Home / Financial Firm (Unknown - Insurer) / Determination 261609

Determination 261609

Delayed and inadequate settlement of cyclone home building claim

FirmFinancial Firm (Unknown - Insurer)
Decided2013-02-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The applicant's cyclone-damaged home claim was not cash settled until July 2012, and she complained of delay, poor handling and an inadequate settlement. AFCA found the FSP's handling unreasonable, ordered further payments on invoices for permits, bin hire, exterior painting and any timber beam, two weeks' loss of rent, $3,000 for non-financial loss and interest, but found the window settlement met the FSP's obligations.

Non-financial loss compensation was available because the FSP's conduct caused an unusual degree of inconvenience and delay, and the policy did not expressly exclude such loss.

Issues

Subjects and remedies

home or building damagemental healthnatural disasterpay claimpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 261609 Determination Page 1 of 25 Case number: 261609 General Insurance - Domestic Insurance - Home Building - Service - Delay in Claim Handling/Inadequate Settlement 17 January 2013 Background 1. The Applicant held a home buildings insurance policy with the Financial Services Provider (FSP) which was current at the time of loss. The insurance policy provided a sum insured for buildings of $332,800 and had an applicable policy excess of $300. 2. On 7 February 2011 the Applicant contacted the FSP to report extensive damage to her property caused by cyclone, which occurred on or about 2 February 2011. 3. The FSP accepted the claim and provided an emergency payment to the Applicant in accordance with the terms and conditions of the insurance policy of $2,500. The FSP then arranged assessments of the damage to the Applicant’s property and the Applicant arranged temporary accommodation which was paid for by the FSP. 4. Upon receipt of the advice from its experts, the FSP attempted to authorise repairs to the Applicant’s property, howe ver the Applicant had numerous concerns regarding the extent of repairs and whether the scope of works (SOW) she had been provided encompassed all cyclone damage repairs. 5. Over the ensuing months, a number of discussions and reinspections of the property were undertaken however the “SOW” was not accepted by the Applicant. The Applicant reluctantly accepted a cash settlement offer on 14 June 2012, which was sent to the Applicant on 3 July 2012, to enable her to begin repairs on her property. The settlement was accepted on the basis that it was not a full and final settlement, dependant on the outcome of the dispute she lodged with FOS. Summary of Applicant’s position 6. The Applicant says the FSP attempted to authorise repairs to her property in April 2011 based on a “SOW” prepared by its builder/assessor, despite the fact that she had not met on site with any builder to ensure the “SOW” Determination Case No: 261609 Determination Page 2 of 25 suggested encompassed all necessary repairs to the cyclone damaged property. 7. Her attempts to have the FSP attend to outstanding issues has resulted in unnecessary delays, countless reinspections of her property by various people, with and without her presence, changes to the “SOW” resulting in cyclone damaged items being excluded then reintroduced at her request, herself and her children being displaced from their residence for approximately 21 months and an inadequate settlement figure being offered to her by the FSP. 8. The current outstanding issues relate to inadequate settlement offers for the removal of rubbish and debris (associated bin hire costs), external painting of her property and costs associated with obtaining relevant council approval for the structural repairs required to the property. In addition, the Applicant seeks additional settlement amounts for the replacement of windows to current code specifications and for temporary accommodation of two weeks for a delay in being able to start repairs due to termites. 9. One item authorised for repair by the FSP is a timber beam and it is as yet unknown if this beam can be successfully repaired until repairs are attempted. Should the beam require replacement, the Applicant also seeks to have the additional costs paid to her by the FSP. 10. As a result of the cyclone and other personal issues, the unreasonable delays in rebuilding caused by the FSP and endless reinspections of her property by the FSP has caused the Applicant additional stress and anxiety which she says could have been avoided. This has resulted in her taking extended sick leave and having to leave her previous employment. 11. The Applicant seeks to have the FSP provide to her a settlement which is fair and reasonable and which takes into account all damage caused by the cyclone. Summary of FSP’s position 12. The FSP says there has been no undue delay in processing or finalising the Applicant’s claim especially considering the magnitude of the cyclone event and the extensive damage to the Applicant’s home. It notes that the Applicant was unwilling to allow any of its representatives onto her property without her presence and therefore, delays caused by this were out of its control. 13. The Applicant has failed to provide any supporting documentation or evidence to support her suggestion of the inadequacy of the settlement offered by the FSP in relation to building permits and rubbish removal (bin hire). 14. The windows/glass sliding doors at the property were not installed to the required building code requirements and as such, the FSP is not responsible Case No: 261609 Determination Page 3 of 25 for any additional costs in ensuring the windows/glass sliding doors are replaced to meet those requirements. 15. The FSP regrets the level of service provided by it to the Applicant did not meet the Applicant’s expectations. However, there is no cover for any consequential loss under the terms and conditions of the insurance policy and as such, it cannot provide any compensation in this regard. 16. The FSP relies on the following policy provisions of its Product Disclosure Statement (PDS): “ We do not cover ... Extra costs following an insured incident Consequential losses or extra costs following an insured incident ... ” (Page 126) “ How we settle your claim We choose how your claim is settled If we agree to pay a claim for loss, theft or damage to your home, contents or landlord’s fixtures and fittings, we will decide if we will: - repair damage new for old or - replace home or contents new for old or - pay you what it would costs us to repair or replace home or contents new for old. The meaning of new for old is defined on the next page. We will not: - pay extra to replace your home, contents or landlord’s fixtures and fittings to a better standard, specification or quality that it was before the loss or damage occurred except as stated in ‘new for old’ on the next page - fix a fault that existed before the loss or damage occurred. New for old means: - new materials, new items We replace or repair with new items or new materials that are available at the time of replacement or repair from Australian suppliers. - new for old, regardless of age We replace or repair new for old regardless of age, with no allowance for depreciation. ... - same type, standard and specification as when new We replace or repair to the same type, standard and specification as when new. If the same is not available, it means of a similar type, standard and specification when new. It can be a different brand. New for old does not: Case No: 261609 Determination Page 4 of 25 - include paying the extra cost of replacing or purchasing an extended warranty on any home or contents item or - mean of a better standard, specification or quality than when new.” (Pages 134 and 135) “ How we settle your claim (continued) ... Home Claims How we settle home claims If we agree to pay a claim for loss, theft or damage to your home, we will decide if we will: - repair new for old or - rebuild your home new for old or - pay you what it would cost us to repair or rebuild your home new for old. When we repair or rebuild your home We will do our best to obtain new materials that are the same type, standard and specification as when new. If the same is not available, we will use new materials of a similar type, standard and specification that are commercially available and compliant with the latest building regulations.” (Page 138) Issues 17. Whether the FSP caused any undue delays in the claims handling process. 