Flood inundation of rental home denied under flood exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2012-07-25
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$60,984
SourceAFCA PDF

Summary

The landlord's rental home in Darra was inundated in January 2011 during Queensland floods and she claimed about $60,984. AFCA's panel found the loss was caused by flood, which the policy excludes, and that the PDS clearly informed her of the exclusion.

Under section 35 of the Insurance Contracts Act, a clear and unambiguous PDS exclusion for flood applies, and water released from a dam that overflows watercourses falls within the flood definition.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 259567 Determination Page 1 of 9 Case number: 259567 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - Inundation - Storm or Flood Event 17 July 2012 Note: As the Applicant has legal representation, for ease of reference the term ‘Applicant’ covers all relevant submissions. Background 1. The Applicant held a landlord insurance policy with the Financial Services Provider (FSP) from 25 October 2008. The policy provided building cover for up to $166,920. 2. On or about 12 January 2011 , the Applicant‟s tenanted home in Darra was inundated with water as a result of the storms and flooding that affected much of the Queensland area at that time. 3. The FSP investigated the cause of the loss and determined that the inundation of the rental ho me was due to a flood. It denied the Applicant‟s claim on the basis that the policy did not cover such a loss. 4. The Applicant disputes the outcome on several grounds. She seeks cover for her losses estimated at $60,984. Summary of Applicant’s position 5. The Applicant says that the damage caused to her home was directly related to the storms that hit the area at the time. 6. The Product Disclosure Statement (PDS) received from the FSP at the time of incepting the policy failed to adequately notify her of the poli cy‟s limitations as did the FSP itself. The Applicant says that the FSP had failed to properly see to her interests and failed to act in good faith in marketing the policy. In the circumstances, the policy should revert to a prescribed contract. 7. The FSP‟s website advertised that it provided flood cover and the Applicant should therefore receive the benefit of this. 8. Even if the loss was due to flood, the proximate cause of this event was the release of water from the Wivenhoe Dam and this is not excluded under the policy. The FSP should be obliged to cover her loss. Determination Case No: 259567 Determination Page 2 of 9 Summary of FSP’s position 9. The FSP says that the cause of the loss was flooding and the policy excludes all damage resulting from flood. 10. A copy of the PDS was sent to the Applicant and it is therefore entitled to rely upon the limitations of cover cited in the policy. 11. The Applicant has provided no evidence that the FSP‟s website ever stated that it covered flood. 12. Insofar as any aspect of the loss was due to releases from the Wivenhoe Dam, this is still a flood as defined in the policy and not covered. 13. The FSP relies on the following policy provisions: Page 18 of the Product Disclosure Statement (PDS) “WHAT YOU ARE COVERED FOR Storm If your Landlord buildings or Landlord contents suffer loss or damage caused by  a violent wind, cyclone or tornado  thunderstorm or hail which may be accompanied by rain or snow, or  a sudden, excessive runoff of water as a direct result of a storm in your local area ... we will under buildings insurance  rebuild or repair those parts of your Landlord buildings that were damaged... ... however ...  we will NOT cover loss or damage caused by flood, unless  you have chosen the option for Flood Cover in SA or WA...” Page 27 of the PDS “ What you are not covered for – general exclusions we will NOT cover ...  loss or damage caused by flood, unless  the property is in SA or WA and you have chosen the option for Flood Cover...” Pages 61-63 of the PDS “ GLOSSARY Case No: 259567 Determination Page 3 of 9 ... flood the covering of normally dry land by water escaping or released from the natural confines of a watercourse or lake, whether or not it is altered or modified. Flood also includes water escaping from the confines of any reservoir, channel, canal or dam. Flood is not covered by this policy, unless  the Landlord buildings or Landlord contents are in SA or WA and you have chosen the option for Flood Cover. ... storm a violent wind, cyclone, tornado, thunderstorm or hail which may be accompanied by rain or snow, or a sudden, excessive runoff of water as a direct result of a storm in your local area. It does not include persistent rain by itself.” Issues 14. Whether the FSP has an obligation to inform the Applicant about whether the cover is suitable for her needs. 15. Whet her the provision of the PDS was sufficient to discharge the FSP‟s obligation to clearly inform the Applicant of the flood exclusion. 16. Whether the Applicant was in any way prejudiced by representations allegedly made on the FSP‟s website in relation to floo d cover. 17. Whether the damage caused to the Applicant‟s property can be attributed to an insured event. 18. If so, whether the FSP is entitled to rely upon exclusion(s) in the policy to avoid payment. Reasons for decision 19. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the issues to be considered. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 20. This decision has been made by a Panel consisting of an Ombudsman, an insurance industry representative and a consumer representative. 21. The Panel is satisfied that a full exchange of the relevant information has taken place between the respective parties and that each party has had the opportunity of addressing any issues raised. Case No: 259567 Determination Page 4 of 9 Provision of advice 22. The Applicant says that the FSP did not provide her with suitable advice as to whether the policy fulfilled her needs, noting the location of her home and its proximity to a flood-prone area. 23. The Panel is not satisfied that there is any obligation on the FSP to ascertain or indeed to inform the Applicant as to whether a policy is suitable for her needs. This is a decision that the Applicant must make or engage the services of a broker or suitably qualified person to assist. 24. The Panel is conscious that if the FSP was to provide specific advice regarding the suitability of the insurance product this might constitute the provision of financial advice under the Corporations Act 2001. The FSP is not authorised to provide such advice. 25. The Panel does not consider a failure to provide specific advice to the Applicant constitutes a breach of the FSP‟s duty of utmost good faith. The onus to clearly inform 26. The Applicant has not disputed that she received a copy of the PDS after incepting the policy in 2008. She contends that she was not “clearly informed” of the limitations of the policy. 27. In order to rely upon the terms and conditions of a prescribed insurance contract, the FSP must ensure that it complied with section 35 of the Insurance Contracts Act 1984 (the Act). 28. Section 35 of the Act allows for an insurer to define and limit the level of cover offered for insurance on the basis that it “clearly informs” the policyholder. This requirement is in writing and no obligation is on the insurer to inform a policyholder of the limitations verbally. 29. The question of what it means to “clearly inform” was considered by the Northern Territory Court of Appeal i n the matter of Marsh v CGU Insurance Ltd t/as Commercial Union Insurance [2004] NTCA 1 (the Marsh case). Mildren J wrote in relation to an insurer‟s obligations under section 35(2) of the Act that: “... a fair reading of sec 35(2) [does] not warrant the c onclusion that the result needed to go further than providing for the relevant exclusion in the policy wording in clear and unambiguous language and in a manner which a person of average intelligence and education was likely to have little difficulty in fi nding and understanding if that person read the policy in question.” 30. With respect to this claim, the clarity of what is written in the PDS determines whether the FSP may limit its cover to exclude losses which are attributable to a “flood”. 31. The PDS provides an overview of important considerations in an index on page 1 of the document. This directs the policyholder to relevant sections for Case No: 259567 Determination Page 5 of 9 making a claim (page 47) and how to review the Glossary (page 60) and the Index (page 64). A more specific outline of what the policy does and does not cover is detailed on pages 4 and 5. Under the titles, “What you are covered for” and “Storm” (page 18) and “What you are NOT covered for” and “General Exclusions” (pages 27 -28), the policy provides relevant information for this claim. Page 18 details the circumstances under which a claim for storm damage may be made. It also specifies that cover will not be provided for a flood (unless you reside in South Australia or Western Australia and have chosen the flood cover option). On page 27, the policy again specifies that flood is not covered, unless the property is located in the relevant States and the option for this cover is chosen. In navigating to the Glossary from page 60, a definition for flood is located on page 61. 32. The Panel considers that the definition of flood in the PDS adequately conveys that the policy does not cover events where water escapes or is released from a watercourse or lake over dry land. It further specifies that flood does not include water escaping from certain water bodies, including a dam. The definition specifically states that losses due to flooding are not covered unless the property is in certain States and the necessary option for this cover is selected. The Applicant‟s property was not in a Sta te that offered flood cover. 33. In the Panel‟s view, the definition of flood is relatively straightforward, although a closer focus on this will be addressed later. More importantly, the PDS makes it clear that the FSP does not provide cover to the Applicant for a flood event. 34. Therefore, on the basis that a PDS is written in plain English and can be understood by a person of “average intelligence and education”, the Panel is satisfied that the provision of it discharges the FSP‟s obligations under section 35(2) of the Act. 35. Accordingly, the Panel is satisfied that the FSP made the Applicant aware through the provision of the PDS that the policy did not provide flood cover. In the circumstances, the Panel is satisfied the FSP has complied with its obligation to clearly inform the Applicant of the flood exclusion, pursuant to section 35 of the Act and may therefore rely upon it where appropriate. Website 36. It is not in dispute that the FSP extended flood cover to some States in Australia but not Queensland (where the Applicant‟s property was located). 