Partial denial of storm damage claim under earth movement and wear exclusions; quantum of repairs
Text of the determination
Case No: 257846 Determination Page 1 of 31
Case number: 257846
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
5 June 2013
Background
1. The Applicants were insured with the Financial Services Provider (FSP)
under a farm insurance policy that covered their home building, which was
insured in the sum of $400,000, sheds insured in the sum of $60,000, fences
insured in the sum of $5,000, and barns insured in the sum of $20,000,
together with cover for “additional increased costs ” of $5,000 . The relevant
period of insurance was 19 February 2010 to 19 February 2011.
2. A claim was lodged under the policy as a result of storm damage to the
property which occurred on 7 December 2010. The FSP appointed a loss
adjuster to attend and inspect the property. The loss adjuster MJ of C&C
attended the property on 10 and 11 December 2010. He indicated that
substantial damage had been caused by water and hail.
3. As a result of the inspection by the adjuster, various tradesmen were
engaged to carry out inspections and rectify immediate damage to the
property. The FSP has paid out the sum insured for fencing.
4. Following several reports from the adjuster, the decision was taken by the
FSP to arrange for a structural engineer to conduct an inspection of the
property. The engineer Mr B of MP has furnished a series of reports
including the provision of a scope of works for work which the engineer
believed would cover all of the damage caused by the c laimed event.
5. As a consequence of the engineer’s first report, the FSP wrote to the
Applicants on 27 July 2011 advising that parts of the claim would be
excluded. The partial denial by the FSP was in a letter which referred to
policy exclusions setting out why all damage was not covered.
6. The Applicants disagreed with the FSP’s decision to partially deny the claim.
Ultimately after many submissions from the Applicants to the FSP, the
Applicants requested review through its internal dispute resolution
procedures (IDR). However following the IDR review, the FSP maintained its
partial denial of the claim.
Determination
Case No: 257846 Determination Page 2 of 31
7. Further submissions were made by the Applicants to the FSP which resulted
in further requests by the FSP that MP review its earlier reports.
Nevertheless, the FSP has maintained its partial denial of the claims.
8. The FSP obtained quotations for the repairs originally estimated by MP to be
required as a result of the damage sustained in the storm. Initially quotations
were obtained in the sum of approximately $12,000.
9. However, by August 2012 and in response to continued submissions by the
Applicants, a further firm “M” was engaged by the FSP to prepare two
scopes of works. The first was a scope of works (number 1) for the work to
be carried out, in order to complete the repairs which the FSP agreed should
be approved, as a consequence of the storm.
10. Two quotes were obtained for the completion of that work from scope of
works number 1. One quotation, from a firm “B” was in the sum of $57,970.
The second quotati on, from the firm “C”, was in the sum of $42,854.50. (Both
quotations included GST).
11. Simultaneously with the preparation of a scope of works in respect to work
for which the FSP had admitted liability, M was also asked by the FSP to
prepare further scopes of works in respect to the work which was required to
be carried out to the property, but for which the FSP denied liability. Again,
two quotations were received from B in the sum of $247,390, and from C in
the sum of $188,127.26 (both quotations included GST).
12. Shortly before the preparation of the two scopes of works by M, the
Applicants, for the first time, engaged an expert for an opinion as to the
damage sustained to their property as a result of the storm. On 26
November 2012 the consulting engineer PC furnished a first report to the
Applicants. In summary, that report expressed conclusions which were
largely at odds with the conclusions reached by MP in their various reports.
13. In a subsequent report PC provided a commentary on the scopes of works
provided by M. But the FSP has maintained its partial denial.
Summary of Applicants ’ position
14. The Applicants submit that all of the damage which is referred to in both of
the scopes of works, is related to the storm, and is damage for whic h they
are entitled to be indemnified by the FSP.
15. They point to the initial assessment by MJ from the firm C&C and the fact
that MJ who inspected the property within a few days of the storm, appeared
to have no doubt about the magnitude of the damage which had been
caused to the property by the storm. MJ has since died and his work was
subsequently carried out by another adjuster at C&C.
16. They point to the fact that the first adjuster had attempted to illustrate to the
FSP the magnitude of the storm. Whilst it appears that MP have accepted
Case No: 257846 Determination Page 3 of 31
that indeed the storm was severe, the Applicants doubt that the FSP has
ever accepted the true magnitude of what happened on 7 December 2010.
17. They rely upon statutory declarations by KH and CK, two friends who
assisted them when they bought the property and who have declared that
after the storm they attempted to reach the Applicants by road but were
unable to do so. In the statutory declarations they state that “the main
bitumen road that runs past the front of the property had completely erupted
and was torn apart and lifted and it was impassable and so was the unmade
dirt road that runs alongside. A car had been swept across the other side of
the main road and was turned on its side on the land adjacent to the road. ”
18. After being turned back by attendants, KH and CK made their way to the
subject property on foot. They found that the driveway had completely
washed away and was full of huge holes, the entry gates were forced shut
with debris and earth fill, concrete was holding the gate posts which had
been pushed up and out and the surface of the veranda was covered in
water. Even when the water was removed from the top of the veranda, water
was still coming through to the surface from underneath the concrete and the
veranda was very badly cracked and damaged.
19. CK and KH have also commented that “the basement and the beautiful
cottage directly next to the house are at a lower level and the inside kitchen
floor surfaces were completely inundated. The basement used for storage
was completely flooded. The force and massive volume of water had forced
its way through the window above ground level and ruined the inside walls ” .
They helped the Applicants pump the water out and remove the contents.
The outbuildings/shed gutters had failed because of the storm and sheer
weight of the water and hail. All communications and power services were
destroyed and a generator was required to provide power. Domestic water
service and irrigation pipe were destroyed, all paddock and perimeter
fencing was ripped out of the ground and taken with the storm. Many farm
animals were lost.
20. CK and KH also commented upon the condition of the property at the time
that it was purchased by the Applicants. They have declared that the
description of the property made by the Applicants is true and accurate.
21. Regarding the condition of the property before the storm, the Applicants in
their statutory declaration state that the surface appearance of the return
veranda surrounding the entire main residence was even, flat and without
any raised areas, perfectly sound and entirely consistent with normal use
and normal insignificant surface marks. There were no visible signs of open
cracking or deterioration as a result of wear and tear. Neither were there
visible signs during any of the inspections which they made prior to the
purchase of the property some ten months before the storm.
22. The pillars and posts and the balustrade walls showed no visible signs of
cracking or deterioration. The integral properties of the fascia, the gutter or
its fixings were also not deteriorated. They had consistently and continuously
Case No: 257846 Determination Page 4 of 31
served their intended purposes up until the events of 7 December 2010. The
gutters and fixings collapsed during that event.
