Determination 259390

Dispute over whether flood-damaged piles, walkway and flood chain fall within the fixed pontoon sum insured

FirmFinancial Firm (Unknown - Insurer)
Decided2012-07-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$7,155
Non-financial loss—
Amount claimed$85,350
SourceAFCA PDF

Summary

The applicants' insurer limited a flood claim for pontoon and jetty works by allocating items to a $30,000 fixed pontoon sum insured. AFCA held the walkway and flood safety chain were outside that term and ordered an additional $7,155 with interest, but upheld the denial for the piles.

A policy term is construed by its ordinary meaning, context and commercial purpose, and contra proferentem favours the insured where ambiguity remains.

Issues

Subjects and remedies

pay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 259390 Determination Page 1 of 7 Case number: 259390 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 12 June 2012 Background 1. The Applicants entered into an insurance contract managed by the Financial Services Provider (FSP) on behalf of its underwriters. This contract insured the Applicant s’ home and contents , which included a pontoon and jetty. 2. The Applicants lodged a claim for damage sustained following the extreme weather events in Queensland. The FSP accepted the majority of the claim but a dispute has arisen regarding the pontoon and jetty. 3. The total amount being sought by the Applicants is based on the following quotations provided by a contractor (JS): Pontoon reinstatement $30,000.00 Ancillary works, including roller system, walkways, aluminium headstocks, etc. $44,350.00 Re-driving two existing piles $11,000.00 TOTAL $85,350.00 4. The FSP has noted that under the policy, the “fixed pontoon ” was limited to a sum insured of $30,000. Based on this, it considered some of the ancillary works and the two existing piles set out above fell within this sum insured. Accordingly, based on its calculations, it has maintained its liability is limited to $65,794. 5. The Applicants have disputed this and are seeking the balance. In substance, the Applicants have disputed the FSP’s interpretation to term “pontoon” in justifying its settlement. Summary of Applicants ’ position 6. The Applicants, who are represented by their broker, have provided the following submissions (summarised): Determination Case No: 259390 Determination Page 2 of 7 a. Neither the proposal n or the policy defined “pontoon” or “jetty”. Applying their dictionary meanings, this would not include the items contained in the FSP’s settlement for the pontoon. b. A “Flood Fact Sheet” provided by the council corroborates their position that walkways, pylons or other associated items does not constitute part of a pontoon. c. The first report by the FSP’s loss adjuster supported their interpretation of the word “pontoon” as did a builder’s quote. d. The contra proferentem principle applies to support their position. 7. Given this, the Applicants are seeking payment of the balance owing, namely $19,556. Summary of FSP’s position 8. The FSP, in summary, has argued the following to substantiate its position: a. The insured premises consist of both a fixed jetty and a fixed pontoon. The sections of the structure that is able to be articulated by the movement of water and connected to the fixed pontoon form part of the “fixed pontoon” . This includes the flood safety chain, piles and walkway. b. The piles and the walkway cannot be considered part of the fixed jetty. Therefore, they should be considered as part of the fixed pontoon, particularly given they serve a function solely for the pontoon’s benefit. 9. The FSP maintains that the interpretation it has applied t o the term “fixed pontoon ” is consistent and appropriate to the commercial purpose of the policy. Accordingly, there is no ambiguity and it follows that its application of this term in the Applicants’ circumstances is appropriate. 10. The FSP relies on the following policy provisions: “ Definitions … Building means - the dwelling, residential flat, home unit or other buildings classified by the National Trust or Historical Foundation or which is the subject of any State or Local Authority classification order including any ancillary building at The Situation and includes unclassified buildings forming part of a Building subject to a classification order including that portion of the Building used as a business office. In both cases, Building includes: 1. … 2. fixed pontoons up to four metres in length and fixed jetties unless otherwise stated in the Insurance Schedule.” Case No: 259390 Determination Page 3 of 7 Issues 11. Whether the FSP’s interpretation of the term “fixed pontoon” is appropriate. Reasons for decision 12. Due to the issue and amount in dispute, the matter has been expedited for Determination in line with the Operational Guidelines to FOS’s Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination 13. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 14. The issue in dispute between the parties is essentially distilled to the interpretation of the term “fixed pontoon” and how it should be applied to the Applicant s’ claim. 15. Under the Applicant s’ insurance contract with the FSP, an endorsement was applied to the insurance schedule that noted the pontoon is 11 metres at length with a sum insured of $30,000. It is the FSP’ s application of this sum insured that is in dispute. 