Text of the determination
Case No: 268817 Determination Page 1 of 11
Case number: 268817
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
3 April 2013
Background
1. The Applicant is a member of a Body Corporate which held a Residential
Property Insurance policy with the Financial Services Provider (FSP).
2. The Applicant lodged a claim on 17 March 2008 following the Mackay Floods
which damaged the Applicant‟s unit.
3. The FSP accepted the claim and arranged for repairs to be undertaken. The
Applicant was unhappy with the standard of repairs.
4. The FSP has reviewed the matter and maintains the standard of repairs has
been completed to the requisite standard. The FSP has declined to perform
further repairs.
5. The Applicants dispute the FSP‟s declinature to perform further re pairs on the
basis that the original repairs were not up to the previous standard.
Summary of Applicant ’ s Position
6. The Applicant has enclosed photographs depicting the tiling to the unit. The
photographs particularly focus on the bathroom area and I note that there is
uneven grouting/gapping in some portions of the bathroom. There are
unrepaired holes in the ceiling where an original shower rail was positioned.
7. A further series of annotated photographs depicts a hole placed into the
exterior wall through to the interior of the property where the bathroom is
situated. It appears this hole was then patched.
8. The Applicant has enclosed a number of emails between the repairer/assessor
and the FSP. She notes the following in relation to same:
Email dated 17 December 2008. The builder states the work has been
completed in accordance with the scope of works. He has met with the
owner numerous times for sign off but the owner is not prepared to sign
and is:
Determination
Case No: 268817 Determination Page 2 of 11
“..finding fault with everything and anything, we have tried to appease her and
have provided a number of services outside the scope, we have had the
electrician return 3 times (at our cost) as she keeps finding things that were
supposed there prior for example GPO’s that we installed 2 pin she has insisted
t hey were 4 pin, doesn’t like the tile as they are not exactly like the old ones (she
did choose the new tile)…”
The Applicant notes she does like the tiles and GPOs (General Power
Outlet) were 1x4 GPO that she requested for the second bathroom.
Further, she has never seen a customer satisfaction form.
Email dated 1 June 2009 notes a shower curtain was returned with
additional portion stitched on and this has gone mouldy. The email states
the Applicant was going to purchase a new curtain, which the Applicant
denies. Further, some notations suggest additional support was required
to the rear wall.
Email dated 1 June 2009 states the shower curtain is not acceptable. The
shelving needs to be cut differently to ensure it contours with the pipe
work. This would allow the shelf to be supported. Further, there are
electrical and fire safety defects that need rectification.
Email dated 3 June 2009 alleges the Applicant agreed to make the
shower curtain longer. Further, the issue with the shelving will be rectified
as will the GPO in the bathroom.
Email dated 17 November 2009 states the shower curtain has been
relocated back to its original position and all other rectifications have been
finalised. The Applicant states this is untrue and the original hole from the
shower curtain is still visible. The Applicant has a photograph to evidence
this. The Applicant states this is why the shower curtain no longer fits,
because the rail had been placed too high.
9. Whilst the Applicant has nominally claimed for the rectification of the whole unit,
she has provided a quotation for repairs to the bathroom alone. The quotation
by “JL” is dated 26 June 2012 and is for the amount of $15,245.
10. The Applicant has enclosed a BSA report dated 17 January 2012 from which I
note the following:
The original contract was signed on 6 June 2008 and the contract amount
was for $44,650. The work was completed on 31 January 2009.
The lipping to the entryway tiles was present and measured to be 1.5mm.
The Australian Standards state the lipping between two adjacent tiles
should not exceed 2mm so there is no defect according to the standards.
The Applicant stated the main bedroom window had not been replaced,
only the window pane broken by the repairer. The manufacturer‟s
warranty has expired and BSA believed this was the responsibility now of
the Applicant.
The colour change of grout in front of the kitchen sink was inspected. The
BSA noted that the grout appears to have absorbed oil giving the
appearance of a wet surface. At the time of inspection there was no water
Case No: 268817 Determination Page 3 of 11
on the floor or inside the cabinet. The colour change did not affect the
function of the tiles.
There was no discernible evidence that the pavers near the front door had
rising damp due to water from the adjacent bathroom.
