Unit inundation claim through body corporate denied under flood exclusion; catastrophe cover and legal costs disputed
Text of the determination
Case No: 264018 Determination Page 1 of 9
Case number: 264018
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
30 July 2012
Note: The Applicant is legally represented; for ease of reference both himself
and his legal representative are referred throughout as the Applicant.
Background
1. The Applicant is an owner of a property which forms part of a Body
Corporate. The Body Corporate holds a Home Building policy of Insurance
underwritten by the Financial Services Provider (FSP).
2. On 11-12 January 2011 the Applicant‟s unit in Westlake Queensland, was
inundated by water causing damage. The Applicant subsequently lodged a
claim through the Body Corporate.
3. The FSP declined the claim on the basis the water inundation arose from
flood which is an excluded cause of loss under the policy.
4. The Applicant disputes the declinature on the basis the policy is confusing as
it provides „catastrophe‟ cover but excludes flood. Further, that storm water
runoff caused water inundation prior to flooding.
5. It should be noted that the Applicant originally made submissions in relation
to Section 35 of the Insurance Contracts Act (1984) but has since withdrawn
same, although the Applicant maintains the FSP failed to provide the
Product Disclosure Statement (PDS).
Su mmary of Applicant’s position
6. The Applicant has enclosed a „Floodwise property report‟ from the local
Council. The document indicates the ground levels range from 7.9-12.3m
AHD. Further, this property is located in an overland flow path and a
waterway corridor.
7. The Applicant relies on a letter dated 23 February 2011 from the Body
Corporate from which the Panel notes the following:
The Body Corporate notes that on 11 January 2011 at 10.42am the
main 1.4m drain was discharging somewhere between 50-75% of its
volume at high velocity.
Determination
Case No: 264018 Determination Page 2 of 9
The heavy rain continued until approximately 5.30pm with the rain
ceasing around 8.30pm. This resulted in an elevation of the normal lake
level.
The cause of water inundation into the villas was contributed to by
runoff from surrounding catchment drains.
It should also be noted that the roadway drains at the corner of Tennant
Street and Horizon Drive had overflowed due to heavy rainfall.
The drains could not cope with the volume of water runoff from heavy
rain causing this runoff water to flow through the residential premises.
8. The Applicant contends that it is the FSP‟s responsibility to provide a PDS to
every insured which includes the owners of the Body Corporate.
9. There is catastrophe cover under the policy of insurance. The definition of
catastrophe only requires it to be deemed a catastrophe by an external
party. The Federal Attorney General Robert McClelland made Emergency
(Queensland and New South Wales Floods) Declaration 2011 No.1 on 13
January 2011. The Applicant conte nds that the definition of „catastrophe‟
which is an inclusion of cover and „flood‟ which is an exclusion fall within the
contra proferentum rule. Accordingly, the FSP should be prohibited from
relying on the flood exclusion.
10. The Applicant submits that the rainfall charts provided by the FSP are not for
his locale. The rainfall gauges at Jindalee and Moggill indicate the heaviest
rainfall in the location of the insured property was on 11 January 2011.
11. The hydrology report relied on by the FSP refers to the peak inundation
rather than addressing the prior flooding event described by the Applicant
and other residents of the Body Corporate. Further, the Applicant disagrees
with the recording of the information purportedly provided by the hydrologist.
The Applicant left prior to the commencement of the inundation and did not
witness the inundation.
12. The peak rainfall in the locale of the property occurred on 11 January 2011
and continued until the evening. This makes it more likely that the water
inundation experienced in the early hours of 12 January 2011 was due to
rainwater run-off. This is particularly in light of the fact the insured property is
situated in an overland flow path for water draining from the surrounding
area into Westlake. The Applicant submits that under common law, this initial
inundation was a separate event to any flood inundation.
