Home / Financial Firm (Unknown - Insurer) / Determination 269016

Determination 269016

Flood exclusion used to decline water damage to strata unit (Jan 2011)

FirmFinancial Firm (Unknown - Insurer)
Decided2012-09-14
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's strata unit in Rocklea was inundated in January 2011 and the FSP declined the claim as flood damage. AFCA accepted the hydrology evidence that flood, not stormwater runoff, caused the inundation, so the decline was upheld.

Flood is excluded under the policy, and the insurer's site-specific hydrology evidence established that the inundation was flood rather than storm or rain runoff.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 269016 Determination Page 1 of 7 Case number: 269016 General Insurance - Domestic Insurance - Residential Strata Title - FSP Decision - Denial of claim-Exclusion/ condition - Flood 12 September 2012 Note: The Applicant being legally represented, any reference to Applicant is taken to include both himself and his lawyer. Background 1. The Applicant‟s home (located in Rocklea, Queensland) was insured with the Financial Services Provider (FSP) under a residential strata insurance policy. 2. He claimed for damage caused to his home by water inundating it in January 2011. 3. The FSP declined liability on the basis the damage was caused by flood, which the policy excluded. 4. The Applicant says he was unaware of the flood exclusion and in any case, maintains that his home was damaged by events covered by the policy. 5. The Applicant‟s contents were insured with another insurer whose denial of the claim is also the subject of a separate dispute before the Service. Summary of Applicant’s position 6. His account of the events that transpired on 11 January 2011 are as follows:  He was at work on that day, and was asked to go home sometime between 1.00pm and 2.00pm because some roads were being closed.  He went home and left to stay with his brother at about 3.00pm on 11 January 2011.  He did not take anything except for a change of clothes because: i. He did not believe his home would be inundated by water. ii. He was planning on returning at night to get more things.  However, the roads to his home became blocked a few hours later so he was unable to return home. Determination Case No: 269016 Determination Page 2 of 7 7. He is unsure when his home was inundated, but believes it likely occurred in the early hours of 12 January 2011. 8. He was unaware he was not covered for flood damage because:  He “did not have the benefit” of reading the policy.  The policy limitatio ns were “unusual”.  The FSP did not draw his attention to the “unusual” terms which would otherwise have enabled him to seek appropriate insurance.  He “did not get the benefit of the knowledge” of the FSP‟s product range. 9. The damage to his home was caused by storm and rain water runoff because:  The Brisbane area was subjected to a multitude of lightning strikes between 11.00pm 9 January 2011 and 11.00pm 11 January 2011.  The Bureau of Meteorology (BOM) had issued a severe weather warning just before 9.00am on 11 January 2011.  The ICA Reports as well as BOM records show Brisbane ‟ s western suburbs had experienced heavy rainfall on the morning of 11 January 2011.  His solicitor has many clients (living along the Brisbane River) who have recalled severe thunderstorms and heavy rains on the morning of 11 January 2011.  BOM records show there were 41kmh and 33kmh winds in his area on 10 and 11 January 2011 respectively. 10. In the alternative, the damage was caused by water escaping from a drain fixed pipe, sink, basin, bath, shower, toilet etc. 11. The FSP‟s hydrological evidence is inconclusive because:  The conclusions of the hydrology reports issued by the Insurance Council of Australia (ICA Reports) were general in nature and the reports specifically indicated that they sho uld not be relied upon in determining the cause of inundation of a specific property.  Flood mapping carried out by the Queensland Reconstruction Authority merely show flood peaks. It does not shed any light on what occurred prior and cannot be relied on to determine the source, flow direction, or type of water that first inundated the property.  The FSP did not properly investigate the claim before declining liability. It declined the claim based on generic hydrology reports and maps. Determination 238186 says it is inappropriate for insurers to decline claims based on limited evidence and then later seek to gather evidence to support its denial. Case No: 269016 Determination Page 3 of 7  The FSP‟s site specific hydrology report was obtained 11 months after the event and the report was done without considering witness accounts or a site inspection.  