The Applicant reported the old vanity was 750mm but the tiler left only
748mm for the vanity to be installed. This meant the builder had to
dismantle the cabinet and install it. There was no apparent defect with the
operation or finish of the cabinet which could be dealt with by the BSA.
There were no defects in the tiling of the shower recess. A water test also
eliminated a defect in the waterproofing membrane under the tiles. The
Applicant had noted the layout/design differed to the original.
The shower hob shape and design is different from the original shower
recess. However, the hob was not deemed to be defective.
The water pipes or sink waste do not appear to be defective or leaking
water.
There were no discernible defective works that would allow insects to
enter the dwelling whilst windows and doors were closed.
There is no defect to the laundry shelf or the installation of same.
Although it was noted the laundry shelf was pre-fabricated and not
designed to take a lot of weight as would be expected of a laundry shelf.
A reinspection occurred but did not provide any alteration of the previous
report.
11. The Applicant had recently renovated the unit by a builder/tiler and the work
was excellent.
12. After the floods the FSP arranged poor quality repairs and from the beginning
the Applicant contacted the FSP to inform them of her concerns. The FSP
repeatedly informed her that it would be alright.
13. The repairs took 8 months to complete and the Applicant was in a motel during
this time. The unit is only 60 square meters.
14. There was no hand over of the property at the finalisation of the works and the
Applicant never signed off on any documents.
15. The Applicant is particularly disappointed about the works to the bathroom. The
tiling throughout the unit is now uneven.
16. The Applicant believes the new kitchen was installed over the area where the
flood waters had entered through the kitchen wall. Consequently it is the
Applicant‟s position that the new walls have been absorbing the old flood water
and the tiles placed over a „filthy space‟.
17. The Applicant submits that the experts have adopted a tone of „acceptable‟ or
„good enough‟. This is not the same thing as restoring her bathroom to the
same high standard that it was in, prior to the flooding. It is the Applicant‟s
Case No: 268817 Determination Page 4 of 11
contention that the standard of her bathroom is not the same as her old
bathroom. This is clear from the photographic evidence provided.
18. The Applicant notes that any rectification of the areas would require removal of
existing tiles and replacement. However, this will likely cause damage to the
existing structure of the kitchen, walls, built in robes etc. The Applicant notes
approximately 60 square meters would need to be removed and replaced.
19. The Applicant also seeks $3,000 for stress. The Applicant submits she is
entitled to compensation under paragraph 9.3(b) of the FOS Terms of
Reference as she was physically inconvenienced due to the displacement from
her home for approximately 8 months. During this time, she lived in a motel with
all the difficulties that entailed. She was also experiencing serious health issues
including hypertension, arterial plaque, lupus, diabetes, hyperthyroidism,
vertigo and vocal cord palsy. These conditions were exacerbated by being
away from the comforts of home.
20. The Applicant also contends there has been an unusual amount of time taken
to resolve the situation as 5 years has now passed. The constant contact with
the FSP and its builder also created an unusual degree of interference with her
expectation of enjoyment and peace of mind, The complaints regarding the
standard of work were dismissed as “petty” and she felt disrespected and
belittled when voicing her views.
21. The Applicant seeks for the unit to be reinstated to its previous condition. She
would like the bathroom to be replaced to the standard it was prior to the
flooding in accordance with the insurance policy. Further, that accommodation
and furniture storage costs be paid whilst the bathroom renovation works are
carried out.
Summary of FSP’s Position
22. The FSP relies on the following policy terms and conditions (in addition to those
relied upon by the Applicant):
“Important terms explained
…
term
new for old
..
meaning
This is:
- replacing or repairing with new items or new materials that are available at the time
of replacement or repair from Australian suppliers and
- new for old regardless of age, with no allowance for depreciation and
- of the same type, standard and specification as when new.
Case No: 268817 Determination Page 5 of 11
If the same is not available, it means of a similar type, standard and specification when
new. It does not mean of a better standard, specification or quality than when new.
…
Building Cover
When we insure your Building, we will cover it for accidental loss or damage or theft, in
the period of insurance if the loss, damage or theft is not excluded by any part of your
policy.