18. Whether the FSP’s level of service to the Applicant was acceptable. 19. Whether the Applicant has received adequate settlement for a variety of items. 20. Whether the Applicant is entitled to any additional loss of rent payment. 21. Whether the Applicant is entitled to compensation. Reasons for decision 22. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 23. I am satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. Case No: 261609 Determination Page 5 of 25 24. This dispute essentially relates to the claims handling process conducted by the FSP which the Applicant says, resulted in unnecessary delays and an inadequate claims settlement. Time Line 25. To assist in reviewing the issues of this dispute, I have confirmed the following time line of events, based on file notes provided by the FSP:  Date of Loss – 3 February 2011  Loss reported to FSP by Applicant – 7 February 2011  Emergency payment made to Applicant of $2,500 – 7 February 2011  Temporary accommodation arranged by Applicant – 16 February 2011  Temporary accommodation arrangements approved by FSP – 26 February 2011  Assessor attended to inspect property – 26 February 2011  Applicant advised FSP temporary accommodation arranged is not suitable for her family and looking for alternative based on assessor’s advice that she will be out of her home for 12 months – 5 March 2011  Assessor’s report noted as being on file and awaiting review – 5 March 2011  Approval given for alternative temporary accommodation by FSP – 14 March 2011 (to start from April 2011)  Make safe to make property watertight arranged on Applicant’s advice that water is still entering property – 23 March 2011  First rental payment made by FSP for period 15 April 2011 to 15 May 2011 – 26 April 2011  Email sent by Applicant to FSP requesting temporary accommodation payment as overdue – 25 May 2011  Payment for temporary accommodation from 15 May 2011 to 15 June 2011 made – 30 May 2011  Payment for temporary accommodation from 15 June 2011 to 15 July 2011 made on email request from Applicant – 9 June 2011  Applicant requested “SOW” /quote, advised she wanted her own builder to complete work and requested FSP to note her file with the following: “The builder from [LL] had contacted me and asked for permission to look at the home when I wasn’t at home. He said he would contact me after that to discuss the quote and “SOW” in person with me before lodgement. This was never done. Because of this can you please notate my file to say that I do not give permission ever under any circumstances for anyone to enter my property unless I am present. Can you please ensure this information is passed onto [LL] and any other relevant representatives who are acting on [the FSP]’s behalf.” – 6 July 2011 Case No: 261609 Determination Page 6 of 25  “SOW” without costings emailed to Applicant by FSP – 6 July 2011  Payment for temporary accommodation from 15 July 2011 to 15 August 2011 made on email request from Applicant – 9 July 2011  Quotation for works received from FSP’s builder for $71,811 – 18 July 2011  FSP’s file notes indicate an email was received from Applicant advising items appear to be missing from “SOW” . FSP requested builder to review – 18 July 2011  Payment for temporary accommodation from 15 August 2011 to 15 September 2011 made on telephone request from Applicant – 8 August 2011  Payment for temporary accommodation from 15 September 2011 to 15 October 2011 made on telephone request from Applicant – 19 September 2011  Applicant called FSP requesting rent payment and requesting that this be set up automatically each month so she did not have to call – also complained as having never spoken to the Case Manager (CM) handling her claim and requested to speak to “CM” or a Team Leader – these requests were denied by FSP’s call operator as no -one was available, however Applicant was advised that “CM” would call her back within two working days. Call operator advised Applicant that automatic payments could not be guaranteed due to the volume of claims as a result of this event – 19 September 2011  Complaint from Applicant reviewed by FSP – Applicant was called and a message left. “CM” was emailed “appointment” to make temporary accommodation payments on the 1 st of every month – 23 September 2011  FSP’s file note indicates a request to the builder to provide the “SOW” which had been provided by builder to Applicant to sign (appears not to have been received by FSP at this time) and a quotation had been received from the Applicant – 26 September 2011  FSP calls Applicant as a courtesy – no other details of call – 28 September 2011  Payment for temporary accommodation from 15 October 2011 to 15 November 2011 made on telephone request from Applicant – 10 October 2011  Telephone discussion between FSP and Applicant – Applicant advised that she was concerned with “SOW”, had been told an engineer was required and as one had not been appointed by FSP, she had appointed her own – FSP advised Applicant her concerns would be raised with its builder – 19 October 2011  Complaint lodged by Applicant – FSP responded – advised FSP will pay for Applicant’s engineer’s costs. Applicant advised people still Case No: 261609 Determination Page 7 of 25 entering her property whilst she is not there and make safe of property still needs to be done – 31 October 2011  “CM” spoke with Applicant who became agitated after being advised by CM that temporary accommodation payment would be made for two weeks only to bring Applicant a month in advance on payments which senior staff of FSP agreed was all the FSP could pay. Applicant cancelled appointments with assessor and FSP’s engineer. FSP’s builder disagreed with Applicant’s engineer’s report – 1 November 2011  FSP’s builder provided advic e to FSP that the Applicant was not co- operating – 9 November 2011  FSP responds to Applicant’s complaint – reinspection with Assessor and FSP’s engineer arranged , apology made for inconvenience, temporary accommodation checked and up to date to 15 November 2011 – 11 November 2011  Payment for temporary accommodation from 15 November 2011 to 15 December 2011 made – 11 November 2011  Applicant contacts FSP – requests no contact from FSP while the matter is being reviewed by FOS, assessor’s appointment to be cancelled and make safe requested by FSP – 14 November 2011  FSP calls Applicant noting that, “... -insd has specifically requested we only email her – due to restrictions of conversation i called insd mobile, no answer, LMTCB – insd called back whilst drafting note .. .”