Determination 261351

Claim amount

FirmFinancial Firm (Unknown - Insurer)
Decided2012-09-13
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The landlord claimed that Cyclone Yasi lifted roof battens and required full roof replacement, while the insurer accepted other damage but denied the roof claim. AFCA preferred the insurer's engineers and found no evidence the roof was structurally damaged by the cyclone.

The applicant bears the onus of proving the loss falls within cover, and the expert evidence of batten uplift was not persuasive compared with the insurer's engineering evidence.

Issues

Subjects and remedies

natural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 261351 Determination Page 1 of 7 Case number: 261351 General Insurance - Domestic Insurance - Home Building – FSP Decision – Claim amount 11 September 2012 Background 1. The Applicant held a landlord insurance policy with the Financial Services Provider (FSP) for his duplex property. The relevant period of insurance operated for 12 months beginning from 9 February 2010. During this time, the building was insured up to a sum of $382,454. 2. The Applicant lodged a claim for damage sustained to the property as a result of Cyclone Yasi. The FSP accepted various parts of the claim but a dis pute has arisen regarding the Applicant’s claim for the roof to be replaced. 3. The FSP states there is no evidence the roof was structurally damaged as a result of the cyclone and has denied this aspect of the claim. The Applicant has disputed the FSP’s deci sion. Summary of Applicant ’s position 4. The Applicant has relied on three reports provided by engineer MV along with a number of photographs to substantiate his position that the roof battens have uplifted as a result of the cyclone. 5. As a result, the battens are structurally inadequate and therefore the roof requires replacement pursuant to MV’s recommendation. Summary of FSP’s position 6. The FSP has engaged a building consultant and a number of structural engineers to inspect the damage. They have all concluded that there is no evidence that the battens were damaged as a result of the cyclone. 7. Instead, the evidence supports the fact that water entered the ceiling cavity as a result of the relevant flatness of the roof and the omission of any sarking. Further, any gaps in the battens was due to: Determination Case No: 261351 Determination Page 2 of 7  The unseasoned hardwood which has subsequently shrunk and left minor gaps between the roof battens and trusses.  The strap bracing being installed in such a manner as to hold the edge of the battens higher than the trusses.  The failure to securely nail some trusses to the underlying batten. 8. The FSP therefore relies on the above and the following policy provisions to substantiate its position: “ General Policy Exclusions … We will not pay for: … 2. loss of or damage to your property caused by: a. … c. settling, shrinkage or expansion in the Building, its foundations, or any walls or pavements; … e. faulty materials, faulty workmanship, wrong or incorrect design, plan or specification or failure of design; f. wear, tear, rust, corrosion, depreciation, gradual deterioration, mildew, mould, dampness of atmosphere or variations in temperature.” Issue 9. Whether the FSP is required to replace the Applicant’s roof. Reasons for decision 10. As advised to the parties, due to the nature of the dispute, the matter has been referred to an Ombudsman for Determination in line with the Operational Guidelines to the Service’s Terms of Reference . This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 11. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. Expert Evidence 12. Approximately ten expert reports have been provided by the parties in respect to this issue. For the sake of brevity, I do not proposed to recite all of them at length, but will instead extract the relevant portions. Case No: 261351 Determination Page 3 of 7 13. With respect to the Applicant’s expert, MV, his conclusions are relatively brief so I consider it is worthwhile setting these out: [First report dated 5 May 2011] “Most of the battens in both units have separated from the trusses by up to 10mm, due to the uplift forces and are now structurally inadequate. Also the trusses are fixed in place by hold down battens, a practice which is no longer used.” [Second report dated 2 November 2011] “The site has been reinspected and photos taken with knives placed so as to clearly show the gap between the battens and the trusses. The initial inspection did not include an inspection of the roof sheets and this was also completed. The above photographs are only a small sample of all the batten connections, as it is not physically possible to inspect each one. There would be more battens and roof screws which have lifted in areas which were not accessible. Roof sheet laps have permanently lifted and the roof metal shows stress signs around the roof screws. The roof has leaked, most likely at the lifted sheet laps. Debris is and will be lodged between the sheets and future roof leaking will be an issue. Lifted roof sheet laps will provide the starting point for the whole roof sheet to be ripped off during the next cyclonic event.” [Third report