Determination 259392
Settlement of bushfire fencing claim with fencing left incomplete by contractor, and adjuster handling
Summary
A farm insurer paid $103,726.70 to a contractor to replace bushfire-damaged fencing, but about 2km was left unrepaired. AFCA found the insurer's adjuster approved invoices without inspecting the work and ordered $10,000 partial compensation, while the claimant's unauthorised side works reduced his recovery.
The insurer had paid up to the sum insured on the contractor's invoices and was not liable for uncompleted works, but the adjuster's overpayment contributed to the dispute and justified partial compensation.
Issues
- Claim amount dispute primary · upheld
“I determine that the FSP must pay $10,000 to the Applicant in partial compensation for the work remaining to be completed.”
- Inadequate claim investigation secondary · upheld
“I am greatly concerned that in approving the invoices up to 18/7/09, the adjuster did not actually inspect the work done by the contractor.”
- Repairs or contractors secondary · upheld
“The contractor did not complete the job as quoted leaving about 2 kms of fire damaged fencing unrepaired and did not remove the debris.”
Subjects and remedies
natural disasterpay compensation
Text of the determination
Case No: 259392 Determination Page 1 of 8
Case number: 259392
General Insurance - Small Business/Farm Insurance - Fire or accidental
damage - Service - Delay in claim handling - Quantum
25 October 2012
Background
1. Fencing on the Applicant’s farm was insured for $100,000 under the farm
property section of their farm insurance policy issued by the Financial
Services Provider (FSP)
2. On 23 February 2009 the fencing was destroyed during the severe Victorian
bushfires.
3. The FSP accepted liability for a claim under the policy and authorised a
contractor to replace the damaged fencing for the sum of $109,186 which
included removal of debris. The FSP paid out $103,726.70 in accordance
with invoices submitted by the contractor.
4. The Applicant contends the fencing works are incomplete and that he is
entitled to have the remaining fencing replaced.
5. The FSP states that the Applicant entered into an arrangement with the
contractor to perform unrelated work not authorised by it which was included
in invoices submitted to it and paid. The FSP further states that as the
contractor ’ s original quotation was reasonable it was not liable for the cost of
replacing the remaining unrepaired fencing.
Summary of Applicant’s position
6. As the original quote to replace the fencing was more than that covered by
the policy, they decided to handle the claim instead of paying out the money.
7. The original quote was for $10 a metre to fence and $2 a metre to clean the
line. They cleaned most of the fence line and agreed to spread the posts an
extra metre between each other.
8. In the first year the contractor completed only 4km of fencing but spent
$80,000 which the FSP did not monitor. The second year the contractor
fenced another 3km. As the money ran out this 3km is still uncompleted and
not tied off properly.
Determination
Case No: 259392 Determination Page 2 of 8
9. A copy of the contractor’s original quote provided to him was dated before
the fire occurred and a statement of his expenses did not appear to be
accurate.
10. They lost $20,000 in grants because of the time taken by the fencing
contractor.
11. Fencing material was stolen from the site and was reported to police.
12. Fence posts allocated to their site were used by the contractor on a
neighbour’s fence.
13. The contractor did not replace the electric outrigger wire or remove old wire.
14. The original quote set aside money to employ an earth moving contractor to
clear the timbered fence line. They paid the earthmover over $5,000 which
was to be reimbursed but was not.
15. A local supplier is owed $10,000 for materials used by the contractor on their
fencing.
Sum mary of FSP’s position
16. A contractor was engaged to carry out repairs based on a quotation in the
sum of $109,186.
17. The sum insured of $100,000 for fencing has therefore been paid out.
18. The loss adjuster had been appointed to conduct a site inspection with an
independent fencing contractor to review the work which had been
completed by the original contractor. The loss adjuster confirmed that areas
of fencing that were not subject to the claim had been repaired by the
contractor and paid by it. Invoices submitted for the unrelated fencing repairs
was done so without it having been notified that they did not relate to the
original claim.
19. As such, it had paid for works carried out by the contractor which had not
been authorised by it.
20. Based on the independent fencing contractor’s quote, it has established that
the original quote prepared by the contractor was reasonable for the 9.8km
of fencing which was damaged by the fire.
21. Had the Applicant not sought repairs for fencing not damaged by the
bushfire from the contractor, the original quote would have been sufficient.
22. It follows the Applicant is not entitled to any further payment under the policy
in respect of the fire damaged sections of fencing.
23. The FSP relies on the following policy terms:
Case No: 259392 Determination Page 3 of 8
“ Section A – Farm Property Cover
...
Accidental Damage Cover
Accidental Damage Cover applies to Buildings, Contents, Fences, Hay,
Immobile Machinery and Silage and Grain insured by the Section.