. FSP advised Applicant payment to be made for fence and engineer’s report, that the appointed assessor was not appointed to hurt her case or void her claim, rather to clarify areas in dispute between her and the builder – Applicant advised FSP no further assessments until FOS have reviewed – 15 November 2011  Payment made to Applicant for fence and engineer’s report – 16 November 2011  Applicant discusses site visit with assessor before his attendance to clarify some issues – 17 November 2011  FSP file note detailing a diary entry received to review file for next temporary accommodation payment – file reviewed and re-filed for payment to be made on 12 December 2011 – 1 December 2011  Applicant contacts FSP as temporary accommodation payment not received and now due – call was made as outside of work hours – email sent to claims handler to follow up – 16 December 2011  Payment for temporary accommodation from 15 December 2011 to 15 January 2012 made on review of file and note by FSP that payment had been overlooked – 20 December 2011  Payment for temporary accommodation for balance of limit of this cover made, due to works not yet started and Applicant requiring to provide lessor with six weeks notice if not continuing rental agreement – 21 December 2011 Case No: 261609 Determination Page 8 of 25  Letter sent to Applicant requesting urgent response regarding whether or not she accepts the new “SOW” – 5 January 2012  Quotation from FSP’s suppliers requested for replacement stove – 10 January 2012  FSP’s builder advises quote for stove is $4,224 and FSP’s suppliers suggest $6,676 – review required. Final “SOW” quote from FSP’s builder on items agreed by Applicant at previous review is $196,931 including stove – 11 January 2012  FSP requested revised quote from suppliers for stove as specifications of original stove have now been received and original quote provided by supplier does not match specifications – 13 January 2012  Email sent to Applicant advising her concerns regarding the “SOW” are being addressed, including if there is any asbestos in walls – 13 January 2012  Follow up call made by FSP to supplier regarding quote for oven – 13 January 2012  Email received from Applicant regarding her concerns with new “SOW” issued – sent to FSP’s builder for a response – 16 January 2012  Complaint from Applicant addressed by FSP by appointing another assessor to assist in resolving current issues with “SOW” etc – 17 January 2012  Telephone call received by FSP from co- insured (Applicant’s ex - partner) requesting an update on file – FSP advised that all payments regarding claim would be made into a joint account or via cheque in both parties names as at the time of the loss, both parties were listed on the policy (at renewal, ex-partner had been removed from policy) – 19 January 2011  Email received by FSP from Applicant advising she does not wish to discuss claim on telephone and date of appointment for second assessor to attend is not convenient for her – better time would be 6pm however this does not suit assessor due to others also having to be onsite. FSP requested via email a suitable time for FSP to call Applicant to discuss – 24 January 2012  SMS sent to Applicant for her to call FSP – 24 January 2012  FSP called Applicant and left message on voice mail to call FSP – 24 January 2012  Co-insured called FSP for update on claim – advised close to a settlement and currently awaiting another assessment to confirm final “SOW”. FSP notes that both co -insured and Applicant are to be provided with update on claim – 25 January 2012  Payment for temporary accommodation made to cover period to 22 March 2012 made on an ex-gratia basis as this is over policy limit – 2 February 2012 Case No: 261609 Determination Page 9 of 25  Make safe repairs organised for 7 February 2012 – 3 February 2012  FSP confirms with suppliers that quotation sent by Applicant for replacement stove is the closest match to what she had as original manufacturer no longer exists. Applicant’s quotation is $7,149 which is accepted by FSP – 15 February 2012  FSP follow up email to builder for amended “SOW” and email sent to Applicant with copies of asbestos report and glazing report – 15 February 2012  FSP advised Applicant via email that FSP required evidence that windows installed at property were installed to code at the time property was built. FSP also called Applicant’s solicitor regarding co -insured and how any settlement may be affected by any agreements between Applicant and co-insured regarding their separation – 16 February 2012  Applicant advised FSP that property was built to code and disputed codes quoted by FSP’s glazing expert – Applicant requested details to discuss with other experts – 21 February 2012  FSP followed up builder for amended “SOW” – 21 February 2012  Co- insured contacted FSP for update, advised that the Applicant’s name is incorrect on policy and asked how he could change it – Co- insured was advised could only be changed at policy level and was provided with update on claim – 24 February 2012  Co- insured contacted FSP and requested “SOW” and cash settlement details to also be emailed to him at a different email address to what he had provided previously. FSP advised co- insured that the final “SOW” was not yet ready – 27 February 2012  Applicant contacts FSP disputing windows report advising when house was built, it was built to code, including windows and that she has documentation to support th is. FSP file note indicates FSP has “asked insd on numerous occasions for these reports with no docs received.” (Only one previous file note mentions a request for this information by FSP). Applicant also raises that windows previously repaired under a previous cyclone claim lodged with FSP. FSP reviews previous claim and finds Applicant was cash settled, and therefore, FSP did not authorise any previous window repairs. FSP notes that Applicant has also raised further concerns with “SOW” and that these conc erns were not previously raised with FSP – 27 February 2012  FSP reviewed file and notes that issues with “SOW” raised by Applicant are correct as items were removed from “SOW” by builder with no apparent reasoning for same – FSP requested builder add these items back into “SOW”. FSP agrees to cover windows to be repaired/replaced to the condition they were in prior to loss due to them not being installed to code at time of property being built and Applicant failing to provide any documentation or evidence to the contrary – 28 February 2012 Case No: 261609 Determination Page 10 of 25  FSP follows up builder for amended “SOW” and sends email to Applicant advising what it is waiting on from her, namely, documentation relating to windows being installed to code, documentation relating to pool and legal doc uments from Applicant’s solicitor regarding settlement with co-insured regarding property etc – 2 March 2012  FSP contacts builder to follow up amended “SOW” – 7 March 2012  Ex-gratia payment made for temporary accommodation from 23 March 2012 to 19 April 2012 – 7 March 2012  “SOW” received from builder by FSP – FSP contacted builder to discuss its concerns as quote was significantly less than previous and items had in fact been added to previous – there was no reason why from builder. Update sent to Applicant advising additional temporary accommodation payment made and awaiting correct “SOW” from builder – 7 March 2012  Email received from Applicant with concerns and reply sent by FSP addressing those concerns (no information regarding what concerns were are detailed in file notes) – 8 March 2012  Co-insured contacted FSP requesting copies of all documents on file as he had received