…
How claims are paid
Your Building and Common Contents claims
If we agree to pay a claim for accidental loss or damage or theft to your Building or
Common Contents, we will decide if we will:
- repair damage new for old or
- replace your Building or common Contents new for old or
- Pay what it would cost us to repair or replace your Building or Common Contents
new for old.
If the sum insured is not enough to cover repairing or replacing your Building or
Common Contents new for old, we will pay you the sum insured (see page 8.) ”.
23. The FSP has enclosed a claim record dated 19 December 2008 noting all
issues. There are 22 items listed and the Applicant also stated the builder had
ignored her regarding the variation changes and renovation work that had been
carried out in the home. The Applicant was asked to check the variations
approved were correct. The review did result in approximately 8 items to be
rectified and 8 questions for the builder. The tiling in the kitchen and laundry
was not considered to require action as it is normal building practice.
24. The FSP has enclosed a number of emails which show the time lines of the
claim, these emails include those provided by the Applicant. I note the following
two emails in particular:
The first email is dated 4 June 2009. I note the following from this email:
“Enclosed below the response from [name removed]. It would appear they are
agreeing to do everything except the shower curtain, but they have been silent
on the curved shower hob.
I have phoned there (sic) office. [name removed] is away on site to-day. Spoke
with [Applicant’s name removed], but she was vague on the reason why this was
done. She thinks she may have some pre-condition photos which she will search
for….”
The email then encloses another email dated 3 June 2009 referred to above
in the Applicant‟s material.
The email dated 5 January 2010 from the assessor provides the following:
“The following comments are based on photos that have been downloaded onto
Claim Centre and my previous notes from various site visits during 2009.
Item One:
Case No: 268817 Determination Page 6 of 11
Wall tiles on the hob don’t line up with the existing wall tiles because the wall
tiles have been laid on a 45 degree angle as shown on photo 10 in Claim Centre.
Also note that the design of the shower recess was discussed with the insured
and [name removed] floor tiller (sic) as stated by [name removed] re email 4 th of
June 2009
Item 2:
Yes there are cut tiles on the hob, there (sic) sharp edges have been removed
(photo 12).
Item 3:
Shower floor tiles are at an acceptable standard.
Note. Lippage may also be unavoidable where tiles are larger than 150mm x
150mm are graded to a floor waste. In this case the floor tiles are larger than
150mm x 150mm. See [name removed] photos dated 1/6/2009
Item 4:
Entrance floor tiles are at an acceptable standard.”
25. The FSP maintains that the bathroom accords with relevant standards and it
has complied with its obligations under the policy. The FSP has repaired the
damage, new for old. The policy definition of new for old requires the FSP to
repair to the same type, standard and specification as when new. If the same
standard is not available, then the FSP will repair to a similar type, standard
and specification.
26. The FSP relies on its assessor opinion that the tile works in the bathroom were
completed to an acceptable standard. The FSP further notes that the
Applicant‟s Inspection and Re -Inspection reports from the BSA state the issues
do not constitute building defects. The reports do not conflict with the evidence
provided by the assessor.
27. The FSP has noted the Applicant‟s request for compensation under FOS Terms
of Reference 9.3b). The FSP submits that FOS may only decide that an FSP
should compensate an Applicant for non-financial loss where an unusual
degree or extent of physical inconvenience, time taken to resolve the situation
or interference with the Applicant‟s expectation of enjoyment or peace of mind
has occurred. The FSP submits that an award for compensation is not justified
in this matter as the FSP has responded to the Applicant‟s complaints in a
timely manner and all rectification works were completed by 17 November
2009. Since this time, all the expert evidence has established the bathroom and
other parts of the property were completed to an appropriate standard.
Issues
28. Whether the FSP was entitled to decline the Applicant‟s claim to rectify the tiling
work performed at the insured residence.
29. Whether the Applicant is entitled to compensation.
Case No: 268817 Determination Page 7 of 11
Reasons for Decision
30. There has been an exchange of material between each party, and I am
satisfied each party has had an opportunity to reply to the issues raised.
31. I have read each party‟s submissions and materials and will only refer to the
relevant submissions and materials raised.
32. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is
due to the circumstances and quantum of the dispute. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
Whether the FSP was entitled to decline the Applicant’s claim to rectify the
tiling work performed at the insured residence.