13. The Applicant is critical of the FSP‟s extrapolation and interpretation of the
hydrology report. There was no evidence for the FSP to determine there was
only a likelihood of ponding up to 0.6m. The Applicant contends that there
was no finding made at all regarding the amount or timing of the stormwater
inundation. The suggestion that the property was not inundated until 8.00pm
on 12 January 2012 is incorrect as the hydrologist states this was the peak
of inundation in the property. Further, whilst the hydrology report notes
eyewitness evidence it does not consider these statements in the context of
events over 11-12 January 2011. Similarly, the swinging fence whic h directs
Case No: 264018 Determination Page 3 of 9
some water flow is noted by the hydrology report but no findings are made
on this issue.
14. In addition to payment of the claim, the Applicant further seeks the legal
costs of its representative. The Applicant contends that the FSP did not
obtain a hydrology report until after legal intervention and the hydrology
issues were complex and accordingly the Applicant‟s representative should
be entitled to costs. The Applicant relies on common law to support his
position that the legal representative from a Community Legal Service is
entitled to legal costs.
Summary of FSP’s position
15. The FSP relies on its site specific hydrologist‟s report completed by „W‟
dated 15 September 2011 (the report) from which the Panel notes the
following:
The Body Corporate is made up of 48 medium density residential villas
located approximately 500m south of the Brisbane River and adjacent
to Westlake. Westlake is an open water body which drains to the
Brisbane River via a concrete overflow structure. The property is further
considered to be within the lower reaches of the Brisbane River
catchment.
The property has two overland flow paths traversing it which drain
towards Westlake.
The hydrologist met with the property manager and two residents and
was informed:
i. There were heavy downpours leading up to the inundation of the
property.
ii. The property is subject to flash flooding as a result of flows
through the property from the south west corner of the property.
iii. There are a number of fences throughout the property that are
designed to allow for conveyance of overland flow through the
property towards Westlake.
iv. The Applicant noted that there was a large catchment upstream of
his particular property. He also noted that there was meant to be a
swinging fence along the southern boundary of the Body
Corporate to allow conveyance of overland flow from this
catchment; however this fence was not a swinging fence. He
reported that water came up through drains in the driveway
outside his villa, although it wasn‟t raining when the water started
coming up.
v. The high tide in the Brisbane River in the vicinity of the property
occurred at 2.30am on Wednesday 12 January 2011. At that time
the gully between Westlake and the Brisbane River was three
quarters full of water. That water began to overtop the edge of the
pool within the property at 4.30am that morning.
Case No: 264018 Determination Page 4 of 9
The river gauge information indicates the Brisbane River was first
affected by catchment inflows early Sunday 9 January 2011 with
gradual but steady rises in levels until about 12.00pm on Tuesday 11
January 2011. From this time both gauges indicate a steep rise in
levels with an eventual peak of approximately 17.9m around 3.00pm on
Wednesday 12 January 2011 at the Moggill alert gauge and 12.9m at
around 10.30pm on Wednesday 12 January 2011 at the Jindalee
Bridge gauge.
Based on the peak water levels recorded at the Moggill and Jindalee
gauges, the interpolated peak water level in the Brisbane River
adjacent to the property was approximately 13.3m AHD at
approximately 8.00pm on Wednesday 12 January 2011. This
interpolated peak level concurs with the peak inundation mark pointed
out by the Property Manager.
Due to the limited size of the local catchments that drain towards the
property (each less than 1km²) and the low rainfall intensity at the
property in the lead up to inundation, it is unlikely that there was
sufficient local stormwater runoff for this to be a major contributing
factor to the inundation that occurred on the property. The hydrologist
concluded the inundation of the residences was caused by water
escaping the normal confines of the Brisbane River, backing up into
Westlake and ultimately into the property.
16. The FSP has enclosed an assessor‟s report from which the Panel notes the
following:
The unit complex was constructed around a small lake which has an
easement through it with respect of overflow from stormwater drains in
the surrounding residential areas.
The heaviest rainfall occurred on 10-11 January 2011 and stopped on
11 January 2011.
The property inundation of the yard occurred at 2.30am on 12 January
2011. The house, garage and shed inundation occurred at 4.30am on
12 January 2011. The peak inundation is recorded however as at
3.30am 12 January 2011.
17. The FSP relies on letter dated 18 January 2011 from the Body Corporate to
Unit holders. The letter states that to its knowledge, there is no policy
available to Body Corporates within the Brisbane region which responds to
flood.
