Claim declined as flood, not flash flood and stormwater run-off, after Brisbane River inundation
Text of the determination
Case No: 260107 Determination Page 1 of 13
Case number: 260107
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
28 September 2012
Background
1. The Applicants insured their home and contents with the Financial Services
Provider (FSP). The relevant period of insurance operated for twelve months
beginning from 18 August 2010. During this period, the building was insured
up to a sum of $498,000 and the contents for $89,000.
2. On 17 January 2011, the Applicants lodged a claim under the policy due to
extensive water inundation to their home in Oxley following severe weather
events in Queensland.
3. The FSP denied the claim on the basis the damage was due to “flood”. The
Applicants, through their solicitors, has disputed this.
4. For the sake of simplicity, reference to the Applicants will include their legal
representatives.
5. Both the Applicants and the FSP have provided detailed submissions on the
relevant issues. For the sake of brevity, the Panel will only briefly summarise
these submissions given all of the material made available has been
exchanged with the other party. Summary of Applicants ’ position
6. The Applicants have both provided Statutory Declarations from which the
Panel notes:
On Tuesday 11 January 2011 the Applicants looked out over the back
fence towards the east end of the park behind the property. There was
either a sewer line or a storm water drain and the water was being
forced out about a foot in the air.
On Tuesday morning 11 January 2011 it was raining and by the
evening there was water in the yard.
The Applicants evacuated early Wednesday morning around 1.30am.
The Applicants returned at 5.00am Wednesday morning at which time
they discovered 6 inches of water in the house.
The water probably rose 2.8m into the house.
Determination
Case No: 260107 Determination Page 2 of 13
7. The Applicants submit the following as alternative arguments in response to
the FSP‟s decision:
a. The Applicants contend that the definition of flood and flash flood,
layout of the policy, payment caps and the FSP‟s failure to properly
inform them of the flood exclusion definition does not meet the
requirements of Section 35 of the Act. The Applicants state that flood is
a prescribed event for the purposes of Section 35 of the Act, as defined
by Section 14 of the Insurance Contracts Regulations 1985 (“the
Regulat ions”). The Corporations Act 2001 further requires clear,
concise and effective disclosure. The Applicants argue the policy
should revert to the standard cover allowed for under the Act and
Regulations. The Applicants further rely on an expert report in support
of their position that the wording is too unclear to meet the requirement
of Section 35 of the Act or the clear, concise and effective disclosure
under the Corporations Act.
a. The FSP breached its duty of utmost good faith by failing to ensure the
policy the Applicants had taken out was suitable to their needs.
b. The damage was due to “Flash flood and stormwater run - off”, which is
an insured event. In particular, the inundation was due to heavy rain
that fell from 4.00am on 11 January 2011 which resulted in the
Wivenhoe Dam operators elevating their strategy to W4. This decision
resulted in massive discharges of water into the Brisbane River that
ultimately inundated their property. The dam operating engineers‟
actions cannot be deemed an intervening cause based on the
evidence.
c. The Applicants note that the evidence provided indicates that 17.5-23.5
hours elapsed before the dam releases reached Oxley causing sudden
flood. Anything less than 24 hours should be deemed as flash flood
under the policy. This in formation corroborates the Applicants‟ version
that inundation commenced at 1.30am on Wednesday 12 January 2011
and the conclusion of hydrologist “SC” that inundation of the residence
occurred at 3.30am on the Wednesday.
d. The FSP is unable to discharge its onus in establishing the loss was
caused by “flood”.
8. The Applicants seek to be indemnified for their claim.
Summary of FSP’s position
9. In response to the Applicants‟ arguments, the FSP submits the following:
a. The policy structure and layout meets the requirements of Section 35 of
the Act and the requirement for clear, concise and effective disclosure
under the Corporations Act. The flood exclusion is noted several times
in both the PDS and the Certificate of Insurance. Further, the report
relied upon by the Applicants states the PDS flood exclusion could be
understood by a person of average intelligence and education.
