Determination 263770

Escape of liquid claim: scope of covered water damage and repair amount for bathroom and ensuite

FirmFinancial Firm (Unknown - Insurer)
Decided2012-09-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$9,859
Non-financial loss—
Amount claimed$35,860
SourceAFCA PDF

Summary

The insureds claimed about $35,860 for water damage to bathroom and ensuite areas after the FSP paid $836.34 for subfloor repairs only. AFCA found leaking waste pipes were the proximate cause, excluded waterproofing and applied an 80% share, ordering $9,859.16 plus interest.

Leaking waste pipes fell within the Escape of Liquid insured event, and AFCA apportioned the repair cost because a lack of waterproofing may have aggravated the damage.

Issues

Subjects and remedies

pay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 263770 Determination Page 1 of 8 Case number: 263770 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - Escape of Liquid 14 September 2012 Background 1. The Applicants held a home building insurance policy with the Financial Services Provider (FSP) from 5 July 2005 to 5 July 2011. 2. On 15 December 2010, the Applicants lodged a claim with the FSP who recorded the following claim description: “INSD ADV THAT HIS BATHROOM AN D ENSUITE HAS WATER DAMAGED DUE TO LEAKAGE FROM TRAP UNDERNEATH THE FLOOR INSD ADV ALOS THAT THE BEDROOM OUTSIDE THE BATHROOM HAS WATER DAMAGE TO THE TIMBER FLOOR DAMAGE -BATHROOM -ENSUITE - BEDROOM”. (sic) 3. The FSP accepted liability only for “the damage ca used by the incorrectly installed or failed waste pipe leaking into the subfloor”. It obtained a repair quote in the amount of $1,036.34 and sent the Applicants a cheque in the amount of $836.34 after deducting the policy excess. Summary of Applicants ’ position 4. The Applicants say that the majority of the water leaks was from the waste outlet. They rely on the report they obtained from M Builder and the reports obtained by the FSP from B Builder and C Builder. 5. They seek $35,860 based on the quote from M Builder. 6. They say that 15 years ago, the male Applicant built his house with his brother-in-law who is a builder and they did everything possible to waterproof the shower base at that time. Determination Case No: 263770 Determination Page 2 of 8 7. They also say that they lodged the claim with the FSP on 15 December 2010 but the first inspection by the FSP’s builder was only done on 11 March 2011. Summary of FSP’s position 8. The FSP relies on the reports from B Builder and C Builder. 9. The FSP relies on the following policy provision contained on page 22 of the Product Disclosure Statement (PDS): “WHAT IS COVERED ...  Escape of liquid from the following:  any water main or fixed pipe, gutter or guttering, fixed tank or drain,  a sink, toilet, bath, basin or waterbed,  a fixed heating or cooling system,  a dishwasher or washing machine,  an aquarium.” 10. The FSP accepts that the damage to the subfloor caused by the failed waste pipe is covered under the insured event of “Escape of Liquid” as it falls under the item “water main or fixed pipe” . 11. It contends that the list of items under the insured event of “ Escape of Liquid ” is an exhaustive list of items covered under “Escape of Liquid”. This list does not include “ shower ” . 12. Further, it says that the insured event of “Escape of Liquid” specifically excludes cover for “Costs incurred in repairing or replacing the item from which the liquid escaped”. Therefore, the FSP is not liable for repairing the “shower, shower base, grout breakdown, failed wat erproofing, shower waste trays, missing sealant, leaking plugs and washers”. 13. It also relies on the following policy exclusions on pages 44 -45 of the PDS: “ EXCLUSIONS APPLICABLE TO YOUR POLICY IN RESPECT OF ALL SECTIONS IN THE POLICY, WE WILL NOT COVER YOU FOR DAMAGE, LOSS OR LIABILITY CAUSED BY, ARISING FROM OR INVOLVING ANY OF THE FOLLOWING: ... X Water entering your home:  as a result of your failure to perform adequate maintenance on your home building, or a structural defect, faulty design or workmanship, ... Case No: 263770 Determination Page 3 of 8 X Wear and tear, lack of maintenance or inherent defect, including gradual deterioration.” Issue 14. Whether the FSP ’s payment of $1,036.34 (less the policy excess) satisfies the FSP’s o bligations under the policy. Reasons for decision 15. Due to the nature of the dispute, the Financial Ombudsman Service (FOS) has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. Thus, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 16. I am satisfied that there had been an exchange of all relevant information between the parties and that each party has had the opportunity to address all issues raised. Applicant’s expert evidence 17. The Applicant submitted an undated report from H Plumbing stating: “Whilst working under the floor structure to upsize the gas line to cater for the pool heater, we noticed the plug and washers on the fibreglass shower bases appear to have been leaking for several years. Due to the amount of time the leak has been there, condensation has formed causing the chipboard flooring to swell up underneath the floor structure and is rotting. Damage is also evident to floor joists as swelling and rotting has also occurred.” 