Determination 260107

Claim declined as flood, not flash flood and stormwater run-off, after Brisbane River inundation

FirmFinancial Firm (Unknown - Insurer)
Decided2012-10-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Floodwaters from Brisbane River and Wivenhoe Dam releases damaged the complainants' home. The FSP denied the claim as flood; AFCA found flash flood cover applied only to damage up to 100mm above floor, with interest from denial, and the FSP may deduct its compassionate payment.

Under the proximate cause test, heavy rain from 4.00am on 11 January 2011 triggered the W4 release strategy, so the inundation fell within the 24-hour flash flood definition.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 260107 Determination Page 1 of 13 Case number: 260107 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 28 September 2012 Background 1. The Applicants insured their home and contents with the Financial Services Provider (FSP). The relevant period of insurance operated for twelve months beginning from 18 August 2010. During this period, the building was insured up to a sum of $498,000 and the contents for $89,000. 2. On 17 January 2011, the Applicants lodged a claim under the policy due to extensive water inundation to their home in Oxley following severe weather events in Queensland. 3. The FSP denied the claim on the basis the damage was due to “flood”. The Applicants, through their solicitors, has disputed this. 4. For the sake of simplicity, reference to the Applicants will include their legal representatives. 5. Both the Applicants and the FSP have provided detailed submissions on the relevant issues. For the sake of brevity, the Panel will only briefly summarise these submissions given all of the material made available has been exchanged with the other party. Summary of Applicants ’ position 6. The Applicants have both provided Statutory Declarations from which the Panel notes:  On Tuesday 11 January 2011 the Applicants looked out over the back fence towards the east end of the park behind the property. There was either a sewer line or a storm water drain and the water was being forced out about a foot in the air.  On Tuesday morning 11 January 2011 it was raining and by the evening there was water in the yard.  The Applicants evacuated early Wednesday morning around 1.30am.  The Applicants returned at 5.00am Wednesday morning at which time they discovered 6 inches of water in the house.  The water probably rose 2.8m into the house. Determination Case No: 260107 Determination Page 2 of 13 7. The Applicants submit the following as alternative arguments in response to the FSP‟s decision: a. The Applicants contend that the definition of flood and flash flood, layout of the policy, payment caps and the FSP‟s failure to properly inform them of the flood exclusion definition does not meet the requirements of Section 35 of the Act. The Applicants state that flood is a prescribed event for the purposes of Section 35 of the Act, as defined by Section 14 of the Insurance Contracts Regulations 1985 (“the Regulat ions”). The Corporations Act 2001 further requires clear, concise and effective disclosure. The Applicants argue the policy should revert to the standard cover allowed for under the Act and Regulations. The Applicants further rely on an expert report in support of their position that the wording is too unclear to meet the requirement of Section 35 of the Act or the clear, concise and effective disclosure under the Corporations Act. a. The FSP breached its duty of utmost good faith by failing to ensure the policy the Applicants had taken out was suitable to their needs. b. The damage was due to “Flash flood and stormwater run - off”, which is an insured event. In particular, the inundation was due to heavy rain that fell from 4.00am on 11 January 2011 which resulted in the Wivenhoe Dam operators elevating their strategy to W4. This decision resulted in massive discharges of water into the Brisbane River that ultimately inundated their property. The dam operating engineers‟ actions cannot be deemed an intervening cause based on the evidence. c. The Applicants note that the evidence provided indicates that 17.5-23.5 hours elapsed before the dam releases reached Oxley causing sudden flood. Anything less than 24 hours should be deemed as flash flood under the policy. This in formation corroborates the Applicants‟ version that inundation commenced at 1.30am on Wednesday 12 January 2011 and the conclusion of hydrologist “SC” that inundation of the residence occurred at 3.30am on the Wednesday. d. The FSP is unable to discharge its onus in establishing the loss was caused by “flood”. 