23. The Applicants further state that prior to their purchase, there was no
evidence whatever of any dampness anywhere. There was no evidence
whatever of mould or mildew growth and no evidence to indicate there ever
had been. The house did not smell of damp and the atmosphere was not
representative or indicative of damp. There were no happenings or events
between 25 February 2010 (when they moved into the property) and 7
December 2010, which changed the very good condition or appearance of
the property as described.
24. After the inspection of the property by “B” of MP whose initial inspection was
in the absence of the Applicants, they queried and disputed a number of the
points made by Mr B. At various times they have pointed out numerous
errors in the original report of Mr B - errors which they suggest cast great
doubt upon the reliance which should be placed upon his various reports. As
examples, Mr B said “there are photographs o f the cracked northern veranda
slab two days after the rain event with weeds growing within the cracks. An
inspection of the edges of the cracked surface suggest the cracks are
weathered and fretting. They do not look to be of a recent origin.”
25. After correspondence from the Applicants, Mr B belatedly (12 months later)
admitted that in making this statement, he was in error, and that the “weeds
growing within the cracks” was in fact debris washed in by the storm.
26. Mr B also commented that the condition of the eaves, gutters and timber
fascia to the nearby south-eastern shed was always likely to collapse. The
gutters were severely rusted and the timber fascia and fixing into the end
grain of the timber rafters were rotted. The weight of a rapid build-up and the
continuing impact of the rainwater from the roof overloaded a structurally
inadequate fixed gutter and fascia. Mr B subsequently admitted that he had
not inspected the site of the gutters but had remained on the ground when
making this observation.
27. When commenting on the homestead, Mr B stated that “the solid masonry
dwelling has generally timber floors throughout”. In fact the property has
predominantly concrete floors, a fact which made impossible his suggestion
(when later commenting upon the dampness i n the kitchen) that a hole
should be cut in the floor to judge the degree of dampness under the kitchen
floor.
28. The Applicants say that the FSP’s handling of the matter must have been
influenced by that report, and that even though they made many
submissions to the FSP, it remained inflexible and not prepared to revisit its
opinion. This is despite the fact that one of the Applicants is a qualified
builder and therefore well able to make comment on the matters contained in
Mr B’s report.
29. In their submission the Applicants say the damage was caused by the
destructive effect of the inundation of water which became deep and which
Case No: 257846 Determination Page 5 of 31
proceeded across their property, in circumstances outlined by KH, and by
MJ of C&C.
30. The Applicants also rely upon the pre -purchase report obtained from M and
H (National Valuers). In this report, which was produced some ten months
before the storm event, it was stated that
“ the main building external condition is good;
the main building internal condition is good;
essential repairs – no essential repairs required;
additional comments – the property presents in good condition and at
the time of our inspection we did not observe any major problems or
faults with the property;
additional comments – we confirm that the property is readily saleable
at the assessed value herein and that there are no adverse features. ”
31. Accordingly, the Applicants say that this report, together with their own
submissions, the statutory declarations by KH and CK, combined also with
the initial assessment report of MJ of C&C, provide the best evidence of the
condition of the property prior to the storm, and that this evidence as to the
pre-storm condition of the property should be preferred to the conclusions
reached by Mr B of MP.
32. Regarding the two scopes of works prepared by MCS, the Applicants believe
that they are entitled to be compensated in respect to all of the items
referred in both scopes of works and that in addition to those scopes of
works, allowance must be made for the damage sustained to the
outbuildings described as the cottage and barn respectively.
33. The Applicants rely upon the expert opinions of “ P C”, an engineer whom
they engaged in September 2012.
Summary of FSP’s position
34. The FSP has relied upon the opinions of Mr B of MP.
35. Following the initial report by MP, the FSP partially denied the Applicants’
claim, and it has maintained that decision ever since.
36. The FSP relies on the following policy provisions:
“Section A – Home Cover
What you are not insured for
Under Section A – Home Cover, we will not pay for:
A. ...
B. Loss or damage to your property caused by:
a. ...
Case No: 257846 Determination Page 6 of 31
b. earth movement, vibration, erosion, landslide or subsidence
(except when caused by earthquake);
c. settling shrinkage or expansion in the Building, its foundations,
or any walls or pavement;
d. ...
e. ...
f. wear, tear, rust corrosion, depreciation, gradual deterioration,
mildew, dampness of atmosphere or variations in
temperature;”
37. The FSP points out that for a substantial period, the Applicants did not
s ubmit any expert opinion to dispute MP’s findings.
38. The FSP has received a significant number of submissions from the
Applicants challenging the MP findings, but the FSP has not seen fit to
change its earlier position.
39. Now that the Applicants have engaged the services of PC, the FSP has
considered the two opinions prepared by PC but it still maintains its partial
denial based upon the original MP report, and other information which has
been supplied to the FSP by MP, in response to the various submissions of
the Applicants.
40. In late 2012, the FSP instructed M to prepare two scopes of works. The first
is for work which the FSP acknowledges it is responsible. In response to that
scope of works, two tenders have been produced, in the sum of $42,000 and
$57,000 respectively and the FSP is prepared to permit the work proposed in
scope of works one, to be carried out by the lowest tenderer. Alternatively,
and now that the Applicants have left the property, it accepts its liability to
pay to the Applicants the sum of $42,000 being the lowest of the two tenders
submitted.
41. As to the second PC report, the FSP makes the following comments.
42. As to the significant reference which is made to the pre-purchase report
referred to above. The FSP replies that the firm which prepared the pre-
purchase report, is a firm of property valuers and not civil engineers.
43. The FSP again relies upon the opinion from Mr B of MP, that the 7
December 2010 rain event was “the str aw that broke the camel’s back”. In
other words, the bond between the surface of the wall and the underlying
stone work had been gradually weakened over period of time and the
inundation was simply the last event in the chain of causation. ”
44. It again submits that the dominant or effective cause (or the proximate
cause) was gradual water entry over a number of years. “The stormwater
runoff was simply a contributing factor without being the proximate cause”. It
is an established principle that a policy of insurance will only respond to the
“proximate cause” of a loss.
Case No: 257846 Determination Page 7 of 31
45. The FSP notes that the photographs appearing in the original MP report of
20 May 2011 clearly demonstrate where pre -existing damage had
undergone cosmetic repairs.