The hydrologist‟s conclusion (that the initial inundation occurred at mid - day 12 January 2011) is based on conjecture and assumptions. 12. The Applicant has referred to Section 35 of the Insurance Contracts Act, 1984 (the Act) and the Corporations Act, 2001 for purposes of his submissions. Summary of FSP’s position 13. Its evidence shows that the damage to the Applicant‟s residence was caused by flood, which the policy excludes. 14. The Applicant has not provided evidence to substantiate his claim that the damage was caused by storm or rain water runoff. 15. Flood cover was offered as an option which was not taken. 16. Section 35 of the Act is inapplicable to the dispute because:  The Applicant is not the policyholder. The polic yholder was the body corporate.  The policy was arranged by a broker acting for the body corporate. Pursuant to Section 71 of the Act, it has no obligation to clearly inform the Applicant of the policy terms.  The Applicant was not yet the owner of his home unit when the policy was taken out. 17. The FSP relies on the following policy provisions: “ Building and Common Contents … Definition specific to this Cover Section … Flood flood means the covering of normally dry land with water released or that has escaped from the normal confines of: (a) any watercourse whether natural or altered; (b) any lake whether natural or altered; or (c) any reservoir, canal or dam. … Exclusions Case No: 269016 Determination Page 4 of 7 We do not insure you against loss or damage caused directly or indirectly by or arising out of: … 5. flood. … Optional Extensions of Cover … 2. Flood When Flood is shown in the schedule of insurance we will provide cover for damage to property caused by flood . …” Issues 18. Whether the Applicant was unaware he was not covered for flood damage and if so, is he entitled to indemnity on this basis. 19. Whether the damage to the Applicant‟s home was caused by storm or rain water runoff and/or water escaping from a drain, fixed pipe, sink, basin, bath, shower, toilet etc. and/or flood (as defined in the policy). Reasons for decision Preliminaries 20. Due to the nature of the dispute, this matter has been referred to the Panel for Determination in line with the Operational Guidelines to the Financial Ombudsman Service‟s Terms of Reference. 21. The Panel consists of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 22. The Panel is satisfied that the relevant material has been exchanged and the parties have had the opportunity to respond to the issues raised. 23. The Panel Chair Ombudsman attended on site where he met with the Applicant, a representative of the FSP and the FSP‟s hydrologist. 24. The Panel notes that the Applicant is legally represented and that the provisions of Sections 35 and 71 of the Act have already been set out in the exchanged material. For the sake of brevity, the Panel will not repeat these provisions here. Case No: 269016 Determination Page 5 of 7 Broker involvement 25. It is plain that the Applicant‟s policy was arranged through a broker who was acting on behalf o f the body corporate that manages the Applicant‟s strata residence. 26. The FSP was therefore excused from its usual Section 35 of the Act obligation (pursuant to Section 71 of the Act), so the Applicant ‟ s assertions of being unaware of the policy‟s limitation s with respect to flood damage do not assist him. 27. The Panel has carefully reviewed the Product Disclosure Statement (PDS) and is satisfied that it clearly sets out that it does not cover flood damage. Proximate cause of loss 28. The policy provides cover whereby: „the FSP agrees to indemnify you (the Applicant) against physical loss or damage to your building and common contents ….‟ Accordingly, as the Applicant has prima facie suffered loss encapsulated by those words, the onus of proof in demonstrating the applicability of a policy exclusion falls to the FSP‟s account. 29. In respect of the FSP‟s contention that it was the policy excluded event of flood that inundated the Applicant‟s home -unit, the Panel observes the following salient information from the site specific desk-top hydrology report completed in December 2011; in considering this material the Panel also notes the hydrologist, at the FSP‟s behest, did not interview the Applicant:  The ground level of the Applicant‟s home is elevated at 7.7m AHD (Australian Height Datum).  