8. The Applicants seek to be indemnified for their claim. Summary of FSP’s position 9. In response to the Applicants‟ arguments, the FSP submits the following: a. The policy structure and layout meets the requirements of Section 35 of the Act and the requirement for clear, concise and effective disclosure under the Corporations Act. The flood exclusion is noted several times in both the PDS and the Certificate of Insurance. Further, the report relied upon by the Applicants states the PDS flood exclusion could be understood by a person of average intelligence and education. Case No: 260107 Determination Page 3 of 13 b. The Applicants were aware that flood was not covered and in fact attempted to obtain flood cover. c. The duty of utmost good faith does not extend to an obligation to ensure a policy is suitable to the Applicants‟ needs. d. The inundation arose from rainfall that occurred more than 24 hours earlier and falls under the policy definition of „Flood‟. Further, the releases from the Wivenhoe Dam would not have had as significant an impact on the inundation of the Applicants‟ property as the earlier releases. 10. The FSP relies on an assessor‟s report which notes the reserve for building costs were listed as $80,000 and contents at $25,000. 11. The FSP relies on a number of hydrology reports authored by SC. The Panel notes the following from the information provided by SC:  The level of the subject property varies between 4.5m AHD and 7.4m AHD. The terrain underneath the house of the insured property is a level of approximately 6.25m AHD. It should be noted the FloodWise Report relied upon by SC did not provide a habitable floor level but did indicate the property was in a waterway corridor. The stormwater infrastructure in the street includes curb and channelling and stormwater pits. There is a localised channel to the north of the property. The terrain generally slopes form the insured property to this channel to the north. Local run-off from the subject property would travel towards this channel which leads to Oxley Creek and ultimately to the Brisbane River.  The rainfall around the time of inundation was insufficient to cause inundation by stormwater run-off or local run-off. The inundation is consistent with the rising river levels. The terrain does not suggest the property is particularly vulnerable to either stormwater or other local run-off during rainfall intensities experienced in January 2011.  The Brisbane River was elevated prior to the releases on 11 January 2011. The Bremer River contributed in the order of 15-25% to the Brisbane River‟s peak flow.  A small proportion of the overall depth of the Brisbane River prior to 6.00am on 12 January 2011 may be partially attributable to the rain that fell in the Bremer River catchment on 11 January 2011. However, the overwhelming influence on the flooding of the Brisbane River was the rain that fell days earlier over the Wivenhoe Dam catchment and subsequent releases from the dam.  The data indicates that by 3.30am on 12 January 2011 the Brisbane River levels backing up into Oxley Creek reached a level of approximately 6.25m AHD which would be sufficient to inundate the ground level of the insured home. This is also consistent with the Applicants‟ comments that water first came into the house sometime during Tuesday evening or early Wednesday morning. Case No: 260107 Determination Page 4 of 13  The normal Brisbane River Level is 1.5m AHD and the approximate benchmark level is 6.2m AHD. The time the Brisbane River reached the approximate benchmark level is 3.45am on Wednesday 12 January 2011. The effect of the W4 releases first reached the vicinity of the property at 2.39pm on Tuesday 11 January 2011 but the river level would first inundate the benchmark level at 6.52am on Wednesday 12 January 2011. The approximate contribution of the W4 releases to the benchmark level of inundation was 0.3m and the peak contribution of the W4 releases to the inundation was 1m. The approximate peak contribution of W4 releases to Brisbane River level pre-4.00am on Wednesday 12 January 2011 was 0.4m. SC then goes on to state that the river level at 4am on 12 January 2011 would have been approximately 5.9m AHD which is 0.3m below the benchmark level. With the W4 releases the river level at 4am on 12 January 2011 would have been approximately 6.2m AHD which is 0m below the benchmark level.  The releases from the Wivenhoe would have reached the Applicants‟ property between 15 hours and 30 minutes and 20 hours and 30 minutes. This means that the inundation due to the Wivenhoe Dam may have occurred after 4.30am which does not fall within the 24 hour period. Alternatively, the earlier releases are a proximate cause of the damage. 