16. The quotes provided by JS have been referred to by both parties in justifying their respective amounts. I note the actual totals provided by the quotations and the breakdowns provided by the FSP’s loss adjuster are not in dispute. Instead, the Applicant s have disputed the FSP’s allocation of the following scope of works to the sum insured of $30,000 associated with “fixed pontoon” : One of the four 12 meter walkways $6,468.00 Two 8 roller pile brackets $1,401.00 25 metres of flood safety chain $687.00 TOTAL $8,556.00 17. The FSP maintained these elements formed part of the “fixed pontoon”. Accordingly, it deducted this from the amount of $44,350 allowed for in JS’s ancillary works. In addition to this, the FSP maintained the $11,000 for the re-driving of two existing piles is either not covered or forms part of the fixed pontoon. Interpretation of the term “fixed pontoon” 18. Both parties have referred to the dictionary definition of the term “pontoon”. The Macquarie dictionary provides the following definition: Case No: 259390 Determination Page 4 of 7 “a boat, or some other floating structure, used as one of the supports for a temporary bridge over a river” 19. However, the policy refers to a “fixed pontoon” rather than a pontoon. In this regard, the FSP has argued that the commercial efficacy for such a term should include the following ancillary attachments: “walkways such as gangways or sections of the walkway leading down to and attached to the floating part of the pontoon, the anchor poles or pylons or piles which assist the pontoon in rising up and down but fix it to one spot and associated attachments to the pontoon structure such as winches, flood chains, weights, super fenders, pontoon pile caps etc.” 20. The FSP quoted this from legal advice it obtained. 21. The Applicants, in contrast, have argued the application of the term “pontoon” , in the context of the policy, is at best ambiguous. In support of this, the Applicants have relied on various documents, such as dictionary and Wikipedia definitions, a fact sheet provided by the Council and the FSP’s own loss adjuster’s reports. 22. However, I consider the Applicant s’ submissions in this regard to be somewhat misconceived. The policy refers to the phrase “fixed pontoon” and it is this term that must be interpreted. This is consistent with contractual principles which state that we take the ordinary and natural meanings of the words or phrases used taking into consideration their context and the commercial object and purpose of the policy. 23. Contra proferentum is generally a principle of last resort. That is, it is normally applied when the phrase in question is ambiguous to the extent that even after considering the context and commercial object and purpose of the policy, numerous interpretations can still apply. At that point, the principle of contra proferentum, for the purposes of contractual construction, state the most favourable interpretation to the insured should be adopted. 24. The High Court in the case of Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52 have provided the following comments regarding the principle of objectivity by which the rights and liabilities of the parties to a contract should be determined: “ It is not the subjective beliefs or understandings of the parties about their rights and liabilities that govern their contractual relations. What matters is what each party by words and conduct would have led a reasonable person in the position of the other party to believe. References to the common intention of the parties to a contract are to be understood as referring to what a reasonable person would understand by the language in which the parties have expressed their agreement.” 25. It is commonly accepted that principles of construction underpinning an insurance contract operate in the same manner as any other commercial contract ( Australian Casualty Co Ltd v Federico (1986) 66 ALR 99). 26. With this in mind, I will now consider the phrase “fixed pontoon”. Case No: 259390 Determination Page 5 of 7 27. I accept the dictionary definition of the word “pontoon” should be considered when determining the appropriate construction of the phrase “fixed pontoon”. This word is a noun and as commonly understood, a noun is associated with a person, place or thing. Pontoon, as self evident, is a thing. 28. The use of the term “fixed”, as evident by its definition, is an adjective and is described as followed: “made fast or firm; firmly implanted” 29. In interpreting the phrase “fixed pontoon” I accept , at a minimum, this clearly conveys to a reasonable person, keeping in mind the relevant definition of the words, that the description includes both the actual pontoon itself and ancillary items that affix it to a certain place in the water. Items in dispute Piles 30. There is no dispute that the piles ’ primary function was to secure the pontoon to a certain point in the water. This function was further corroborated in the council’s fact sheet included by the Applicants. 31. Accordingly, I accept that the costs involved in repairing the piles, which would include re-driving them and purchasing the roller pile brackets, would fall within the reasonable person’s understanding of the phrase “fixed pontoon”. I therefore accept that the FSP was correct in not providing any further allowance for these costs. Walkway 32. The FSP has submitted that, in order to give the term “fixed pontoon” commercial efficacy, it should include ancillary items such as walkways and the flood safety chain. However, I do not accept a phrase that is not specifically defined should be given a meaning that is not readily associated with its ordinary and natural meaning. 