The home was located approximately 4.7km upstream of the confluence between Stable Swamp Creek and Oxley Creek, and approximately 430m from the confluence between open stormwater drains and Stable Swamp Creek.  Peak intensity rainfall in the Applicant‟s area was likely to have occurred prior to or at about 11.00am on 11 January 2011. There appeared to be little to no rainfall in the area by late afternoon (i.e. from 4.00pm to 5.00pm) onwards on 11 January 2011.  After interpolating the Brisbane River water levels at the Corinda High and Oxley Creek Mouth Alerts, the FSP‟s hydrologist estimates that the river was likely to have reached a height (9.2m AHD) sufficient to clear 7.7m AHD (given an estimated water inundation of approximately 1.5m above floor level) at sometime between midday and 1.00pm on 12 January 2011.  The FSP‟s hydrologist also says that peak stormwater runoff would usually occur within 15 minutes of peak intensity rainfall activity. As peak intensity rainfall occurred prior to or at about 11.00am on 11 January 2011, the hydrologist concluded that any inundation after 5.00pm on 11 January 2011 was unlikely to be stormwater, but Case No: 269016 Determination Page 6 of 7 backflow from the Stable Swamp Creek and relevant stormwater channels.  Sa tellite images of the Applicant‟s home unit and its surrounds do not show any features that would promote stormwater runoff.  The hydrological evidence provided by the insurer involved in the Applicant‟s other dispute before the Service is fairly consistent with this FSP‟s hydrological evidence. 30. When he attended on site, the Panel Chair Ombudsman noted that the Applicant‟s home is raised on stumps to a height of approximately 800mm at the front and 450mm at the rear. 31. The Panel understands the Applicant evacuated his home unit at about 3.00pm on 11 January 2011 and the home had not yet been inundated then. The Applicant believes that the initial inundation occurred in the early hours of 12 January 2011. 32. The Panel must now consider whether, on the balance of probabilities, the FSP‟s hydrology is persuasive as to whether „flood‟ defined as „ the covering of normally dry land with water released or that has escaped from the normal confines of: a) any watercourse whether natural or altered; b) any lake whether natural or altered; or c) any reservoir, canal or dam. was solely responsible for the inundation of the Applicant‟s home -unit. It is instructive to note, in the event stormwater drain overflow proximate to the Applicant‟s home -unit had caused an initial level of inundation to say 100mm, prior to midday on 12 January 2011 , such damage would not necessarily be subject to the excluded event of flood. 33. However, after carefully considering these matters, on the balance of probabilities particularly in light of the fact the Applicant is unable to provide any probative evidence as to the time of the home- unit‟s inundation, other than his statement: “ I am not sure when exactly the water hit our property, but I think it came in on 12 January 2011 in the early hours ” , the Panel is satisfied on the hydrologist‟s evidence that the damage to the Applicant‟s home unit was caused by flood as defined in the policy. 34. Putting the Applicant‟s case at its very best, when he left the home at 3.00pm on 11 January 2011, 2 hours after the peak rainfall, there was no inundation at that time. 35. In those circumstances, the Panel is satisfied that stormwater runoff was not the cause of the inundation. 36. The Applicant notes that the Brisbane River is to the west of the property, whereas the waters that inundated the property came from the east, as evidence by floating water tanks. Case No: 269016 Determination Page 7 of 7 37. The Panel does not doubt the accuracy of this statement but given the height of the Brisbane River and the resultant backup of the Oxley Creek, Stable Swamp Creek and the open channel running across Salisbury Street and the park opposite the Applicant‟s home, the Panel is satisfied that the water which inundated the Applicant‟s home came from Stable Swamp Creek and the open channel. 38. Having regard to the terms of the policy and the Panel Chair Ombudsman‟s observations at the site visit, the Panel accepts that the channel is a watercourse as defined by the policy and the water which escapes from that channel as well as Oxley Creek is flood water as defined by the policy. Determination 39. In the circumstances, the Panel determines that the FSP is entitled to decline liability in response to the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.