12. The FSP contends that the rainfall on 9 and 10 January 2011 was more significant than the rainfall on 11 January 2011 and this rainfall occurred over 24 hours prior to the inundation. The W4 releases could not have caused the inundation because the property was inundated before those increased releases reached the home. Alternatively, even if the W4 releases were the sole cause of the loss, the event is not a „flash flood and stormwater run- off‟ event as the Wivenhoe Dam operators are an intervening cause. 13. The FSP also notes that the Applicants received $12,500 from the FSP‟s compassionate fund. 14. The FSP relies on a number of hydrology reports authored by SC and the following policy provisions to deny the Applicants ‟ claim: Page 4 of the Certificate of Insurance (COI) “ What optional covers are included and not included Home Contents ... Flood and storm surge not included not included...” Pages 10-12 of the PDS “ Words / terms with special meanings Word / term Meaning Case No: 260107 Determination Page 5 of 13 ... Flood Rising water which enters your home as a result of it running off or overflowing from any origin or cause. This policy does not cover flood unless we have agreed and it is shown on your certificate of insurance. Flash flood and stormwater run - off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run - off . ... Storm A violent disturbance of the atmosphere associated with strong winds including a cyclone, lightening, heavy rain, hail or snow, but not continuous bad weather by itself. ...” Pages 17-18 of the PDS “ Insured events you are covered for Damage caused by weather... What is covered What is not covered Storm Loss or damage:  caused by rain, hail or snow after it has reached the ground... ... Flash flood and stormwater run-off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run - off Loss or damage caused:  by flood... ...” Page 27 of the PDS “ Your home The most we will pay you for home claims What is covered What is not covered Flash flood and stormwater run-off We will pay up to 50% of your home sum insured or $25,000, whichever is higher. ... ...” Page 32 of the PDS Case No: 260107 Determination Page 6 of 13 “ Your contents The most we will pay you for contents claims What is covered What is not covered ... ... Flash flood and stormwater run-off We will pay up to 50% of your contents sum insured or $25,000, whichever is higher, but not exceeding your contents sum insured. ... ...” Issues 15. Whether the FSP was entitled to rely on the policy terms and conditions. 16. Whether the FSP was entitled to decline the Applicants‟ claim for damage arising from water inundation. Reasons for decision 17. Due to the nature of the dispute, the parties have been informed that the matter has been referred to the Panel for Determination in line with the Operational Guidelines to FOS‟s Terms of Reference. This dispute has not been the subject of a FOS Recommenda tion and has proceeded directly to Determination. 18. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 19. It is appropriate to consider the issues under the various headings. Whether the FSP is entitled to rely on the policy terms and conditions 20. The Applicants contend that the definition of flood is too broad, too difficult to comprehend and that the FSP has not met its obligations under Section 35 of the Act to “clearly inform” them of what is and is not covered under the policy. 21. The Panel has previously considered this issue for the FSP‟s policy. It is satisfied that the two events (“flood” and “flash flood and stormwater run- off”) can be distinguished. 22. In simple terms, the policy provides cover where damage is attributable to a flood caused by a run-off of stormwater after a period of excessive rainfall Case No: 260107 Determination Page 7 of 13 and occurring within 24 hours of the rain event. It does not cover any other type of flood. 23. The PDS has an index on the inside cover which highlights the areas of the policy in which the policyholder finds information. Included in this is “Words/terms with special meanings” on page 9, for which definitions of relevant terms in the policy are provided. Flood is included in this, together with the qualification that: “... This policy does not cover flood unless we have agreed and it is shown on your certificate of insurance. ” 24. In addition to this, page 53 directs th e reader to “Flood and storm surge”, which is explained under the broader definition of “Optional covers for extra peace of mind”. This section explains that: “... This policy does not cover flood unless we have agreed and it is shown on your certificate of insurance. ” 25. It is further noted that the Certificate of Insurance also clearly stated there was no flood cover. 