Determination 261777

Replacement of rental property roof after Cyclone Yasi denied as wear and tear and faulty workmanship

FirmFinancial Firm (Unknown - Insurer)
Decided2012-07-31
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The landlord claimed replacement of the roof after Cyclone Yasi, and the FSP denied that part of the claim. AFCA determined the FSP was entitled to deny liability for roof replacement.

The consultant's evidence of corrosion, deteriorated fixings and salt spray outweighs the plumber's view, so the roof's condition is attributed to gradual deterioration.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 261777 Determination Page 1 of 8 Case number: 261777 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 31 July 2012 Background 1. On 2 February 2011 the Applicant‟s rental property was damaged during cyclone Yasi. 2. The Financial Services Provider (FSP) accepted liability for a claim under the Applicant‟s landlord‟s residential property insurance policy but denied that part of the claim for replacement of the roof on the ground the condition of the roof was due to wear and tear and poor workmanship. Summary of Applicant’s position 3. There is clear evidence the roof was damaged by cyclone Yasi for the following reasons: I. The fascia was ripped off the house. II. Dents from storm blown debris. III. Most of the gutter was ripped off. IV. Water penetration caused by wind driven rain through the gap caused by the missing facia, collapse of the soffit and sheet lift-up. V. Structural movement to the house with cracked linings and junctions to the wall ceiling. VI. Movement of the roof structure and up -lift of roof sheeting. The roof now cracks when walked on indicating batten lift and folding of timber framing during the cyclone. VII. Movement of roof fixings which are now loose and elongated fixing holes. Had the event gone on longer the fixings would have withdrawn and the roof sheeting blown off. As it did not, this indicates the initial integrity of the roof. The house was constructed in the correct manner and has been well maintained. VIII. The roof did not leak prior to cyclone Yasi. The roof now leaks. Determination Case No: 261777 Determination Page 2 of 8 IX. Two independent plumbers have reported the roof was damaged by cyclone Yasi. 4. The Applicant states:  Approximately ¼ of the roof was installed some time ago with correct cyclone fittings. Although showing signs of surface rust in some areas and some holes over the eaves, this is a consequence of salt deposits from the cyclone and does not structurally compromise the roof or its ability to shed water.  Dents on the roof over the eaves from the cyclone have rusted. Much of the roof has dust stains which occurred during a site development behind the house and could be mistaken for rust.  The roof was sound and did not leak before cyclone Yasi.  Although the surface protection has worn away on many fixing screws they remain in good condition. Summary of FSP’s position 5. The FSP relies substantially on reports provided by its loss adjuster and a consultant builder. 6. Repairs were approved for rectification of the internal damage and a payment of $16,620 was made to the Applicant. 7. Based on the loss adjuster‟s and consultant builder‟s reports it considers damage to the roof was a result of general wear and tear over time and faulty workmanship. 8. The FSP refers to the following policy terms: “Exclusions to your cover ... Accidental damage cover, Additional cover and Optional cover exclusions We will NOT cover any loss or damage as a result of, or caused by ...  erosion, rust, corrosion, gradual deterioration, wear or tear...  a defect in an item, structural defects, or faulty workmanship or design” Issue 9. Whether the FSP was entitled to deny liability for the cost of replacing the roof. Case No: 261777 Determination Page 3 of 8 Reasons for decision 10. As advised to the parties this matter has been expedited in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the complex nature of the issues. The dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 11. There has been an exchange of material between the parties. Each party is therefore aware of the issues and had the opportunity to respond. 12. The decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer matters. 13. When making a claim under an insurance policy the responsibility rests with the policyholder to establish on the balance of probabilities that the cause for the loss claimed falls within the cover provided by the policy. As this policy has been expanded to include the Accidental Damage (AD) option and damage from Cyclone Yasi prima facie satisfies that description, the Applicant is taken to have enlivened the AD provision. 14. An FSP seeking to rely on a clause in the policy to deny a claim has the burden of establishing on the balance of probabilities that the terms of the relevant clause apply to defeat the claim. 15. Reports have been presented to the Panel by both parties in relation to the condition of the roof of the Applicant‟s property. A summary of the information provided in those reports follows. Loss adjuster - report dated 25 March 2011 16. Damage to the roof consisted of:  Approximately 4m of villa board eaves lining torn away.  Sarking in this area had been removed prior to the inspection.  