dated 11 April 2012] “Previously two knife blades were able to easily fit in the gap between batten and truss chord. Due to walking on the roof to maintain the tarp and subsequent inspections, the gap has closed so only one knife blade fits. It appears that there has been some downward movement of the roof due to battens settling back down on the truss cords. This is evidenced by the reduced gap between some of the battens and truss chords. The roof also creaks when walked on and there is slight movement under foot in places. The frequent inspections of the roof tarp have supplied the downward point loads which have caused the batten/truss chord gap to close. If the gap was solely due to timber shrinkage, then the batten connection would be solid and no downward movement would be possible and the gap would remain the same. The fact there has been downward movement shows that the batten nail/screw has been pulled up by the wind load causing the timber fibres to shear around the fixing. This fixing has lost most of its structural strength and is now easily pushed back into place by the weight of a person walking on the roof.” 14. The FSP engaged a senior consulting builder (GD), two structural engineers (KA & BH) and another engineer (BS) to inspect and report on the roof. However, it appears the evidence from KA & BH (the FSP’s engineers) is th e most preferred by the FSP, particularly as their reports predominantly focused on this issue whereas GD and BS reported about the overall damage sustained to the Applicant’s property. 15. The FSP’s engineers’ main findings are set out in their report dated 1 7 July 2011 which contained the following information (summarised):  The roof pitch is relatively flat (estimated to be approximately 5 degrees). No roof sarking was located within the roof space. Case No: 261351 Determination Page 4 of 7  An attempt was made to inspect the roof structure from inside the roof space on 20 June 2011 but this was severely restricted. However, on 21 June 2011, a section of roof sheeting was removed to enable an external inspection of the roof framing to be undertaken.  As the roof battens appeared to have originally been unseasoned hardwood, long term drying would have the effect of shrinking the timber. Such a process generally results in minor gaps being visible between the battens and trusses.  The minor gaps that were visible between the battens and trusses are consistent with this drying process and not an indication of batten uplift.  Lifted battens will generally slide back into place with the weight of people walking over them during repairs. As such, they may visually appear to still be correctly fastened. With this in mind, a small crow bar was used to apply moderate force to the battens to determine if movement had occurred. No movement was able to be produced, which corroborates their opinion that the battens did not lift from the cyclone.  Moderately sized gaps were observed between the roof battens and the trusses where the location of the batten coincided with the strap bracing installed in the roof.  An inspection from on top of the roof sheeting revealed no loose roof sheets or any other signs of structural damage related to the cyclone. 16. Based on the above, the FSP’s engineers provided the following conclusions in their report: “While a gap was visible it was determined that this was due to the strapping holding the edge of the batten higher than the truss while the batten itself was fixed hard against the strap. It is our opinion that these gaps are due to the location of the strapping and are not due to lifting of the battens during TC Yasi. … It is our opinion that the water damage to the residence was most li kely due to the relatively flat roof and the lack of roof sarking, allowing water to enter the ceiling cavity through the gaps between the roof flashings and the roof sheeting. … It is our conclusion based on our inspections that there is no evident damage to the roof frame of the dwelling under study as a result of Cyclone Yasi.” 17. GD and BS could not find any evidence of roof damage from the cyclone during their various inspections. 18. The FSP’s engineers had an opportunity to review MV’s latest report and di d not consider MV’s observations and conclusions were meritorious for various reasons, which will be discussed further below. Case No: 261351 Determination Page 5 of 7 Analysis of the Evidence MV’s findings 19. The Applicant’s dispute is heavily reliant on MV’s evidence. In particular, MV in his initial report stated that there was separation between the trusses and the battens of up to 10mm. The FSP’s experts in their last report appeared to acknowledge that if separation to this degree or higher occurred, this would be more consistent with uplift. 20. However, these experts also identified that there was no evidence of the battens containing such a gap. For instance, MV’s second report showed two knives being wedged at various points as evidence that gaps of these lengths existed but as pointed out by KA & BH, the knives were not fully wedged in at those points. Further, by assuming a thickness of 2mm was prevalent for the knives’ blades, this would indicate the gap was at most approximately 4mm, which is consistent with their conclusions. 