26. It is well established that a proper reading of Section 35(2) of the Act requires that the relevant exclusions or limitations be in clear and unambiguous language and in a manner which a person of average intelligence and education is likely to have little difficulty in finding and understanding if that person reads the policy. The Panel is satisfied that if the Applicants had read the policy they would have been informed of the relevant exclusions and limitations. The Panel is satisfied the FSP has met its obligation to clearly inform. Whether the FSP was entitled to decline the Applicants ’ claim for damage arising from water inundation The Evidence 27. The Applicants have provided evidence that water entered the yard of the insured property on the evening of 11 January 2011. The Applicants evacuated at 1.30am and returned at 5.00am to discover 6 inches of water in their property. 28. SC has provided differing information regarding the timing of the inundation. In the first instance, SC indicated that by 3.30am on 12 January 2011 the Brisbane River levels backing up into Oxley Creek reached a level of approximately 6.25m AHD which would be sufficient to inundate the ground level of the insured home. In the Key Conclusion Statement, SC indicated the Brisbane River reached the approximate benchmark level of 6.2m AHD at 3.45am on 12 January 2011 although he said the inundation above benchmark was 0.00 at 4.00am 12 January 2011. Case No: 260107 Determination Page 8 of 13 Releases from Wivenhoe Dam 29. The central issue for determination in this matter is whether the property was inundated by flash flood which is defined under the policy as: “A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run- off” . 30. On 21 May 2012, FOS issued a memorandum to all relevant stakeholders advising of the broad approach adopted in considering a proximate cause of the implementation of the W4 Wivenhoe Dam strategy that led to the development of a flood wave in the Brisbane River. This in turn led to significant inundation of properties below the Wivenhoe Dam in the time after the W4 strategy was invoked. 31. In that memorandum FOS advised that after considerable deliberation, the Panel formed the view that the heavy rain occurri ng from 4.00am on 11 January 2011 and in particular the heavy rain between 4.00am and 8.00am was a proximate cause of the W4 strategy being invoked. This was therefore a proximate cause or trigger that led to the flooding of many of the properties along the lower reaches of the Brisbane River. 32. The approach was reached after consideration of all material that had been provided to FOS by stakeholders and contrary to the comments of the FSP in its reference documents, after the FSP was given the opportunity of addressing the issue of the relationship between the heavy rain that fell from 4.00am on 11 January 2011, the adoption of the W4 strategy and the particular wording of its policy. 33. The Panel noted in relation to the broad approach that each individual dispute will depend upon the basis of the individual and unique factors relevant to the dispute. In that regard, the parties were invited to make further submissions in relation to the disputes before FOS. 34. In view of the issues arising, detailed further submissions were made by the FSP on 14 June 2012. Included with the submissions were the following documents: a. A reference document for disputes relating to Queensland Floods (this is a general reference document). This sets out various submissions the FSP makes in relation to a number of topics. Not all issues raised in the reference document appear in the current dispute. b. Letter from SC attaching a key information sheet for the Applicants‟ property dated 7 June 2012. c. WT Report “Investigation of the January 2011 Inundation event – Brisbane” dated March 2011. d. Statement from SC dated 7 June 2012. 35. A supplementary Reference document was issued on 11 July 2012. Essentially the FSP maintains that on any reasonable view, the damage sustained to the downstream properties was the combined effect of all of the Case No: 260107 Determination Page 9 of 13 rainfall that had fallen commencing from 9 January 2011 (or earlier) and not just the rain that had fallen from 4.00am on 11 January 2011. Insofar as the proximate cause is not the first or last cause of the loss but the dominant or effective direct or efficient cause, and by adopting a commonsense evaluation of the facts, the FSP argues that the proximate cause could not be the rain that fell from 4.00am on 11 January 2011. Instead, on any reasonable view, the damage sustained was the combined effect of all of the rainfall that had fallen. 