nothing – FSP advised co-insured a privacy request would need to be made by him and that a timeframe to supply documents could not be provided – 12 March 2012  Applicant’s solicitor calls FSP at FSP’s request and confirms that all property was signed over to the Applicant as part of the property settlement and as such, all interests in property and claim need to be signed over to Applicant – FSP agrees if a letter is obtained from the co- insured’s solicitor confirming this agreement, then this would suffice for the FSP’s needs – 13 March 2012  Email received by FSP from Applicant advising that the make safe completed by FSP’s builde rs has failed. Requested floors be reviewed as they have now suffered possible water damage and Applicant also requested FSP’s builder re -attend to rectify. FSP contacts builder to arrange – 14 March 2012  Applicant’s solicitor called FSP to confirm letter has been drafted and will be sent to FSP – 15 March 2012  Co-insured called FSP seeking an update – matter referred to claims team – 15 March 2012  Email sent by Applicant to FSP outlining concerns with new “SOW” – FSP advised Applicant the matter is under review – 19 March 2012  Co-insured called FSP seeking an update – matter referred to claims team as call received out of hours – 20 March 2012  Co-insured called FSP seeking an update – FSP advised it was currently arranging the relevant information to send him and no timeframe could be given. FSP notes that information regarding Case No: 261609 Determination Page 11 of 25 Applicant’s accommodation was not to be provided to co -insured – 21 March 2012  FSP reviewed Applicant’s concerns and referred concerns to builder for comment – Applicant advised of th is. Call made to Applicant’s solicitor seeking letter previously requested and message left for him to return FSP’s call – 21 March 2012  Co-insured called FSP for an update – advised documentation still being compiled and someone would call him when it was ready – 27 March 2012  Co-insured called FSP for an update – advised matter would be followed up with him early the following week – 30 March 2012  Review of claim – email received from builder addressing Applicant’s concerns over “SOW” and email sent to FSP’s legal advisers regarding an email it received on 2 April 2012 (details of which are not provided in file notes) – 2 April 2012  Co-insured called FSP for update and advised FSP he will call every day until the information is received – FSP advised “SOW” is still under review – 4 April 2012  Applicant contacted FSP requesting further temporary accommodation payment – payment approved and made – 4 April 2012  Applicant contacted FSP and asked if her builder could be paid direct – denied by FSP as no guarantee applies to her builder – 5 April 2012  Co-insured called FSP wanting update – advised that matter is currently under review. Co-insured advised matter has be going on for too long and requested to speak to someone “legal” at FSP. FSP advised no- one “legal” he could speak to however process is under review – 11 April 2012  FSP sent email to builder following up concerns/queries with “SOW” – 11 April 2012  Response received by FSP from builder – FSP agreed that a floor specialist report was required and this was authorised – 12 April 2012  Email sent to Applicant by FSP outlining builder’s response to her concerns and email sent to builder requesting floor report by the following week – 13 April 2012  Email sent to Applicant by FSP regarding her concerns – 16 April 2012  FSP notes builder is to provide it with details of floor specialist so this information can be provided to the Applicant – 17 April 2012  Emails sent to builder and Applicant by FSP to arrange floor specialist attendance – 19 April 2012  Co-insured called FSP for update and complained that repairs need to be authorised to FSP’s builder as the property affects his children’s inheritance – 20 April 2012 Case No: 261609 Determination Page 12 of 25  Email received by FSP from builder advising floor report has been completed and will be sent through to FSP – 27 April 2012  Applicant called FSP seeking further temporary accommodation payment – 30 April 2012  Payment for temporary accommodation from 19 May 2012 to 16 June 2012 made – 30 April 2012  Emails sent by FSP to builder (requesting floor report) and Applicant to see if paperwork from her lawyer has been received – 14 May 2012  FSP received floor report from builder – emailed builder to confirm no further changes required to “SOW” . Email received by FSP from Applicant advising paperwork from lawyer has not yet been received – 16 May 2012  Co-insured requested update and at least a copy of the assessment report be sent to him – FSP advised this is still being reviewed – 23 May 2012  FSP received email from builder on 24 May 2012 with a revised “SOW” and quotation for $196,080. FSP received email from Applicant on 25 May 2012 advising she will review offer being made and seek to have FOS mediate the issues which the parties cannot agree on. She also says that she has been classed unfit for work for a further three months due to the stresses associated with the cyclone – 29 May 2012  Email sent by FSP to Applicant confirming cash settlement to be made of $203,229 which is $196,080 for repairs and $7,149 for replacement stove/oven – 6 June 2012  Email received by FSP from Applicant requesting a further one month of temporary accommodation – ex-gratia payment approved by FSP – 8 June 2012  Applicant telephoned FSP following up temporary accommodation payment – 12 June 2012  Payment for temporary accommodation from 17 June 2012 to 15 July 2012 made – 13 June 2012  Payment for claim made to Applicant via cheque and to be sent registered mail – 14 June 2012  Claims team still awaiting cheque to be received so it can be posted via registered mail – 25 June 2012  Cheque received by claims team to send as registered post. Email sent to Applicant to advise and Applicant requested a copy of most recent “SOW” as she has so many on file – 3 July 2012  Email sent to Applicant with latest “SOW” and floor report – 4 July 2012  Email received by FSP for temporary accommodation – agreed to pay 120 days from date of settlement. Review of claim saw that payments had already been paid to 16 July 2012 (date of settlement was 3 July Case No: 261609 Determination Page 13 of 25 2012). Temporary accommodation agreed to paid until 30 October 2011 and settled at $11,754.14 – 16 July 2012  Payment for final temporary accommodation made – 16 July 2012  Additional temporary accommodation payment made for period from 30 October 2012 to 15 November 2012 – 23 July 2012  Applicant contacted FSP and advised payment was cleared in her account and then transferred – FSP to look into – 23 July 2012  Additional temporary accommodation payment made on 23 July 2012 was recalculated and reissued ($1,648.40) – 24 July 2012  Applicant’s complaint regarding payment of $11,754.14 being paid into the joint account belonging to her and the co-insured was reviewed. Applicant had previously advised this money was to be paid to her account only and as a result of FSP’s actions, co - insured has “stolen” money. FSP originally advised that they could not reissue and had not done anything wrong. IDR review resulted in this decision being overturned and FSP agreeing to re-pay the money to Applicant – 13 August 2012  Email to FSP from Applicant requesting payment of temporary accommodation – email from IDR received with letter to Applicant – 21 August 2012  Email from Applicant to FSP confirming bank account details for payment – 22 August 2012  Reissuing of payment made by FSP to Applicant’s bank account – 22 August 2012 26. Whilst the timeline above details the FSP’s file notes, many of these notes reiterate the email documentation provided by the Applicant. On reviewing the FSP’s file notes, I found that there was some communication documented by the Applicant which did not appear in t he FSP’s file notes and that the file notes are scant, at best, in some respects. Nonetheless, the file notes provide a relatively accurate picture of the issues in dispute. Delays 27. The Applicant says she was subjected to unnecessary and long delays in the processing of her claim and the eventual settlement of her claim due to the FSP’s continuous request to reinspect her property and its failure to properly amend the “SOW” , as required. 