46. As to other aspects of the PC reports, the FSP argues that there are
inconsistencies in them. PC alleged originally that the cause of damage to
the veranda floors, pillars, posts and the balustrades, is “soil consolidation
settlement”, in other words , earth movement or the settling of a bu ilding’s
foundations. The FSP points out that even if PC is correct and the cause of
damage is “soil consolidation settlement” , then the policy exclusion for
foundation movement/settlement would nevertheless exclude cover. ”
47. If PC is now changing his opinion and is expressing the view that the cause
of the damage has been hydrostatic pressure from the stormwater runoff,
i.e., that the stormwater was the direct cause of the damage, the FSP argues
that this is inconsistent with his e arlier report. The FSP says “ the FSP
continues to refute this suggestion on the basis of Mr B’s opinion which has
been discussed in detail in its earlier submissions. However, in a letter of 17
December 2012, it pointed out that even if PC was correct and the cause of
damage was “soil consolidation settlement”, then the policy’s exclusion for
foundation movement/settlement would nevertheless exclude cover.
48. The FSP refutes PC’s claim that it has acted inconsistently by admitting
liability for the cracking and structural damage to the north facing exterior
wall, together with various cracks around window frames and ledges in that
region, but otherwise denying the claim.
49. It submits that its decision to allow those items of damage was based upon
the opinion of Mr B as set out on page 7 of his report dated 20 May 2011,
that in the case of that damage, the underlying cause was the inundation
event itself which the FSP concedes would be covered under the policy.
50. Thus, there is no basis for arguing that the FSP has waived its right to
decline damage caused by foundation movement, to other parts of the
property.
Issues
51. The fundamental issue in dispute in this case, relates to the extent of the
damage to the Applicants’ property, caused by the 7 December 2010 storm.
52. If it is determined that any particular item of damage is referable to the
storm, a secondary question arises as to whether the exceptions contained
within the FSP’s policy, enable it to deny liability for any part of the damage.
Case No: 257846 Determination Page 8 of 31
Reasons for decision
53. There has been an exchange of material between the parties. However, I do
not intend to recite information in this Determination except where
considered relevant.
54. Ultimately, and since the Applicants have had the benefit of expert advice
provided by PC, I am of the opinion that the matters in dispute between the
parties have been adequately set out and that each has had ample
opportunity to address the contention of the other.
Preliminary Comments
55. This is a very complex matter which follows a storm of unprecedented
magnitude. The evidence conclusively establishes that more rain fell in the
area of the Applicants’ property than on any previous recorded occasion.
The photographs produced by the Applicants showing the devastation to
their property are dramatic.
56. Whilst this issue is not now relevant to this dispute, I note that the Applicants
have effectively lost the entire benefit of the property due to the damage
which was sustained to it. Apparently a ravine now runs through the property
whereas there was no such creek, water course or physical feature
previously.
57. There have also been other most unfortunate matters which have affected
this dispute. The first assessor who inspected the property on behalf of the
FSP, MJ of C&C, unfortunately died shortly after his inspection. The
Applicants have claimed that his successor at C&C, who has been
responsible for preparation of some eight reports for that firm, has never,
nevertheless, inspected the property. It is unfortunate that the expert
personal knowledge of MJ, who had immediate knowledge of the post-storm
effects upon the property, was lost.
58. Based upon the original comments of MJ, the Applicants believed that they
had a reasonable expectation that the claim would be favourably dealt with
by the FSP. In making this comment I do not suggest MJ in any way made
representations on behalf of the FSP which it has not honoured but the clear
thrust of M J’s first report was to highlight the extent of the damage, to alert
the FSP to the fact that certain policy limits would undoubtedly be met (for
example fencing) and also to point out the likelihood that further damage
would become evident with the passage of time. Vitally, MJ also reported on
the generally very good condition of the homestead.
59. Thus, the partial denial of the claim, after Mr B of MP had inspected the
property, and had reported to the FSP in May 2011, came as a considerable
shock to the Applicants. Because of the background of the male Applicant as
a builder, the course adopted by the Applicants was to continue to
endeavour to negotiate with the FSP by means of very lengthy submissions
in an endeavour to point out that the MP report was incorrect. Some sixteen
months elapsed between the MP report (upon which the FSP has placed so
Case No: 257846 Determination Page 9 of 31
much reliance) and the obtaining of the first report by the Applicants from
PC.
The MP Reports
60. At the recommendation of the adjusters C&C, the company MP was
appointed and Mr B of that firm provided his first report in May 2011.
61. Mr B apparently first attended the site on 15 February 2011. According to
one of the submissions from the Applicants, they were not present at the
time of his first inspection, but before he furnished his report of 20 May 2011,
he had met with the Applicants, who had provided to him photographs of the
scene of the damage, and a video which shows quite extraordinary damage
to the land. It also showed the torrent of water flowing down towards the
Applicants’ front gate and Mr B had no difficulty in accepting that a water
inundation event occurred. He commented that there appeared to be no
natural watercourse which overflowed, but the long and gentle uphill sloping
topography of the land north of the Applicants’ dwelling had acted to collect
and channel some of the torrent of water towards the northern and western
faces of the veranda. He commented that water was reported to have flowed
over the concrete pavement between the dwelling’s northern side and the
outbuilding which contained a basement. Water had conti nued to flow south
and to wash away the gravel driveway.
62. The report indicated that the Applicants had advised that there had been no
inundation of water above the kitchen/meals door threshold and that no
surface water was reported to have covered the floor. It was reported that
there was an approximate 180mm step between the concrete pavement and
the veranda slab located in front of the kitchen external door and that the
Applicants had reported water seeping out of the cracked vertical face of the
veranda slab.
63. Mr B reported that initially “the only dwelling cracking was to the northern
wall of the office.” Between his first inspection on 15 February 2011, and the
13 April 2011 inspection, other cracks had appeared “adjacent to the office
window”. He also re ported that the Applicants had advised that veranda slab
cracking had got progressively worse and that there was now cracking
damage to the masonry pillars, perimeter balustrade and the clear roof tiles,
that there was flaking/pitting damage to the reddit face of the southern
masonry pillars, that there was a washout to some of the sand matrix and
the internal rendered surface to the nearby northern building’s basement
walls and to the dwelling’s perimeter balustrade, that there was minor
cracking to some of the ground level masonry walls to the building north of
the dwelling (the cottage) and that a stone rendered timber framed sheet
roof shed had lost a number of its eaves and gutters which had fallen to the
ground including some sections of the timber fascia. He reported that over
subsequent months, the remaining gutters had discharged water down the
external face of the rendered wall leaving a noticeable damp outline and that
the external wall had now cracked.
Case No: 257846 Determination Page 10 of 31
64. Importantly, Mr B included in his report a h eading “Evidence of previous
damage, relationship to the rain event and general observations”.