36. There is no dispute that heavy rain fell over the Wivenhoe Dam catchment area and in fact parts of the Brisbane River from 4.00am on 11 January 2011. 37. The information exchanged and relied upon by all parties and contained in the SEQWater report dated 2 March 2011 identifies the rapid increase in the inflows to the Wivenhoe Dam commencing from about 4.00am. The information confirms that the inflows into the dam had been steadily decreasing from as early as 8.00am and steadily from 3.00pm 10 January 2011 to 2.00am on 11 January 2011. In the Panel‟s view, prior to the commencement of the heavy rainfall on or about 4.00am on 11 January 2011, the dam releases were being managed consistent with the inflows. 38. The information exchanged confirms that prior to approximately 4.00am on 11 January 2011; the dam releases were being managed at the W3 strategy. Whilst the W3 strategy had led to an increase in the levels of the Brisbane River, the W3 strategy was designed to avoid where possible inundation of the properties below the Wivenhoe Dam by flooding from the Brisbane River. 39. The rainfall data and information relied upon by the parties and not disputed, confirms that there were two significant rai nfall spikes with the rain that fell from 9 to 10 January 2011 being the “first spike” and the rain that fell on 11 January 2011 being the “second spike”. This is confirmed by the FSP‟s hydrologist in his statement of 7 June 2012. 40. There is no dispute that following the second spike, that is, the heavy rainfall that commenced on or about 4.00am on 11 January 2011 over the Wivenhoe Dam, that the W4 release strategy was adopted. 41. The information provided by SEQWater confirms that from about 4.00am on 11 January 2011, there was a significant increase in the inflows to the Wivenhoe Dam and that as a result of the significant increase in the inflows, by 8.00am on 11 January 2011, the Wivenhoe Dam‟s operating engineers were left with no alternative but to adopt the W4 release strategy. 42. The information provided by the parties and in particular the information provided by the FSP‟s hydrologist confirms that the increased releases from the Wivenhoe Dam after the adoption of the W4 strategy led to the development of a flood wave that ultimately caused the flooding from the Brisbane River downstream of the Wivenhoe Dam. Case No: 260107 Determination Page 10 of 13 43. The Panel agrees that in determining the proximate cause of the inundation of the properties, it is necessary to look at the effective or dominant cause of the inundation. The Panel agrees with the FSP‟s submission that the proximate cause is the cause determined by a commonsense valuation of the relevant facts. In the event that there are two or more proximate causes, one within the policy and the other excluded, the policy does not respond. The proximate cause is not determined by identifying the last event or final trigger, but by determining what is the dominant, effective, direct or efficient cause of the loss. 44. The Panel is satisfied having considered all of the information that prior to the rainfall commencing on or about 4.00am on 11 January 2011, there had been a steady reduction in the inflows to the Wivenhoe Dam from about 3.00pm on 10 January 2011. At that time, the Wivenhoe Dam was being managed at the W3 release strategy. This release strategy whilst causing some increase in the level of the Brisbane River was being maintained with the aim of avoiding flooding of the areas below the Wivenhoe Dam wherever possible. 45. The FSP has maintained that the impact on the dam from the rainfall that fell in the early hours of 11 January 2011 was only 29% whilst 71% of the volume inflow came from rain that fell on 9 and 10 January 2011 or earlier. The FSP maintains that to find that the rainfall from 4.00am on 11 January 2011 is a proximate cause, is without foundation as such an approach produces an entirely artificial outcome. 46. Alternatively, the FSP argues that if it is accepted that there are other proximate causes apart from the implementation of the W4 strategy, then the Wayne Tank principle applies, as the earlier rain was also a proximate cause of the inundation. The FSP also argues that with respect to the inundation caused by the W4 release that was due to an intervening decision by the dam operators and is not covered under the current policy. 