Home / Financial Firm (Unknown - Insurer) / Determination 257974
Determination 257974
Rectification work - Claim amount
Summary
The insured disputed storm damage repairs and the insurer's scope of settlement, including roof tiles and carport concrete. AFCA found the insurer's $11,500 settlement offer met its obligations and did not interfere with it, so no order was made.
The insured bears the onus of proving covered damage, the roof leaks were wear and maintenance related, and carport cracking was dominated by subsidence which the policy excludes.
Issues
- Claim denial primary · not upheld“The FSP is not obliged to replace all the tiles as requested by the Applicant as, on the balance of probabilities, the problem with the roof leaking is a wear, tear, and maintenance related issues”
- Repairs or contractors secondary · not upheld“The Applicant has provided no evidence in support of her assertions and without such evidence I rely on the reports provided by the FSP”
Subjects and remedies
home or building damagenatural disasterno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 257974 Determination Page 1 of 8
Case number: 257974
General Insurance - Domestic Insurance - Home Building – Rectification work -
Claim amount
15 August 2012
Background
1. The Applicant is insured under a home building and contents insurance
policy with the Financial Services Provider (FSP).
2. The Applicant lodged a claim under the policy as result of storm damage
caused on or around 22 March 2010. The FSP arranged for a builder and
loss assessor to attend the property and report on the damage.
3. The FSP accepted a claim for storm related damage that had been
identified. The FSP cash settled the Applicant for damage to the garden
shed and authorised for repairs to the home dwelling.
4. The Applicant was not happy with some of the repairs and raised issue with
the qualifications of the repairers undertaking the work.
5. The FSP arranged for the property to be re-inspected by its loss assessor
and another builder. The builder identified the flowing repairs issues:
- Laundry security door to be replaced
- Ease laundry door and repaint
- Patch and feather painting to internal edge of wall parallel with rear door
and paint wall, seal and paint laundry ceiling, bathroom ceiling and
lounge ceiling
- Remove roof sheets, flashing and battens on patio, install new battens,
roof sheets and flashing, paint battens
- Repair flashing on roof around chimney in the car port
- Clear building debris
6. The quote to attend to these repairs was $9,320.30.
Determination
Case No: 257974 Determination Page 2 of 8
7. The report identified other repairs that was not storm damage or related to
faulty workmanship but was the responsibility of the Applicant:
- Replace 12 cracked roof tiles, re-point ridge capping, remove and replace
chimney flashing on main dwelling
- Strip rear skillion roof tiles, replace installation, install sisulation and refit
roof tiles on new battens.
8. The quote to repair this additional work was $1,465.20
9. The FSP offered cash settlement of $10,717.70 for covered repairs which
included replacement of 12 cracked tiles in order to assist settlement.
Summary of Applicant’s position
10. The Applicant says she is dissatisfied with the repairs undertaken and that
the FSP has failed to identify all storm related damage.
11. The Applicant says the FSP has failed to provide her with information she
has requested about the repairers who have attended her property.
12. The Applicant says she is seeking replacement of all the roof tiles. She says
the roof is still leaking and the FSP initially had repairs undertaken to the
roof. She disputes that the cause of the roof leaking is to do with
maintenance related issues.
13. The Applicant listed rectification works still required to reinstate her property
and must be done by appropriately qualified and registered persons:
The door frame that is moving is to be replaced with a jarrah door
frame;
The damage to the underlying brickwork behind the door frame is to
be fixed by replacement of the brickwork;
The inferior brand deadlock on the back door is to be replaced with a
Whitco deadlock;
The back door is to be repainted back to its original colour. Although
she agreed to allow the door to be painted to match the lattice this
was not done;
The ceiling in the second bedroom has been inadequately patched
and will need to be re-done and painted;
The costing for the replacement of the patio is to be recalculated
using hardwood;
The carport is to be replaced using hardwood;
Case No: 257974 Determination Page 3 of 8
The mouldy laundry cupboard needs to be replaced;
The mouldy gyprock in the laundry needs to be replaced;
Any ceiling panels damaged by water are to be replaced;
Gyprock above the back door needs to be replaced;
Insulation batts are to be properly inspected and if mouldy or water
affected are to be replaced;
Plastic pot plants damaged by the carpenters are to be replaced;
Wasted expenses in boarding her budgies when work was supposed
to be attended to at the property;
The front gutter to be replaced as it was damaged by workmen
stepping on it;
Any damage to the air conditioning compressor by water running into
the carport due to no flashing installed is to be covered;
Impact damage to the concrete carport is to be covered. If the FSP
maintains it is not storm related that it should get a report from an
appropriately qualified person.
Summary of FSP’s position
14. The FSP says it has identified repairs it is responsible for.
15. It says the Applicant has not discharged her onus of establishing all the
damage in question was caused by an insured event.
