Cash settlement offered instead of authorised repairs for prime mover cabin

FirmFinancial Firm (Unknown - Insurer)
Decided2012-08-16
ProductGeneral Insurance · Motor
OutcomeFor the complainant
Amount awarded$1,263
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The applicant's prime mover was damaged in an accident and the FSP offered a cash settlement based on a quote for a cabin part not available for at least 8 weeks, while the applicant wanted repairs by an alternative repairer within weeks. AFCA ordered the FSP to authorise repairs by the applicant's preferred method, refund $1,262.50 towing costs, and pay $2,000 for non-financial loss.

Under the policy's settlement terms the insurer could not rely on a quotation for a part that was not available, and the claim must be settled on a real-time basis, with non-financial loss awarded under the FOS Terms of Reference for inconvenience caused.

Issues

Subjects and remedies

motor vehicle collisionsmall businesspay compensationpay non financial lossreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 263257 Determination Page 1 of 8 Case number: 263257 General Insurance - Small Business/Farm Insurance - Commercial Vehicles - FSP Decision - Claim Amount 23 July 2012 Background 1. The Applicant held a commercial motor vehicle policy with the Financial Services Provider (FSP) from 29 October 2010 which included cover for a 2004 Isuzu FVL 1400 Prime Mover (the insured vehicle) for market value up to the sum insured of $110,000, subject to a 1% excess, plus excesses associated with age and experience of drivers. 2. On 25 October 2011 the insured vehicle was involved in a traffic accident for which the Applicant lodged a completed claim form on 28 October 2011. An assessment of the damage was arranged by the FSP and estimates were provided by two repairers. 3. On 7 November 2011 the FSP advised the Applicant it could authorise repairs to the vehicle or provide a cash settlement based on the most cost effective quotation provided. The offer for a cash settlement was made as the most cost effective method of settlement and included the supply of a part which was not available in Australia and had an estimated wait time of 3 months. 4. The part concerned is a fully trimmed replacement cabin. The alternative was to use a bare shell cabin and fit it with all necessary components, to reinstate the cabin portion of the vehicle to its pre-loss condition, or as close as possible to its pre-loss condition, considering some second hand parts could and would be used. 5. The offer of settlement was rejected by the Applicant as was the proposed repair option due to there being an extended wait for the required part. The Applicant requested repairs be authorised to the alternative repairer which, whilst less cost effective, would see the insured vehicle repaired within approximately two weeks. 6. The FSP has not changed its position on repairs or cash settlement options originally provided to the Applicant. Determination Case No: 263257 Determination Page 2 of 8 Summary of Applicant’s position 7. The Applicant says he has contacted a local Isuzu dealer to discuss the proposed wait time for the required part to effect repairs as quoted by repairer W. 8. The Applicant says he has been informed there is an estimated wait time of between 6 to 12 months for the part. This is due to the production plant being located in Japan and the production plant being non-operational as a result of the earthquake which struck Japan on 11 March 2011. 9. The Applicant says the alternative quotation provided by repairer R, i ncluded an alternative repair option, which could be completed, as advised by R to the Applicant, within two weeks. 10. The Applicant acknowledges he does not have any cover for “down time” as advised by the FSP, however says the FSP is placing too much importance on this issue and not the issue at hand, being the FSP‟s unreasonable expectation for the Applicant to wait on a part where there is no certainty of delivery. 11. The Applicant says during discussions with the FSP‟s representative, L, he queried what would happen in the event it took two years for the part to arrive. The Applicant says L informed him it would become an issue between the Applicant and W as the FSP would forward its payment to W and close the case. 12. On this basis, the Applicant says the FSP is acting in its own interest and against the principles of utmost good faith. 13. In addition, the Applicant has raised concerns over any unseen damage which may come to light during the course of repairs and is concerned these additional damages may not have been considered by the FSP when offering the cash settlement. 14. The Applicant seeks to have repairs authorised to the insured vehicle to the alternative repairer, R, as R has indicated repairs could be completed within two to four weeks. Summary of FSP’s position 15. The FSP advises of the two quotations provided by repairers W and R , W‟s was the most cost effective and correct. It says W ‟s quote would reinstate the insured vehicle to a condition equal to its pre- loss condition. It says J‟s quotation would not provide the best method of repair as it would involve using second hand parts and the FSP believes its proposal would provide the best end result for the Applicant. Case No: 263257 Determination Page 3 of 8 16. The FSP became aware of the delays in obtaining the part used in W‟s quote on receipt of W‟s quote, which indicated there were nil parts in Australia and Japan and there was an approximate wait of “8 weeks+”. 17. On receipt of R ‟s quote it was noted R quoted to supply a bare shell and fit the part with second hand parts to reinstate the vehicle. The quotation to adopt this method of settlement was over $20,000 more expensive. 