The applicant alleged the mortgagee FSP unreasonably delayed processing a request to assign its mortgage to a third party. AFCA found the delays, shared by all parties, were not unreasonable and ordered no compensation.

A delay must be unreasonable in all the circumstances, and the FSP had no contractual obligation to assign the mortgage.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Case No: 268193 Determination Page 1 of 3 Case number: 268193 Credit - Consumer Credit - Home Loans - FSP Decision - Maladministration in loan management 12 February 2014 Summary Description  This dispute is about whether the FSP unreasonably delayed in processing an Assignment of its mortgage and as a result caused the Applicant ’ s loss. Basis of Determination  While there were periods of delay on the part of the FSP such delays were not, having regard to all of the circumstances, unreasonable. Determination  The FSP is not liable to pay compensation to the Applicant. Background 1. The issue in this dispute is whether the FSP unreasonably delayed in dealing with a request from the Applicant to assign the FSP’s mortgage to a third party. At the time the request was made, the FSP was a mortgagee in possession of the property. Reasons for decision 2. The Applicant and the proposed Assignee entered into a Deed on 25 April 2011 (“the 25 April Deed”) whereby the proposed assignee agreed to pay out the FSP’s mortgage in order to invest in the a business conducted at the mortgaged property. 3. After the 25 April Deed was signed, the Applicant asked the FSP to consent to the assignment of its mortgage as proposed in that Deed. On 6 June 2011, the FSP gave its conditional in principle agreement to assign the mortgage. Determination Case No: 268193 Determination Page 2 of 3 4. It is common ground that there was no contractual obligation on the FSP to assign the mortgage. It was a commercial decision for the FSP as to whether it agreed or not. It is therefore my view that the FSP cannot be liable for any delay between when the request was first made to assign the mortgage and when the FSP responded to that request. The FSP therefore cannot be held responsible for any delay between 25 April and 6 June 2011. 5. However, having agreed to assign the mortgage, the FSP could be held liable if the FSP (which in this case also includes the FSP’s solicitors unreasonably delayed in processing that request. In this regar d, “delay” is not sufficient to mean that the FSP is liable. The delay must be unreasonable in all of the circumstances. 6. The available information shows that having agreed to the request on 6 June 2011, the FSP provided the proposed Deed of Assignment to its solicitors on 7 June 2011. The Deed was reviewed by an Associate on 12 June and a Partner on 15 June 2011. The Associate and the Partner discussed the Deed on that day. 7. In reviewing the available information, it appears that there was no activity on the part of the FSP between 15 and 27 June 2011. Between 27 June and 15 July 2011, the FSP’s solicitors finalised the Deed of Assignment. 8. On 19 July 2011, the Applicant asked that the matter be given priority. On 20 July 2011, the FSP’s solicitors sought instruct ions about the proposed Deed and the existence of a guarantee. 9. On 21 July 2011, the proposed Deed of Assignment was provided to the Applicant’s solicitors. It took from 6 June 2011 to 21 July 2011 to provide the revised draft Deed. There appears to be a period of 2 weeks where there was little or no activity in relation to this matter. 10. On 1 August 2011, in response to an email of 28 July 2011, the FSP’s provide a copy of the loan contract and mortgage. 11. On 10 August 2011, the solicitors for the Proposed Assignee requested amendments to the Deed, including a request for any Deed of Priority with the second mortgagee. Finally, I note the 10 August 2011 letter indicates an intention on behalf of the proposed assignee to proceed to settlement. 12. Following the request to provide any Deed of Priority, the FSP immediately started searching for the security packet. 13. On 15 August 2011, the FSP’s solicitors drafted the changes to the Deed of Assignment, although the revised Deed was not provided at this time. 14. On 23 and 24 August, the Applicant’s solicitors asked the FSP for a response about whether there was a Deed of Priority. The FSP’s solicitors indicated that they were seeking their client’s instructions . 15. On 29 August 2011, the assignee’s solicitor wr ote to the F SP’s solicitor and said: Case No: 268193 Determination Page 3 of 3 “considering it has taken a significant amount of time for your client to provide the Consumer Credit Contract to our client and further considering we are yet to receive your client’s response to our letter of 10 August 2011, our client has instructed us it no longer wishes to proceed with the assignment.” 16. It appears that a copy of the Consumer Credit Contract has already been provided to the Applicant’s solicitors on 1 August 2011. 17. As I noted earlier, the issue for my consideratio n is whether the FSP and its solicitors unreasonably delayed in processing the request. In making that assessment, I need to take into account the conduct of all of the parties. 18. While there was a two week delay on the part of the FSP and its solicitors in providing a draft Deed, it also took the Assignee’s solicitors some two and half weeks to respond to the Draft Deed. 19. There was also a delay in the FSP providing a response to the question about whether there was a Deed of Priority with the Second Mortgagee, but I do not regard this as an unreasonable delay, given that it necessarily required the FSP to make further enquiries and try and locate it security packet. It is not uncommon for there to be some delay on the part of an FSP when it is required to locate a security packet. What is an important consideration for me is that the FSP commenced the process of retrieving the security packet on 10 August 2011 and followed up the request on 15 August 2011. 20. While there could have been better communication between the various parties regarding the difficulties the FSP was having in locating the security packet, the delays were not so significant, in my view, as to amount to an unreasonable delay. 21. Having regard to the whole of the circumstances and the various delays at different times by all parties to the transaction, it is my view that the delay on the part of the FSP was not so unreasonable as to warrant the compe nsation sought by the Applicant. Determination 22. On the basis of the available information I determine that the FSP did not unreasonably dela y in processing the Applicant’s request for an Assignment of its mortgage. 23. The Applicant is therefore not entitled to compensation.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.