Case No: 260107 Determination Page 3 of 13
b. The Applicants were aware that flood was not covered and in fact
attempted to obtain flood cover.
c. The duty of utmost good faith does not extend to an obligation to
ensure a policy is suitable to the Applicants‟ needs.
d. The inundation arose from rainfall that occurred more than 24 hours
earlier and falls under the policy definition of „Flood‟. Further, the
releases from the Wivenhoe Dam would not have had as significant an
impact on the inundation of the Applicants‟ property as the earlier
releases.
10. The FSP relies on an assessor‟s report which notes the reserve for building
costs were listed as $80,000 and contents at $25,000.
11. The FSP relies on a number of hydrology reports authored by SC. The Panel
notes the following from the information provided by SC:
The level of the subject property varies between 4.5m AHD and 7.4m
AHD. The terrain underneath the house of the insured property is a
level of approximately 6.25m AHD. It should be noted the FloodWise
Report relied upon by SC did not provide a habitable floor level but did
indicate the property was in a waterway corridor. The stormwater
infrastructure in the street includes curb and channelling and
stormwater pits. There is a localised channel to the north of the
property. The terrain generally slopes form the insured property to this
channel to the north. Local run-off from the subject property would
travel towards this channel which leads to Oxley Creek and ultimately
to the Brisbane River.
The rainfall around the time of inundation was insufficient to cause
inundation by stormwater run-off or local run-off. The inundation is
consistent with the rising river levels. The terrain does not suggest the
property is particularly vulnerable to either stormwater or other local
run-off during rainfall intensities experienced in January 2011.
The Brisbane River was elevated prior to the releases on 11 January
2011. The Bremer River contributed in the order of 15-25% to the
Brisbane River‟s peak flow.
A small proportion of the overall depth of the Brisbane River prior to
6.00am on 12 January 2011 may be partially attributable to the rain that
fell in the Bremer River catchment on 11 January 2011. However, the
overwhelming influence on the flooding of the Brisbane River was the
rain that fell days earlier over the Wivenhoe Dam catchment and
subsequent releases from the dam.
The data indicates that by 3.30am on 12 January 2011 the Brisbane
River levels backing up into Oxley Creek reached a level of
approximately 6.25m AHD which would be sufficient to inundate the
ground level of the insured home. This is also consistent with the
Applicants‟ comments that water first came into the house sometime
during Tuesday evening or early Wednesday morning.
Case No: 260107 Determination Page 4 of 13
The normal Brisbane River Level is 1.5m AHD and the approximate
benchmark level is 6.2m AHD. The time the Brisbane River reached the
approximate benchmark level is 3.45am on Wednesday 12 January
2011. The effect of the W4 releases first reached the vicinity of the
property at 2.39pm on Tuesday 11 January 2011 but the river level
would first inundate the benchmark level at 6.52am on Wednesday 12
January 2011. The approximate contribution of the W4 releases to the
benchmark level of inundation was 0.3m and the peak contribution of
the W4 releases to the inundation was 1m. The approximate peak
contribution of W4 releases to Brisbane River level pre-4.00am on
Wednesday 12 January 2011 was 0.4m. SC then goes on to state that
the river level at 4am on 12 January 2011 would have been
approximately 5.9m AHD which is 0.3m below the benchmark level.
With the W4 releases the river level at 4am on 12 January 2011 would
have been approximately 6.2m AHD which is 0m below the benchmark
level.
The releases from the Wivenhoe would have reached the Applicants‟
property between 15 hours and 30 minutes and 20 hours and 30
minutes. This means that the inundation due to the Wivenhoe Dam
may have occurred after 4.30am which does not fall within the 24 hour
period. Alternatively, the earlier releases are a proximate cause of the
damage.
12. The FSP contends that the rainfall on 9 and 10 January 2011 was more
significant than the rainfall on 11 January 2011 and this rainfall occurred
over 24 hours prior to the inundation. The W4 releases could not have
caused the inundation because the property was inundated before those
increased releases reached the home. Alternatively, even if the W4 releases
were the sole cause of the loss, the event is not a „flash flood and
stormwater run- off‟ event as the Wivenhoe Dam operators are an intervening
cause.