18. The FSP has enclosed a property assessment questionnaire presumably
completed by the Body Corporate from which the Panel notes the following:
Rainfall was heaviest from 10.00am-1.00pm and 5.30pm-8.30pm on 11
January 2011.
The yard became inundated during the evening of 11 January 2011.
The property was first inundated at 8.00am on 12 January 2011.
The water level peaked at 3.30am on 13 January 2011.
Case No: 264018 Determination Page 5 of 9
The water came from drains surrounding the complex, the lake to the
north and from various directions.
The water was dirty.
19. The FSP relies on an email dated 19 September 2011 from the policy
underwriters. An email dated 24 September 2010 confirms a policy
„Alteration‟. There are then two attachments which the policy manager states
included an electronic PDS.
20. The FSP relies on rainfall observations for a location several suburbs over
from the location of the Ap plicant‟s residence. The rainfall on Monday 10
January 2011 is listed as 61mm and on Tuesday 11 January 2011 as
28.4mm.
21. The FSP contends the emails provided demonstrate that the Body Corporate
arranged insurance pursuant to the Body Corporate and Community Title Act
and received the PDS. Once the insured entity ( the Body Corporate) has
been provided with the PDS, then there is no requirement for each unit
owner to be forwarded a copy of the PDS.
22. The FSP contends that a reasonable person reading the Policy Disclosure
Statement (PDS) would understand flood was not covered. Further, it is clear
from the correspondence that the Body Corporate was aware there was no
flood cover. In respect of the Applicant‟s assertion that ambiguity exists in
respect of „Catastrophe Cover‟, pages 9 to 10 of the policy clearly informs
this represents an „Additional Benefit‟ where a claim has been admitted
under the „ Section 1: Building(s) and Common Contents’ section of the
policy. In light of the circumstances of the incident (to be discussed below)
arising from „Flood‟ which is an excluded event, the additional benefit
afforded under „Catastrophe Cover‟ is not available.
23. The FSP relies on the hydrologist‟s opinion that the inundation arose from
flood rather than local rainfall. F urther, the FSP submits that the witness
evidence provided corroborates the findings of the report. The FSP further
states the Applicant‟s alteration to his version of events does not alter this.
24. Whilst rainfall did occur on 11 January 2011, the Applicant‟ s property was
not inundated until 8.00pm on 12 January 2011. There was essentially a 12
hour period between rain cessation and the inundation. Further, there was
no evidence of prior rainfall inundation and this was why the hydrologist has
made no finding in relation to same.
25. The FSP contends the policy excludes any overflow of water from the lake or
the river. Further, it relies on common law principles to argue that any
inundation arising from a mixture of storm water and flood water discharging
through the storm water drain is deemed flood and therefore excluded.
26. The FSP disputes the Applicant‟s request for legal costs on the basis that
their involvement did not prompt the provision of a hydrologist‟s report.
Further, the issues were not complex but rather simple. The legal
representative advertises free legal advice funded from grants by the
Case No: 264018 Determination Page 6 of 9
Government and Insurance Council Australia and no costs have been
generated by the Applicant.
Issues
27. Whether the FSP is entitled to rely on the PDS and the flood exclusion.
28. Whether the FSP is liable to make payment of the Applicant‟s claim.
29. Whether the FSP is liable for the legal costs of the Applicant.
Reasons for decision
30. There has been an exchange of material between each party and the Panel
is satisfied each party has had an opportunity to reply to the issues raised.
31. The Panel has read each party‟s submissions and materials and will only
refer to the relevant submissions and materials raised.
32. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in insurance industry matters and a
representative with extensive experience in consumer claims.
33. The Panel considers that there are three discrete issues (listed above) which
will be dealt with separately below.
Whether the FSP can rely on the PDS and the flood exclusion
34. There is no allegation from the Body Corporate that it did not receive the
PDS, only that the owners of the units making up the Body Corporate did not
receive the PDS. Further, there is information provided by the FSP that the
Body Corporate did in fact receive the PDS.
