Alleged loss from construction delay caused by loan drawdown conditions and release of funds
Text of the determination
Case No: 263524 Determination Page 1 of 6
Case number: 263524
Credit - Business Finance - Business Loans - Disclosure - Incorrect
product/service information
12 December 2013
Summary
Description
This dispute is about whether the actions of the FSP caused the delay in the
construction of a building for a business the Applicants intended to open, resulting in
a loss of profit and other losses.
Basis of Determination
The FSP’s actions were not the cause of the losses claimed by the Applicants. The
delay in construction was caused by the delay in obtaining the appropriate permits,
responsibility for which rested with the Applicants or their builder, and for the delay in
completing certain works by the Applicants. The builder was not required to
commence work until those works had been completed
Determination
As the losses claimed were not caused by the FSP no compensation is payable.
Background
1. In 2009, the Applicants refinanced their loan with the FSP and borrowed
additional funds in order to build a day spa facility. Construction was delayed
and the Applicants say that the delay was caused by the FSP in two ways.
2. First, the FSP released the first drawdown to the builder without obtaining a
copy of the building approval. It was a pre-condition of the loan that the
Applicants obtained a building approval certificate. It turns out that
construction commenced without building approval.
3. The second way that the Applicants say the FSP caused a delay is that, they
say the FSP told them on a number of occasions that they needed to have
Determination
Case No: 263524 Determination Page 2 of 6
$20,000 in an account with the FSP before the FSP would allow the second
(and any subsequent) drawdown from the loan.
Issues
4. Did the release of the first payment by the FSP without a building approval
certificate cause the Applicants’ loss?
5. Did the requirement that the Applicants have $20,000 in a bank account prior
to the release of further funds cause the Applicants’ loss?
Reasons for decision
The release of the first payment without building approval
6. The Applicants say that if the FSP had exercised due care and skill, it should
not have released the first payment without obtaining the certificate. If it had
demanded the certificate it would have become obvious to the Applicants
that they did not have building approval and would therefore have taken
steps to obtain that approval earlier.
7. In essence, what the Applicants are saying is “but for” the FSP’s failure to
insist on the provision of a building approval they would not be in the position
they find themselves in.
8. In sorting out the cause of a loss, it is necessary to go beyond the simple
application of the ‘but for’ test. We must also apply common sense to the
cause of loss. In this case, primary responsibility for the need to obtain
building approval rested with the Applicants and their builder, not the FSP.
Item 14 of the contract entered into between the Applicants and their builder
provides as follows;
Item 14 BUILDING APPROVAL (clause 4)
Party responsible for obtaining building approval
Builder
Owner
Party responsible for obtaining development approval
(if applicable)
Builder
Owner
9. Had the FSP insisted on the approval being provided before releasing the
funds to the builder then the Applicants would have been alerted about the
need to get approval. However, it did not, in my view, cause the failure to
obtain building approval and the subsequent delays that followed. Rather it
was the builder’s failure to obtain the approval in accordance with the
building contract. In any event, at the time the first payment was released, it
was to pay the deposit to the builder. It could reasonably have been
anticipated that having received the deposit, the builder would then take
steps to obtain the necessary certificate.
Case No: 263524 Determination Page 3 of 6
10. In my view, therefore, the FSP’s failure to not insi st on the building approval
when it agreed to the Applicant ’ s request to make the first payment due to
the builder under the contract, did not cause the losses the Applicants
incurred in not having the building approval before construction commenced.
The requirement to have $20,000 in an account
11. The second way that the Applicants say the FSP caused a delay is that, they
say the FSP told them on a number of occasions that they needed to have
$20,000 in an account with the FSP before the FSP would allow the second
(and any subsequent) drawdown from the loan.
12. The loan provided by the FSP was insufficient to meet the price to be paid to
the builder. In fact, it was $20,000 less. It was a condition of the loan that:
“construction funding to be drawn down progressively on a cost to complete
basis ie undrawn loan funds remain sufficient to cover building contract price”
13. The Applicants say that if the funds were released for the Base Stage and
subsequent completion stages directly after the initial deposit, they would
have completed building by January 2010 and not January 2012 as was the
case.
14. Under the building contract, the Applicants were required to carry out certain
works, including the laying of a concrete slab, before the builder would
commence construction.
15. Under the loan contract, the FSP would pay to the builder the relevant
amount for the completion of each stage of the construction. That is, the
loan could be drawn down to pay for the works the builder had completed.
In order to complete a stage of the works, the builder had to start building
and this would not happen until the Applicants had carried out their part of
the works.
16. The loan contract was signed on 2 October 2009. On 9 November 2009 the
Applicants telephoned the FSP. The Applicants have provided a diary note
dated 9 November 2009 which contains the following record:
“Spoke to [FSP] about releasing loans as they are holding so much collateral
and
that interest repayments would amount to $20,000 requirement being held in
the account.
Would not budge on this requirement”
17. The FSP disagrees that it said it required money to be held in the account.
The FSP has a number of file notes where the requirement for the Applicants
to fund the $20,000 is discussed. On balance, it is my view that it is more
likely than not that the FSP did lead the Applicants to believe they needed to
have $20,000 in an account.
18. In particular, the FSP’s file note of 3 February 2011 indicated that the
arrangement did require the $20,000 in the account. This note says:
Case No: 263524 Determination Page 4 of 6
“[Applicant] phone today and advised they have the $20,000 previously
requested now available to facilitate further loan draw down.