47. With respect to the last argument, the Panel is of the view that it was not an intervening factor that led to the adoption of the W4 strategy, but a fact that the level the dam had reached by 8.00am on 11 January 2011 left the operating engineers with no alternative but to adopt the W4 strategy at that time. 48. With respect to the argument regarding the Wayne Tank principle and the rainfall prior to the 24 hour period being a contributing factor or proximate cause of the loss, the Panel notes the policy wording provides cover for sudden flood caused within 24 hours of heavy rainfall. The relevant question is whether the inundation is caused by heavy rain that fell no more than 24 hours prior to the flood inundating the risk address. 49. Whilst the Panel accepts there had been a significant impact on the levels of the Wivenhoe Dam by the rainfall that had commenced falling on or about 9 January 2011 (and earlier), the Panel is satisfied that having regard to all of the information exchanged and the relevant legal principles, that the heavy rain that commenced falling at or about 4.00am on 11 January 2011 was a Case No: 260107 Determination Page 11 of 13 proximate or effective cause of the adoption of the W4 strategy. This in turn caused the inundation of many of the properties below the Wivenhoe Dam as a result of the flood wave created by the increased releases. The Panel is satisfied the proximate cause of the inundation of the Applicants‟ property was the heavy rain that fell from approximately 4.00am 11 January 2011 over the Wivenhoe dam and Brisbane River combined with the heavy rain the fell over the Bremer River from 6.00am that day. The Applicants‟ property 50. SC‟s statement, particularly his updated key conclusions attachment of 7 June 2012, indicates the effect of the W4 releases first reached the vicinity of the Applicants‟ property at 2.39pm on 11 January 2011 . The releases reached benchmark level by 3.45am on 12 January 2011 and were estimated by SC to be 0.00m above the benchmark level as at the relevant time of 4.00am on 12 January 2011. The Panel notes that the peak height above the benchmark level was 3m. SC identified this peak inundation occurred at approximately 3.01am on Thursday 13 January 2011. 51. The Panel accepts that these assessments are necessarily approximations and may not be entirely accurate. This is particularly in circumstances where SC appears to have provided different heights in relation to the key benchmark level (6.2 and 6.25m AHD) and different times for reaching the benchmark level (3.30am 11 January 2011 at 6.25m AHD and most recently 3.45am at 6.2m AHD) 52. The Panel notes that the June 2012 Key Conclusion Statement by SC appears to vary from his conclusions of 16 November 2011. The information provided by this June 2012 Key Conclusion Statement appears to focus on the Brisbane River level and its inundation height. In contrast the November 2011 statement addresses the back-flow and inundation from Oxley Creek. The Panel further notes the Key Conclusion Statement refers to the water reaching the benchmark level at 3.45am 12 January 2011 but being at 0.00 above benchmark at 4.00am. 53. In light of these issues, the Panel Chair Ombudsman attended a site meeting on 21 September 2012. Present were the Applicants and a representative of the FSP. The house is built on a slab and it is about equal in height as the freestanding garage. The Applicants explained the water was in the garden (which abuts the garage – which contained a large number of items such as furniture and tools, all of which were water damaged) by about 7.00pm on 11 January 2011. The Applicants confirmed that when they left their home, water had not entered the home, but on return at approximately 5.00am on 12 January 2011, the water was roughly 250mm deep inside the lower part of the house. They also explained the water outside was actually higher than this with the walls acting as a kind of levee. 54. Based on the information exchanged the Panel accepts on the balance of probabilities, that most likely that the Applicants‟ property was inundated above floor level (benchmark) prior to 4.00amon 12 January 2011. Case No: 260107 Determination Page 12 of 13 55. In the absence of precise assessment of the level of inundation (the Panel does not accept SC‟s estimate of 0.00 at 4.00am is in this instance reliable in view of the inconsistencies previously outlined) the Panel accepts it would be fair in the circumstances to assess the inundation before 4.00am on 12 January 2011 to a level of 100mm above floor throughout the home and garage. In respect of damage to items outside the house and garage the Panel notes the air conditioner and hot water service were below benchmark level and should be treated as total losses. The FSP will need to assess if the water pump that was on a stand should also be covered. Quantum 56. The Renewal Certificate of Insurance for the relevant period provides a sum insured of $498,000 for the home with contents of $89,000. Pursuant to the policy cap for the insured event of “Flash flood and stormwater runoff”, the FSP is liable for up to 50% of the sum insured for the building and 50% of the contents sum insured. This is of course subject to the applicable excesses. 