Determination 263524

Alleged loss from construction delay caused by loan drawdown conditions and release of funds

FirmFinancial Firm (Unknown - Credit)
Decided2013-12-12
ProductCredit · Business lending
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants said the FSP's release of loan funds without building approval and its $20,000 cash requirement delayed construction of their day spa, causing lost profit. AFCA found the delay was caused by permits and the applicants' own preparatory works, so the FSP was not liable for compensation.

Causation was not established because responsibility for building approval rested with the builder and the delays were caused by council approvals and the applicants' preparatory works.

Issues

Subjects and remedies

business interruptionsmall businessno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Case No: 263524 Determination Page 1 of 6 Case number: 263524 Credit - Business Finance - Business Loans - Disclosure - Incorrect product/service information 12 December 2013 Summary Description This dispute is about whether the actions of the FSP caused the delay in the construction of a building for a business the Applicants intended to open, resulting in a loss of profit and other losses. Basis of Determination The FSP’s actions were not the cause of the losses claimed by the Applicants. The delay in construction was caused by the delay in obtaining the appropriate permits, responsibility for which rested with the Applicants or their builder, and for the delay in completing certain works by the Applicants. The builder was not required to commence work until those works had been completed Determination As the losses claimed were not caused by the FSP no compensation is payable. Background 1. In 2009, the Applicants refinanced their loan with the FSP and borrowed additional funds in order to build a day spa facility. Construction was delayed and the Applicants say that the delay was caused by the FSP in two ways. 2. First, the FSP released the first drawdown to the builder without obtaining a copy of the building approval. It was a pre-condition of the loan that the Applicants obtained a building approval certificate. It turns out that construction commenced without building approval. 3. The second way that the Applicants say the FSP caused a delay is that, they say the FSP told them on a number of occasions that they needed to have Determination Case No: 263524 Determination Page 2 of 6 $20,000 in an account with the FSP before the FSP would allow the second (and any subsequent) drawdown from the loan. Issues 4. Did the release of the first payment by the FSP without a building approval certificate cause the Applicants’ loss? 5. Did the requirement that the Applicants have $20,000 in a bank account prior to the release of further funds cause the Applicants’ loss? Reasons for decision The release of the first payment without building approval 6. The Applicants say that if the FSP had exercised due care and skill, it should not have released the first payment without obtaining the certificate. If it had demanded the certificate it would have become obvious to the Applicants that they did not have building approval and would therefore have taken steps to obtain that approval earlier. 7. In essence, what the Applicants are saying is “but for” the FSP’s failure to insist on the provision of a building approval they would not be in the position they find themselves in. 8. In sorting out the cause of a loss, it is necessary to go beyond the simple application of the ‘but for’ test. We must also apply common sense to the cause of loss. In this case, primary responsibility for the need to obtain building approval rested with the Applicants and their builder, not the FSP. Item 14 of the contract entered into between the Applicants and their builder provides as follows; Item 14 BUILDING APPROVAL (clause 4) Party responsible for obtaining building approval  Builder  Owner Party responsible for obtaining development approval (if applicable)  Builder  Owner 9. Had the FSP insisted on the approval being provided before releasing the funds to the builder then the Applicants would have been alerted about the need to get approval. However, it did not, in my view, cause the failure to obtain building approval and the subsequent delays that followed. Rather it was the builder’s failure to obtain the approval in accordance with the building contract. In any event, at the time the first payment was released, it was to pay the deposit to the builder. It could reasonably have been anticipated that having received the deposit, the builder would then take steps to obtain the necessary certificate. Case No: 263524 Determination Page 3 of 6 10. In my view, therefore, the FSP’s failure to not insi st on the building approval when it agreed to the Applicant ’ s request to make the first payment due to the builder under the contract, did not cause the losses the Applicants incurred in not having the building approval before construction commenced. The requirement to have $20,000 in an account 11. The second way that the Applicants say the FSP caused a delay is that, they say the FSP told them on a number of occasions that they needed to have $20,000 in an account with the FSP before the FSP would allow the second (and any subsequent) drawdown from the loan. 12. The loan provided by the FSP was insufficient to meet the price to be paid to the builder. In fact, it was $20,000 less. It was a condition of the loan that: “construction funding to be drawn down progressively on a cost to complete basis ie undrawn loan funds remain sufficient to cover building contract price” 13. The Applicants say that if the funds were released for the Base Stage and subsequent completion stages directly after the initial deposit, they would have completed building by January 2010 and not January 2012 as was the case. 14. Under the building contract, the Applicants were required to carry out certain works, including the laying of a concrete slab, before the builder would commence construction. 15. Under the loan contract, the FSP would pay to the builder the relevant amount for the completion of each stage of the construction. That is, the loan could be drawn down to pay for the works the builder had completed. In order to complete a stage of the works, the builder had to start building and this would not happen until the Applicants had carried out their part of the works. 16. The loan contract was signed on 2 October 2009. On 9 November 2009 the Applicants telephoned the FSP. The Applicants have provided a diary note dated 9 November 2009 which contains the following record: “Spoke to [FSP] about releasing loans as they are holding so much collateral and that interest repayments would amount to $20,000 requirement being held in the account. Would not budge on this requirement” 17. The FSP disagrees that it said it required money to be held in the account. The FSP has a number of file notes where the requirement for the Applicants to fund the $20,000 is discussed. On balance, it is my view that it is more likely than not that the FSP did lead the Applicants to believe they needed to have $20,000 in an account. 