13. The FSP also notes that the Applicants received $12,500 from the FSP‟s
compassionate fund.
14. The FSP relies on a number of hydrology reports authored by SC and the
following policy provisions to deny the Applicants ‟ claim:
Page 4 of the Certificate of Insurance (COI)
“ What optional covers are included and not included
Home Contents
...
Flood and storm surge not included not included...”
Pages 10-12 of the PDS
“ Words / terms with special meanings
Word / term Meaning
Case No: 260107 Determination Page 5 of 13
...
Flood Rising water which enters your home as a result of it
running off or overflowing from any origin or cause.
This policy does not cover flood unless we have
agreed and it is shown on your certificate of insurance.
Flash flood and
stormwater run - off
A sudden flood caused by heavy rain that fell no more
than 24 hours prior to the flash flood or stormwater
run - off .
...
Storm A violent disturbance of the atmosphere associated
with strong winds including a cyclone, lightening,
heavy rain, hail or snow, but not continuous bad
weather by itself.
...”
Pages 17-18 of the PDS
“ Insured events you are covered for
Damage caused by weather...
What is covered What is not covered
Storm Loss or damage:
caused by rain, hail or snow
after it has reached the
ground...
...
Flash flood and stormwater run-off
A sudden flood caused by heavy rain
that fell no more than 24 hours prior to
the flash flood or stormwater run - off
Loss or damage caused:
by flood...
...”
Page 27 of the PDS
“ Your home
The most we will pay you for home claims
What is covered What is not covered
Flash flood and stormwater run-off
We will pay up to 50% of your home sum
insured or $25,000, whichever is higher.
...
...”
Page 32 of the PDS
Case No: 260107 Determination Page 6 of 13
“ Your contents
The most we will pay you for contents claims
What is covered What is not covered
... ...
Flash flood and stormwater run-off
We will pay up to 50% of your contents
sum insured or $25,000, whichever is
higher, but not exceeding your contents
sum insured.
...
...”
Issues
15. Whether the FSP was entitled to rely on the policy terms and conditions.
16. Whether the FSP was entitled to decline the Applicants‟ claim for damage
arising from water inundation.
Reasons for decision
17. Due to the nature of the dispute, the parties have been informed that the
matter has been referred to the Panel for Determination in line with the
Operational Guidelines to FOS‟s Terms of Reference. This dispute has not
been the subject of a FOS Recommenda tion and has proceeded directly to
Determination.
18. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and a
representative with extensive experience in consumer claims.
19. It is appropriate to consider the issues under the various headings.
Whether the FSP is entitled to rely on the policy terms and conditions
20. The Applicants contend that the definition of flood is too broad, too difficult to
comprehend and that the FSP has not met its obligations under Section 35
of the Act to “clearly inform” them of what is and is not covered under the
policy.
21. The Panel has previously considered this issue for the FSP‟s policy. It is
satisfied that the two events (“flood” and “flash flood and stormwater run- off”)
can be distinguished.
22. In simple terms, the policy provides cover where damage is attributable to a
flood caused by a run-off of stormwater after a period of excessive rainfall
Case No: 260107 Determination Page 7 of 13
and occurring within 24 hours of the rain event. It does not cover any other
type of flood.
23. The PDS has an index on the inside cover which highlights the areas of the
policy in which the policyholder finds information. Included in this is
“Words/terms with special meanings” on page 9, for which definitions of
relevant terms in the policy are provided. Flood is included in this, together
with the qualification that:
“... This policy does not cover flood unless we have agreed and it is shown on
your certificate of insurance. ”
24. In addition to this, page 53 directs th e reader to “Flood and storm surge”,
which is explained under the broader definition of “Optional covers for extra
peace of mind”. This section explains that:
“... This policy does not cover flood unless we have agreed and it is shown on
your certificate of insurance. ”
25. It is further noted that the Certificate of Insurance also clearly stated there
was no flood cover.