28. On 16 October 2012 the FSP provided additional comments to its original NOR. In these comments, the FSP says: “[The FSP] submits that the nature and extent of the damage to the applicant’s home required investigation over a period of time and that specialist opinion was required to ensure that an objectively correct claim outcome was provided to the applicant in accordance with the terms and conditions of the policy. Case No: 261609 Determination Page 14 of 25 The applicant eventually obtained engineering opinion in October 2011, upon which it was appropriate that [the FSP] sought further qualified opinion. Upon receipt of such further expert opinion, [the FSP] was able to come to a fully informed decision as to the quantum of the building damage claim. [The FSP] promptly sought to cash settle the applicant accordingly.” 29. The Applicant sought an engineer’s opinion and rep ort on her home approximately seven months after the event and after several months of attempting to have the FSP address her concerns, which it had failed to do to this point. The FSP after investigating the issues raised by the Applicant’s engineer then set tled the Applicant’s claim on 3 July 2012, some eight months after the Applicant had submitted her engineer’s report. 30. The FSP’s comments that the Applicant “eventually” obtained an engineer’s report and that it “promptly sought to cash settle” are somewhat surprising giving the facts detailed above. 31. Having reviewed all of the material provided by both parties I can find no instances where any delays were caused by the Applicant, other than her request to be present when inspections/site attendances were made and co- ordinating these times with the relevant parties. 32. However I note numerous instances of delays caused or created by the FSP throughout the entire claims handling process, essentially relating to the FSP’s requirement to have the Applicant’s home repeatedly re-inspected. 33. The FSP suggests that the magnitude of the cyclone event and the extensive damage caused to the Applicant’s property contributed to the delays and I am satisfied this is the case. 34. However the FSP also suggests that the Applicant’s “ongoing submissions as to damage to the home building” and the FSP’s need to quantify this damage were the prime contributors to the unusual delays experienced. 35. I am not satisfied that the issues raised by the Applicant throughout the claims process were unusual or new. In fact, the only additional items queried by the Applicant throughout the course of the claim were relevant to the FSP’s failure to conduct proper “make safe” repairs and resultant damage from that failure, or the fact that the property had been left unprotected for such a lengthy period of time. The issues were ongoing, however this was largely contributed to by the FSP’s lack of care or attention in amending the “SOW” in accordance with the Applicant’s concerns (see “ Handling of claim ”, below). Handling of claim 36. The Applicant has raised many issues in respect to the way in which her claim was handled by the FSP. These issues include:  A loss of rent payment made into a joint bank account in the name of her former partner and herself. This amount was subsequently withdrawn by her former partner before she was aware of it and Case No: 261609 Determination Page 15 of 25 effectively “stolen” by him. This payment was made by the FSP despite the fact it was aware of the Applicant’s situation with her former partner (ie: separated, intervention orders in place due to his violence etc). The FSP initially advised it could not do anything about this and it was the Applicant’s responsibility, despite the fact it was aware that the Applicant had been paying the rent and had organised the rental agreement in her name and her name only for the duration of the claims handling process. The money was eventually repaid by the FSP to the Applicant by cheque.  Rent payments by the Applicant to her real estate agent were due on the 15 th of each month and a month’s ren t was due on each occasion to be one month in advance each time. Loss of rent payments from the FSP were frequently late, had to be followed up by the Applicant or, on one occasion, were made as a fortnightly payment only.  The original “SOW” issued to her by the builder was done without any previous contact with her by the builder and she did not have the opportunity to walk through her home with a builder to ensure all aspects of cyclone damage were included initially.  Despite repeated requests that no-one to attend her property without her being present, this continued to occur.  On more than one occasion, revised scope of work documents were provided to the Applicant where items that had been previously agreed to by the FSP and Applicant were deleted without explanation. It was only upon the Applicant bringing these matters to the FSP’s attention that these items were again included on the “SOW” .  The Applicant advised the FSP that a timber beam had been damaged by SES workers when they attended her property shortly after the cyclone event in an attempt to provide some level of protection to her property and prevent further damage. The FSP advised the Applicant that this was not covered as it had been deliberately damaged. Only when the Applicant queried this and the broader consequences of such a denial, did the FSP agree to accept this item as being part of the Applicant’s claim. 37. I am of the opinion that the FSP, whilst entitled to seek opinion from its experts in relation to the Applicant’s concerns, was so mewhat careless when reviewing and relaying the information it received from its experts, especially in the early stages of the claims handling process. This appears to have created an air of distrust on the part of the Applicant who was frequently confronted with conflicting and differing information. 38. I have many concerns over the issues raised by the Applicant as her concerns as detailed above have been confirmed through file notes provided in the material from the FSP. 39. I am therefore satisfied that the Applicant has been subjected to a sub- standard level of service from the FSP in relation to the manner in which it has handled her claim. Case No: 261609 Determination Page 16 of 25 Timber Beam 40. It has been confirmed by both the FSP and the Applicant that the costs settled by the FSP in relation to the timber beam repairs, is subject to the timber beam actually being able to be repaired. This item remains as an “unknown” until the repairs are attempted. 