18. The FSP relies on the following policy provisions of its Product Disclosure Statement (PDS): “ Section 1 – Loss, Damage or Theft Your Cover Subject to the other terms, conditions and exclusions of Your Policy, We will pay for loss of (including theft) or damage to Your Vehicle caused by an Accident which occurs during the Period of Insurance. Basis of Claim Settlement A. We will at Our option: (a) repair, reinstate or replace Your Vehicle to a condition substantially the same as, but not better than, its condition immediately before the Accident; or (b) pay the amount of the loss, damage or theft to You, ...” (Page 10) “ Section 12 – Expediting Expenses We will pay the reasonable costs incurred, with Our prior permission, for express cartage rates and extra payment for overtime, night, Sunday or holiday pay incurred in connection with a claim on Your Vehicle up to the amount set out on the Schedule for “Policy Section 12: Expediting Expe nses”.” (Page 15) “ Exclusions We will not pay any amount: ... 5. Loss of Use, Wear and Tear etc For Your loss of use, depreciation, wear and tear, rust or corrosion, mechanical or electrical breakdowns, failures, malfunction or breakages.” (Page 21) Issue 19. Whether the FSP should have authorised repairs to the alternative repairer using the alternative repair method. Case No: 263257 Determination Page 4 of 8 Reasons for Decision 20. I am satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. 21. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operation Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceed directly to Determination. 22. There is no dispute over the accident circumstances or the acceptance of the claim. The dispute relates solely to the repair/settlement method being offered by the FSP. 23. The FSP has placed some importance on the Applicant not having any “down time” cover, saying this was an additional benefit offered to the Applicant by his broker at the time of policy inception. From documentation provided by the FSP and Applicant, I have been unable to see where this cover was offered and/or rejected by the Applicant. However, cover was arranged through a broker, M. This might be a matter for discussion betweent the Applicant and M. 24. I have reviewed both quotations and it would appear both W and J provided costs for the bare shell and these costs are the same on both quotations. I am unaware as to why W provided a quotation to provide a part that was not available in Australia or Japan and had a wait of at least 8+ weeks. 25. I acknowledge that the method of repair quoted by W is the most cost effective. However I do not believe it is the most realistic given the circumstances relating to the waiting period for the part. I note, with surprise, that the FSP has not supplied any evidence as to any attempts to access a fully trimmed replacement cabin anywhere else in Australia. 26. In addition to this, I am of the opinion the FSP has not given appropriate consideration to the commercial impact the waiting period will have on the Applicant. 27. The FSP in an email communication with its Assessor, says: “As per the original appointment, once you are satisfied that either of the repairers are agreeing to the most economic method of repair (within a reasonable time frame of course), they can be authorized.” (sic) 28. It appears from this statement and the subsequent actions of the FSP in offering for repairs to be authorised to a repairer who could not source a part for at least 8+ weeks, the FSP believes the 8+ week wait is a “reasonable” time frame. 29. In addition to this, the FSP made an o ffer of $5,000 under „Expediting Expenses‟ to the Applicant, however on reading the policy wording for this section of cover, I am unable to determine why this amount was offered. Case No: 263257 Determination Page 5 of 8 30. The FSP has subsequently advised this $5,000 was offered as a good will or ex-gratia payment to the Applicant. 31. It should be noted from the FSP‟s Notice of Response (NOR), it had made further enquiries on 4 November 2011 with Isuzu which resulted in it being informed the part may not be available until March 2012 as at that time (November 2011). This realises a wait period of four months. 32. Enquiries made with Isuzu by the Applicant resulted in him being informed no expected delivery date could be given as production in Japan had not started. He says he was told by Isuzu it could be up to 6 or 12 months before the part could be supplied. Repairer R indicated the bare shell could be sourced immediately. 33. A n email sent to the Applicant‟s current broker, LN, on 11 November 2011 by the FSP, in response to the Applicant querying if the FSP felt it was reasonable to authorise repairs to a repairer when a quoted part is not available, says: “In response to the insured‟s question, it is based on the incorrect contention that parts are not available. Parts are available, it is only a question of the length of time it will take for delivery of the parts. Our policy section 12 covers expediting expenses up to a sub limit of $5,000, which we have included in our cash settlement offer to the Insured, to assist in getting the required part as soon as possible.” 34. I disagree with the FSP‟s contention above. The FSP appears to have based its decision on the contention that the part was/is available. At the time the quotation was prepared in November 2011, the part concerned was not available in Australia or Japan and it was not in production and was not expected to start production until sometime in November 2011. It is my opinion the part was not available to effect the repairs in November 2011 when the FSP made their offer of settlement to the Applicant. 35. The Applicant, in his further submissions to FOS, has indicated Isuzu have informed him the relevant part is still not available in Australia. This is relevant to advice he received around November 2011 that Isuzu had four of these parts on back order and, according to the Applicant, these have still not arrived in Australia, as at June 2012. 