35. It is clear from the policy documentation that the Body Corporate is itself the
insured and the entity which obtains insurance on behalf of all unit owners
under the relevant legislation. Accordingly, the production of the PDS to the
insured satisfies the notification requirements under the Insurance Contracts
Act (1984) .
36. Even if the Panel were minded to consider the Body Corporate as a type of
agent for the owners, the provision of the PDS to the Body Corporate would
satisfy the notification requirements under Section 71 of the Insurance
Contracts Act (1984) .
37. The Panel accepts that the FSP provided the PDS to the Body Corporate
and accordingly the FSP can rely on the PDS document.
Case No: 264018 Determination Page 7 of 9
Whether the FSP can rely on the flood exclusion
38. The Panel has carefully considered the Applicant‟s arguments in relation to
ambiguity arising from the PDS in respect of „Catastrophe Cover‟. The FSP
in its IDR response dated 17 October 2011 argues, Catastrophe Cover (CC)
is an additional benefit payable only in the event of an insured loss. That is
the loss claimed, in this matter the building and contents damage, must
respond to the policy and not be subject to any exclusion arising therein. In
the circumstances of this dispute, if the loss is shown to have arisen from
flood, then there is no insured loss. The CC is an additional benefit on top of
the existing benefit where the amount of the loss exceeds the sum insured; it
is not an additional „Insured Event‟ as such. Accordingly, the Panel
determines the FSP has complied with Section 35 of the Act and clearly
informed the Applicant of the flood exclusion.
Proximate Cause of the Loss
39. The loss adjustor attended the property on behalf of the FSP on 19 January
2011. On attending the property, the loss adjustor noted that the property
(yard) was not inundated until 2.30am on 12 January 2011 with water first
entering the lowest level of the property at 4.30am on 12 January 2011.
Ultimately, the property was inundated to an average depth of 1.8m.
40. Despite the FSP‟s allegation that the hydrology report was required as
standard procedure for any claim involving a Strata Complex, it would
appear that no hydrology report was in fact obtained by the FSP until such
time as the Applicant disputed the FSP‟s decision. It was only after this that
the FSP sought to obtain a site specific hydrology report. Nevertheless, that
does not prevent the FSP from relying upon that report.
41. The FSP‟s site specific hydrology report of 15 September 2011, notes that
topographic data for the property shows the elevation of the property varies
significantly with a ground level of approximately RL 10m AHD along the
northern property boundary adjacent to Westlake and a ground level of
approximately RL 14m AHD at the entrance to the risk address off „H‟ Drive.
The ground level at the top of the stairs to the tennis court is approximately
RL 13m AHD. Hence, the peak inundation level reported at the property
(depth plus ground level) was approximately RL 13.4m AHD.
42. The Brisbane River in this region was first affected by catchment inflows
from as early as Sunday 9 January 2011, with a gradual but steady rise in
levels until about 12.00pm on Tuesday 11 January 2011. From this time,
both gauges indicate a steady rise in levels, with an eventual peak of
approximately 17.9m at around 03.00pm on Wednesday 12 January 2011 at
the Moggill Alert gauge and approximately 12.9m a t around 10.30pm on
Wednesday 12 January 2011 at Jindalee river gauge. Based on the peak
water levels reported at the Moggill and Jindalee gauges, the interpolated
peak water level in the Brisbane River adjacent to the property was
approximately 13.3m AHD and would have occurred at approximately
8.00pm on Wednesday 12 January 2011. This interpolated peak level
concurs with the peak inundation mark pointed out by the risk address‟
property manager (that being about 400mm above ground level).
Case No: 264018 Determination Page 8 of 9
43. Due to the limited size of the local catchments that drain towards the
property (each less than 1km 2 ) and the low rainfall intensity at the property in
the lead up to inundation, it is unlikely that there was sufficient local
stormwater runoff for this to be a major contributing factor to the inundation
that occurred on the property.
44. It should be noted the Applicant was not present at his unit at the time of
water inundation; however the property manager indicated to the FSP‟s loss
assessor that inundation to 44 of the 48 units within the complex occurred
from approximately 3.30am on the morning of Wednesday 12 January 2011.