We will pay for accidental loss or damage to your Farm Property anywhere
within Australia unless t he loss or damage is excluded in “What we do not
insure you for ” below.
We will pay up to the Sum Insured shown on the Schedule per Occurrence.”
Issues
24. Whether the FSP has settled the claim according to the terms of the policy.
Reasons for decision
25. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is because of the complex nature of the issues. This dispute
has not been the subject of a FOS Recommendation and has proceeded
directly to Determination.
26. There has been an exchange of material between the parties. Each party
therefore is aware of the issues and has had the opportunity to comment.
27. Prior to arriving at a determination I have read and considered all the
material submitted by the parties to FOS.
28. The Applicant is seeking a benefit under the policy and therefore has the
burden of establishing on the balance of probabilities that they are entitled to
that benefit.
Original quotation
29. It is common ground between the parties that 9,820 metres of fencing was
damaged by the bush fires in February 2009.
30. The FSP obtained quotations for replacement of the fire damaged fencing
being in the sums of $109,186 (including GST) and $125,000 (including
GST). Both quotations included an allowance for removal of debris.
31. The FSP accepted the lower of the quotations and authorised the contractor
to proceed with the work.
32. The Applicant says when they sought a copy of the original quotation from
the FSP, the document provided to them was dated several days before the
Case No: 259392 Determination Page 4 of 8
loss occurred. The Applicant had not been provided with copy of the
quotation before the FSP approved the quotation.
33. The document submitted to FOS is dated 6 March 2009 being after the loss
occurred.
34. The loss adjuster stated that a copy of the quote was provided by them to
the Applicant during a site visit on 16 August 2009. However they had not
looked at the date until sometime later. The loss adjuster went on to explain
that when the anomaly with the date was discovered the original contractor
said his original estimate had not been dated and he put the date on it later
and guessed that the fire occurred around mid February.
35. The loss adjuster further stated that his office requested the document from
the contractor as the contractor had made reference to his original price
being well over the sum insured and that discussion had taken place with the
Applicant about how they may remain within the sum insured limits.
36. While this provides an explanation for the incorrect date, it is of concern that
the dates have obviously been altered some time later. Nevertheless I am
satisfied that a quotation was submitted and that an authorisation to
commence the work was based on that quotation. It is unfortunate however
that the Applicant did not receive, originally, the quotation.
37. The contractor submitted the following invoices for the work.
28.4.09 $32,755.8 30%
28.5.09 $32,755.80 30%
18.7.09 $27,296.50 25%
30.10.09 $10,918.60 10%
Total $103,726.70
38. The invoices were approved by the loss adjuster and paid by the FSP.
According to the loss adjuste r’s report of 11 November 2009 a small run o f
fencing was to be completed which was anticipated to be finalised by the
end of November 2009. However I am greatly concerned that in approving
the invoices up to 18/7/09, the adjuster did not actually inspect the work
done by the contractor.
Additional work authorised by the Applicant
39. Following the Applicant’s complaint that only 7,126m of the 9,820m of
fencing had been replaced, the FSP commissioned a consultant building
contractor to inspect all the fencing and report on any short fall or
discrepancies.
40. The consultant provided the following relevant information in his report of 13
July 2011.
Areas of fencing not seriously damaged by the fire were not replaced in
lieu of some boundary fencing that required urgent attention.
Case No: 259392 Determination Page 5 of 8
A large portion of internal fencing was not replaced as a consequence
of the fire damage. Six damaged gates were not replaced. There was
no attempt to remove the debris. A total of 47 concrete end assemblies
had been replaced with an estimated 23 concrete assemblies requiring
replacement.
The Applicant had agreed to undertake the removal works to reduce
the overall costs.
The Applicant had paid for an excavator to provide clearance for
boundary fencing.
The consultant concluded:
“I am of the opinion that the fencing replaced as a result of the bush fire
during February 2009 has not coincided with the nominated repair
measurement of 9.8km of fencing.
I am also of the opinion that private negotiation between the insured and the
fencing contractor has digressed from the original outlined scope of works
causing an uncertainty in the overall fence replacement quantity.
From my inspection I consider that the completed work does not correspond
with the original estimation provided by the fencing contractor. I recommend
replacement of a further 6 gates, 23 concrete assemblies and 2km of fencing
plus scrap removal.”
41. I consider that in making this recommendation, the consultant concluded that
the contractor had not completed anything like the 90% of work supposed to
have been completed by 18/7/09 (according to the Certificate provided by
the contractor). Vitally, the Applicant was not informed that the adjuster was
certifying any such figure – had he been informed, the result would have
been very different.
42. The loss adjuster in company with an independent fencing contractor met
with the Applicant and provided the following relevant information in his
report of 16 March 2012.