26. It is well established that a proper reading of Section 35(2) of the Act
requires that the relevant exclusions or limitations be in clear and
unambiguous language and in a manner which a person of average
intelligence and education is likely to have little difficulty in finding and
understanding if that person reads the policy. The Panel is satisfied that if
the Applicants had read the policy they would have been informed of the
relevant exclusions and limitations. The Panel is satisfied the FSP has met
its obligation to clearly inform.
Whether the FSP was entitled to decline the Applicants ’ claim for damage
arising from water inundation
The Evidence
27. The Applicants have provided evidence that water entered the yard of the
insured property on the evening of 11 January 2011. The Applicants
evacuated at 1.30am and returned at 5.00am to discover 6 inches of water in
their property.
28. SC has provided differing information regarding the timing of the inundation.
In the first instance, SC indicated that by 3.30am on 12 January 2011 the
Brisbane River levels backing up into Oxley Creek reached a level of
approximately 6.25m AHD which would be sufficient to inundate the ground
level of the insured home. In the Key Conclusion Statement, SC indicated
the Brisbane River reached the approximate benchmark level of 6.2m AHD
at 3.45am on 12 January 2011 although he said the inundation above
benchmark was 0.00 at 4.00am 12 January 2011.
Case No: 260107 Determination Page 8 of 13
Releases from Wivenhoe Dam
29. The central issue for determination in this matter is whether the property was
inundated by flash flood which is defined under the policy as:
“A sudden flood caused by heavy rain that fell no more than 24 hours prior
to the flash flood or stormwater run- off” .
30. On 21 May 2012, FOS issued a memorandum to all relevant stakeholders
advising of the broad approach adopted in considering a proximate cause of
the implementation of the W4 Wivenhoe Dam strategy that led to the
development of a flood wave in the Brisbane River. This in turn led to
significant inundation of properties below the Wivenhoe Dam in the time after
the W4 strategy was invoked.
31. In that memorandum FOS advised that after considerable deliberation, the
Panel formed the view that the heavy rain occurri ng from 4.00am on 11
January 2011 and in particular the heavy rain between 4.00am and 8.00am
was a proximate cause of the W4 strategy being invoked. This was therefore
a proximate cause or trigger that led to the flooding of many of the properties
along the lower reaches of the Brisbane River.
32. The approach was reached after consideration of all material that had been
provided to FOS by stakeholders and contrary to the comments of the FSP
in its reference documents, after the FSP was given the opportunity of
addressing the issue of the relationship between the heavy rain that fell from
4.00am on 11 January 2011, the adoption of the W4 strategy and the
particular wording of its policy.
33. The Panel noted in relation to the broad approach that each individual
dispute will depend upon the basis of the individual and unique factors
relevant to the dispute. In that regard, the parties were invited to make
further submissions in relation to the disputes before FOS.
34. In view of the issues arising, detailed further submissions were made by the
FSP on 14 June 2012. Included with the submissions were the following
documents:
a. A reference document for disputes relating to Queensland Floods (this
is a general reference document). This sets out various submissions
the FSP makes in relation to a number of topics. Not all issues raised in
the reference document appear in the current dispute.
b. Letter from SC attaching a key information sheet for the Applicants‟
property dated 7 June 2012.
c. WT Report “Investigation of the January 2011 Inundation event –
Brisbane” dated March 2011.
d. Statement from SC dated 7 June 2012.
35. A supplementary Reference document was issued on 11 July 2012.
Essentially the FSP maintains that on any reasonable view, the damage
sustained to the downstream properties was the combined effect of all of the
Case No: 260107 Determination Page 9 of 13
rainfall that had fallen commencing from 9 January 2011 (or earlier) and not
just the rain that had fallen from 4.00am on 11 January 2011. Insofar as the
proximate cause is not the first or last cause of the loss but the dominant or
effective direct or efficient cause, and by adopting a commonsense
evaluation of the facts, the FSP argues that the proximate cause could not
be the rain that fell from 4.00am on 11 January 2011. Instead, on any
reasonable view, the damage sustained was the combined effect of all of the
rainfall that had fallen.