33. The issue before me is essentially that of workmanship. The Applicant states
that the repairs undertaken by the FSP are of a lesser quality than the
previously installed bathroom. The FSP in turn notes that the building works
meet relevant standards and it considers that it has met its policy obligations.
34. In my view there is a disjunct between the types of standard each party
expects. The Applicant contends that the new for old policy definition includes
„standard‟ which includes quality of finishing. In contrast the FSP is considering
building standards and whether the work completed accords with the Australian
Standards. Unfortunately there is no definition of „standard‟ contained within the
policy from which to seek guidance. In circumstances where a policy term is not
defined, the plain ordinary English meaning shall be applied. I note the
Macquarie Dictionary provides the following relevant definitions of standard:
“ standard
/ˈstændə d/ (say 'standuhd)
noun 1. anything taken by general consent as a basis of comparison; an
approved model.
...
6. a grade or level of excellence, achievement, or advancement: a high standard
of living.
7. a level of quality which is regarded as normal, adequate, or acceptable.
...
9. (usually plural) behaviour, beliefs, etc., regarded as socially desirable or
acceptable.
...
15. something which stands or is placed upright.
16. an upright support or supporting part.
Case No: 268817 Determination Page 8 of 11
17. an upright timber, bar, or rod.
...
– adjective 22. serving as a basis of weight, measure, value, comparison, or
judgement.
23. of recognised excellence or established authority: a standard author.
24. normal, adequate, acceptable, or average: standard goods; a standard
fitting; standard petrol. ”
35. The term „standard‟ is somewhat broad. It includes normal, acceptable or
adequate as well as a grade or level of excellence. There is therefore no
reason to read the term „standard‟ down to address solely the Australian
Standards. The term can conceivably cover a standard of finishing or quality
similar to the original bathroom and other areas of the renovated property. I
also note that the purpose of an insurance policy is to place the person back
into the position they were prior to the damage. Unfortunately, such a decision
is somewhat subjective – particularly without sufficient photographs to allow a
comparison to the previous bathroom. Accordingly, it is necessary to review
whether the bathroom or property repairs have met the original property
condition standards.
36. There are minimal photographs available of the pre-existing bathroom.
However, I note there is a different hob, the shower rail has been altered (with
original holes still visible) and the vanity cabinet has been placed differently to
the original. I also note the untidy and large amount of grouting depicted on
what may be part of the hob and white leg/frame/base of a structure which did
not appear to exist in the photographs of the original bathroom. There is a
suggestion from the FSP that the emails demonstrate that the Applicant has
agreed to the alteration of the hob. The emails referred to indicates the
assessor asked the builders regarding the hob, but they “...have been silent on
the curved sho wer hob ”. The Applicant was described as “vague” regarding the
reason the hob had been altered. This does not establish an agreement by the
Applicant to the alterations of the hob, and her behaviour would indicate the
contrary.
37. It is unknown whether any lipping pre -existed the works. The Applicant has
taken issue with the tiling on this basis, but the FSP‟s experts note that lipping
often occurs with larger tile sizes. It is possible that the tiles were smaller
previously although it is unknown. Accordingly, I cannot make any
determination on the issue of tile lipping.
38. There is no clear evidence regarding the laundry shelving other than the
assessor‟ s comment that he would expect it to be stronger due to its placement
in the laundry. Again, it is unclear whether the laundry shelving was similar or
different to the original and I can make no determination on same.
39. I note the issue raised by the BSA regarding different coloured grouting and the
wet look to the tiles is of concern. Whilst I accept it certainly does not affect the
function of the tiles, it is unlikely that the Applicant had multi-coloured grout
throughout her property or tiles of different appearance. This would certainly be
tiling of a lesser standard or finish as the Applicant previously had.
Case No: 268817 Determination Page 9 of 11
40. There is no evidence from the Applicant to support her contention that the
kitchen walls are absorbing the flood waters or the tiling was done over „a filthy
mess‟. Similarly there is no evidence to suggest a leak has occurred in the
bathroom which has resulting in a rising damp issue on the front paving.