18. The Applicant also submitted a report and quote from Builder M dated 25 March 2012. The report relevantly reads: “Probable Cause A sub floor and interior inspection clearly shows faulty shower bases on which the wastes have not been incorporated or sealed (faulty manufacturing). This has allowed water engress (sic) to the pine board sheet flooring below, causing serious deterioration to the flooring and sub floor members – some shrinking/rotting between 10 and 20 mm. This would be a contributing factor to the grout and tile movement in the shower walls. Both these bathrooms need to be completely stripped and rebuilt.” 19. Builder M quoted repair costs in the amount of $35,860 for the complete stripping and rebuilding of (a) main bathroom/passage; and (b) ensuite in bedroom 1. Case No: 263770 Determination Page 4 of 8 FS P’s expert evidence 20. B Builder inspected the insured property on 11 March 2011 and issued a report dated 14 March 2011. The report reads, in part: “ SCOPE & CAUSATION OF DAMAGE: Our inspection of the ensuite and bathroom of the premises revealed water penetration to the surrounding areas of both shower recess areas has been an ongoing problem over several years as evidenced by the extent of damage. Ensuite: It should be noted that the architrave of the door frame has expanded and distorted due to constant water penetration, and the door jamb displayed significant damage to such an extent that a section has completely rotted. Furthermore, several parquetry flooring sections in the main bedroom doorway, adjacent to the ensuite, have severely rotted. We also observed missing sealant to all internal areas of the shower recess, which intersect with the top lip of the plastic moulded shower base. Bathroom: Similarly, we observed substantial damage to the door-stop, door jamb and architrave of the painted door frame, as evidenced in the attached photographs that clearly exhibit expansion, distortion, and rotting of the materials. In addition, we noted water damage to the laminated kickboard of the vanity unit adjacent to the shower recess. The attached photographs depict evidence of water marks on the tiled flooring, which is indicative that water is escaping the confines of the shower recess due to missing sealant to all internal perimeters of the walls that intersect with the top lip of the plastic moulded shower base. Subfloor: The timber materials in both the ensuite and bathroom shower recess areas of the subfloor have sustained significant damage due to constant water penetration caused predominantly by leakage from defective waste pipe connections. Hence over a period of time, the integrity of the timber materials has been severely compromised. Please refer to photographs displaying black mould and rotted subfloor timbers. COMMENTS: Our enquiries with [male Applicant] clarified that the building was constructed by himself as an Owner/Builder some 14 years ago, and that the wall materials in both the ensuite and bathroom shower recess areas comprised of Villa-board, also that a waterproof membrane had not been applied to the walls and flooring areas prior to tiling of same. SUMMARY: In summary, we can only deduce that the Insured, who is a cabinet maker by t rade and thus having a “trained eye for detailing”, has not taken immediate action in identifying the source of the water leakage when first noticing obvious water damage to the door frames in both the ensuite and bathroom areas, including the damaged parquetry flooring in the main bedroom. Thus the contributing factor identifying the causation of water damage is as follows: - Case No: 263770 Determination Page 5 of 8 1. Missing sealant to interface of internal shower recess screens, bases and tiled walls; 2. No waterproof membrane to ensuite and bathroom walls and floors; and 3. Defective application of shower recess waste outlets in subfloor of ensuite and bathroom. It should be noted that our conclusions as to the causation of water leakage to the insured premises is based on a visual inspection only, and that we have not conducted any exploratory works to support a definitive result.” 21. Builder C inspected the insured property on 21 June 2011. It issued the following report: “ RESULTING DAM AGE Damage has occurred to timber door frames and parquetry flooring where it is swollen and lifted. We also believe there could be substantial damage to the timber sub-floor and sub-structure. However, until excavations are carried out and areas of flooring and tiling are removed, we will not know the full extent of this damage. CAUSE OF DAM AGE Our plumber has attended and carried out various tests to both shower trays in the ensuite and bathroom to ascertain cause of damage. Our plumber believes that the most likely cause to all the damage that we have quoted on is due to leaks from wastes of the two shower trays. Our plumber believes that these wastes have been leaking for a long period of time and caused the majority of the damage that we have quoted on. Our plumber has also reported that the shower recess areas are leaking when in use, due to a lack of adequate waterproof membrane and/or tile and grout breakdown. This lack of waterproof membrane and possible tile and grout breakdown in the shower recess areas, may also have contributed to the water damage we have quoted on. Scope of Works .... CONCLUSION Damage has occurred to timber door frames and parquetry flooring where it is swollen and lifted. In our opinion we believe that the damage stated above is due to leaks from the wastes of the two shower trays, a lack of adequate waterproof membrane and/or tile and grout breakdown. ” 22. Builder C quoted $12,938.52 to repair the (a) main bedroom/ensuite; and (b) second bathroom/passage/wardrobe to rear bedroom. 