The Applicant's contents were damaged by floodwater in Oxley, Queensland in January 2011 and the FSP denied the claim under the river flood exclusion. The Panel found the PDS adequately informed her of the exclusion and no payment was ordered.

Clear PDS wording satisfied section 35 of the Insurance Contracts Act 1984, and the loss was attributable to excluded river flood rather than stormwater.

Issues

Subjects and remedies

natural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 259117 Determination Page 1 of 8 Case number: 259117 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - Water Inundation - Flood 18 June 2012 NOTE: The Applicant was represented by a legal representatives; for ease of reference, the term Applicant will be taken to include all submissions made on her behalf. Background 1. The Applicant held a home contents policy with the Financial Services Provider (FSP) from 2006. The policy provided contents cover for up to $57,000. 2. On or around 12 January 2011, the Applicant’s home in Oxley was damaged as a result of water inundation at the time of the flood events that affected significant parts of Queensland. 3. Based on the report from its loss adjuster and the hydrology reports from the Insurance Council of Australia (ICA), the FSP denied the claim. It later retained a hydrologist to assess the damage via site specific report and reiterated the denial as it considered the loss was due to flooding, which is excluded under the policy. 4. The Applicant disagrees with the decision and seeks reimbursement for her losses, which should be to the limit allowed under the policy. Summary of Applicant’s position 5. The Applicant says she was verbally informed that the policy provided flood cover when incepting the policy in 2006. 6. The definitions provided regarding flooding and other issues in the FSP’s policy are confusing and contradictory. It does not discharge the FSP’s obligation to “clearly inform” her of what is covered under the policy. 7. Her home was subject to water inundation from local stormwater drains and should be covered. Determination Case No: 259117 Determination Page 2 of 8 Summary of FSP’s position 8. The FSP says that the loss was caused by the flooding of the nearby Brisbane River and Oxley Creek. Losses due to “river flood” are excluded under the policy. 9. The Applicant does not deny that she was supplied with and read a copy of the Product Disclosure Statement (PDS) in 2006. This document is clear and unambiguous in defining the cover for the policy. 10. No evidence of any undertakings allegedly given by the FSP has been provided and the PDS clearly contained information to the contrary. This document discharged the FSP’s obligations under Section 35 of the Insurance Contracts Act 1984 (the Act). This provides that, where a claim is made under a prescribed contract and the event giving rise to the claim is a prescribed event in relation to the contract, an insurer may not refuse to pay an amount equal to the minimum amount of cover set out in the regulations made pursuant to the Act unless it can prove that before the contract was entered into, the insurer clearly informed the insured in writing of the relevant provisions of the contract, or that the insured knew or a reasonable person in the circumstances could be expected to have known of such provision. 11. The FSP relies upon the following policy provisions: Page 4 of the PDS “ What you are not covered for There are certain times when this insurance may not provide cover. Some events we may not cover include:  Damage caused by... river flood (see Section 1.12).” Pages 13-18 of the PDS “ Definitions (The Meaning of Some Words) ... “flash flood” means what occurs when there are heavy, intense bursts of rainfall, usually during thunderstorms where so much water falls in a very short time that it cannot get away quickly enough and collects and flows into your home . but does not include when rainwater on the site :  cannot run off into a water catchment system, because it is overflowing in flood; and  mixes with the flood water coming from the water catchment syste m and then flows into your home . ... “rain” means water that has fallen from the sky on to your home and the site but not water from flash flood . “river flood” means when water that is normally contained in a water catchment system increases because of rainfall or snow melt (whether in the immediate region or elsewhere) or is deliberately released by an authority, Case No: 259117 Determination Page 3 of 8 and the water overflows onto land that is not normally covered by water into your home . For example water may be deliberately released by an authority from a dam or reservoir. ... “water catchment system” means;  a river, creek, other natural watercourse or lake, whether they are in their original state or have been modified, are named or unnamed, or normally dry that only run during periods of rain;  a dam, reservoir, storm water channel or canal.” Pages 19-25 of the PDS “ SECTION 1 INSURED EVENTS CAUSING LOSS OR DAMAGE ... This policy insures you up to the amount of the sum insured for loss or damage to your contents caused by an insured event listed below. ... 1.12 Storm, Rain Or Flash Flood You are insured for damage to your contents caused by storm , rain , or flash flood . ... We will not pay for damage caused by: …  river flood ...” Issues 12. Whether the FSP’s representative made any representations to the Applicant which might entitle her to cover for flood damage under the policy. 13. If not, whether the Applicant was adequately informed that the policy did not provide cover for flooding, as required under Section 35 of the Act. 14. Whether the Applicant’s loss should be covered under the ambit of the policy. Reasons for decision 15. The Panel is satisfied that a full exchange of the relevant information has taken place between the respective parties and that each party has had the opportunity of addressing any issues raised. Case No: 259117 Determination Page 4 of 8 16. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the potential amount of the claim a nd the issues to be considered. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 17. This decision has been made by a Panel consisting of an Ombudsman, an insurance industry representative and a consumer representative. The limitations of the policy and whether the Applicant was informed 18. The Applicant insured with the FSP initially in 2006. The Applicant recalls that: “... I spoke to a few insurance agencies and a salesperson from [the FSP] told me that they insured for flood. What I do remember is I rang around for flood insurance on purpose. When I asked if they had flood insurance, they said yes without any qualifying statements. I bought the insurance then they sent out a brochure with all the definitions after I had bought it. I had read the brochure before the next year and didn’t change my insurance as I didn’t realise that the 1974 floods had been defined as river flood.” 19. No specific details about who the Applicant spoke with, the exact nature of the representations made or her exact understanding of the cover itself were provided. The Applicant read the PDS but saw no reason to question the apparent differences between the cover specified and what she believed she had been provided. 20. The Applicant renewed the policy over the subsequent years. Outside of the initial representation allegedly made, she has suggested no other reason for her belief that flood cover was provided and/or was continued through the subsequent renewals of the policy. 21. The FSP has no recording of the conversation to incept the policy, although it states that such an alleged representation from the (unnamed) person would be extraordinary in light of the PDS, which specifically excludes losses due to “river flood”. 22. The Panel considers it difficult to accept that the Applicant would be informed that the policy provided flood cover without any qualification. This is not to suggest that the issue was not discussed or that the Applicant may have been left with the impression that such co ver was available. A finding on this cannot be reached as there is simply not enough information to discern what representation (if any) was actually made. Any ambiguity on the issue should have been resolved through provision of the policy documents. 23. It i s clear from a review of the PDS that it was the FSP’s intention that this policy should not provide cover for “river flood”. This is clearly at odds with the stated aim of the Applicant in obtaining such cover and any possible representation made to her at the time of inception. Case No: 259117 Determination Page 5 of 8 24. Section 35 of the Act allows for an insurer to define and limit the level of cover offered for insurance on the basis that it “clearly informs” the policyholder. This requirement is in writing and no obligation is on the insurer to inform a policyholder of the limitations of cover verbally. 25. Therefore, the clarity of what is outlined in the PDS determines whether the FSP has complied with its obligations under section 35 and whether it is entitled to limit its cover to exclude losses which are attributable to flooding. 26. Whilst the Panel does not doubt that the Applicant may have intended to obtain flood cover under her policy and/or thought that she did, the document outlines on page 4 that some items (including “river flood”) may be excluded from cover. It further outlines through pages 13-25 the various definitions to cover, what is classified as “river flood” or “flood” and the distinctions between these definitions. It also clarifies that “river flood” is a specific exclusion for lo sses relating to claims for “storm, rain or flash flood”. 27. The Panel accepts that the PDS adequately demonstrates that the policy does not provide cover for damage attributable to “river flood”. 28. Accordingly, the Panel is satisfied that the FSP has discharged its obligations under the Act to make the Applicant aware of the conditions of the policy. The FSP is therefore entitled to rely upon the limitations stipulated to restrict cover for the loss. Cause of the loss 29. There is an onus on an insured to establish on the balance of probabilities that a claim fits the definition of an insured event. Should this onus be discharged, it is then the responsibility of the insurer to establish the application of any exclusion on which it relies to deny the claim. 30. To be entitled to cover from the FSP, the onus therefore rests with the Applicant to establish that her loss fits within the scope of what is covered by the FSP’s policy. 31. The policy provides cover for a series of defined events as outlined in the PDS. It does not provide blanket cover for all types of loss. 32. It is not in dispute that the Applicant’s property was inundated with water on or about 12 January 2011 as a result of a significant weather event that affected much of Queensland in early 2011. An estimation of the Applicant’s losses from this event has not been made. 33. Given that heavy rains had occurred and that the home was inundated by water, the Panel accepts that a prima facie claim for cover under “storm, rain or flash flood” can been establish ed. The onus then turns to the FSP to establish that this loss was directly attributable to the policy excluded event of a river flood. 34. After the report of the loss, the FSP retained a loss adjuster, MY, to visit the site and to provide a report. MY noted in his report of 3 February 2011 that Case No: 259117 Determination Page 6 of 8 the single storey home was inundated to a depth of about 2.5m. The home was located about 300m from Oxley Creek. MY attributed the cause of the loss to flooding of Oxley Creek and the Brisbane River. 