Possible damage/loosening of roof fixings, screws and uplift barge capping/flashing.  Flashing near a skylight was torn away. 17. Repairs to the roof involved:  Replacing approximately 6m of ea ves lining in front of premises.  Replace approximately 4m of timber facia.  Removal and set aside roof sheeting to allow removal of sarking.  Replace sarking. Case No: 261777 Determination Page 4 of 8 Consultant building contractor S – report dated 29 June 2011 commissioned by the FSP  The inspection was carried out in the Applicant‟s company and the tenant.  The sheet metal roof displayed no storm created openings from either Cyclone Larry in 2006 or Cyclone Yasi in 2011.  The sheet metal roof to the north-western corner of the residence displayed surface corrosion with several corrosion holes to the low end of the roof sheets above the eaves lining.  The newer area of sheet metal roof displayed several corrosion holes to the low ends above the eaves lining.  Proprietary roof screws that secure the sheet metal roof to the roof frame displayed corrosion with several screw heads almost non- existent.  Numerous neoprene washers which provide waterproof seal at the junction of the screw and surface of the sheet metal roof displayed splits and shrinkage from ageing.  Several side lap joints of the sheet metal roof displayed no screws along the ridge cap flashings.  Screws that secure the skylight dome to the sheet metal roof were covered with flexible sealant. Extensive corrosion on the screws had caused the sealant to split.  The sealant at the lap joint of the ridge capping displayed a gap 40mm long by 2mm wide.  In his opinion the side lap joints of the sheet metal roof should have been screwed along the ridge cap flashing in accordance with the manufacturer‟s recommendations.  Water ingress would have been.  through the side lap joints of the sheet metal roof lifting during the cyclone.  through the deteriorated neoprene washers in the roof screws.  through the deteriorated sealant to the screws that secure the skylight dome to the metal roof.  through the gap of the sealant to the ridge cap flashing .  as the roof displayed several corrosion holes over the eaves lining, it was considered the sheet metal roof had exceeded its serviceable life and requires replacement as part of ongoing maintenance.  The metal roof had been affected by salt spray over a long period of time as indicated by the corrosion noted and the corroded roof screws.  In his opinion the roof had not been damaged by cyclone Yasi in 2011 or cyclone Larry in 2006. Case No: 261777 Determination Page 5 of 8 Plumber DS – report dated 6 September 2011 – commissioned by the Applicant  Water damage to the interior of the building means the roof is leaking.  The roof did not leak before cyclone Yasi.  This indicates the cyclone has caused the problem.  Guttering around the entire house is damaged and needs replacing.  Front eaves have blown out and sisalation under the roof has been ripped and blown apart.  Some of the roof screws have lifted.  The roof cracks in some areas when walked on indicating the roof has moved during the cyclone.  8 sheets on the front of the house near the guttering are damaged and have been scratched back to bare metal. This has taken off the protective coating and will eventually rust. This is now visible.  More than 20% of the roof has been damaged by the cyclone. The BSA and local council require where there is more than 20% damage to the entire roof the roof must be brought up to current building Codes.  The roof needs to be replaced. Consultant builder S – report dated 25 October 2011 18. This report was provided in response to the plumber‟s report.  During his inspection of the roof on 24 June 2011 there was no evidence the roof was still leaking. This was apparent since there had been continual tropical rain following the cyclone that would have caused extensive interior damage had the roof been still leaking.  At the time of his inspection he and the Applicant walked on the roof and at no time did the roof crack or make any other noise. He weighs 110 kilograms which would cause any abnormal noise.  No scratches were observed to the 8 roof sheets at the front of the house during his inspection.  The roof did not display any damage due to the cyclone.  The roof does need replacing as it had exceeded its serviceable life some years prior to cyclone Yasi. Plumber (CGP) – undated report commissioned by the Applicant  Some of the roof screws were loose and about 10 screws were missing out of the edge capping.  The remaining screws were in good condition.  Two skylights had not been flashed properly and would cause some water to enter the building. Case No: 261777 Determination Page 6 of 8  There appears to be some movement in the roof as the laps close to the ridge capping are spread leaving a possible entry point for stormwater.  Overall water penetration appears to be from around the edge and on laps where the sheets meet. The only way to check would be to remove sheets and check for stains.  If the roof were to come off it would not be able to be refitted without future problems.  The roof would not be worth patching and it would only continue to leak in other spots if disturbed.  