18. In particular, the FSP’s file note of 3 February 2011 indicated that the arrangement did require the $20,000 in the account. This note says: Case No: 263524 Determination Page 4 of 6 “[Applicant] phone today and advised they have the $20,000 previously requested now available to facilitate further loan draw down. She indicated Bank had been “holding back” on release of loan funds. She had been talking to friends who advised her the Bank could not hold back loan funds given funds released for contract etc I reminded [the Applicant] that this was NOT the case and Bank approval clearly stipulated that the loan would only be drawn down on the basis of a costs to complete contract” 19. In my view, this note confirms that at best the Applicant and the FSP were at cross purposes as to whether the $20,000 needed to be in the account. It is more likely than not that the FSP did lead the Applicants to believe the funds needed to be in the account. However, in my view, this was not the cause of the loss because: The Applicants knew (or believed) that this was a requirement before they entered the loan; The FSP was not obliged to suggest or agree to any change to this requirement: and The requirement was not the cause of the delays to construction 20. The FSP’s notes dated 15 June 2009, (before the loan contract was signed), contains the following entry: “Customers are able to contribute minimum $20k cash to reduce borrowings” 21. It is my view that the Applicants were of the view that they needed $20,000 in a bank account before they signed the loan contracts. They would therefore have known that they would have had to fund not only the $20,000 but also the preparatory works before being able to commence construction. 22. The Applicants’ diary notes of 1 and 23 April 2010 record their further contact with the FSP to change the requirement as it was causing financial stress. As I said, the requirement was known to the Applicants before they signed the loan contracts. The financial stress was, therefore, caused by events other than the requirement to have $20,000 in the account. 23. The Applicants have said in their letter to FOS of 29 January 2013: “After the Building Contract price had been finalised, we negotiated a $20,000 reduction in the contract price agreeing to complete part of the building works. Therefore $20,000 was not needed by the builder...[The FSP] was aware of this and waived the requirement of $20,000 cash being maintained in an account for the release of the first drawdown but insisted on it for the release of the second drawdown.” 24. Later, in the same letter, the Applicants say: Case No: 263524 Determination Page 5 of 6 “In September 2011, after we contacted FOS, we paid approximately $9,000 to the Builder and $11,000 credit was given to us for works we had performed in an attempt to resolve this cash requirement. This alternative....could have been explored or suggested earlier by [the FSP] so that building works could commence and finish earlier and then in turn we could start trading an earning income earlier.” 25. Perhaps the alternatives could have been explored earlier, but there is nothing in the Applicants ’ or the FSP’s notes to suggest that it was raised for consideration. In my view, it was not the responsibility of the FSP to suggest alternatives. Rather it was for the Applicants to make the suggestion to the FSP and seek a response. This does not appear to have happened. 26. In any event, the arrangement said to be made with the builder in 2009 was verbal and the builder would have needed to confirm the arrangement in writing before the FSP could be satisfied that the Applicants had adequately covered the cost to complete requirement. Finally, I note that while there may have been a verbal agreement in 2009, it was not implemented until September 2011 when the Applicants paid the $9,000 and received the $11,000 credit. 27. Even if I were to accept that the requirement was in some way unreasonable, I am not satisfied that it caused the construction to be delayed. Th e FSPs’ notes suggest that the delay was caused by other factors. 28. A note made on 1 April 2010 records: “[The Builder] highlighted that his contract was limited to building only and there were considerable external works which require completion / contribution by [the Applicants]. This has previously been acknowledged”. and “For the record customers have indicated that a number of site works have commenced and the following items will still need to be covered from their capital $12,000 Bio Cycle Sewerage Treatment Plant $12,000 Rainwater Take $15,000 Works to Driveway and car park $10,000 Landscaping Works $ 5,000 Concreting Labour $54,000 plus actual concrete costs They propose to complete further meeting with [the Builder] to confirm further site works to be completed prior to building commencing”. 29. The works that needed to be carried out prior to construction were known at the time the loan was entered into. The Applicants needed to fund these works and have $20,000 set aside. It is my view that it was not the $20,000 requirement that delayed construction. Rather the delays were caused by the delays in obtaining council approvals in early 2010 and the ability to fund and complete the preparatory works. Case No: 263524 Determination Page 6 of 6 30. It should be understood that the FSP had no obligation to release further funds until the builder had started construction and completed the various stages. This could not happen until the Applicants had completed their preparatory works, such as the concrete slab. 31. The Applicants have said that the FSP failed to assist them in their financial difficulties at the time by not releasing them from their obligation to fund the $20,000 and therefore breached Clause 25.2 of the Code of Banking Practice. 32. The purpose of Clause 25.2 is to allow customers and subscribing banks to come to some arrangement to assist in repaying the loan where the customer is having difficulties in making the payments. It does not require an FSP to vary a pre-existing loan condition to provide more funds to the customer. 33. For the reasons stated above, it is my view that the FSP was not the cause of the delays in construction. It follows that the FSP does not have to pay any compensation to the Applicants. An increase in the interest rate 34. In November 2013, the Applicants wrote to FOS to say the FSP had increased their interest rate by 2.5% because the loan was in arrears. I understand that the arrears have been paid. 35. Subsequently, the FSP wrote to the Applicants reversing its decision to increase the interest rate and saying that a refund would be made in the next statement cycle. 36. As this issue has been satisfactorily resolved and an appropriate refund has been made, I do not need to consider this aspect any further. Determination 37. On the basis of the available information I determine that the FSP did not cause the delay in the construction of the building. It follows that the FSP is not liable to pay compensation to the Applicants.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.