65. In this section, Mr B commented that the Applicants acknowledged that there
had been some existing cracking of the veranda slab. Vitally, he reported
that “there are photographs of the cracked northern veranda slab two days
after the rain event with weeds growing within the cracks. An inspection of
the edges of the cracked surface suggest the cracks are weathered and
fretting. They do not look to be of a recent origin. ” In making these
comments he either disregarded or was unaware of the first report by MJ of
C&C.
66. He commented that although the Applicants believed that the pillar and
balustrade cracking had only appeared after the rain event, the majority of
the cracking had occurred where there had been a previous repair. He did
concede that a section of horizontally cracked balustrade at the northeast
corner was overly damp.
67. He reported that although the Applicants believe that the timber veranda
posts had inclined as a result of the rain event, there was no indication of
any recent movement of the timber post at the top of the masonry pillar.
There was also no indication that the veranda slab at the base of the pillar or
balustrade had recently moved. The edges of the veranda slab were
generally uncracked against the balustrade-pillar stucco pattern finished
rendered surface.
68. He commented that the condition of the basement walls was severely
structurally compromised and deteriorated and that the basement walls had
been exposed to long-term moisture ingress over many years. He
commented that a heavy and rapid saturation of hydrostatic water pressure
behind the wall would have caused any loose or compromised material
within the stonewalls matrix to push out from the wall face.
69. He also commented that the condition of the eaves, gutters and timber fascia
to the nearby south-eastern shed (the barn) was always likely to collapse.
“The gutters were severely rusted and the timber fascia and fixing into the
end grain of the timber rafters were rotted. The weight of a rapid buildup and
the continuing impact of the rainwater from the roof overloaded a structurally
inadequately fixed gutter and fascia .”
70. He then made comments about soil types and the possibility of soil testing,
to which I shall refer subsequently.
71. In the section of his report entitled “Discussion”, Mr B made comments in
relation to the basement. The basement is in the cottage which is the
building immediately to the north of the property. In commenting upon this
b uilding, he stated that “over many years of water entry or from the influence
of dampness, the walls crystallise salt matrix within the stone and can
expand resulting in a fretting of the surfaces of the wall. Over time the walls ’
rendered internal surface can de-bond its walls or weaken off from the stone
work. ”
Case No: 257846 Determination Page 11 of 31
72. “In the writer’s opinion the 7 December 2010 rain event was effectively the
straw that broke the camel’s back in relation to the partial collapse of the
rendered internal wall finish. ”
73. In summary, he commented thereafter that any repairs done to the wall
would likely exceed the condition of the wall prior to the 7 December 2010
storm.
74. Similarly, he commented that the damage to the gutters and fascia of the
shed, being the building to the south-east of the homestead, was a result of
water rapidly filling the gutters and overloading the fixing to either the fascia
and/or fascia to the rafters’ ends. He commented that the condition of both
the gutters and fascia was severely compromised as were a number of the
other gutters and fascia around the property. “Their collapse was inevitable
given the amount of rust and the rotting of the timbers”.
75. As indicated earlier, when discussing the homestead, Mr B did comment that
the damage to the northern elevation of the dwelling adjacent to the northern
“office room window” was most likely the result of the 7 December 2010
inundation. He commented that before any repairs could be considered, the
soil needed to dry out and the crack patterns needed to stabilise.
76. He repeated his view that the vertical cracking to the perimeter veranda
pillars was not the result of the 7 December 2010 inundation.
77. He commented that the horizontal cracking to the infill balustrade be tween
the pillars had also been previously repaired and that in his opinion the water
inundation was not the proximate cause of the cracking.
78. In dealing with the veranda, he commented that the concrete slabs were
highly likely to have had a history of prev ious cracking. “The edges of the
cracks are not recent. There were weeds growing between the cracks in an
area of the veranda which is severely uneven. The veranda slab in front of
the external kitchen door is likely to have replaced a previous slab. The s lab
is of a different colour. The newer slab has also cracked and there is a
horizontal crack to the vertical face of the step-up slab as shown in the
accompanying photograph. ”
79. There is a great deal more along similar lines in Mr B’s report. For the
assistance of the FSP, Mr B did prepare a scope of works for repairs which
he considered were the responsibility of the FSP.
80. I shall make reference to Mr B’s subsequent reports, but because of the
significance of this first report, I think that some comments sho uld be made
at this point.
81. I have absolutely no reason to question the honesty of Mr B, and indeed his
reports impressed me as being prepared by an engineer with a desire to be
as accurate as possible but I think that even he would concede that there
were some significant errors in this initial report. First, Mr B has
subsequently apologised for his comment that “there were weeds growing
Case No: 257846 Determination Page 12 of 31
between the cracks in an area of the veranda which is severely uneven ”.
When he made this comment, it was to demonstrate his belief that there had
been a history of previous cracking. In my view anyone reading this
comment must be affected by it. If there were cracks of sufficient width for
weeds to be growing out of them, it would demonstrate to the average
reader two things. The first is that the condition of this property prior to the
storm was not very good. If the cracks were wide enough to demonstrate
weeds, it would also tend to indicate that the Applicants were not too
concerned about the condition of their property.
82. I think it is clear also that Mr B was entirely incorrect in his reference to the
fact that “the veranda’s slab in front of the external kitchen door is likely to
have replaced a previous slab.” I am satisfied that part of the slab had been
painted thus giving him the impression that some part of the slab may have
been earlier replaced.
83. Mr B, as stated earlier in this report, made no reference to the findings of MJ
(see paragraph 109).
84. Of less significance is his categorisation of the room on the north side of the
property in the region of the damage which he considered was storm related,
as an office, whereas the Applicants have pointed out that it was a bedroom.
85. It is important to stress also the thrust of the first MP report. In this report
there was no suggestion that any damage whatsoever had been brought
about by earth movement. Rather, it was suggested, that the proximate
cause of much of the damage was the pre-existing condition of the areas
affected. In effect, Mr B was saying that but for the condition of these items,
such as the guttering and fascia on the barn, the damage which was
sustained to them would not have occurred.
86. It was to these contentions of Mr B that the Applicants directed their
attention, in very detailed submissions to the FSP whic h they addressed
through C&C. Indeed at one point the Applicants attended the offices of C&C
in the nearest capital city in order to discuss the matter.
87. The immediate contention of the Applicants was that the scope of works
which had been prepared for the reinstatement of the damage was
incomplete and did not in any way represent the extent of the damage to
date. They went further and suggested that it did not represent all of the
damage noted in the body of the report by Mr B.