41. Until repairs are attempted, the FSP would be unable to consider any additional settlement amount towards this item. 42. Should the timber beam be irreparable, a detailed report from the Applicant’s builder providing what repairs were attempted, why the repairs were unsuccessful and any costs associated with the repair attempt, will need to be supplied to the FSP, in addition to an invoice or receipt for the replacement of the timber beam. 43. As the FSP has had ample opportunity to have these costs quoted/substantiated by its own builders, the Applicant should only be required to produce her invoices or receipts for these costs without the FSP requiring any additional investigation or information to substantiate same. Windows 44. The Applicant says that the windows at her home were installed professionally when the house was originally built and some of those windows were replaced after a previous cyclone in 2006, a claim for which was lodged with the FSP. 45. The FSP says it did not pay for the replacement of any windows as a result of the 2006 claim and cash settled the Applicant for the necessary building repairs. It also says, based on its expert’s advice, that the windows at the Applicant’s property were not installed in accordance with current building codes, nor would they have complied with the relevant building codes at the time the house was constructed. 46. The Applicant says she was provided with a Certificate of Occupancy when took possession of the property after it was built and believes this Certificate would not have been issued by her local council if there were any breaches of the building code, including the installation of windows. Unfortunately, the Applicant is unable to produce a copy of this Certificate as it, along with a lot of other personal paperwork, was destroyed or lost during the cyclone in February 2011. 47. The FSP says it has settled the Appli cant’s claim for windows based on the replacement cost of the same type of materials and construction which was present at the time of loss. It initially said it was not responsible for the costs associated with bringing these items up to current building codes as they did not meet the appropriate building codes at the time the house was constructed. In this regard, it relied on its PDS wording, which says: Case No: 261609 Determination Page 17 of 25 “ 4. Extra costs to comply with the latest home building regulations ... Complete details for this feature We cover When rebuilding or repairing damaged parts of your home we will pay for the extra cost of making these parts comply with the latest home building regulations and laws. The extent of the upgrade needed will depend on how old your home is and what building regulations have changed since your home was built. The cover in this feature is not paid in addition to your home sum insured, so always keep your sum insured up to date with the latest new rebuilding cost. We do not cover - costs to upgrade undamaged parts of your home to comply with the latest building regulations - costs to make your home comply with building regulations that existed when the home was originally built or altered.” (Page 84) 48. I have reviewed the FSP’s glazier ’s report and note h is comments which read: “  Upon inspection of the above property, windows were fabricated inadequate materials & assembled insufficiently and fail all AS1288 requirements. The windows appear to have failed because of the following reasons:  Selection & installation AS1288-2006: Does not meet requirements  The design of the structure for strength and serviceability. As/NZS 1170.0 does not meet the wind loads for housing requirements  Standard specification of structural silicone sealants complying with ASTMC1184, does not meet the minimum requirements ...  The house appears to be situated in a C3 area, and windows & doors should meet the Australian standards that were in effect when the house was built in 1996.” (sic) 49. On receiving queries from the Applicant and FOS, the FSP appointed an Engineer to provide a report on the Applicant’s windows. The FSP has confirmed the engineer did not attend the Applicant’s property or inspect the windows. This engineer provided the following comments: “ The windows that have been installed are not standard glazed window frames. The question has been asked what is the insurer to do with respect to returning the dwelling to pre event condition and how does this relate to the requirements of the Building Code of Australia. The original construction must comply with the Building Code of Australia – not necessarily the Australian Standards. The Building Code provides for installations that are what are called “deemed to comply” installations (often Case No: 261609 Determination Page 18 of 25 these reference the Australian Standards to advise that if you construct in accordance with the Australia Standards then you are in compliance with the Building Code) and alternate solutions. An alternate solution is allowed under the Building Code which may not comply with any Australian Standard. This alternate solution is only required to meet the performance requirements of the Building Code. The Building Code is designed to promote innovation in building design and construction. For windows for example the performance requirements of the Building Code of Australia are contained in section P2.2 Weatherproofing; “P2.2 Weatherproofing A roof and external wall (including openings around windows and doors) must prevent the penetration of water that could cause- (a) Unhealthy or dangerous conditions, or loss of amenity for occupants; and (b) Undue dampness or deterioration of building elements.” As the windows are not glazed an alternate solution would have been part of their application to Council. There is no requirement under the Building Code that requires all windows to be glazed. ... I would confirm that the contents of this quote [from FSP’s builder] in section B are commercially realistic prices to return the windows to pre event condition and that the installation is compliant with the requirements of the Building Code of Australia.” 50. Based on this report, the FSP in its further submission to FOS advised that: “[The FSP] submits that the applicant installed “ an alternative solution ” on construction, compliant with the Building Code of Australia. Consequent upon event-related damage to the windows, the applicant was cash settled for the reasonable cost of repairs and reinstatement of windows of the same type, standard, and specification as when new. [The FSP] submits that the allowance in t he [FSP’s builder] quotation provides for windows which will comply with the requirements of the Building Code of Australia, as advised by [FSP’s engineer].” 51. I am of the opinion that the FSP has met its obligation with respect to the replacement cost of windows, however, had it not been for its original advice to the Applicant that the windows did not meet the Australian Standards (based on the information the FSP received from its original glazier) the Applicant would not have sought an alternative installation method or materials for the damaged windows. 52. I note that should the Applicant be required by any code or standard to install a different type of window, the FSP will be required to meet any additional costs associated with the installation of same, given the FSP has now accepted that the original windows installed at the Applicant’s property met the required building codes/standards. Case No: 261609 Determination Page 19 of 25 Repainting of property exterior 53. The Applicant says the costs settled by the FSP in relation to repainting the exterior of her home are inadequate. She bases this on the quoted amount of $30m 2 and suggests the FSP’s advice that scaffolding used for roof and other exterior repairs could be utilised at the same time to repaint the exterior is not feasible. 