36. There is no dispute that heavy rain fell over the Wivenhoe Dam catchment
area and in fact parts of the Brisbane River from 4.00am on 11 January
2011.
37. The information exchanged and relied upon by all parties and contained in
the SEQWater report dated 2 March 2011 identifies the rapid increase in the
inflows to the Wivenhoe Dam commencing from about 4.00am. The
information confirms that the inflows into the dam had been steadily
decreasing from as early as 8.00am and steadily from 3.00pm 10 January
2011 to 2.00am on 11 January 2011. In the Panel‟s view, prior to the
commencement of the heavy rainfall on or about 4.00am on 11 January
2011, the dam releases were being managed consistent with the inflows.
38. The information exchanged confirms that prior to approximately 4.00am on
11 January 2011; the dam releases were being managed at the W3 strategy.
Whilst the W3 strategy had led to an increase in the levels of the Brisbane
River, the W3 strategy was designed to avoid where possible inundation of
the properties below the Wivenhoe Dam by flooding from the Brisbane River.
39. The rainfall data and information relied upon by the parties and not disputed,
confirms that there were two significant rai nfall spikes with the rain that fell
from 9 to 10 January 2011 being the “first spike” and the rain that fell on 11
January 2011 being the “second spike”. This is confirmed by the FSP‟s
hydrologist in his statement of 7 June 2012.
40. There is no dispute that following the second spike, that is, the heavy rainfall
that commenced on or about 4.00am on 11 January 2011 over the
Wivenhoe Dam, that the W4 release strategy was adopted.
41. The information provided by SEQWater confirms that from about 4.00am on
11 January 2011, there was a significant increase in the inflows to the
Wivenhoe Dam and that as a result of the significant increase in the inflows,
by 8.00am on 11 January 2011, the Wivenhoe Dam‟s operating engineers
were left with no alternative but to adopt the W4 release strategy.
42. The information provided by the parties and in particular the information
provided by the FSP‟s hydrologist confirms that the increased releases from
the Wivenhoe Dam after the adoption of the W4 strategy led to the
development of a flood wave that ultimately caused the flooding from the
Brisbane River downstream of the Wivenhoe Dam.
Case No: 260107 Determination Page 10 of 13
43. The Panel agrees that in determining the proximate cause of the inundation
of the properties, it is necessary to look at the effective or dominant cause of
the inundation. The Panel agrees with the FSP‟s submission that the
proximate cause is the cause determined by a commonsense valuation of
the relevant facts. In the event that there are two or more proximate causes,
one within the policy and the other excluded, the policy does not respond.
The proximate cause is not determined by identifying the last event or final
trigger, but by determining what is the dominant, effective, direct or efficient
cause of the loss.
44. The Panel is satisfied having considered all of the information that prior to
the rainfall commencing on or about 4.00am on 11 January 2011, there had
been a steady reduction in the inflows to the Wivenhoe Dam from about
3.00pm on 10 January 2011. At that time, the Wivenhoe Dam was being
managed at the W3 release strategy. This release strategy whilst causing
some increase in the level of the Brisbane River was being maintained with
the aim of avoiding flooding of the areas below the Wivenhoe Dam wherever
possible.
45. The FSP has maintained that the impact on the dam from the rainfall that fell
in the early hours of 11 January 2011 was only 29% whilst 71% of the
volume inflow came from rain that fell on 9 and 10 January 2011 or earlier.
The FSP maintains that to find that the rainfall from 4.00am on 11 January
2011 is a proximate cause, is without foundation as such an approach
produces an entirely artificial outcome.
46. Alternatively, the FSP argues that if it is accepted that there are other
proximate causes apart from the implementation of the W4 strategy, then the
Wayne Tank principle applies, as the earlier rain was also a proximate cause
of the inundation. The FSP also argues that with respect to the inundation
caused by the W4 release that was due to an intervening decision by the
dam operators and is not covered under the current policy.
