Home / Financial Firm (Unknown - Insurer) / Determination 260171

Determination 260171

Denial of claim for replacement of collapsed bridge

FirmFinancial Firm (Unknown - Insurer)
Decided2012-05-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$17,370
SourceAFCA PDF

Summary

The complainants' timber bridge collapsed under a water truck and the FSP declined the claim for the bridge itself under exclusions for structural fault, lack of maintenance, and wear, tear and rot. AFCA preferred the FSP's independent engineer and found the FSP entitled to decline.

The independent engineering evidence established that structural fault, lack of maintenance and gradual deterioration caused the collapse, which the policy excludes.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 260171 Determination Page 1 of 7 Case number: 260171 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion/ condition 15 May 2012 Background 1. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the Background as set out in the Recommendation is accurate and is as follows. 2. The Applicants have Home Building and Contents cover under a Rural Plan policy of insurance. The policy covers structures at the property including a bridge. 3. On 5 July 2011 the Applicants‟ bridge was damaged when a water delivery truck drove over it. The FSP engaged an engineer to assess the cause of the bridge‟s failure. 4. The FSP accepted other liabilities and the truck damage but declined the claim for bridge damage on the basis that the damage arose from the excluded causes of structural defect, failure to maintain and wet or dry rot. 5. The Applicants dispute the declinature of the bridge claim on the basis that the bridge was maintained regularly and was not in breach of any Council requirements. 6. The Applicants did not agree with the FSP‟s decision, hence the dispute, which was the subject of a Recommendation. The Recommendation was in favour of the FSP and was not accepted by the Applicants. The FSP accepted the Recommendation. In the circumstances, the matter has been referred to me for Determination. Summary of Applicants’ p osition 7. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied with the Applicants‟ position as set out in the Recommendation is accurate and is as follows. 8. The Applicants have enclosed a tax invoice dated 10 March 2010 that indicates the purchase of timber in the sum of $1,083.06. Determination Case No: 260171 Determination Page 2 of 7 9. The Applicants have enclosed letter dated 11 July 2011 from a sawmilling company “P” quoting $17,369.71 (inclusive of GST) for the replacement of the bridge. 10. The Applicants rely on letter dated 10 September 2011 from P which provided the following information:  P originally constructed the bridge and has been in the timber industry for 50 years.  In March 2010, the Applicants purchased twelve planks of wood to replace timber considered to be showing signs of deterioration. This formed part of the regular maintenance carried out to the bridge.  P also inspected the girders and decking planks and advised the Applicants the girders were in good condition and should last another ten years.  The bridge was well maintained as the Applicants replaced planks as they showed signs of deterioration. 11. P constructed the bridge and specialises in bridge building and timber. He is often called to advise on the construction of farm bridges. The Applicants deny that the bridge had a construction or workmanship fault that led to its failure. 12. The Applicants state the bridge was last inspected in March 2010 when 12 planks were replaced and at the same time an inspection of the girders was also carried out. 13. The Applicants submit the bridge was maintained in good condition. The Applicants would have rectified any deterioration had they become aware of it. 14. The Applicants note the submissions from the FSP and its engineer and respond as follows:  The deterioration of the right hand girder came from the inside out and this would not have been detected by inspections. Further, another engineer consulted by the Applicants stated the only way to confirm the deterioration would have been to drill holes in the girder. The action of drilling such a hole would have led to water entering the structure and further deterioration.  At the time of constructing the bridge in 1983 there were no council engineering requirements and the bridge was constructed to the best- known methods. There is further no requirement in the policy that bridges are subject to an engineer‟s design or supervision , only a reference to all structures conforming to Council requirements.  The Applicants dispute that P did not have sufficient expertise. P has been in the timber industry for more than 50 years and has an expert understanding of timber. Case No: 260171 Determination Page 3 of 7  The Applicants contend they have done everything a reasonable person would be expected to do in the circumstances.  The liability section of this claim has been accepted by the FSP and therefore the claim for the bridge should also be accepted. 