33. That is, it is difficult to accept that a reasonable person, who considered the term “fixed pontoon”, would readily accept this would include a walkway. Although I accept the walkway serves an essential feature in that it enables access to the pontoon, I do not accept it necessarily follows that it would be considered part of the policy description of “fixed pontoon”. 34. Further, there is no evidence to establish that the walkway, in the Applicant s’ circumstances, serves any function to secure the pontoon in place. Its function, as the term describes, is to enable access to the pontoon by foot. 35. The FSP, in advocating its position, has attempted to distinguish the fact that the Applicant s’ property contains a fixed jetty and a fixed pontoon and that the walkway must be associated with one of the two given the definition of “Building” . Case No: 259390 Determination Page 6 of 7 36. However, I would disagree with this argument of construction. The fact the pontoon would be inaccessible without a walkway does not therefore lead to the construction that it must be associated with either the phrase “fixed pontoon” or “fixed jetty” . 37. The policy definition of “Building” is fairly wide . Although it includes a number of examples as to what is included in this description, such as fixed pontoons, this list is not exhaustive. As a result, it is both open to me and consistent with the policy’s commercial purpose to give it a broad and liberal interpretation, particularly given the policy provides accidental damage cover, which is broad in nature. 38. In addition to the above , I also refer to the description provided about “fixed pontoons” that is contained in the definition of “Building” , namely: “fixed pontoons up to four metres in length …” 39. If the policy’s intention was to include a walkway in the description “fixed pontoon”, then it is reasonable to conclude that the length referred must include the walkway. 40. However, this is inconsistent with both parties’ conduct. For instance, both parties agree that the length of the “fixed pontoon”, as specific to the Applicant s’ circumstances, was limited 11 metres. This is the approximate length of the actual pontoon. 41. Accordingly, if it was intended by the parties tha t the term “fixed pontoon” included the walkway, then the length of the walkway had to be included in its length in order for this interpretation to be consistent with its context . This clearly was not the case. 42. I therefore accept that my interpretation of the description “fixed pontoon” is consistent with its context, its ordinary and natural meaning, the commercial purpose of the policy, and the intention of the parties by both their words and conduct. 43. Accordingly, I am not satisfied the costs associated with the walkway should have been included in the sum insured for “fixed pontoon”. It therefore follows that the amount allowed for by the FSP’s loss adjuster in this regard, being $6,468, should be paid. Flood Chain 44. In my opinion, there is ambiguity regarding whether a flood safety chain would fall within the description of “fixed pontoon”. Although I accept it serves as a safety function in the event the piles fail, it does not necessarily fix the pontoon to one position. Instead, it limits the boundaries the pontoon could travel in the event the piles’ integrity fails. 45. As explained previously, I accept the reasonable person’s interpretation of the term “fixed pontoon ” would include ancillary items that keep the pontoon fixed at a certain point in the water. I do not accept it is reasonable to Case No: 259390 Determination Page 7 of 7 incorporate an interpretation that includes other items associated with it that cannot be characterised or described as being part of a “pontoon” or whose primary function is not to keep it fixed at a certain point in the water. 46. As explained previously, a flood safety chain ’s primary function is to limit the boundaries the pontoon can travel in the event the piles fail. It does not fix the pontoon to a specific spot on the water. This is the piles ’ function . Accordingly, I do not accept it falls within the term “fixed pontoon” . 47. In addition, I note the flood safety chain is secured to the “fixed jetty” in order to achieve its primary function. Although I appreciate its purpose is to secure the pontoon, its primary function is established by the fact it is secured to the “fixed jetty”. It is therefore arguable that it is associated with the fixed jetty. 48. Accordingly, even if I were to accept that there is scope to interpret the phrase “fixed pontoon” to include the flood safety chain, I also accept there is enough ambiguity in the phrase that it can also be interpreted to exclude the item. As such, the principle of contra proferentum would apply in that the more favourable interpretation to the insured should be adopted. 49. Given this, I therefore accept the costs involved in this item, namely $687, should be allowed. Determination 50. On the basis of the available information I determine the following: a. The FSP is entitled to deny liability for the costs and works involving the two piles, namely the re-driving and the two roller pile brackets, totalling $12,401. b. The FSP is required to pay an additional amount of $7,155 for the walkway and flood safety chain. c. The FSP is required to pay interest on the amount of $7,155 pursuant to section 57 of the Insurance Contracts Act 1984 , from 17 May 2011 (being the date it first proposed to limit its settlement in regards to the walkway and flood safety chain) to the date of payment. 51. In the event the Applicants accept this Determination, the FSP should pay the appropriate sum within 14 days of being notified of their acceptance.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.