88. The Applicants raised (in the opinion of the FSP for the first time) the issue
of damp which had been created in the kitchen saying “we have a valid claim
for the damage resulting from the moisture and damage attributed only as a
result of the storm which has caused the wood surrounding the door frame to
move and also cause damage to the door. The kitchen flooring has also
been affected as a consequence. We have concerns that the areas of damp
are spreading and evidenced by a damp and musty smell in the kitchen and
other areas adjacent (hall and bathroom) .” They commented that “ both the
paintwork and flooring were new and as part of the renovations undertaken
Case No: 257846 Determination Page 13 of 31
by the previous owners ” . They point out that the renovations had been both
documented and photographed in the document prepared by the Real Estate
Agent and submitted.
89. They further pointed out that although “impact” damage to the northern
veranda skylights had been repaired, the repair was not suitable as a
permanent measure. The submission is too detailed to be summarised here.
What is important is that the submission of 3 August 2011 was given to Mr B
who, on 5 August, replied with a “bullet point reply” to the adjusters. In this
bullet point reply, he did acknowledge several minor errors in his report also,
but as to a number of items commented that further inspection of the
property was required.
90. Critically, he returned to what he described as a threshold issue. (At this time
he was dealing with the pillars in the homestead, not the cottage in respect
to which he had made his “straw that broke the camel’s back” comments ).
91. In dealing with the pillars and balustrade cracking, he posed the question
“the whole matter revolves around the answer to the following question – has
the water inundation provided a mechanism to support the evidence of the
pillar and balustrade cracking? Is it the proximate cause of the damage or is
it just the “straw that broke the camel’s back , however in the Applicants’
defence, the straw that broke the camel’s back was a significant single
weather event. Soil testing is strongly recommended. This will require coring
a number of holes in the veranda slab and penetrating the veranda soffit
lining and removing root tiles to get the depth of tube we need to embed into
the soil. ”
92. Thus, again, Mr B was presenting to the FSP a picture whereby the primary
cause for a partial rejection of the property might be the pre-existing
condition of the property. His ref erence to “the straw that broke the camel’s
back” is not consistent with any other possible exclusion. In short, the
damage discussed by Mr B in the reports to which I have referred thus far is
described as being exluded by paragraph 14.2 (f) of the policy, namely
wear/tear, rust, gradual deterioration etc.
93. The FSP asked Mr B to examine the property again which he did on 30
November 2011. He first dealt with kitchen dampness and airborne testing,
and conceded that in his earlier report (in which he had described the
homestead as having a wooden floor), he was incorrect. After a detailed
discussion about changes in the kitchen since he had last inspected it, he
then went on to the question of the masonry pillars. Two masonry pillars had
been cut into by a jackhammer exposing corroded vertical reinforcing bars.
He commented that the damage to these bars was a function of long term
corrosion of the vertical reinforcement which had resulted in an increase in
volume around the reinforcing bar due to the formation of a rust layer. It was
his view that the masonry pillar crack pattern is not consistent with an impact
from the inundation of water or from an in-plan vertical movement (either a
settlement or a lifting of the pillar and balustrade).
Case No: 257846 Determination Page 14 of 31
94. When discussing soil sampling, he commented that in his view the samples
taken in relation to the veranda slab indicated that “it has not undergone a
heave caused by an increase in soil moisture due to the inundation. “ He
repeated his earlier observation that “as discussed in the first report,
photograph taken by the loss adjuster two days after the 7 December 2010
inundation shows the veranda slab had some weed growth within the
cracks. ” Thus, this error which I regard as highly prejudicial to the Applicants’
position, was perpetuated.
95. He summarised his opinion as to the soil tests, which was that the soil was
not reactive and would not heave with an increase in soil moisture. “There is
no evidence of a perimeter settlement consistent with the veranda slab and
pillar/balustrade cracking. The lack of any recent movement to the junction
between veranda slab and pillar/balustrade, post and pillar and post and
pitching beam supports the premise that inundation is not the proximate
cause of the reported damage ” .
96. In his “ summary ” he commented that the proximate cause of the damage to
the veranda slab and masonry pillar/balustrade was not the result of the 7
December 2010 inundation and that the cracking to the masonry pillar was
due to corroding steel reinforcement and that the inundation had not led to
the cracking to the veranda slab.
97. By this time the FSP had received another submission from the Applicants
and this was again referred to Mr B of MP. On this occasion, Mr B
acknowledged in his report that a detailed examination of the shed, timber
fascia and gutter at roof height was not made, and that he had made the
judgement that the condition of the timber fascia and guttering appeared
deteriorated based on his view from ground level. He referred to a
photograph which did appear to display one very small area of deterioration
in the condition of the gutter. He had therefore concluded that the
deteriorated condition was the proximate cause of the guttering failure.
98. He commented that to be more accurate in the assessment of the
mechanism of the gutter’s failure, an examination of the fixing of the gutter
straps would need to be made. “ Given the volume of water impacting on the
shed roof, it would only have taken a failure of one or two gutter straps for
the weight of water or hail to exceed the remainder of the gutter straps
fixing ” .
99. He did comment that the section of timber fascia on the ground
(approximately 1metre long) which he had examined, had been sound.
Examination of the gutter straps and the mechanical fixing had not been
made at that time.
100. In his most recent inspection of the property, Mr B said he had conducted a
detailed examination inside the house. He had commented that “the
relatively good condition of the dwelling’s walls suggest that the dwe lling’s
foundations were more protected from the influence of the flow of water or
undermining of the foundation. “Damage to the dwelling appears confined to
the reopening of some previously repaired cracking to the dwelling’s
Case No: 257846 Determination Page 15 of 31
northern elevation, although there was an argument that the cracking could
b e the result of a slight settlement to the dwelling’s north -eastern corner and
not related to the inundation ” .
101. In his report he repeated his view that the cracking of the concrete veranda
slab, masonry balustrade and pillars had not been caused by an impact
force of water. He did concede that some susceptible areas of the rendered
stucco finish at the bottom of the balustrade could have been dislodged due
to the flow of water. He commented that “the corrosion o f the masonry pillars
vertical reinforcement is the cause of the pillar cracking.”
102. In response to still further submissions from the Applicants, Mr B prepared a
further report on 2 May 2012. He reiterated his previous opinions as to the
cause of damage to the veranda slab and the cracking of the pillars. He
maintained that photographs showed previous repairs to the face of the
veranda slab near the north-eastern corner, and thus he did not agree that
the cracking of the pillars had only occurred since the storm event of 7
December 2010.
103. On this occasion, and for the first time, Mr B did acknowledge a number of
errors. First he acknowledged the error in referring to weed growth two days
after the 7 December 2010 inundation. He also acknowledged several other
errors which had been pointed out in the Applicants’ submission of 11 March
2012 but he still maintained that the proximate cause of the damage to the
dwelling and veranda was not the result of the storm.