23. Subsequently, the FSP requested Builder C to quote only on the repair of the subfloor. Builder C issued a quotation on 23 September 2011 in the amount of $1,036.34. Case No: 263770 Determination Page 6 of 8 Analysis/Conclusion 24. I have carefully reviewed the expert reports. 25. Builder B identified three causes of water damage, namely:  missing sealant to interface of internal shower recess screens, bases and tiled walls;  no waterproof membrane to ensuite and bathroom walls and floors; and  defective application of shower recess waste outlets in subfloor of ensuite and bathroom. 26. Builder C has also identified three causes of water damage:  leaks from the wastes of the two shower trays;  lack of adequate waterproof membrane; and/or  tile and grout breakdown. 27. However, it is noted that within Builder C ’s report it is stated that the plumber who actually inspected the insured property and conducted tests was of the belief that:  “ the most likely cause to all the damage that [Builder C] has quoted on is due to leaks from wastes of the two shower trays ” ; and  “ these wastes have been leaking for a long period of time and caused the majority of the damage that [Builder C] has quoted on ” . (underscoring mine) 28. The plumber also reported that due to a lack of adequate waterproof membrane and/or tile and grout breakdown, the shower recess areas are leaking when in use. “ This lack of waterproof membrane and possible tile and grout breakdown in the shower recess areas, may also have contributed to the water damage [Builder C has] quoted on ” . (underscoring mine) 29. It is my view t hat great weight should be given to the plumber’s opinion that the most likely cause of “all the damage” or the “majority of the damage” was the leaking wastes of the two shower trays because the plumber was actually the one who conducted the inspection and tests. 30. The plumber’s opinion is more consistent with Builder M who identified one cause of damage, that is “(w)astes have not been incorporated or sealed (faulty manufacturing)”. According to Builder M, the faulty waste pipes resulted to water ingress to the pine board sheet flooring below, causing serious deterioration to the flooring and sub floor members, and contributing to the grout and tile movement in the shower walls. 31. It is noted that in the FSP’s Internal Dispute Resolution letter date d 8 September 2011 (IDR letter), the FSP wrote that it obtained further information from Builder C and was advised as follows: “I confirm [Builder C] advised: Case No: 263770 Determination Page 7 of 8 The extent of damage beneath the sub-floor, as a result of failed leaking waste pipes, would not be reasonably perceptible until an inspection of the floor beneath would be carried out.... [Builder C] further advised signs of the failed waste pipe may not be visible from floor level or above at the early stages of defect and that penetration of water into a sub-floor is not easily identifiable until investigation in that area occurs for some other reason.” 32. It is further noted that in the same IDR letter, the FSP noted section 46 of the Insurance Contracts Act (1984) which provides that that if a claim is made in respect of a loss that occurred in whole or in part as a result of a defect or imperfection in a thing and the insured was not aware of the defect or a reasonable person in the circumstances could not be expected to have been aware of the defect or imperfection the insurer may not rely on an exclusion clause that refers to the condition of the thing before the contract was entered into. 33. Therefore, it is my opinion that, on the balance of probabilities, the leaking waste pipes were the proximate cause of the water damage. There is no dispute that leaking waste pipes fall under the insured event of “Escape of Liquid”. 34. I accept that, on the balance of probabilities, the lack of waterproof membrane and/or grout and tile breakdown may have aggravated the water damage, and I therefore make some allowance for it. 35. I note that the FSP’s representative did not inspect the insured property until after almost three months from lodging of the claim. It is likely that the water damage worsened during the time the Applicants were waiting for the FSP’s inspection/repair of the property. 36. I accept B uilder C’s quote dated 29 June 2011 in the amount of $12,938.52. 37. This quote includes a total of $614.56 for waterproofing of the shower recess areas. The FSP should not be held liable for the waterproofing. Thus, deducting $614.56, Builder C’s quote would be $12,323.96. 38. In my view, it is fair and reasonable that the FSP bear 80% of $12,323.96. Determination 39. On the basis of the available information and the above reasons, I determine that the FSP must indemnify the Applicants $9,859.16. 40. In addition, the FSP must pay interest at the rate of 6.75% from 13 July 2011 to the date of the settlement of this Determination. Case No: 263770 Determination Page 8 of 8 41. The FSP must make payment to the Applicant within 30 days from notice that the Applicant has accepted this Determination.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.