35. The FSP initially chose not to retain a hydrologist to provide a site-specific report. It instead relied upon the findings from the ICA general report into the flooding events. 36. After the matter was referred to the Service, the FSP retained WR to visit the site and prepare a report to evaluate the cause of the damage. This report of 5 August 2011, noted:  the property was inundated around 5am on 12 January 2011. It was ultimately inundated to a depth of approximately 2.5m above floor level;  the Corinda High Alert rainfall station was located about 1.3km northeast of the property. It recorded 125mm of rain fell during the period 10-12 January 2011. The peak rainfall occurred in the hour up to 11am on 11 January 2011. No rainfall was recorded after 5pm on this day. Peak stormwater run-off for the area would have occurred within 10-30 minutes of the peak rainfall;  the property is located about 260m from an open drain. Oxley Creek is about 750m east of the property;  ground contours in the vicinity of the subject property indicate that the ground level adjacent to the house is approximately 6.0m AHD. The floor level of the property is raised about 0.6m above the ground level which indicates that that the floor level of the house on the subject property is approximately 6.6m AHD;  the rainfall for the area was of a low intensity and not sufficient to account for stormwater run-off inundating the property; and  inundation of the property was due to flood water from the Brisbane River backing up along Oxley Creek. 37. The Applicant suggested that the water emanating from the drains surrounding the property opened the possibility of cover under a separate section of the FSP’s policy: “ 1.7 Water Or Other Liquid You are insured for damage to your contents caused when water or another liquid suddenly escapes from: ...  the  road gutter or curbing,  water main or pipe.” Case No: 259117 Determination Page 7 of 8 38. The above insured event is not subject to the specific flood exclusion reserved for storm claims. 39. In the Applicant’s submission to FOS dated 19 April 2012 that the Applicant finally asserts: ‘We note the presence of a number of stormwater drains in the (name of road and area). In our submission as there is no definition of a water pipe in the (name of FSP) policy its natural and ordinary meaning should be preferred. A Stormwater (sic) drain has been identified as running directly along the street where our client is located. Additionally, A (sic) number of Stormwater Maintenance Holes (sic) are located on and around our client’s property. A reasonable person is likely to view a stormwat er drain as a ‘water pipe’ because its function is to drain water from a residential area safely. As a consequence, any water escaping from the stormwater drains in the (name of area), which then damaged our client’s property is covered by the (name of FSP ) policy. As a consequence, in our submission, our client’s property experienced multiple events which saw significant water first enter the property through the water pipe (stormwater drains) in the area. The (name of FSP) policy responds to this damage under clause 1.7 and as a consequence, our client’s claim should be paid’. 40. The FSP has argued that such an argument by the Applicant must fail as: a) There was no sudden escape of water, the inundation was not unexpected and did not occur quickly. The FSP argues that there were numerous flood warnings some as early as 7 January 2011 and therefore the inundation could not be considered sudden. b) The water built up in the storm water drains over a period of time and cannot be said to have happened quickly. c) The overwhelming effect of the backwater flooding means the inundation was proximately caused by the river flood as defined. d) The policy must be read as a whole to understand the commercial intent and it is clear that it was never intended to cover river flood. 41. The Panel has considered the issues involved with respect to this. The Applicant’s property is raised approximately 0.6 metres above ground. The available information suggests the rainfall ceased around 5pm on 11 January 2011. The peak rainfall had occurred at 11am. Most likely based on the hydrology information, the peak runoff would have occurred within around one hour of the peak rainfall, the inundation did not occur until around 5am on 12 January 2011 some 18 hours after the peak rainfall. In the circumstances, it is unlikely that it was rainfall runoff or storm water runoff into the drains that led to the inundation. 42. The policy wording is not clear. The policy wording creates as a defined event water suddenly escaping from a road gutter or curbing, water main or pipe. It does not under that defined event expressly exclude flood water that might backflow through the water main or pipe causing the water to overflow or water that backflows and overflows the street gutters. Case No: 259117 Determination Page 8 of 8 43. Despite this wording, the Panel is satisfied given the height of the house at .06 metres above ground level that the property would not have been inundated by water that had suddenly escaped whether it be considered backflow water or otherwise the road gutter or curbing, water main or pipe. The Panel is satisfied based on the information exchanged that in order to inundate the property given the height of the property above ground that the inundation was most likely due to the overflow of flood water from the Oxley Creek as a result of the flooding of the Brisbane River. 44. Accordingly, the Panel is satisfied that the Applicant’s loss is excluded under the policy. Determination 45. On the basis of the available information, the Panel determines that the FSP is not obliged to cover the Applicant for his loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.