104. Notwithstanding the concessions which he had made as to his absence of
above ground inspection (in his previous report) he maintained his
contention that the cause of the outbuilding’s gutter collapse was correct.
105. At this time he did acknowledge that he had incorrectly assessed that the
kitchen floor had a sub-floor space where it might have been possible for
mould and bacteria spores to form. However he stated that after the 30
November 2011 inspection, he had not maintained in this suggestion.
106. I find it un surprising that in the face of Mr B’s persistence, the FSP
essentially remained unmoved by all of the submissions by the Applicants.
However, once Mr B conceded his errors, I think the FSP should have re -
assessed its position.
107. It must be conceded that there were significant errors in Mr B’s original
report, and that for almost twelve months he persisted in the incorrect view
that there had been cracks in the veranda slab of such significance that
weeds had been growing out of them. I also find it concerning that his
comments in relation to the fascia and guttering appeared to have been
based upon very inadequate information. Indeed, even in the absence of the
reports which were subsequently provided by PC for the Applicants, I would
have reached the conclusion that Mr B’s treatment of the two “outbuilding”
was perfunctory. It may be true that they were old and that they would be
difficult to repair, but it does not mean that they did not exist, or that they
performed no useful function (indeed there is evidence that the cottage was
Case No: 257846 Determination Page 16 of 31
used for accommodation). Further, significant values were attributed to both
of these buildings in the cover provided by the FSP.
The Loss Adjuster’s Reports
108. Throughout the course of the matter, C&C, the loss adjusters, have prepared
some nine reports. The first two reports were prepared by MJ who
subsequently died. Whilst MJ has set out details of the rainfall and storm
event in dramatic detail, I do not think it necessary to deal further with that
subject. But it is important to record what he observed on his first inspection,
two days after the storm –
“ Boundary and subdivisional fencing for an estimated 3kms has been
uprooted and dragged through the property.
Debris from the fencing had uprooted the mains water supply both to
the dwelling and sheds and the watering system in the paddock.
Concrete lined cellar and the cottage behind the dwelling was filled with
water and suffered damage to its walls and wall lining.
The nine metre section of the veranda floor on the western side of the
dwelling has been raised up and has subsequently substantially
cracked. The undamaged veranda flooring around the other sides of
the dwelling indicate that the flooring was in a pre-loss good condition.
The dwelling walls and the veranda walls are coated with pebble and
concrete and the hail has stripped a lot of the paint from the southern
side of the building and veranda. Hail has also broken skylights in the
rear of the dwelling.
Several gates have been pushed out of alignment – new remote
controlled gates had been installed - - - -
Some minor damage to buildings where doors have been pushed in by
the flow of water and there is debris strewn across the southern section
of the property.
It is not known exactly how much water went underneath the dwelling
which has timber flooring and the insured will monitor the area and
advise us should any movement in doors or walls become evident. ”
109. I regard as significant the fact that MJ specifically commented that apart from
the nine metre section of veranda floor which had been raised up and
substantially cra cked “the undamaged veranda flooring around the other
sides of the dwelling indicated that the flooring was in a pre -loss good
condition”.
110. This is quite inconsistent with the report of Mr B. I am somewhat surprised
that he did not take MJ’s initial report more seriously into consideration when
he furnished his first report.
Case No: 257846 Determination Page 17 of 31
The FSP’s response to this Service
111. In the summary of facts in the response (which was dated 5 December
2011) after three of Mr B’s reports were to hand, the response included the
following statement “Mr B inspected the damage and determined that some
of the damage was due to the storm, but other damage may have been pre -
existing or caused by a non-covered event (such as corrosion and wear and
tear). “Based on Mr B’s report, the FSP partia lly rejected the Applicants’
claim ” . I note that in this response, although all of the relevant sections of the
policy were set out, there was no actual reference to any reliance upon an
exclusion or loss of or damage to the property caused by earth moveme nt or
erosion or subsidence or loss of damage caused by settling, shrinkage or
expansion in the building, its foundations or any walls or pavements. Rather,
the FSP was relying upon the “pre - existing damage.”
112. Although there have been a number of responses from the FSP thereafter, it
was only after the receipt of the first report from PC (on behalf of the
Applicants) that the FSP has adverted to the possibility that the claim may be
(at least partially) defeated by reference to the “earth movement” exception .
113. At this point, I should comment upon the most recent submission from the
FSP dated 21 May 2013. In this submission, when commenting upon the
significance of the pre-purchase inspection report, the FSP has again relied
on the wording used by Mr B. After saying that all that can be drawn from the
pre-purchase inspection report, is that the basement walls contained no
grossly visible defects at the time of their inspection, t hey state “Mr B clearly
opined that the 7 Decemb er 2010 rain event was the “straw that broke the
camel’s back” i.e. the bond between the surface of the wall and the
underlying stone work had been gradually weakened over a period of time
and the inundation was simply the last event in the chain of causation. It can
be clearly seen how influenced was the FSP by the earlier reports of Mr. B.
114. The FSP also said:
“ In other words, the dominant or effective cause (or the proximate cause in
insurance law) was gradual water entry over a number of years. The
stormwater runoff was simply a contributing factor without being the proximate
cause. It is an established principle that a policy of insurance will only respond
to the proximate cause of a loss. ”
115. There is no question that the statement of law contained in the paragraph
above is accurate. But I find it hard to apply that statement to the
circumstances following the 7 December 2010 storm, when the wall to which
Mr B was referring, was a wall of a building which was inundated by water. It
has been clearly established that the cellar in this building filled up with
water. I must say that I consider that the proximate cause of the damage to
the wall of the cottage was plainly the storm event of 7 December 2010.
116. I shall deal in due course with the other responses of the FSP, to the report
supplied by Mr C on behalf of the Applicant.
Case No: 257846 Determination Page 18 of 31
Reports provided by PC on behalf of the Applicants
117. As the Applicants had been making no progress in their dealings with the
FSP, they eventually consulted Mr PC of C Consulting Engineers. His first
report was dated 26 November 2012.
118. In the report, PC set out the fact that in addition to inspecting the property,
he had read some 41 documents many of which are the documents to which
I have referred in this Determination. This was plainly an essential part of his
task.
119. PC first noted the information which was available as to the condition of the
property pre-storm.
120. He specifically noted the findings of MJ of C&C that other than the nine
metres of direct impact damage to the veranda, his onsite inspection
revealed that the flooring of the veranda was in a pre-loss good condition.
MJ further suggested that the nine metres of damaged floor that he observed
would also have been in that same pre-loss good condition but for the storm.
