuant to the Act unless it can prove that before the contract was entered
into, the insurer clearly informed the insured in writing of the relevant
provisions of the contract, or that the insured knew or a reasonable person in
the circumstances could be expected to have known of such provision.
Case No: 269311 Determination Page 11 of 15
23. The policy issued to the Applicants is in the form of a packaged document
which provides cover under a number of policies from which the policyholder
may choose. Each policy is a unique contract containing the terms of cover
for that policy. Sections titled „Important information‟, „General exclusions‟,
„General conditions‟ and „General definitions‟ are universal.
24. The policy relevant to this matter is the Classic home cover. This section of
the p ackage has a clearly set out index which includes „The types of cover
we offer‟.
25. The policy provides cover for accident damage, burglary and theft. As this
cover is broad and does not specify define insured events, it is then usual for
an FSP to state in what circumstances cover is excluded. As loss or damage
arising from storm is not an excluded event (other than for contents not in a
domestic building when damaged) and may be regarded as something which
is unplanned and unforseen, damage to insured property arising from storms
is therefore covered by the policy.
26. In these circumstances the Panel is satisfied the FSP has clearly informed
the Applicants of the terms of cover and as storm is not an excluded event,
the FSP has no obligation to specify storm as an insured peril.
27. Importantly, in so far as it relates to this matter, the policy clearly states that
loss or damage caused by flood is excluded from cover except for limited
amounts.
28. As such, the Panel is of the opinion the FSP has complied with Section 35 of
the Act and clearly informed the Applicants of the cover provided by the
policy.
Consideration of the evidence
29. The dispute centres on whether the initial inundation of the Applicants‟ home
was from stormwater or from flood water as defined by the po licy.
30. In establishing whether water which inundated a property is surface runoff
rainwater or flood water, in many cases, the time of the initial inundation,
direction of water flow, colour of water and height of the property above
ground level are helpful factors.
Time of inundation of the Applicants’ property
31. Contradictory information has been presented to the Panel in relation to the
reported time of inundation. According to the WT report of 19 July the
Applicants agreed the timing of inundation of his property was similar to that
of another property being at 7.00pm on 14 January.
32. Conversely, through his representative, the Applicants contend that his
home was inundated by fast moving water at 5 .00pm.The Applicants cannot
explain the difference in time other than to say a misunderstanding may
have occurred when he met with the hydrologist.
Case No: 269311 Determination Page 12 of 15
33. During a site visit to Charlton, the Ombudsman discussed the event with the
male Applicant in the company of the FSP‟s representative. The male
Applicant acknowledging when he met the hydrologist at the other property
he agreed the timing of inundation of his property was the same as for the
other property. The male Applicant informed the Ombudsman he was
uncertain what question was asked at the time he met the hydrologist and
whether or not he thought very carefully about it.
34. The male Applicant also described his movements during the afternoon to
the Ombudsman, saying that at about 5 .00pm he went to observe the river.
At that time the area was fairly dry and the road was not covered with water.
He came straight back from the river and water was coming from the south.
Sheds at the rear of his property had been inundated at that time. He
described water entering his home at around 5.30pm.
35. Given that the male Applicant was present at the time of the inundation and
based on his movements was able to recall the time, the Panel is of the
opinion that his estimate of the initial inundation at 5.30pm may be relied on.
36. It should also be noted that the Applicants‟ description of e vents, as detailed
to the Ombudsman, is consistent with the times detailed in the hydrology
report of March 2012, commissioned by the Applicants.
Direction/source of water
37. The Applicants‟ property is located to the south east of Charlton close to
open ground.
38. The male Applicant says the water came from the south and his sheds at the
rear of his property were inundated at about 5.30pm.
39. Charts showing the flow paths of the water show water flowing towards
Charlton from the south and south east across the ope n ground. Both
hydrologists agree with this flow direction.
40. The expert evidence in relation to the source of the water which first entered
the Applicants‟ home is divided.
41. WT refers to unnamed drainage lines/tributaries of Yeungroon Creek which
have been referred to as Charlton-St Arnaud Road tributary and the other as
Calder Highway tributary. The Charlton-St Arnaud Road tributary crosses the
open ground upstream of the town.
42. WT submits that any flow from rainfall over the Calder Highway catchment
would have passed through the town by about 8.00am. WT further says the
continuing flows from the tributary/depression from after about 8.00am were
caused by overflows from the Charlton-St Arnaud Road tributary waterway of
the Calder Highway(sic), overland flows from „breakouts‟ from Yeungroon
Creek and later from the Avoca River upstream.
Case No: 269311 Determination Page 13 of 15
43. On the other hand, the PM report observes a combination of surface water
from the south and east of the town would have been directed to a series of
linear depressions which led it to go through the eastern end of Charlton.
This water combined with town drainage overflow so that inundation from
stormwater probably occurred. PM considered inundation from overbank
flooding would not have occurred until late afternoon/early evening on 14
January.
44. The undisputed evidence is that water which inundated parts of Charlton
approached Charlton from the south and south/east.