54. Until building works are completed, she is unable to confirm the exact costs involved. 55. The FSP says the amount it has offered in settlement of this aspect is adequate based on the quotation provided to it by its builders. It says the scaffolding required to repaint the exterior would already be in place for other exterior repairs and thus, could be utilised to effect the exterior painting activities. 56. The Applicant suggests that painting of the exterior could not be completed simultaneously as the other repairs, as suggested by the FSP, due to dust and other debris which would fall onto the painted surface, causing an unacceptable finish. 57. I am of the opinion the FSP could only consider the Applicant’s suggestion on receipt of documented evidence to confirm the exact costs associated with the repainting of the exterior of her home with the same materials used as the exterior paint . The Applicant’s invoices and/or receipts should provide full details of equipment and materials required, in addition to any equipment which may already be in place for other external repairs, or any additional time this equipment was required to effect the painting. 58. As the FSP has had ample opportunity to have these costs quoted/substantiated by its own builders, the Applicant should only be required to produce her invoices or receipts for these costs without the FSP requiring any additional investigation or information to substantiate same. Permit costs 59. The Applicant says the costs settled by the FSP in relation to bin hire to remove the rubbish and debris associated with the repairs are not adequate. However, until building works are completed, she is unable to confirm the exact costs involved. 60. The FSP says the amount it has offered in settlement of this aspect is adequate based on the quotation provided to it by its builders. 61. I am of the opinion the FSP could only consider the Applicant’s suggestion on receipt of documented evidence to confirm the exact costs associated with the removal of rubbish and debris (bin hire). The Applicant’s invoices and/or receipts should provide full details of the services provided by her local council, ie: plan application etc. Case No: 261609 Determination Page 20 of 25 62. As the FSP has had ample opportunity to have these costs quoted/substantiated by its own builders, the Applicant should only be required to produce her invoices or receipts for these costs without the FSP requiring any additional investigation or information to substantiate same. Removal of rubbish and debris costs 63. The Applicant says the costs settled by the FSP in relation to obtaining relevant building permits from her local council are not adequate. However, until she is in a position to be able to submit the relevant plans to her council, she is unable to confirm the exact costs involved. 64. The FSP says the amount it has offered in settlement of this aspect is adequate based on the quotation provided to it by its builders. 65. I am of the opinion the FSP could only consider the Applicant’s suggestion on receipt of documented evidence to confirm the exact costs associated with obtaining the relevant pe rmits etc. The Applicant’s invoices and/or receipts should provide full details of what was hired, ie: bin(s), size of bin(s), time on site etc. 66. As the FSP has had ample opportunity to have these costs quoted/substantiated by its own builders, the Applicant should only be required to produce her invoices or receipts for these costs without the FSP requiring any additional investigation or information to substantiate same. Loss of rent 67. The Applicant has suggested that the loss of rent already paid by the FSP may not be adequate to effect repairs. She has, since 15 November 2012, been living back at her residence after she arranged for kitchen and bathroom repairs to be completed out of the settlement sum provided by the FSP. The Applicant says despite her and her children moving back to the property, the property still has no power or water facilities, however as the loss of rent payments ceased as of 15 November 2012, she could no longer afford to remain in the temporary accommodation and pay her mortgage as well. 68. The FSP says the loss of rent payments already paid to the Applicant are adequate and the final payment made was to cover 120 days which it says, its experts have suggested is the time it would take to repair the Applicant’s home. It also suggests that the Applicant has failed to mitigate her loss by not applying for relevant building permits through her council to start the repair process. 69. After reviewing the material and comments made by both parties on this issue, I am of the opinion that due to the normal financial constraints of the Applicant, she would not have been in a position to make application for any permits until she had received settlement from the FSP. Upon receiving this settlement, she immediately set about arranging for a termite condition Case No: 261609 Determination Page 21 of 25 report and to have the kitchen and bathroom repairs started by her own builder. 70. Upon receipt of the termite report, she was advised that termite activity had increased and required treatment due to the length of time the property had been unoccupied and subjected to usual weather conditions. This put the commencement date of repairs back by approximately two weeks. The Applicant has provided a copy of the termite report which confirms this information. 71. The FSP has not disputed this termite report and says only that it is not responsible for the costs associated with the termite treatment. 72. The Applicant says she is not seeking the costs for the termite treatment as she understands this is an expense she would have had to have incurred if the property had not been damaged by cyclone, however, she is seeking an additional two weeks loss of rent. 73. I am somewhat perplexed at the FSP’s opinion that the Applicant has not attempted to mitigate her loss when she has been proactively attempting to use the funds she has received from the FSP to effect repairs to the home as quickly as possible to make the property habitable so she could move out of the temporary accommodation and so as to not incur any additional costs. The fact remains that the FSP failed to adequately settle the Applicant for any part of her claim, other than loss of rent, until July 2012. 74. I am therefore of the opinion that the Applicant is entitled to an additional two weeks loss of rent. Conclusion 75. FOS acknowledges and accepts that during times of catastrophic weather events the resources of any FSP are stretched to cope with the unusually high influx of new claims and the additional demands of policyholders who have been displaced from their usual residences. The cyclone event the subject of t he Applicant’s claim certainly falls into this category. It is therefore reasonable to accept that some delays would occur during the claims handling process. 76. However, in this particular claim, I find the circumstances surrounding the delays and countless inspections/reinspections conducted by the FSP to address the Applicant’s concerns to be unreasonable. 