57. Given the time since the loss was sustained, the Panel accepts that the parties may be unable to provide an exact estimate of the total loss sustained, or a breakdown of that loss. The assessment report pursuant to a site inspection on 4 February 2011 indicated a reserve of $80,000 for the house and $25,000 for the contents. The report described inundation of the entire lower level and described the damage as „severe‟. 58. The Applicants and the FSP are asked to work cooperatively together to establish the extent of the loss sustained to the first level of the property as a result of inundation to a level of 100mm throughout the house and garage and to reach an agreement as to cost of repairs and replacement of the various contents lost. The Panel accepts that inundation at this level would cause significant damage and loss of contents. 59. The Panel accepts the FSP is not responsible for damage that occurred after 4.00am on 12 January 2011 as such inundation would be outside the relevant 24 hour period. 60. In respect to interest accruing on these payments, the FSP has argued that interest is only payable from the date from which it was unreasonable to withhold payment. The FSP maintains that it is entitled to a reasonable period to investigate and determine its position, and given the complex nature of the flood disputes, the delays are not unreasonable. Further, complex situations require substantial periods of time for independent bodies such as the Queensland Flood Commission of Inquiry and FOS, to make conclusions on the issues in dispute. 61. The FSP maintains that it did not act unreasonably in this dispute and therefore interest is not payable. Alternatively if some period of interest is to be awarded it should be reduced to account for the substantial delays through th e course of the process which were not the FSP‟s fault. Case No: 260107 Determination Page 13 of 13 62. Section 57 of the Act requires interest be paid when it becomes “unreasonable for the insurer to have withheld payment”. An examination of relevant case law indicates that most probably, interest will be awarded from either when an insurer first emphatically denied liability or disputed a matter, or from when in the normal course of events the claim should have been paid if liability had not been disputed. 63. In this dispute the Panel accepts that the FSP was entitled to withhold payment of the settlement monies until such time as it had properly investigated the dispute and made its decision as to liability. 64. The FSP made its original decision to deny the claim after receiving relevant assessment reports, hydrology reports and other information. The FSP was aware of the terms of its policy and aware of the relevant provisions under which liability might arise and chose to deny the claim, having reviewed those relevant provisions and the evidence available to it. 65. In the Panel‟s view, at that point the FSP has made its decision on the claim and it is appropriate that from that time interest be paid unless it can be established that the Applicants had withheld information from the FSP that would have led to an alteration of its decision. 66. Accordingly, the Panel determines that it is appropriate that the FSP in this dispute pay interest from the day upon which the FSP determined to deny liability of the Applicants‟ claim, until payment of the claim. 67. Insofar as the FSP may have made payment of a compassionate sum to the Applicants, FOS does not have jurisdiction to deal with this payment but acknowledges that the FSP, given the terms on which the compassionate payment was made, may be entitled to deduct this payment from any settlement sum. Determination 68. The FSP is to meet the cost of repairs incurred by the Applicants and the cost of the replacement of items damaged as a result of the „flash flood‟ inundation to a level of 100mm above floor throughout the home and garage. 69. Insofar as the FSP is to cash settle the claim, the FSP is to pay interest from 29 March 2011 (being the date of rejection of the claim) to date of payment of the claim, in accordance with Section 57 of the Act.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.