16. The FSP says that the expert evidence relied upon establishes, on the
balance of probabilities, this damage was not caused by a storm event but is
the result of:
a) wear, tear and deterioration; and or
b) the Applicant‟s failure to maintain the house in good repair and condition.
17. The FSP relies on the following policy provisions:
“ Storm
If loss or damage is caused by a storm,
...
Covered
► violent wind, cyclone or tornado
► thunde rstorm, hail rain or snow
Case No: 257974 Determination Page 4 of 8
► sudden, excessive run -off of water as a direct result of a storm in your local
area.
...
General exclusions
The exclusions shown in this section apply to all cover under your policy.
What we don’t cover
Loss, damage, injury or death arising from:
► wear, tear, rust, corrosion or deterioration
...
Maintaining and occupying your home
We don‟t cover loss, damage, injury or death arising from:
► you not maintaining your home in good repair and condition. This means
your home must be structurally sound, secure and well maintained
...
Lifetime guarantee
We provide a „lifetime guarantee‟ when your home is repaired or rebuilt by
one of our preferred repairers or builders.
This means:
► we guarantee the workmanship of repairs that we authorised for the
lifetime of your home
► we will fix any defect caused by poor workmanship.”
Issues
18. Whether the FSP ‟s offer fulfils it s obligation under the terms and conditions
of the policy.
Reasons for decision
19. FOS has considered it is appropriate to expedite the dispute in accordance
with clause 8.6 of the FOS Terms of Reference. This is because of the
issues in dispute and quantum. This dispute has not been the subject of a
FOS Recommendation and has proceeded directly to Determination.
20. There has been an exchange of material between the parties. It therefore is
not intended to recite details of the information in this Determination except
where considered relevant.
21. The Applicant has raised issues regarding the FSP breaching the General
Insurance Code of Practice (the Code). The allegations include
unlawful conduct by the FSP and its representatives;
the FSP failing to provide her with requested information;
Case No: 257974 Determination Page 5 of 8
not been fair and transparent in the conduct and management of the
claim.
22. The FSP says it has not breached the Code and has conducted itself
reasonably and appropriately at all times and has cooperated with the
Applicant.
23. Nevertheless, I will refer the allegations of the breaches of the Code onto the
Service‟s Compliance Team to consider if inve stigation of this is warranted.
24. The Applicant is seeking indemnity under the policy so the onus is on her to
establish that the damage claimed which has been not accepted by the FSP,
was caused by an event covered by the policy or for which the FSP is liable
for.
Further damage.
25. The FSP states the Applicant has alleged further damage is occurring to the
property. It says it has not had the opportunity to inspect this damage. It says
it should be given the opportunity to undertake a further assessment.
26. I concur with the FSP. If the Applicant is asserting further damage has
occurred which she holds the FSP liable for the FSP should be entitled to
assess this damage so that it can ascertain as to whether is liable under the
policy for this damage.
27. The Applicant and the FSP should arrange an appropriate time for this
additional damage to be assessed.
Is the FSP obliged to replace all the roof tiles?
28. It is not disputed that further works are required to complete repairs at the
property. The FSP has outlined it its letter to the Applicant dated 6 January
2012 its proposed settlement for the works for which it says it is responsible.
29. The FSP listed repair work from (a) to (h) but advised the Applicant it was
not responsible for items (f) and (g) and advised the Applicant she was.
30. In correspondence, to the Service dated 15 June 2012, in attempt to finalise
this matter, the FSP advised it was now prepared to :
1. offer a cash settlement of $11,500; or
2. complete repairs (a) through to (e) and (h), and
3. repair the dislodged gutter above the front door, and
4. repaint the back door.
31. The FSP maintained the Applicant must first undertake repairs noted as (f)
and (g) in its letter of 6 January 2012.
32. However, the Applicant advised she would not be attending to any repairs
and that she holds the FSP liable for rectification of the roof.
Case No: 257974 Determination Page 6 of 8
33. Under the lifetime guarantee provided for in the Applicant‟s policy the FSP
guarantees the workmanship of repairs that it authorises and any defect
caused by poor workmanship.
34. The Applicant says the roof suffered hail damage and/or was the subject of
faulty workmanship and/or damaged by persons acting on behalf of the FSP.
35. The Applicant complained that the roof continued to leak even though she
says she was advised the roof was sound. The Applicant says the policy
provides her with a lifetime guarantee and as such believes the FSP is
obliged to attend to rectify the problem with the roof by replacing all the tiles.
36. The FSP does not dispute that rectification of repairs was required. It says
these repairs have been identified and have been conveyed to the Applicant
in the correspondence.
37. However, the FSP says it is not obliged to replace all the roof tiles. It says
the problem with the roof leaking is not the result of an insured event or
faulty workmanship but is the result of wear, tear and deterioration. The FSP
relies on the information obtained from its loss assessor and builders who
attended the property.