77. The FSP in its NOR has suggested that these additional inspections of the property were due to: “various items [were] reported by the applicant on many occasions.” (Page 2, “ The Claim ”, paragraph 3) 78. After reviewing the material provided by both parties, I am not satisfied that the Applicant raised “various” items on “many” occasions, rather, the Case No: 261609 Determination Page 22 of 25 Applicant was not invited to attend the property when the initial builder’s assessment was conducted to ensure all items, or at least the majority of items, were addressed. In addition, other items were raised by the Applicant with the FSP during the cours e of the claim due to inadequate “make safe” repairs which resulted in additional damage being caused, and additional damage being caused generally due to the property being subjected to normal weather conditions for the area, in its cyclone damaged state. 79. I would suggest that many delays have been caused by the FSP and this in turn has caused a degree of stress and anxiety for the Applicant. Other factors to consider in the Applicant’s stress levels are the quality of “make safe” repairs and the lack of ca re taken by the FSP to safeguard the Applicant’s property from further damage, allowing third parties to enter the Applicant’s property in her absence and without her express permission to do so, the removal of repairs from the “SOW” which were later returned to the “SOW” and the Applicant’s belief that the FSP has provided an inadequate settlement. Compensation 80. I have given consideration to another aspect of the matter which concerns me. FOS Terms of Reference “ 9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute. b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non- financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; or (ii) in the case of a Dispute pertaining to an individual’s privacy r ights - injury has occurred to the Applicant’s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. ” 81. I raised the relevance of paragraph 9.3(b) with the FSP. In a detailed submission the FSP argued that no award should be made to the Applicant as the Applicant has not satisfied the requirement of paragraph 9.3(b)(i). 82. I do not accept the FSP’s submmission , given the facts as detailed above, regarding its handling of this claim. In its final settlement offer to the Applicant, the majority of items listed by the Applicant in the initial stages of the claim as having been excluded from the “SOW” , had been subsequently Case No: 261609 Determination Page 23 of 25 included by the FSP, indicating t he Applicant’s concerns were not only valid, but correct. 83. Additionally, the FSP agreed to settle the Applicant for 120 days (approximately 4 months) of temporary accommodation being the time its builder had estimated it would take to effect repairs to the property. However, the FSP did not settle the Applicant’s claim until Ju ly 2012, some 16 months after the event and the Applicant remained in temporary accommodation until 15 November 2012 approximately 21 months after the event. 84. I am therefore of the view that the FSP’s conduct of the matter has been such as to cause a good deal of physical inconvenience and time taken to resolve the matter, thus having an impact upon the Applicant’s expectation of enjoyment and peace of mind. 85. I need not set out the facts again. In my opinion the FSP has contributed to the Applicant’s stress due to its actions, after a catastrophic weather event which displaced her and her children from their home. 86. The FSP also relies upon its PDS in relation to consequential loss, which reads: “ We do not cover ... Extra costs following an insured incident Consequential losses or extra costs following an insured incident ...” 87. The Terms of Reference 9.3(c) says: “c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation for: (i) consequential financial loss; or (ii) non-financial loss, in a Dispute arising as a result of a claim on a General Insurance Policy that expressly excludes such liabili ty.” 88. As the FSP’s PDS does not “expressly” exclude non -financial loss, I consider the Applicant is entitled to receive compensation for the stress and anxiety caused by the FSP’s actions. 89. I therefore consider that the FSP should further compensate the Applicant by payment of the sum of $3,000 under this heading. Determination 90. On the basis of the available information I determine that the Applicant must produce documentation in the form of invoices and/or receipts to support her actual costs associated with: Case No: 261609 Determination Page 24 of 25  permit application etc with her local council  removal of rubbish and debris (bin hire) 91. On receipt of the invoices and/or receipts, the FSP will settle the Applicant any and all amounts above what it has already settled the Applicant for these costs (including GST) for the removal of rubbish and debris (bin hire) costs. 92. In relation to the timber beam, I also determine that if the timber beam is unable to be repaired, a detailed report from the Applicant’s builder providing what repairs were attempted, why the repairs were unsuccessful and any costs associated with the repair attempt, will need to be supplied to the FSP, in addition to an invoice or receipt for the replacement of the timber beam. On receipt of this information, the FSP is to pay to the Applicant any and all amounts over the amount already settled for the timber beam repairs, including GST, for the attempted repairs and replacement cost of the timber beam. 93. In relation to painting the exterior of the house, I also determine that if additional equipment and/or materials are required to effect the painting of the exterior, over and above what has already been settled by the FSP, then the Applicant is to provide her detailed invoices and/or receipts for these costs, including a detailed report from her builder explaining why the additional costs were incurred. On receipt of this information, the FSP is to pay to the Applicant any and all amounts over the amount already settled for the painting of the exterior, including GST. 94. I further determine that the FSP is to pay to the Applicant an additional two weeks loss of rent for the setback in having to have the property treated for termites before building works could begin. 95. The FSP is to make payment to the Applicant within 14 days of receipt of the invoices and/or receipts in relation to each item detailed in points 90 to 94, submitted by the Applicant, as they are received. That is, the FSP is not to withhold payment for any aspect detailed in points 90 to 94, pending receipt of all documentation for all aspects detailed in these points. 96. In addition, the FSP is to pay interest on all of these amounts from the date of its original settlement to the Applicant, being 3 July 2012, until the date of settlement of each aspect detailed in points 90 to 94. The applicable interest rate is calculated pursuant to Section 57 of the Insurance Contracts Act 1984 (Cth) in the sum of 6.75% given the Applicant would have had access to these settlement amounts at the time of the original settlement. 97. I further determine that the FSP has met its obligations with respect to the replacement of damaged windows, in that it has settled this aspect of the claim based on repairing/replacing the damaged items using similar materials to what was in place when new and prior to the loss. As such, no further payment will be required to the Applicant for this aspect, unless she is required to meet any new or additional building code or standard. Additional Case No: 261609 Determination Page 25 of 25 costs in this regard will need to be forwarded to the FSP for further consideration. 98. Pursuant to paragraph 9.3(b)(i) of the Terms of Reference, I also determine that the FSP should pay to the Applicant the sum of $3,000.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.