45. Based on the hydrologist‟s site specific report, the Panel is not persuaded
that any initial inundation of the Applicant‟s unit by stormwater runoff
occurred prior to the flood event. To the extent local drains were evidencing
backflow, this, on the balance of probabilities, was floodwater back flowing
through the drains from the Brisbane River. Under Australian common law it
is well established that such backflow flooding falls within the definition of
flood for insurance purposes.
46. On the balance of probabilities, the Panel determines the Applicant‟s unit
was inundated by flood which is excluded under the policy and the FSP was
entitled to decline indemnity.
Whether the FSP is liable for the legal costs of the Applicant
47. The Service‟s Terms of Reference do allow for the awarding of legal costs
under 9.4.
48. The Panel is aware that legislation does allow for pro bono schemes such as
Legal Aid and Community Legal Services (if acting under a Legal Aid Grant)
to seek an award for costs. The case of Desmond Francis Lewis and Telstra
Corporation Limited [1995] AATA 94 is also authority that a Community
Legal Service may seek its costs in limited circumstances. This case
indicated that the legal service in question was able to do so because it
reserved the right to recover costs from the Applicant. There is no evidence
of the agreement between the representative and the Applicant.
49. The Terms of Reference provide that FOS may decide that an FSP
contribute to an Applicant‟s legal or other professional costs but unless
exceptional circumstances apply, FOS will not require the FSP to contribute
more than $3,000 to those costs.
50. Whilst the Applicant‟s representative has argued that they are entitled to
costs, the FSP in part of its argument has sought to argue that as the
representative is a legal service, and has been contribution from the
Insurance Council to Legal Aid in Queensland, that no costs are applicable.
The FSP has also argued that as it is a legal service, then those costs are
free.
Case No: 264018 Determination Page 9 of 9
51. In the operational guidelines, issued to accompany, the Terms of Reference,
it is noted it is not usually necessary for either party to be legally represented
in a dispute before FOS. Where an Applicant chooses to be represented,
they will usually have to cover their own legal fees. This should be made
clear to an Applicant when they engage legal services. However, in some
circumstances, given the complexity of the dispute, the legal issues that are
raised, the complexity of the financial information or the circumstances of the
Applicant, it may be fair that the Applicant obtains legal assistance and fair in
those circumstances that an FSP might contribute to an Applicant‟s costs.
This is particularly so, where as a result of the professional assistance
provided by the legal experts, the Applicant‟s case is proved.
52. There is no doubt that there are complex issues involved in the disputes that
arise from the Queensland Floods. The complexity can vary from dispute to
dispute and in many cases, Applicants do require assistance to understand
the nature of the information being relied upon by a n FSP to refuse a claim.
Often the FSP will provide very complicated and legalistic explanations that
for many people are extremely difficult to understand. In this case, however,
there is a professional body assisting the Applicant in the obtaining of
insurance and in the running of the Body Corporate. A number of the issues
raised in this dispute are quite complex. The Panel does not agree with the
FSP that the issues would appear simple to a person without some
experience in the area. Even the FSP faile d to follow “standard procedures”
and did not obtain a hydrologist report until after the IDR request was made
by the Applicant‟s legal advisors. Nevertheless, the Panel is not of the view
in this case that the issues are of such complexity or that the Applicants
were such that they genuinely required expert assistance. The Panel is
satisfied that the Applicant could have requested an IDR Review and on
reading the relevant policy wording and subsequent information obtained,
would have been in a position to present their case to FOS.There are many
circumstances in which the award of legal costs will be appropriate, in
particular in matters relating to the events following from the Queensland
flood. The Panel acknowledges this, but in this case, having considered all of
the information, is of the view that it is not appropriate to award the
Applicant‟s costs pursuant to 9.4 of the Terms of Reference.
Determination
56. On the balance of the available information, the Panel determines that the
FSP was entitled to rely on the PDS.
57. On the balance of the available information, the Panel determines that the
FSP was entitled to rely on the flood exclusion as provided in the policy.
58. The Panel further determines the FSP is not liable for the legal costs sought
by the Applicant.