36. Of further interest, is the FSP‟s Internal Disputes Resolution (IDR) response to the Applicant dated 16 November 2011. In the IDR letter, the FSP has failed to acknowledge the real crux of the Applicant‟s dispute. It has not addressed the wait period for the part, rather it has commented that the accident was an “at fault” accident, there is no avenue fo r recovery of costs and the Applicant had decided not to include the optional extension for “down time”. 37. Leaving aside the argument as to good faith, I am of the view that the five options available to the FSP as set out in paragraph 18 above must be read as requiring reasonable expedition. Any quotation leading to an offer of a cash settlement must be a “real - time” quotation based upon parts now Case No: 263257 Determination Page 6 of 8 available. What if, for example, the ultimate cost of a new fully trimmed cabin, once supplied from Japan in, say, September 2012 was $10,000 higher than the estimated cost in July 2011? Should the Applicant bear the loss in such circumstances? I think not but it does demonstrate the hazards in relying upon quotations for items not currently available. 38. I therefore conclude that the FSP is not entitled to rely upon the quotation from W. The obligation of utmost good faith 39. The Applicant‟s representatives have submitted that the conduct of the FSP evidences a breach of its obligation of good faith towards the Applicant. 40. Gleeson CJ and Crennan J in CGU Insurance Ltd v AMP Financial Planning Pty Ltd [2007], HCA 36, said: “We accept the wider view of the requirement of utmost good faith adopted by the majority in the Full Court, in preference to the view that absence of good faith is limited to dishonesty. In particular, we accept that utmost good faith may require an insurer to act with due regard to the legitimate interests of an insured, as well as to its own interests. The classic example of an insured‟s obligation of utmost good faith is a requirement of full disclosure to an insurer, that is to say, a requirement to pay regard to the legitimate interests of the insurer. Conversely, an insurer‟s statutory obligation to act with utmost good faith may require an insurer to act, consistently with commercial standards of decency and fairness, with due regard to the interests of the insured. Such an obligation may well affect the conduct of an insurer in making a timely response to a claim for indemnity.” 41. I consider that the dicta from the decision referred to above, does accurately reflect the law to be followed in a matter such as this. 42. I have given careful consideration to the Applicant‟s submission that the conduct of the FSP should be categorised as a breach of its obligation to demonstrate good faith towards the Applicant. 43. After long consideration, I have decided not to so categorise the FSP‟s handling of the matter. The FSP has attempted to rely upon policy provisions and I consider that in so doing it has been incorrect in its interpretation of those provisions. However ultimately I have decided that its conduct should not be categorised as evidencing a breach of the good faith obligation. 44. I have given consideration to another aspect of the matter which concerns me. FOS Terms of Reference “ 9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute. Case No: 263257 Determination Page 7 of 8 b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non- financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind has occurred; or (ii) in the case of a Dispute pertaining to an individual‟s privacy rights - injury has occurred to the Applicant‟s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. ” 45. I raised the relevance of paragraph 9.3(b) with the FSP. In a detailed submission the FSP argued that no award should be made under the heading “financial loss.” However the submission did not address the question of compensation pursuant to 9.3(b)(i). 46. I am of the view that the FSP‟s conduct of the matter has been such as to cause a good deal of physical inconvenience and time taken to resolve the matter, thus having an impact upon the Applicant‟s expectation of enjoyment and peace of mind. 47. I need not set out the facts again. In my view in attempting to rely upon an option which could provide no early remedy for the Applicants, without the Applicant being exposed to the risk of great delay and potential heavy expense, the FSP‟s actions were most unfortunate to say the least. 48. I therefore consider that the FSP should further compensate the Applicant by payment of the sum of $2,000 under this heading. Determination 49. On the basis of the available information I determine the FSP must assess th e quotation from the Applicant‟s preferred repairs and authorise repairs as per their repair method, of building a cabin from parts, to reinstate the insured vehicle to an equivalent condition of the vehicle prior to the loss, as near as possible. 50. Should there be further damage caused as a result of this accident, located during the course of repairs, the FSP must assess and authorise these repairs to the insured vehicle. 51. If authorised repairs involve additional cartage rates, overtime, night, Sunday or holiday pay incurred by the repairer, the FSP must pay, subject to the policy limit, Expediting Expenses in accordance with Section 12 of its policy wording. Case No: 263257 Determination Page 8 of 8 52. In addition to authorising repairs, the FSP must refund to the Applicant all relevant towing costs, as detailed in its original settlement offer, of $1,262.50 (excluding GST). 53. Pursuant to paragraph 9.3(b)(i) of the Terms of Reference, I determine that the FSP should pay to the Applicant the sum of $2,000.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.