She indicated Bank had been “holding back” on release of loan funds. She
had been talking to friends who advised her the Bank could not hold back
loan funds given funds released for contract etc
I reminded [the Applicant] that this was NOT the case and Bank approval
clearly stipulated that the loan would only be drawn down on the basis of a
costs to complete contract”
19. In my view, this note confirms that at best the Applicant and the FSP were at
cross purposes as to whether the $20,000 needed to be in the account. It is
more likely than not that the FSP did lead the Applicants to believe the funds
needed to be in the account. However, in my view, this was not the cause of
the loss because:
The Applicants knew (or believed) that this was a requirement before
they entered the loan;
The FSP was not obliged to suggest or agree to any change to this
requirement: and
The requirement was not the cause of the delays to construction
20. The FSP’s notes dated 15 June 2009, (before the loan contract was signed),
contains the following entry:
“Customers are able to contribute minimum $20k cash to reduce borrowings”
21. It is my view that the Applicants were of the view that they needed $20,000
in a bank account before they signed the loan contracts. They would
therefore have known that they would have had to fund not only the $20,000
but also the preparatory works before being able to commence construction.
22. The Applicants’ diary notes of 1 and 23 April 2010 record their further
contact with the FSP to change the requirement as it was causing financial
stress. As I said, the requirement was known to the Applicants before they
signed the loan contracts. The financial stress was, therefore, caused by
events other than the requirement to have $20,000 in the account.
23. The Applicants have said in their letter to FOS of 29 January 2013:
“After the Building Contract price had been finalised, we negotiated a $20,000
reduction in the contract price agreeing to complete part of the building works.
Therefore $20,000 was not needed by the builder...[The FSP] was aware of
this and waived the requirement of $20,000 cash being maintained in an
account for the release of the first drawdown but insisted on it for the release
of the second drawdown.”
24. Later, in the same letter, the Applicants say:
Case No: 263524 Determination Page 5 of 6
“In September 2011, after we contacted FOS, we paid approximately $9,000
to the Builder and $11,000 credit was given to us for works we had performed
in an attempt to resolve this cash requirement. This alternative....could have
been explored or suggested earlier by [the FSP] so that building works could
commence and finish earlier and then in turn we could start trading an
earning income earlier.”
25. Perhaps the alternatives could have been explored earlier, but there is
nothing in the Applicants ’ or the FSP’s notes to suggest that it was raised for
consideration. In my view, it was not the responsibility of the FSP to suggest
alternatives. Rather it was for the Applicants to make the suggestion to the
FSP and seek a response. This does not appear to have happened.
26. In any event, the arrangement said to be made with the builder in 2009 was
verbal and the builder would have needed to confirm the arrangement in
writing before the FSP could be satisfied that the Applicants had adequately
covered the cost to complete requirement. Finally, I note that while there
may have been a verbal agreement in 2009, it was not implemented until
September 2011 when the Applicants paid the $9,000 and received the
$11,000 credit.
27. Even if I were to accept that the requirement was in some way
unreasonable, I am not satisfied that it caused the construction to be
delayed. Th e FSPs’ notes suggest that the delay was caused by other
factors.
28. A note made on 1 April 2010 records:
“[The Builder] highlighted that his contract was limited to building only and there
were considerable external works which require completion / contribution by [the
Applicants]. This has previously been acknowledged”.
and
“For the record customers have indicated that a number of site works have
commenced and the following items will still need to be covered from their capital
$12,000 Bio Cycle Sewerage Treatment Plant
$12,000 Rainwater Take
$15,000 Works to Driveway and car park
$10,000 Landscaping Works
$ 5,000 Concreting Labour
$54,000 plus actual concrete costs
They propose to complete further meeting with [the Builder] to confirm further site
works to be completed prior to building commencing”.
29. The works that needed to be carried out prior to construction were known at
the time the loan was entered into. The Applicants needed to fund these
works and have $20,000 set aside. It is my view that it was not the $20,000
requirement that delayed construction. Rather the delays were caused by
the delays in obtaining council approvals in early 2010 and the ability to fund
and complete the preparatory works.
Case No: 263524 Determination Page 6 of 6
30. It should be understood that the FSP had no obligation to release further
funds until the builder had started construction and completed the various
stages. This could not happen until the Applicants had completed their
preparatory works, such as the concrete slab.
31. The Applicants have said that the FSP failed to assist them in their financial
difficulties at the time by not releasing them from their obligation to fund the
$20,000 and therefore breached Clause 25.2 of the Code of Banking
Practice.
32. The purpose of Clause 25.2 is to allow customers and subscribing banks to
come to some arrangement to assist in repaying the loan where the
customer is having difficulties in making the payments. It does not require an
FSP to vary a pre-existing loan condition to provide more funds to the
customer.
33. For the reasons stated above, it is my view that the FSP was not the cause
of the delays in construction. It follows that the FSP does not have to pay
any compensation to the Applicants.
An increase in the interest rate
34. In November 2013, the Applicants wrote to FOS to say the FSP had
increased their interest rate by 2.5% because the loan was in arrears. I
understand that the arrears have been paid.
35. Subsequently, the FSP wrote to the Applicants reversing its decision to
increase the interest rate and saying that a refund would be made in the next
statement cycle.
36. As this issue has been satisfactorily resolved and an appropriate refund has
been made, I do not need to consider this aspect any further.
Determination
37. On the basis of the available information I determine that the FSP did not
cause the delay in the construction of the building. It follows that the FSP is
not liable to pay compensation to the Applicants.