15. The Applicants rejected the Recommendation and wrote an email dated 13 April 2012, which essentially reiterated their position. They also said: „We would like to add that while the engineer suggested that the timber could be flaked off in the hand, this we feel was totally due to the breakage of the girder under the weight of the overloaded water truck”. Summary of FSP’ s position 16. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the FSP‟s position as set out in the Recommendation is accurate and is as follows. 17. The FSP relies on the following policy terms and conditions: “What You are Insured against This policy insures You against accidental damage, burglary and theft occurring during the Period of Insurance. You have insurance for: i) Your Home if „Building‟ is shown on the certificates of insurance ... What is not insured This policy does not insure You against ... 2 damage directly or indirectly caused by or arising out of: ii) A structural fault, faulty design or faulty workmanship iii) Lack of maintenance (for example, failure to clean out gutters) iv) Mildew or mould or wet or dry rot” 18. The FSP relies on an engineer‟s report dated 31 August 2011 from which I note the following: a. The remains of the bridge were inspected on 11 August 2011. b. The old bridge was built in 1983 and an engineering service was not consulted in the design of the bridge. c. The Applicants replaced planks on the top of the bridge during the years but did not replace the girders. d. P had last advised the Applicants after a visual inspection, that the two main girders were in good condition and would not require a replacement. Case No: 260171 Determination Page 4 of 7 e. The bridge has been subject to flooding three times throughout its lifetime. f. The girder to the right hand side of the bridge fractured when the truck was on it and the truck and the bridge collapsed. g. The engineer saw the remains of the bridge, which consisted of planks supported by circular shaped timber girders of 500mm diameter. The planks and left hand side girder were in fair condition. h. However, the whole right hand side girder has been fractured into three pieces. Significant deterioration and rotting was observed to the internal and external section of the timber girder. A hollow section was observed within the centre of the cross section of the girder, indicating that the deterioration was extended from the internal to the external face of the timber member. i. The decay has occurred over an extended period of time. The timber girder has deteriorated to the extent that fragments could be easily peeled off from the cross section with bare hands. j. Photographs accompanied the report. k. There was no load carrying capacity assessed and provided to warn any party of the maximum weight that a vehicle can have when it crosses the bridge. l. The failure of the original timber bridge is a direct result of inadequate design, lack of professional input, absence of load rating assessment, significant deterioration of the timber girder over the past years and lack of proper inspection and maintenance methods. m. The collapse event would have occurred sooner or later due to the significant deterioration of the timber girders. n. The decay in the timber is believed to have been happening over many years and is not of a sudden or expected nature. 19. The FSP relies on its expert report that outlines the failure of the bridge due to structural fault, faulty design, lack of maintenance, wet or dry rot and/or the damage occurred due to wear, tear, gradual deterioration and wet/dry rot. These causes of loss are specifically excluded under the policy of insurance. 20. The FSP contends that the engineer‟s report should be preferred over P‟s report. P stated that the girders were in good condition that is in stark contrast to the engineer‟s opinion and photographs evidencing deterioration. 21. The FSP notes the Applicants ‟ submissions and responds as follows: a. The engineer has appropriate experience and qualifications to provide an opinion. b. The Applicants refer to another engineer but have failed to provide an opinion from that engineer. The FSP sought a written report or opinion by the engineer from the Applicants who have not provided same. Case No: 260171 Determination Page 5 of 7 c. Given the state of the girders, it was not reasonable to only replace the top planks. d. The Applicants have not disputed the cause of the collapse. e. The FSP states that it would have been reasonable for the Applicants to engage a professional with appropriate qualifications to inspect the bridge and undertake an assessment of the load carrying capacity of the bridge. f. The policy excludes damage directly or indirectly arising out of wear and tear, gradual deterioration and wet or dry rot. Accordingly it contends it is entitled to decline the claim because the cause of damage is specifically excluded under the policy. g. The cover provided for the truck damage is irrelevant to the dispute as it is under a separate policy containing different terms and conditions. h. Whilst the FSP disputes the Applicants performed all reasonable steps to ensure the bridge was maintained, it is irrelevant to the dispute as the cause of t he bridge‟s collapse is undisputed and specifically excluded. 