41. The Applicant has requested the full amount of replacing the tiling to the
property, however, she has focused almost exclusively on the bathroom. The
Case Manager has attempted on a number of occasions to obtain information
regarding the exact nature of the Applicant‟s claim and information regarding
whether rectification or entire replacement of items is required. In response, the
Applicant has provided a quotation for the bathroom alone for entire
replacement. There is no report contained in the quotation to confirm that
rectification would not be possible and only full replacement can occur. Given
this, I am not satisfied that the quotation provided represents the Applicant‟s
loss.
42. I consider the FSP should be entitled to a reinspection with a view of
determining the quality of finish in comparison to the original bathroom, rather
than merely compliance with the Australian Standards. In particular, an
independent building consultant or assessor (acceptable to both parties) should
re-inspect the property with a regard to the overall placement of tiles, the
grouting and the general finish to same. I note that rough cut side up tiles,
regardless of whether the edges have been smoothed, would not be deemed a
quality finish. The independent consultant should also consider whether
rectification is possible or replacement would be required. Unless the FSP can
produce evidence of the Applicant‟s consent to the changes in the placement of
the vanity and hob design, I consider it should rectify this and arrange for the
items to be placed back to their original locations. I consider that the exposed
holes indicating the original placement of the shower rail should be properly
repaired (if not already done so) and a shower curtain of an appropriate length
provided. Further, any item that does not accord with the original specifications,
such as the 4 GPO, should be replaced if it has not already been replaced. I
also consider that the FSP should be able to discharge its liability with a cash
settlement for the works based on reasonable market rates available in the
Applicant‟s location.
Whether the Applicant is entitled to compensation
43. I note the following Terms of Reference are relevant to a consideration of
whether the Applicant should receive compensation.
“9.3 Other compensation
Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential
financial loss or damage up to a maximum amount of $3,000 per claim made
in the Dispute
...
Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the
Financial Services Provider, compensate the Applicant for non-financial loss
but only where:
Case No: 268817 Determination Page 10 of 11
An unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant‟s expectation of enjoyment or
peace of mind has occurred; or
In the case of a Dispute pertaining to an individual‟s privacy rights – injury has
occurred to the Applicant‟s feelings or humiliation has been suffered by the
Applicant.
The maximum amount of compensation for non-financial loss will be $3,000
per claim made in the Dispute.
Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation
for:
Consequential financial loss; or
Non-financial loss,
In a Dispute arising as a result of a claim on a General Insurance Policy that
expressly excludes such liability
...
9.6 Other types of damages
Punitive, exemplary or aggravated damages may not be awarded.”
44. I have reviewed the emails and timelines to this matter. I note that a number of
issues were raised with repair and there appears to be some communication
issues between the parties.
45. I do not agree that the FSP has taken 5 years in relation to this matter, as it
provided an original IDR decision by letter dated 13 January 2010 which the
Applicant did not follow up. Whilst I acknowledge the Applicant has some
serious health conditions, it would be improper to award compensation on the
basis of non-action after this time given the Applicant waited over 2 years later
to lodge a dispute. This inaction cannot be attributed to the FSP.
46. The flood claim was lodged on 17 March 2008 and the builder informed the
FSP it had completed the works by 17 December 2008. I do not consider this
an undue delay given that the flood event to MacKay was significant and the
apparent difficulties of obtaining appropriate tradespersons prepared to perform
the work. The Applicant has noted this issue of obtaining appropriate
tradespersons prepared to perform the work on a number of occasions to the
Case Manager.
47. Based on the documentation, the Applicant waited 4 months to contact the FSP
after the finalisation of works. It was not until 8 April 2009 the Applicant
contacted the FSP regarding unsatisfactory items of repair. The rectification
works to these unsatisfactory items however, took until 17 November 2009. I
consider this time length unduly long and that the time taken would have
interfered with the Applicant‟s expectation of enjoyment of the property.
48. Given this, I consider that an appropriate amount of compensation, keeping in
mind the Applicant‟s poor health, would be $500.
Case No: 268817 Determination Page 11 of 11
Determination
49. On the basis of the available information I determine that the FSP is required to
perform some rectification works in accordance with paragraph 42 of this
Determination. The FSP may cash settle on the basis of the independent
expert‟s report.
50. The FSP shall pay an amount of $500 to the Applicant due to the delay in
responding to the complaint and completion of rectification works.