45. The question arises as to whether the landscape over which the water
flowed was an uncovered watercourse.
46. Following the visit to the area by FOS personnel, the Panel considers the
area of land over which the water flowed from the south and east of the town
cannot be regarded as a watercourse.
47. The following ruling was made by the High Court in Gartner v Kidman [1962]
HCA 27: 108 CLR 12 (30 May 1962):
“This distinction between watercourse and depression follows the language of
Hood J in Lyons v Winter (1899) 25 VLR 464, who in that case held that a
depression which took rainwater for about three months of a year fell short of
the legal definition of a natural watercourse. To constitute such a watercourse
as a matter of law, there must be a stream of water flowing in a defined
channel or between something in the nature of banks. The stream may be
very small and need not run, nor need the banks be clearly or sharply defined.
But there must be a course, marked on earth by visible signs, along which
water usually flows in order to constitute a watercourse such as creates
riparian rights (1899VLR at p485 (at p16)
48. The landscape to the south and south east of the town does not have
evidence of visible banks between which water flows. The landscape may
best be described as a flood plain over which water flows in a direction
determined by the rise and fall of the land.
49. This view is further supported by the description given by PM who observed
Yeungroon Creek has been infilled with flood deposits over many years. The
course of the creek to the south of the town is marked by linear depressions
and vegetation.
50. Additionally, photographs accompanying the WT report of 5 July, apart from
the gauge located downstream of Charlton, depict culverts including at the
crossing of the Charlton-St Arnaud Road and flat expanses of land at a road
crossing about 8km upstream of Charlton.
51. Accordingly the Panel accepts that water which came from the Yeungroon
Creek area to the south and south east of the town may not be regarded as
water which was from an uncovered watercourse.
Case No: 269311 Determination Page 14 of 15
Presence of clear water
52. The male Applicant says when his property was first inundated the water
was clear.
53. According to PM, the presence of clear water was indicative that it was not
water from the Avoca River or from Yeungroon Creek. While WT accepted
the general principle of clear water discussed by PM, WT did not accept that
water from Yeungroon Creek would contain high levels of sediment to colour
the water. WT‟s opinion was based on the extent of vegetation in the creek
and the topography, such that the flow would have spread out over the
undefined channel reducing the sediment.
54. However, the Panel notes that PM does concede that the presence of clear
water cannot be taken as an indicator of local stormwater after 6.00pm [14
January].
55. The Panel has viewed photographs of flood waters in Charlton which clearly
show a distinction in the water colour from clear to substantially discoloured.
While the Panel accepts that clear water is not of itself definitive, given the
timing of the initial inundation reported by the Applicants, the direction from
which that water originat ed and the hydrologists‟ evidence, the Panel is
persuaded that the clear water from the south south/east which initially
entered the Applicants‟ property was not water from the Avoca River.
Conclusion
56. After careful analysis of the available material the Panel concludes on
balance that the initial inundation of the Applicants‟ home was by rainwater.
57. According to the evidence (PM 1/11 p9) the rapid rise of the water occurred
from about 7.00pm being indicative of flood water from the Avoca River.
58. According to the PM report rainwater probably reached a depth of between
15cm to 20cm before the flood water inundated the Applicants‟ property.
59. On site, the Applicants advised the Ombudsman that the property was
inundated to the level of approximately 2 feet.
60. The Panel accepts the major part of the damage was caused by the
subsequent inundation of flood water from the Avoca River combined with
surface rainwater. The FSP therefore is not liable for the total cost of
rectifying all the damage claimed.
61. In order to finalise the matter the FOS Terms of Reference under which the
Panel operates requires that the Panel determine a matter based on what is
fair in all the circumstances having regard to the particular circumstances of
the claim, the relevant terms of the policy, legal principles, good insurance
practice and previous determinations.
Case No: 269311 Determination Page 15 of 15
62. It is now over eighteen months since the loss occurred. The Panel believes
sufficient information is available to finalise the matter. The Applicants‟ home
is a low set building constructed on a slab with one step to the front patio.
Two large sheds at the rear of the property are at ground level.
63. The Applicants have obtained a quotation in the sum of $139,863.24 for
rectification of the building damage. The household contents damaged was
estimated by the assessor in the sum of $81,684.
64. Given the estimated height of the inundation by rainwater at between 15cm
to 20cm, the Panel considers that 25% of the cost to rectify the building
damage and to repair or replace the contents damage is fair.
65. Insofar as the limited flood cover provided by the policy is a separate benefit
from the cover otherwise provided by the policy, the payment to be made as
a result of this determination is to be in addition to the $20,000 payment
made for the limited flood cover.
Determination
66. Based on the available material the Panel determines the FSP is to pay the
Applicants a sum equivalent to 25% of the cost to rectify the damage to the
building and contents arising from the inundation of the property on 14
January 2011.
67. The FSP is to pay interest in accordance with the Insurance Contracts Act
1984 from 8 April 2011 being the date on which the FSP issued its final
decision to the date on which payment is made.