121. To use the expression of PC “M J provides us with an informed industry
practitioner written firsthand account of the initial observation of the site
directly after the event, that settlement based movements had yet to
commence around all of the veranda areas except for in the first nine metres
and that only the force of water, hail damage and water flow scour effects
were observed, including the nine metre section of damage to the veranda
floor. ”
122. PC then points out that by the time of MJ’s next report following a
subsequent inspection, it was now becoming plain that significant movement
of the building may have occurred, and that the concrete pillars of the
veranda were showing severe cracking as well as some of the walls. MJ
noted that a concrete contractor who had been engaged to examine the
scene, had expressed concern as to possible structural damage to the
veranda area, and MJ commented that he agreed with those concerns.
123. Stating his reasons for disagreement with the conclusions of Mr B, as to the
significance of the soil test, PC set out the following as to the veranda slab
“there are two effects the water had upon the soils of this site. Neither are
related to soil reactivity. To explain, firstly this was a hydrostatic flowing
water event. The lifting of the veranda slab at the joints in the veranda slab in
the first nine metres as noted in the MJ first inspection, was due to flowing
water hydrostatic pressure related uplift of the veranda slab. The status of
the soil non- reactivity is irrelevant in this consideration.” Thereafter he also
commented that “the fact that the observations (by MJ) were made
immediately following the event, is completely consistent with the fact that
the uplift and damage response of the slab was a direct and immediate
response to the effect of the flowing water.”
124. Then, in dealing with the subsequent cracking which had occurred, PC has
opined that “secondly in relation to the subsequent cracking that has
Case No: 257846 Determination Page 19 of 31
occurred in the remainder of the veranda slab in the weeks following the
inundation, as observed by MJ in his second report, the effect of the
inundation and consequent settlement of the site, sand and silt soil has
caused a drop, an outward rotation and a n outward lateral displacement
effect upon the footings of the pillars and balustrade walls due to the volume
(evidently some 170mm of rain in two hours) of water. “ He went on to say
“the effect of the consolidation settlement and associated reduction in l oad
bearing support of this site’s sand and silt soil given the heavy masonry
structure of the pillars and the masonry balustrade walls is in itself enough to
explain the movement and related cracking in the balustrade walls, pillars
and the associated veranda slab cracking. This would have been an
unprecedented inundation on the sands and silts including calcareous silts at
this site that would have caused consolidation of the site soils as the
unnatural excess water dissipated through soil profile in the weeks that
follow the event. ”
125. P C went on to deal with the concept known as “collapse settlement” which is
known to occur in the region with which we are dealing.
126. P C’s report is too long and too detailed to set it out entirely, but he
commented “in summ ary, in relation to the veranda slab cracking, reference
to and focus on whether or not the soil is reactive, is in my opinion to
completely misunderstand the response of the sandy and silty soils
(including calcareous silt soils with possible collapse potential) of this site in
the face of this unprecedented rainfall event. It is my clear opinion that the
storm event is the cause of the extent of the veranda slab cracking at this
site. ”
127. When dealing with the pillars, PC was able to comment upon a core of the
three/eight rod taken from the same sample of the rod that Mr B from MP
considered to be the source of the related cracking.
128. PC commented that “whilst there is understandable surface rust, it is my
view with all my over 30 years of experience that this light level of surface
rust is not going to cause the extent of damage to the pillars in the manner
that now can be observed (by way of some tangential force as mentioned by
Mr B). What is a defining difference in the opinion expressed by Mr B and
the opinion expressed by me and what is of great importance here, is the
clear evidence that supports my description as to cause of the damage
apparent in this veranda ” . He then points out the good condition of the pillars
and balustrade wall and the outstandingly good condition of the veranda
floor that all joined to create the structural buttressing of the thus structurally
buttressed entrance-way on the south side of the building. These pillars and
their associated walls are exposed to even more rusting potential than the
remainder of the plain veranda areas as this area of buttressed pillars is
more “out in the open”.
129. However, he points out that “these buttressed pillars and their associated
walls (and the associated veranda floor) show none of the tangential force
related cracking damage that Mr B suggests is caused by the rusting
reinforcement rods. “If Mr B was right, then the same cracking in the plain
Case No: 257846 Determination Page 20 of 31
veranda areas would be apparent even more so in the more “out in the
o pen” exposed buttressed pillars and walls of the front steps area even if
only in the direction perpendicular to the line of the pillars. No such damage
has occurred in this area. Quite the opposite. Look at the completely
acceptable current condition of the buttressed pillars, balustrade walls and
particularly the outstanding associated veranda slab conditions provided in
photos which are in clear contrast to the areas of damage in this dispute ” .
130. In short, the area in the south side of the homestead had remained intact
and in extremely good condition notwithstanding that if Mr B’s conclusions
had been correct, the rusting force effect would apply equally, if not more so,
to those pillars.
131. On this subject, he concludes “it is my certain opinion, which is sup ported by
the evidence from the site as discussed above, that the cracks in dispute in
relation to this item have developed due to the rotation and settlement of the
pillars and the balustrade wall (and thus the associated floor) due to the
inundation and not on basis of pre-existing general wear and tear and rust. ”
He commented that whilst there was no doubt some areas had been
repaired in the past, it is the inundation which was responsible for the
development of the visible cracking in the pillars and balustrade walls of the
veranda, as well as the same development in the veranda slab cracking .
132. When dealing with the box gutter underneath the skylights, PC comments as
follows : “in the (FSP) response item 40 dated 3 August 2012, note 7 states
“box gutter underneath skylights declined see Mr B’s report dated 20 May
2011 at page 9 “rusted gutters and rotted timbers collapsed under the weight
of water within the gutter. Their deteriorated condition is the proximate cause
of the collapse, not the rain event.” ”
133. PC then pointed out that the reference by Mr B to the collapsed gutter, was a
reference to the outbuilding walls. C commented that “in my repeated
reading of the MP 20 May 2011 report, I can find no reference to the box
gutter drain located between the house and the cottage. The box gutter
drains the veranda outside the kitchen window of the main house and has no
relationship at all to the fascia gutter that collapsed on the outbuilding which
was discussed in the report. So the FSP has used the (incorrect)
assessment made by Mr B on the outbuilding gutter to decline this box gutter
matter claim. ”
134. Even then, as PC pointed out, in his correspondence of 21 February 2012,
Mr B had acknowledged that he had not made a detailed examination of the
shed timber fascia and gutter and that a judgement was based on a view
from ground level that the condition of the timber fascia and gutter appeared
deteriorated.