21. The Applicant has also provided a photograph of a roof batten and truss with a measuring tape placed alongside them. According to the Applicant, this photograph indicates a gap exists between 5 and 6mm. 22. I have reviewed this photograph and do not believe this is a conclusion that can be readily reached. The enhanced image of the tape alongside the gap does not confirm that it was placed flush with the relevant wood. 23. Regardless, even if one is to accept this proposition, the gap is not significant or inconsistent with the FSP’s experts’ conclusion, as it is a gap of 5mm to 6mm rather than 10mm. 24. The Applicant has attempted to argue that when this photograph was taken, the gap had decreased for the reasons detailed in MV’s latest report. As a result, the Applicant has inferred that the gap would have been greater than this and likely to have reached approximately 10mm. 25. I do not accept this for the following reasons:  MV based his conclusion on the fact that only one knife could be placed in gaps when previously two knives could. However, as identified by the FSP’s experts, this cannot be conclusive given it is unclear how much force was applied to the knives or whether they were applied at the same points.  It is unclear if the areas identified by MV as containing a smaller gap were the same as the previous areas referred to in his report. Even if they were, the FSP’s experts provided a salient point by stating that knife blades are not themselves necessarily reliable measuring tools.  There is no evidence to establish the gap actually measured by the Applicant was subject to any decrease. That is, it is unclear if the area photographed was the same area that MV identified contained a smaller gap. Case No: 261351 Determination Page 6 of 7 26. Further, even if I was to accept that the gaps have reduced, this is not necessarily inconsistent with the FSP’s position. The FSP’s experts identified that if the gaps did occur due to uplift, then it is expected these gaps would have closed completely upon being subject to roof traffic, as uplift would have weakened the battens’ connecti on to the truss. However, if it was shrinkage, then it is more likely the gaps would not have been closed but were instead reduced because their connection would not have been compromised. 27. I accept the FSP’s experts’ explanation in this regard is logical a nd reasonable. 28. MV has also referred to the roof creaking, which the FSP’s experts have rebutted by stating this could be due to many other reasons, such as atmospheric conditions. In my opinion, a roof creaking would not be unusual and by itself a symptom of cyclone damage. In this regard, I prefer the FSP’s experts’ comments. 29. Given this, I am not satisfied MV’s observations and conclusions have provided persuasive evidence that the gaps between the battens and trusses were due to uplift. The Balance of the Evidence 30. There are also other factors which I consider support the FSP’s experts’ conclusions. These are: a. Although some damage had occurred to the roof structure (such as missing soffit lining), all of the FSP’s experts agreed that there was no evident damage to the roof. In particular, GD was given permission to inspect the ridge capping that was covered by tarpaulin and found no evidence of damage there beyond some missing screws. b. The sole basis MV has stated there was structural damage was due to the gap between the battens and truss, which I have not accepted is conclusive for the reasons discussed. c. MV did not comment at all on the FSP’s experts’ conclusion that the location of the strapping holding the edge of the batten contributed to the gap. This e xplanation from the FSP’s experts appears reasonable on the face of it and therefore persuasive given the lack of rebuttal. d. The FSP’s experts made a fairly significant point about their inability to loosen the batten when applying moderate pressure with the crowbar. I accept this would not have likely occurred if the battens had been loosened by uplift as submitted by MV. e. The FSP’s loss adjuster provided a pertinent observational point, namely that the wind was not substantive enough to damage an aerial mounting bracket, the Foxtel satellite dish or the clip for the aluminium external blinds. Accordingly, it seems unusual that despite this, it was significant enough to structurally damage the battens. Case No: 261351 Determination Page 7 of 7 31. I prefer the FSP’s experts’ evidence as it is more consis tent with the overall factual circumstances surrounding the loss. In contrast, for the reasons already discussed, I am not satisfied that MV’s conclusion is as consistent or supported by the evidence. 32. Based on this, I therefore accept the FSP’s submission that there is no evidence the roof was structurally damaged by the cyclone. It therefore follows that I am satisfied the FSP is entitled to deny the Applicant’s request for the repairs to the roof be completed in line with MV’s recommendations. Determination 33. On the basis of the available information I determine that the FSP is entitled to deny the Applicant’s claim with respect to the roof’s replacement.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.