Fencing along the railway line that had not been damaged in the fire
was replaced by the original contractor.
The Applicant understood that this work would be carried out in lieu of
another 2km of internal fencing.
The total amount of fencing replaced was only 7.2km and the Applicant
feels they should have had a further two kilometres of fencing
completed for the invoiced price.
The independent fencing contractor estimated the cost to replace the
remaining two kms of fencing was $20,086 which allowed for materials
already on hand and for which the Applicant had been paid out. The
value of fencing materials on hand was estimated at about $7,500.
Including the contribution of materials settled to the Applicant, the cost
to replace the additional two kilometres of fencing amounts to about
$27,500 or $13,750 per kilometre. For the 7.2 kms involved this
amounts to $99,000.
Case No: 259392 Determination Page 6 of 8
The contractor had been paid $103,726.70 which included a measure
of pulling down the burnt fence and some of the original work which
was on difficult and hilly terrain.
Based on these estimates the original costs were not considered
excessive and would have been within the normal expected range.
No written agreement was made between the Applicant and the original
contractor for the alternate arrangements which made it difficult to
determine who said what.
I ndeed the Applicant only received a copy of the contractor’s estimate
long after the contractor had departed.
Summary
43. Notwithstanding the incorrect date on the contractor’s original quotation, I am
persuaded that the quotation was fair and consistent with market prices for
the extent of work described in the quotation. As such the FSP was entitled
to rely on the quotation when assessing the claim.
44. It is clear from the evidence that the FSP entered into an agreement with the
contractor to repair/replace 9,820 metres of fire damage fencing and remove
the debris. The contractor did not complete the job as quoted leaving about 2
kms of fire damaged fencing unrepaired and did not remove the debris.
45. In ordinary circumstances the FSP is responsible for the actions of
contractors appointed by it to make good insured damage. However, it is
also clear the Applicant entered into an arrangement with the contractor to
carry out works unrelated to the claim.
46. I have not been provided with any information setting out the specific details
of the arrangement between the Applicant and the contractor, in particular
the extent and cost of the unauthorised works and how this would be off set
against the accepted quotation.
47. The issue is further complicated in that the Applicant agreed to undertake
some of the quoted work such as removing the debris including hiring an
excavator to reduce the overall cost.
48. The FSP was not informed of the arrangement and the contractor continued
to invoice the FSP in accordance with the quoted scope of works. Hence the
FSP was paying for the additional uninsured damage authorised by the
Applicant. I think it is clear that the Applicant must bear some responsibility
for what happened. He should have “OK’d” the changes with the FSP.
49. Given that the FSP has paid for the works carried out and invoiced by the
contractor including any reduction in costs by the Applicant’s contributio n, it
is arguable that the FSP has absorbed the variations in costs brought about
by the departure from the original scope of works.
Case No: 259392 Determination Page 7 of 8
50. While it is clear the insured damage quoted by the contractor has not been
completed, the payments made by the FSP have exhausted the fencing sum
insured.
51. The policy states that payment will be made up to the sum insured. In
relation to the cover for removal of debris, the policy provides that payment
will be made up to the sum insured for removal of debris. If this is insufficient
and the sum insured for the damaged item is not exhausted, payment will be
made up to the balance of the sum insured of the damaged item.
52. It has been established the FSP has paid out $103,726.70 in accordance
with the contractor’s invoices for work carried out.
53. In these circumstances, I would have concluded that the FSP has complied
with the terms of the policy and is not responsible for the cost of repairing the
uncompleted work.
54. I am of the view however that the actions of the adjuster have contributed to
this dispute. The Applicant says that by 18/7/09 the contractor had only
completed about 2km of fencing. I think it is clear that the adjuster had not
inspected the job when he provided the certificate for the payment of
$27,296.50.
55. The assessor should not have authorised 90% of the entire job. The
contractor was overpaid up to that point. Only approximately $7,000 was in
reserve – quite inadequate for all the remaining work.
56. The Applicant says that an account in the sum of $10,000 incurred by the
contractor with a local supplier remains unpaid. This is matter between the
supplier and the contractor and the supplier may seek payment through the
avenues available to him for an outstanding debt.
57. The Applicant says he is owed about $2,500 by the contractor which was
paid to an earth moving contractor to clear the fence line. However,
according to the consultant builder, he was informed by the Applicant that
they were personally undertaking the removal works to reduce over all costs
and that the Applicant had paid for the excavator to clear the boundary fence
line. I take this into consideration below.
58. Having regard to the findings I have made, I consider the FSP must make
some compensation to the Applicant.
Case No: 259392 Determination Page 8 of 8
Determination
59. I determine that the FSP must pay $10,000 to the Applicant in partial
compensation for the work remaining to be completed.