38. I note when the property was first inspected on 5 July 2010 it was indentified
there was up to 4 broken roof tiles. It is understood a tiler attended the
property for the repair/replacement of the tiles. The Applicant says she is
unsure as to whether any repairs were done to the roof at this time.
39. Nevertheless when the Applicant raised her concerns with the roof still
leaking as well as other concerns the FSP arranged for the roof to be
inspected by a builder (CM) representing a building company (RBD).
40. In his report CM noted the roof issues as:
“Roof tiles were checked and we found bedding to pointing has deteriorated in
areas and full length of ridge will require repointing.
Flashing to chimney was found to be deteriorating, there are signs of surface
corrosion and lead flashing found to be split. Damage to lead flashing is
above water damage to lounge ceiling.
Approximately 12 tiles in various areas over roof were found to be cracked
and require replacement.”
41. The FSP has accepted responsibility to cover the cost of the replacement of
the 12 roof tiles. The FSP say it has done this even though there is no
indication these were cracked other than as a result of wear and tear.
42. I accept the FSP was entitled to rely on the CM‟s report although the
Applicant has raised broad concerns about persons acting on behalf or
reporting to the FSP.
43. Although the Applicant disagrees with the FSP she has not obtained any
expert opinion. The Applicant has indicated to the Service that she does not
Case No: 257974 Determination Page 7 of 8
believe it is possible for a report to be obtained two years after the claimed
event occurred.
44. Nevertheless, the Applicant asserts the roof has either been damaged by
hail, faulty workmanship or damaged by a person acting on behalf of the
FSP.
45. However, I would expect hail damage to be able to be identified irrespective
of the age as well as identifying issue with workmanship or poor repairs.
46. The Applicant has provided no evidence in support of her assertions and
without such evidence I rely on the reports provided by the FSP.
47. I am satisfied the extent of the FSP‟s liability to the roof is limited to the
replacement of 12 roof tiles. The FSP is not obliged to replace all the tiles as
requested by the Applicant as, on the balance of probabilities, the problem
with the roof leaking is a wear, tear, and maintenance related issues.
48. It has also been recommended that the insulation in the roof above the
laundry be replaced with sizalation as a preventative measure for moisture.
This is noted as item (g) in the FSP‟s letter of 6 January 2 012.
49. This appears to be a maintenance issue rather than claim related. As such I
am satisfied the FSP was entitled to exclude these repairs from the
settlement. I note the FSP has asked the Applicant replace the insulation
prior to painting of ceilings.
Is the FSP obliged to repair damaged carport concrete?
50. The courts have determined that in order to decide whether the damage is
covered by the policy the proximate cause of the damage must be
established. The proximate cause is not necessarily an occurrence which is
last in the point of time but rather the dominant factor in the damage.
51. Included in the Applicant‟s claim, is the repair of the carport concrete floor
which she says was damaged by the storm event. Specifically the Applicant
has indicated the concrete was damaged by hail.
52. The FSP relies on the findings of its loss assessor to deny repairs to the
concrete floor. According to the loss assessor the crack in the concrete
appeared to be consistent with subsidence or settling; causes which are
excluded by the policy.
53. I have sighted the loss assessor‟s report , which is not extensive and
photographs of the carport concrete. The photographs show a crack that
runs the length of the carport.
54. Although the policy provides cover for storm damage, damage caused by
subsidence is covered only if the preceding event is earthquake or
explosion.
Case No: 257974 Determination Page 8 of 8
55. It is also well established law ( Wayne Tank and Pump Co. Ltd v Employers’
Liability Assurance Corp. Ltd. [1973] 3 AII E.R. 825) that where there are two
effective causes of a loss, one of which is excluded and one which is
included in an insurance policy, the excluded clause operates to over-ride
the included clause and defeats the claim.
56. The FSP made reference to the Wayne Tank principle but not specifically in
regards to the damage to the concrete.
57. I am satisfied the dominant factor, on the balance of probabilities, for the
damage to concrete was subsidence and the storm was merely a precipitate
event.
58. As such the FSP was entitled to deny indemnity for repairs to the carport
concrete.
Settlement amount.
59. The FSP has offered to cash settle the Applicant for the amount $11,500 for
identified repairs or in the alternatively it will attend to the repairs.
60. I accept under the terms and conditions of the policy the FSP is entitled to
cash settle a claim. I am satisfied the amount is inclusive of those concerns
raised by the Applicant.
61. However, once repairs are authorised and undertaken and there are issues
with those repairs, the FSP is obliged to attend to rectify those repairs in
accordance with its obligation under the lifetime guarantee it provides.
62. If the Applicant does not wish to the FSP to attend the rectification works
then the FSP may offer cash settlement of the claim.
Determination
63. On the basis of the available information I determine the FSP‟s settlement
offer of 15 June 2012 fulfils it obligations towards the Applicant. As such I do
not intend to interfere with this offer.