47. With respect to the last argument, the Panel is of the view that it was not an
intervening factor that led to the adoption of the W4 strategy, but a fact that
the level the dam had reached by 8.00am on 11 January 2011 left the
operating engineers with no alternative but to adopt the W4 strategy at that
time.
48. With respect to the argument regarding the Wayne Tank principle and the
rainfall prior to the 24 hour period being a contributing factor or proximate
cause of the loss, the Panel notes the policy wording provides cover for
sudden flood caused within 24 hours of heavy rainfall. The relevant question
is whether the inundation is caused by heavy rain that fell no more than 24
hours prior to the flood inundating the risk address.
49. Whilst the Panel accepts there had been a significant impact on the levels of
the Wivenhoe Dam by the rainfall that had commenced falling on or about 9
January 2011 (and earlier), the Panel is satisfied that having regard to all of
the information exchanged and the relevant legal principles, that the heavy
rain that commenced falling at or about 4.00am on 11 January 2011 was a
Case No: 260107 Determination Page 11 of 13
proximate or effective cause of the adoption of the W4 strategy. This in turn
caused the inundation of many of the properties below the Wivenhoe Dam
as a result of the flood wave created by the increased releases. The Panel is
satisfied the proximate cause of the inundation of the Applicants‟ property
was the heavy rain that fell from approximately 4.00am 11 January 2011
over the Wivenhoe dam and Brisbane River combined with the heavy rain
the fell over the Bremer River from 6.00am that day. The Applicants‟
property
50. SC‟s statement, particularly his updated key conclusions attachment of 7
June 2012, indicates the effect of the W4 releases first reached the vicinity of
the Applicants‟ property at 2.39pm on 11 January 2011 . The releases
reached benchmark level by 3.45am on 12 January 2011 and were
estimated by SC to be 0.00m above the benchmark level as at the relevant
time of 4.00am on 12 January 2011. The Panel notes that the peak height
above the benchmark level was 3m. SC identified this peak inundation
occurred at approximately 3.01am on Thursday 13 January 2011.
51. The Panel accepts that these assessments are necessarily approximations
and may not be entirely accurate. This is particularly in circumstances where
SC appears to have provided different heights in relation to the key
benchmark level (6.2 and 6.25m AHD) and different times for reaching the
benchmark level (3.30am 11 January 2011 at 6.25m AHD and most recently
3.45am at 6.2m AHD)
52. The Panel notes that the June 2012 Key Conclusion Statement by SC
appears to vary from his conclusions of 16 November 2011. The information
provided by this June 2012 Key Conclusion Statement appears to focus on
the Brisbane River level and its inundation height. In contrast the November
2011 statement addresses the back-flow and inundation from Oxley Creek.
The Panel further notes the Key Conclusion Statement refers to the water
reaching the benchmark level at 3.45am 12 January 2011 but being at 0.00
above benchmark at 4.00am.
53. In light of these issues, the Panel Chair Ombudsman attended a site meeting
on 21 September 2012. Present were the Applicants and a representative of
the FSP. The house is built on a slab and it is about equal in height as the
freestanding garage. The Applicants explained the water was in the garden
(which abuts the garage – which contained a large number of items such as
furniture and tools, all of which were water damaged) by about 7.00pm on 11
January 2011. The Applicants confirmed that when they left their home,
water had not entered the home, but on return at approximately 5.00am on
12 January 2011, the water was roughly 250mm deep inside the lower part
of the house. They also explained the water outside was actually higher than
this with the walls acting as a kind of levee.
54. Based on the information exchanged the Panel accepts on the balance of
probabilities, that most likely that the Applicants‟ property was inundated
above floor level (benchmark) prior to 4.00amon 12 January 2011.
Case No: 260107 Determination Page 12 of 13
55. In the absence of precise assessment of the level of inundation (the Panel
does not accept SC‟s estimate of 0.00 at 4.00am is in this instance reliable in
view of the inconsistencies previously outlined) the Panel accepts it would be
fair in the circumstances to assess the inundation before 4.00am on 12
January 2011 to a level of 100mm above floor throughout the home and
garage. In respect of damage to items outside the house and garage the
Panel notes the air conditioner and hot water service were below benchmark
level and should be treated as total losses. The FSP will need to assess if
the water pump that was on a stand should also be covered.