37. The Applicant refers to representations allegedly made on the FSP‟s website that might induce a party to insure with the FSP (with a promise of flood cover) in circumstances where no such cover was provided. 38. The Applicant has not suggested that she was so induced to implement the cover on this basis or provide specific evidence of such a representation being made. In the circumstances, the Panel considers that there is no evidence of her being prejudiced by any such alleged representation. Case No: 259567 Determination Page 6 of 9 Cause of the loss and whether the FSP is entitled to exclude the event 39. The FSP‟s policy is a defined events policy, which provides cover on the basis that a specific event to which the policy caters has occurred. 40. It is the Applicant‟s c ontention that the property was damaged by stormwater runoff. 41. If so, the claim might be considered under “storm”. It is not in dispute that the local area was subjected to heavy rain in the days preceding the loss or that it was ultimately inundated with water. 42. The FSP suggests that the Applicant is unable to discharge her obligation to establish a prima facie claim under the policy. Even if she could, the loss would be excluded as it was due to flooding. 43. After the initial report of the loss, the FSP retained an internal assessor, DT, to inspect the property on 21 January 2011. DT reported that:  the property was a single storey home in good condition;  the water entered gradually from “all around”;  the initial inundation was on 12 January 2011 (but no one was present to witness it);  maximum inundation was to 1,800mm; and  the water emanated from the “creek/canal [across] the road”. The origin of the water was “creek, storm water from catchment”. 44. DT recommended the appointment of a hydrologist as a newly built motorway had changed the drainage for the estate. 45. The FSP eventually retained WP to provide a report. WP visited the site on 28 September 2011 and noted:  the property is located about 14km southwest of the CBD;  Bullockhead Creek is located about 250m wes t of the Applicant‟s property. This creek joins Sandy Creek and Wolston Creek, located about 1.2km northwest of the property. Wolston Creek flows into the Brisbane River, located about 4.5km from the Applicant‟s property;  a small tributary of Bullockhead Creek runs about 50m west of the Applicant‟s property;  the insured property is situated at approximately 12.6m AHD (Australian Height Datum). The land near Bullockhead Creek is situated at about 11m AHD;  no one was present at the time of the loss and the former tenants were no longer in contact with the Applicant;  a low-lying area of land, covering about 0.3km, was situated just west of the Applicant‟s property. This represented an area of “potential flood storage at the downstream end of Bullockhead Creek”; Case No: 259567 Determination Page 7 of 9  the floor level of the dwelling was 240mm above the ground level. The Applicant suggested that the flood rose to about 2.2m above the floor level;  flood levels in the area peaked at around 15m AHD at 7pm on 12 January 2011. This compares favourably with the levels of inundation to the home;  rainfall data from local gauges suggested that runoff would not have been severe enough to have “made any significant contributions to the inundation that occurred in the area”; and  the inundation was caused by the “flo od water escaping the normal confines of the Brisbane River and backing up Wolston and Bullockhead Creeks and then the unnamed tributary that lies to the west of the property in response to the intensity and volume of rainfall in the catchment areas of the Brisbane River upstream of Darra.” 46. The report did not directly address when rain ceased in the area or to what extent (if any) it inundated the Applicant‟s property. The timing of the loss is likely indicative of the true cause, noting that there was no reported inundation prior to 12 January 2011. 47. Publically commissioned area hydrology reports prepared by the Insurance Council of Australia (ICA), were also relied upon by the FSP for consideration of the general area in the vicinity of the Applicant‟s prop erty. 48. The ICA noted that rainfall in the Brisbane city area was heaviest through the 6am to 4pm period on 11 January 2011. Page 41 of Volume 2 of the report notes: “Rain ceased over the Brisbane City area around 1800 hours on Tuesday 11 January, some 24-30 hours before flood levels in the Brisbane River peaked. Thus, when the Brisbane River peaked, there is no evidence that there was any „normal‟ flow of significance from the catchment areas of tributary creeks draining the Brisbane LGA [Local Government Area]. As the floodwave passed downstream along the Brisbane River, backwater flooding occurred up the tributary creeks. The peak flood level and time of peak along the tributary peaks are expected to be the same as those in the Brisbane River at the mouth of the creeks. Flooding along the mainstream of the Brisbane River and along the lower tributaries was principally caused by releases from Wivenhoe Dam (dam release flooding).” 