Summary

The insured's roof repairs, costing about $11,300 after a February 2011 storm, were declined under maintenance, defect and wear and tear exclusions. AFCA found the exclusions were not established and ordered the insurer to pay 50% of the repair costs, $5,665, with interest.

The structural defect and wear and tear exclusions were not made out, so AFCA fairly split the repair cost 50% under the Terms of Reference.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 260647 Determination Page 1 of 6 Case number: 260647 General Insurance - Domestic Insurance - Home Building and Contents - Storm - Loss due to failure of maintenance or inherent defect or fair wear and tear - FSP Decision - Denial of claim 23 October 2012 Background 1. The Applicants held a home building and contents policy with the Financial Services Provider (FSP), which was in force at the time of the loss. The policy covered defined events only. 2. In February 2011, the Applicants lodged a claim for storm damage to the roof of the insured property. 3. The FSP denied the claim on the basis that the damage was caused by lack of maintenance, faulty design or workmanship or inherent defect, all of which are excluded under the policy. 4. The Applicants disputed this decision and referred the matter to this Service. On 16 July 2012, the matter was the subject of a Recommendation. After analysing all of the material then available, a Case Manager recommended that the FSP was not obliged to indemnify for the Applicants’ claim for repairs to his roof, pursuant to the terms and conditions of the policy. 5. The Applicants have not accepted this Recommendation and have since made a number of further submissions. I refer to these submissions below. Summary of Applicants ’ p osition 6. In February 2011, there was a heavy storm, which caused water to enter the house and damage the interior. When they tried to find the entry point, they noticed some roof tiles had broken corners due to rusted steel nails. 7. After lodging the claim, the FSP sent assessors 3 – 4 times to inspect the damage and took long to assess and finalise the claim. 8. Ultimately the Applicants engaged a roofing expert (DWR) to repair their roof at a cost of $11,300. Determination Case No: 260647 Determination Page 2 of 6 9. The FSP has denied liability to reimburse the Applicants for DWR’s invoice, apparently on the basis of a report from the FSP’s appointed repairer (HR) and also some comments in DWR’s invoices. 10. The Applicants dispute the proposition advanced by HR that the damage to the roof was caused by a lack of maintenance. They also dispute the suggestion from DWR that the damage had been caused by the use of incorrect nails. They point out that such nails had been commonly used when the roof was installed 30 years earlier. 11. They also deny any inference which arises from the HR report, that there had been previous problems with the roof. The only time the Applicants had applied silicone to the roof was immediately after 4 February 2011. 12. In a most recent submission to this Service, the male Applicant states that since he was obliged to give up work 11 years ago, he has had others to do the maintenance for him. Summary of FSP’ s position 13. The FSP contends that the roof damage is not storm related. The large volume of water from the February 2011 storm may have led to water ingress, but it did not cause the tiles to crack. It only highlighted a pre- existing problem. 14. HR inspected the damage and said that steel nails fixing the roof tiles had rusted, expanded and caused the roof tiles to crack. 15. It does not agree that the problems with water ingress occurred only after the storm in February 2011. A s per HR’s report, s ome cracked tiles had been sealed in the past, which indicated this was an ongoing issue. 16. The Applicants rely on DWR’s invoice to say that the roof repairs were not maintenance related. However, DWR says the installation of the roof used incorrect nails which rusted and caused the tiles to break. 17. It understands it was common practice to use steel nails for tile fixing at the time the house was built. However, DWR ’s comments confirm that there was an inherent defect with the use of steel nails in the installation of the roof. 18. Once there was a problem with cracked roof tiles, the Applicants were presented with a maintenance issue which needed repair. 19. Accordingly and as per the policy exclusions, the FSP is entitled to deny the claim due to:  wear and tear, lack of maintenance or an inherent defect, and  water entering the house as a result of failure to perform adequate maintenance, a structural defect or faulty design or workmanship. Case No: 260647 Determination Page 3 of 6 20. In relation to the time taken in the claims process, the FSP notes this relates to the repairs of the internal damage. These repairs could only commence once the Applicants ’ repairer DWR completed the roof repairs. The roof repairs were completed over four months after the alleged storm event. 21. It took some time to prepare a scope of works which satisfied the Applicants. However, the internal repairs were completed by 15 November 2011 and the Applicants have not raised any further issues in relation to these repairs. 22. The FSP relies on the following policy provisions: “ Home insurance - What IS covered  Storm, hail or rainwater ... General exclusions applicable to your policy You are not covered under any section of this policy for damage, loss or liability caused by, arising from or involving any of the following.  Water entering your home:  as a result of your failure to perform adequate maintenance on your home, or a structural defect, or faulty design or workmanship, ...  Wear and tear, lack of maintenance or inherent defect. ” 23. The FSP also disputes the recent claims made by the Applicants that after the storm, the Applicants had applied silicone to broken tiles. The FSP points out that the Applicants had never made any such statement earlier in the proceedings. Issue 24. Whether the FSP is entitled to deny liability for the Applicants’ claim pursuant to the terms and conditions of the policy. Reasons for Decision 25. I am satisfied a full exchange of information has taken place between the parties and each party has had the opportunity to address the issues raised. 