Quantum
56. The Renewal Certificate of Insurance for the relevant period provides a sum
insured of $498,000 for the home with contents of $89,000. Pursuant to the
policy cap for the insured event of “Flash flood and stormwater runoff”, the
FSP is liable for up to 50% of the sum insured for the building and 50% of
the contents sum insured. This is of course subject to the applicable
excesses.
57. Given the time since the loss was sustained, the Panel accepts that the
parties may be unable to provide an exact estimate of the total loss
sustained, or a breakdown of that loss. The assessment report pursuant to a
site inspection on 4 February 2011 indicated a reserve of $80,000 for the
house and $25,000 for the contents. The report described inundation of the
entire lower level and described the damage as „severe‟.
58. The Applicants and the FSP are asked to work cooperatively together to
establish the extent of the loss sustained to the first level of the property as a
result of inundation to a level of 100mm throughout the house and garage
and to reach an agreement as to cost of repairs and replacement of the
various contents lost. The Panel accepts that inundation at this level would
cause significant damage and loss of contents.
59. The Panel accepts the FSP is not responsible for damage that occurred after
4.00am on 12 January 2011 as such inundation would be outside the
relevant 24 hour period.
60. In respect to interest accruing on these payments, the FSP has argued that
interest is only payable from the date from which it was unreasonable to
withhold payment. The FSP maintains that it is entitled to a reasonable
period to investigate and determine its position, and given the complex
nature of the flood disputes, the delays are not unreasonable. Further,
complex situations require substantial periods of time for independent bodies
such as the Queensland Flood Commission of Inquiry and FOS, to make
conclusions on the issues in dispute.
61. The FSP maintains that it did not act unreasonably in this dispute and
therefore interest is not payable. Alternatively if some period of interest is to
be awarded it should be reduced to account for the substantial delays
through th e course of the process which were not the FSP‟s fault.
Case No: 260107 Determination Page 13 of 13
62. Section 57 of the Act requires interest be paid when it becomes
“unreasonable for the insurer to have withheld payment”. An examination of
relevant case law indicates that most probably, interest will be awarded from
either when an insurer first emphatically denied liability or disputed a matter,
or from when in the normal course of events the claim should have been
paid if liability had not been disputed.
63. In this dispute the Panel accepts that the FSP was entitled to withhold
payment of the settlement monies until such time as it had properly
investigated the dispute and made its decision as to liability.
64. The FSP made its original decision to deny the claim after receiving relevant
assessment reports, hydrology reports and other information. The FSP was
aware of the terms of its policy and aware of the relevant provisions under
which liability might arise and chose to deny the claim, having reviewed
those relevant provisions and the evidence available to it.
65. In the Panel‟s view, at that point the FSP has made its decision on the claim
and it is appropriate that from that time interest be paid unless it can be
established that the Applicants had withheld information from the FSP that
would have led to an alteration of its decision.
66. Accordingly, the Panel determines that it is appropriate that the FSP in this
dispute pay interest from the day upon which the FSP determined to deny
liability of the Applicants‟ claim, until payment of the claim.
67. Insofar as the FSP may have made payment of a compassionate sum to the
Applicants, FOS does not have jurisdiction to deal with this payment but
acknowledges that the FSP, given the terms on which the compassionate
payment was made, may be entitled to deduct this payment from any
settlement sum.
Determination
68. The FSP is to meet the cost of repairs incurred by the Applicants and the
cost of the replacement of items damaged as a result of the „flash flood‟
inundation to a level of 100mm above floor throughout the home and garage.
69. Insofar as the FSP is to cash settle the claim, the FSP is to pay interest from
29 March 2011 (being the date of rejection of the claim) to date of payment
of the claim, in accordance with Section 57 of the Act.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.