22. The FSP accepted the Recommendation and responded to the Applicants‟ email in its letter dated 1 May 2012. The FSP reiterated the opinion of its engineer who “found the timber could be easily fl aked off in the hand because the decay of the girder had occurred for an extended period of time.” Issue 23. Whether the FSP was entitled to decline the Applicants‟ claim for the bridge. Reasons for Decision 24. There has been an exchange of material between each party, and I am satisfied each party has had an opportunity to reply to the issues raised. 25. Each FOS case is decided on its merits, taking into account the facts of the case. I have reviewed all the material submitted by the parties both before and after the Recommendation was issued, in order to reach my decision. I will only refer to the relevant submissions and materials raised. 26. The Applicants have established a claim in first instance as the bridge has collapsed and caused damage to it and to the truck and other consequential losses. 27. The only issue remaining in dispute is the claim to pay for the replaced bridge. Case No: 260171 Determination Page 6 of 7 28. The FSP has rejected the claim to replace the bridge and relies on an exclusion clause which says it does not have to pay damage directly or indirectly caused by or arising out of: i) A structural fault, faulty design or faulty workmanship ii) Lack of maintenance (for example, failure to clean out gutters) iii) Mildew or mould or wet or dry rot” 29. Further, under Para 10, its policy does not insure the Applicants against “Wear, tear, rust, corrosion or gradual deterioration.” 30. In these circumstances, the onus is on the FSP to establish, on the balance of probabilities, that it can rely on these clauses and reject the claim. 31. In rejecting the claim, the FSP relies on an engineer, C, who looked at the remains of the bridge on 11 August 2011 and took some photographs. 32. The Applicants reject this opinion and rely on a report of P, a sawmilling company who built the bridge years earlier. 33. I have read carefully the reports from P and from the FSP engineer, C. I have also studied the photographs taken by C. 34. On the basis of what C says the FSP can establish that the bridge collapsed for a variety of reasons, which are set out earlier in this Determination. In my view, the report justifies the FSP position as it establishes the bridge collapsed through bad structure and design in the first place, lack of maintenance to the girders and wear, tear and gradual deterioration of the right hand girder. Even though the Applicants had done the right thing and maintained the planks, the girders had not been properly inspected and maintained. 35. P says he had inspected the girders and decking planks in March 2010. He said the girders were in good condition and would last another ten years. He advised some planks were to be replaced and they were replaced. 36. I have looked carefully at the photographs taken by C some 17 months after that inspection by P. I can see the significant deterioration and rotting which C says is to the internal and external section of the timber girder. Accordingly, in my view, a proper inspection would have seen the damage to the girder. C said the decay had occurred over an extended period of time. 37. C also says the inspection of the timber bridge should have included not only the structural condition of the bridge but also its load capacity. If this was done, it is not mentioned by P nor was there a sign to warn the truck driver of the maximum weight of a vehicle before it could safely cross the bridge. 38. On balance, I prefer the report of C who is an independent structural and civil engineer to the report of P a manager from the sawmilling company. Further, P may not have a completely independent view having built the bridge in the first place. Case No: 260171 Determination Page 7 of 7 39. The Applicants refer to the opinion of another engineer but I cannot give this weight in the absence of a written report from that engineer. 40. After the Recommendation, the Applicants also say that the flaking of the timber was due to the breakage of the girder under the weight of the truck. However, I do not believe the photographs bear out that contention. Further, C does say the decay had occurred over an extended period of time. 41. Finally, there is no merit in the argument that the FSP must pay this claim as it has paid out on the liability claim. The nature of the claims and the types of losses are materially different and subject to different policy terms and conditions. Determination 42. On the basis of the available information and for the reasons stated, I determine that the FSP was entitled to decline the claim on the basis of the policy terms and exclusions.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.