49. This report suggests that rainfall had ceased in the local area well before, th e initial inundation of the risk address, as noted by the FSP‟s „DT‟, to be 12 January 2011; but that “backwater flooding” occurred through the Brisbane River and tributary creeks (which would include Wolston Creek and Bullockhead Creek). This flooding was caused by the release of water from the Wivenhoe Dam. 50. Volume 2 of the ICA report also notes that: “Given that rainfall across the Brisbane City [local area] had ceased by 1800 hours on Tuesday 11 January, any flooding after this time will have been Case No: 259567 Determination Page 8 of 9 caused by waterflow inundation from the Brisbane River and its tributary creeks, it being noted that inundation along the tributaries was associated with backwater flooding from the Brisbane River (which in turn was principally caused by the dam release flood f rom Wivenhoe Dam).” 51. The above passage indicates that any inundation of homes in the suburban areas surrounding Brisbane after the cessation of the heaviest rainfall on 11 January was almost certainly due to flooding and not stormwater runoff. Given that th e inundation of the Applicant‟s property was estimated to not have occurred until 12 January 2011, the Panel is satisfied on the balance of probabilities that the cause of this inundation was flooding. 52. The policy specifies the occurrence of a “flood” as: “... the covering of normally dry land by water escaping or released from the natural confines of a watercourse or lake, whether or not it is altered or modified. Flood also includes water escaping from the confines of any reservoir, channel, canal or dam. ” 53. The definition relied upon in the PDS specifically covers the instance where water escapes the confines of a watercourse, which in this case, was the Wolston and Bullockhead Creeks as well as the local tributaries. The flooding of these water bodies was as a direct result of the flooding experienced in the Brisbane River. 54. It is well documented that the Brisbane River was unable to handle the volume of water from the storms and the subsequent releases out of the Wivenhoe Dam from 11 January 2011. The overflow of water from this point caused the Brisbane River to break its banks. 55. The Applicant considered that the release of water from the Wivenhoe Dam in these circumstances was not specifically excluded under the FSP‟s policy. This is due to the construction of the flood exclusion as relied upon by the FSP. 56. Insofar as any flood damage occurred to her property as a result of the releases from the Wivenhoe Dam, the Applicant suggests that the FSP cannot avoid extending cover to her for this loss. 57. The definition used for flood in the PDS is in two parts. The first part states that it is the covering of normally dry land by water escaping or released from the normal confines of a watercourse. It is not in dispute that the Brisbane River (or the other water bodies closer to the Applicant‟s property) constitutes watercourses, so that any damage caused by water escaping from the river will not be covered under the policy. 58. The second part of the definition states flood also includes water escaping from the confines of a dam. The Applicant relies on the release of water from the Wivenhoe Dam under strategy W4 to suggest that this water caused the Brisbane River to overflow its banks and a flow on effect for other water bodies. As this water was “released” and did not “escape”, the Applicant Case No: 259567 Determination Page 9 of 9 submits that the FSP is unable to rely upon the policy exclusion, which must be explicit. 59. There is a clear distinction between the meaning of the words “escaping” and “released” and the Panel is satisfied that the two are not to be interchanged. To “ escape ” implies that the water may exit a designated area despite efforts to constrain it. To be “ released ” implies that the water was able to exit the area through intervention (including a voluntary act). 60. The Panel is satisfied that the reference to “water escaping from the confines of a dam” does not assist the Applicant. Whatever the cause of the release of water from the dam, the cause of the flooding of the Applicant‟s property (insofar as it can be linked to the release of water from the Wivenhoe Dam) was due to the overflow of the Brisbane River and the subsequent flow on effect to other water bodies. That is, that the water escaped from the confines of the Brisbane River and spread to and escaped the subsequent bodies of water in the vicinit y of the Applicant‟s property. 61. Water that enters a watercourse for any reason, including water released from a dam, which in turn is responsible for water escaping from the watercourse, falls within the first part of the flood definition. 62. The evidence is that water overflowed the banks of the Brisbane River and caused widespread flooding. This, on the balance of probabilities, in the Panel‟s opinion , extended to and affected the Wolston and Bullockhead Creeks, as well as the unnamed tributary in t he vicinity of the Applicant‟s property. 63. While it is arguable that the Applicant has failed to establish a prima facie claim, in any event the Panel is satisfied the loss is excluded, as it occurred as a result of a flood. Accordingly, the Panel determines the FSP is entitled to refuse the claim. Determination 64. On the basis of the available information, the Panel determines that the FSP is not obliged to provide cover to the Applicant for her loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.