26. It appears to be accepted that there was a severe storm immediately prior to the making of this claim. Nowhere in the FSP’s extensive material is there any denial of that fact. 27. I also make the assumption, which I consider is reasonable based upon all of the material, that there had been no previous ingress of water into the ceilings of the Applicants’ home. The FSP makes no mention of any earlier claims, and there is simply no evide nce to suggest that there had been Case No: 260647 Determination Page 4 of 6 earlier damage caused by any defect in the roof, other than the disputed evidence as to silicone referred to in paragraph 37. 28. The claim for internal damage has been accepted and finalised to the Applicants’ satisfaction. My task therefore is simply to consider the claim in respect to the repairs which were carried out to the roof and which have been paid for, thus far, by the Applicants. 29. If one considers the policy wording, it is clear the only basis upon which the claim may be brought is that the damage was caused by storm, hail or rainwater. As commented above, there does not appear to be any dispute that there was indeed a significant storm preceding the claim. 30. I therefore reach the conclusion that the Applicants have satisfied the onus which is upon them of establishing that there was damage to the roof caused by storm or very heavy rainwater. 31. The next question however is whether the exclusions which are applicable pursuant to the policy, and which are clearly set out, are relevant in this case. 32. In a somewhat confusing response, the FSP appears at various times to rely upon several grounds of exclusion. 33. At one point, it alleges that the damage to the roof has been brought about by a failure by the Applicants to perform adequate maintenance. 34. The evidence for this is that HR discovered a number of cracked tiles when HR inspected the roof after the storm. 35. Both HR and the Applicants’ tiler DWR appear to be in agreement that the tiles are cracked as the result of nails which had been used to affix the tiles to the roof, when the roof was constructed some 32 years earlier. 36. In their report, HR refer to the fact that there had been silicone applied to various tiles and, not unreasonably, they raised the question as to whether this demonstrates that there had been previous problems with the roof and that the Applicants, being aware of those problems, had, either personally or through others, applied silicone to previously cracked tiles. 37. But as to this suggestion, the male Applicant is quite adamant. He states that the only time he applied silicone was immediately after the storm in an endeavour to stop further water entering the house. I accept what the male Applicant says as to this subject and ultimately I find that there is no evidence of previous repairs to the roof, which would have demonstrated that the Applicants were conscious of faults which may have developed in the roof. 38. The FSP also relies upon a suggestion principally contained in the reports from DWR, that the cause of the cracking has been the use of nails. DWR suggest that these nails were inappropriate for the purpose. Case No: 260647 Determination Page 5 of 6 39. I think it clear that what DWR are suggesting is that at the present time, the use of such nails would not be followed as good practice when laying tiles. But they also (and this is a point which the male Applicant frequently comments upon) concede that when the roof was constructed the use of such nails was common. 40. I find it very hard to accept that a roof which has apparently remained watertight for 32 years, has been suffering from a structural defect, or faulty design or workmanship, throughout that period. Surely, it must ultimately be recognised that however one might, in 2012, deplore the use of nails to affix tiles, if it was a common practice 30 years earlier, and if the roof has remained watertight during that period, it must be recognised that the use of such nails was considered appropriate at the time that this roof was constructed. 41. I am, therefore, not able to accept the FSP’s contention th at the roof was suffering from a structural defect or faulty design or workmanship. Neither can I treat the use of the nails as an “inherent defect” whilst I recognise that they were rusting and apparently the expansion of the nails due to rusting has been the cause of the cracking of the tiles. 42. This then leaves the question as to whether the loss was due to “wear and tear”. I find this difficult to determine. On the one hand it seems plain that an inspection of the roof has revealed that the nails were rusting as might be expected after such a period of time. On the other hand, in the absence of any evidence whatever to the contrary, I accept that the roof had never demonstrated any evidence that it was not watertight notwithstanding the extensive time since the roof had been built. What we are left with is an outcome whereby immediately following a heavy storm, cracks in the tiles have apparently become worse as a result of which water has entered. Terms of Reference 43. Paragraph 8.2 of the Terms of Reference for this Service is in the following form: “8.2 Dispute resolution criteria Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all the circumstances, having regard to each of the following: a) legal principles; b) applicable industry codes or guidance as to practice; c) good industry practice; and d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS will not be bound by these).” 44. Had I believed that the Applicants had been aware of the problems on the roof before the storm, I would have reached a different conclusion, but I accept his statement that since he retired from work 11 years ago, he has been engaging others to carry out his maintenance. Case No: 260647 Determination Page 6 of 6 45. In all the circumstances I conclude that it is fair and reasonable that the FSP reimburse the Applicants for 50% of the total costs of repairs to the roof (in the sum of $11,330). Determination 46. I determine that the FSP should reimburse the Applicants in the sum of $5,665 being half of costs expended by them in repair to the roof. 47. I further determine that the FSP pay interest on the said sum of $5,665 from 16 November 2011 until the date of settlement.