As there were no leaks before cyclone Yasi, the mixture of movement and age have contributed to the ongoing problems with water entering the ceiling. Conclusion Additional independent report on the condition of the roof 19. The Panel is mindful of the Applicant‟s request to have a further independent report obtained in relation to the cause for the condition of the roof. 20. However, the roof has been inspected by three professionals all of whom may be regarded as being appropriately qualified to investigate and report on the probable cause for the current condition of the roof. 21. In addition both parties have had the opportunity to comment on the various reports. 22. In these circumstances the Panel will proceed to determine the issue based on the evidence before it. The damage 23. It is clear that the Panel has been provided with different and diverse opinions in relation to the cause for the condition of the roof following cyclone Yasi. 24. The consultant builder was of the opinion that although the roof required replacement, this was due to gradual deterioration over a period of time. 25. On the other hand the plumber DS was of the opinion replacement of the roof was due to damage caused by cyclone Yasi. 26. After analysis of the evidence the Panel is persuaded that the report provided by the consultant builder S is to be preferred. 27. The consultant builder‟s response to plumber DS commen ts are persuasive. In relation to the roof cracking when walked on, the consultant advised that Case No: 261777 Determination Page 7 of 8 although he weighed about 110kgs, contrary to the plumber‟s report the roof did not crack or make any unusual noise when he and the Applicant walked on it. 28. Further there was no evidence of additional leaking at the time of his inspection on 24 June 2011 notwithstanding the area had experienced continual torrential rain in the intervening period of about four months from the time of the damage. 29. The consultant agreed that gutters to the front of the house were partially damaged but the gutters to the rear elevation did not display any damage. The gables were not fitted with gutters. 30. The consultant confirmed the sisalation was not „ripped and blown apart‟ at the time of his inspection. Photographs taken by the loss adjuster of this area of damage show two panels in which sisalation can be seen. There is no evidence of ripping or other damage consistent with it having been blown apart in that photograph. 31. At the time o f the consultant‟s inspection no lifted roof screws were observed. Significantly his report commented on the condition of the screws and the numerous neoprene washers signifying close attention was given to the condition of the screws. 32. In relation to scratches on roof sheets, the consultant said he did not observe any damage of this nature at the time of his inspection. He went on to say the scratches as described would have been obvious against the dull corroded surface. 33. The Panel is assisted in understanding the condition of the roof and findings by the contractors by photographic material. Photos provided with consultant S‟s report and that of the loss adjuster‟s show what is clearly extensive surface rust to a number of roof sheets. 34. Captioned photos wit h the consultant‟s report of 29 June 2011 show : a) gaps in the sealant applied to a lap joint of the ridge cap flashing. b) one of several corrosion holes on the low end of the metal roof sheet over the eave. c) corrosion adjacent to the skylight and a corroded screw and cracked sealant around the skylight. d) deteriorated neoprene washers. 35. Captioned photographs submitted by the loss adjuster show what appears to be significant rusting to a large number of roof fixings. 36. The loss adjuster‟s photographs also show the d amaged eaves from which the exposed sarking can been seen. There is no indication in these photographs to suggest the sarking having been blown apart and ripped. Case No: 261777 Determination Page 8 of 8 37. Photographs submitted by the Applicant provide a clear distinction between the old and new sections of the roof. The new section appears to be in reasonable condition. 38. Nevertheless, it is difficult to accept that the extent of deterioration shown on the photographs to the roof and fixings occurred in the intervening period from the cyclone and when the photographs were exposed being a period respectively of about one month and four months. 39. Furthermore, plumber GSP reported the screws were in good condition which appears to be contrary to the photographic evidence. His report refers to „ a few rust s pots‟ which again does not fairly represent the overall condition of the roof which has extensive surface rust to the older section of the roof and several rust holes in the new section of the roof. 40. Additionally GSP observed skylights had not been flashed properly which allowed the ingress of rainwater. 41. For these reasons the Panel is of the opinion the evidence does not support a finding that the roof requires replacement as a result of damage caused by cyclone Yasi. 42. The policy does not cover any loss or damage as a result of gradual deterioration. As such, the Panel considers the FSP has established the damage claimed does not fall within the cover provided by the policy. Determination 43. On the basis of the available information the Panel determines the FSP was entitled to deny liability for the claim for replacement of the roof.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.