135. By contrast, PC inspected and photographed the gutter straps, both of the
gutters that had now come away fully as a result of subsequent weather
damage, and portions of the gutter that remained in place. He commented
that the straps and timbers supporting both the removed and the still in situ
gutters were in quite sound, serviceable, good condition. Nothing in his
Case No: 257846 Determination Page 21 of 31
inspection showed any such “rusted and rotted timbers” (this reference being
to the FSP’s reasons for the claim refusal of 3 August 2012). He noted that
whilst Mr B had acknowledged that no proper examination was made of the
outbuilding gutter, he still claimed that the gutter’s poor condition was the
cause of the failure and not the storm event.
136. In conclusion as to the box gutter, P C commented “I am confident that the
box gutter damage is due to the storm and related water damage. I have
also assessed the outbuilding gutter condition and it is also in good condition
as noted above as are the associated outbuilding timbers.” He commented,
based upon the original assessment by C&C, that if 130mm of rain in the
district fell over a very short time and 170mm of rain was recorded at the
insureds’ property including an evident 15 minute hail storm, no box gutter is
going to handle this situation and the damage that needs to be repaired to
the box gutter and the associated framing is the damage caused by the
storm event.
137. Regarding the cracked walkway between the main house and cottage, PC
commented that this area was most evidently exposed to the quickly running
free water and that he believed repair of this area was required and
consistent with coverage under the policy.
138. He also commented on the possibility of damage to the building arising as a
consequence of the process of building work, and the fact that the Applicants
had raised legitimate concerns about the effect of any building work to make
good the damaged areas. He commented on the suggested use of some
sort of vibrating plate as mentioned in Mr B’s repair recommendations, and
stated his view that under no circumstances should vibrating equipment be
used, nor should any bobcat or such mechanical lifting machines be used in
the demolition and removal of the slab. It would have to be saw cut into
sections and removed by hand.
139. He also commented on the extent of damage under the building which had
not been inspected by Mr B. He photographed water stains due to dripping
water down the inner wall face of the formal lounge area particularly over the
door into the main corridor and compared it with a photo which was taken in
the same room from the same location prior to the storm event. There was
no such staining or damage at that time. He commented that this direct
before and after photographic evidence clearly shows this damage.
140. When dealing with the damage to the kitchen, vinyl/lino, he commented upon
Mr B’s error in stating that the kitchen floor had a timber fl oor covering. “ It
does not have a timber floor covering. It has a lino type vinyl floor covering. ”
He pointed out that Mr B states t hat “ he does not retract the possibility that
some moisture from the inundation may have been attracted under the
kit chen’s concrete floor slab. “So on this basis we have a damp concrete
floor and a vinyl floor covering and in those circumstances the vinyl lifts up.
This has happened and the areas remain damaged that need repair.”
141. PC commented that the damage in the main formal lounge room cracking
and water related damage, was in his view covered by the policy.
Case No: 257846 Determination Page 22 of 31
142. As to the “ nursery bedroom wall cracking” which was described by Mr B as
“the office”, PC found that Mr B’s findings were impossible to reconcile
because Mr B had marked on the wall the extent of the crack on 15 February
2011 and then on 13 April 2011 he again marked the wall where the crack
had developed during the ensuing two months. He commented that “it defies
belief that in the face of such evidence of crack development, it is rejected by
Mr B and thus by FSP on the basis of exclusion 2 (f) “ wear, tear, rust,
corrosion etc. ”
143. He commented “this is the same crack that had appeared on the outside
face of the same wall, and for which the FSP had accepted the claim.”
144. PC then dealt with the outbuildings. He commented that the shed is a large
implement store site shed with an elevated timber floor platform with
damaged roofing and gutters from the storm whereas the barn is an open
roof structure that has a flat and an associated toilet attached.
145. As to the shed, and the box gutter issues, he commented that none of the
alleged poor condition rusted and damaged gutter and rotted timber
elements exist and that Mr B appeared to have somehow incorrectly and
assessed and advised the FSP on this matter. PC commented on the fact
that twelve months earlier Mr B had indicated that inaction on this matter
would cause further damage and that such further damage has indeed
occurred and that it included damage to the walls, the roof, the flooring of the
elevated deck and to the tank roof door.
146. He stated that the shed gutters and the associated damage that had
developed do need repair.
147. He was of the view that both the shed and barn were not beyond economical
repair and commented tha t “on the co ntrary, it is these such buildings that
define the character of the area and proper maintenance as is now required
is at the core of the ongoing service of the performance of these structures.
To write them off for unrealistic reasons is inappropriate and these structures
can be repaired and desperately do need repair to the storm related
damage. In the carrying out of repairs to the roofing, this needs to include
renailing of the roofing iron because the now wind exposed edge has caused
lifting of the shee ts. Likewise, cracks in the barn need to be repaired.”
148. When dealing with the cottage, he commented that based upon his 30 plus
years as a professional engineer and in particular with experience consulting
to heritage architects and the National Trust of the relevant State, he can
confidently state that the cottage including the basement (once repaired to
the condition it was in prior to the storm event) is in quite structurally
serviceable condition.
149. In dealing with Mr B’s suggestion that the cottage was li kely to be beyond
practical or economic repair and that repairs to reinstate the damage to its
pre-event conditions, could not be guaranteed without substantial
improvements being made, PC considered that such statements were
misleading and inappropriate for such an existing building. Had the storm
Case No: 257846 Determination Page 23 of 31
event not occurred, the basement condition would have remained
serviceable with ongoing maintenance; it would have remained serviceable
for as long as that ongoing maintenance is provided as had been the case
quite evidently for the past 85 years.
150. Further on he commented that to write off this building on the basis that it
does not meet current Australian standards is a nonsense. “This house (the
homestead) and its outbuildings currently are approved structures by the
Building Act (of State) and to the extent that storm damage has occurred,
this storm damage needs to be repaired. He commented that the barn which
had insured value of $60,000 and the cottage both required professional
scope of repair works to be prepared.
151. It is unfortunate that the preparation of PC ’s report coincided with the FSP
arranging for M Consultants to prepare two separate scopes of works.
152. The first was to particularise the damage which the FSP had agreed to
cover, and the second was to set out the (in the opinion of the FSP)
uninsured loss.
153. The FS P’s appointed loss assessor C&C , was then to arrange for two
separate repair quotations to be prepared for each scope of works.
154. When writing to this Service advising of these two scopes of works which
had been prepared, the FSP did admit liability for additional damage, notably
to the box gutter located underneath the skylight.
155. The FSP did respond to the PC report. Notwithstanding the significant areas
in which PC indicated his disagreement with the findings of Mr B, and in
some cases his rather serious criticisms of the MP reports, it does not
appear that the PC report from which I have quoted so extensively above,
was referred back to MP, or to any other engineer for an opinion.
156. By this stage, the FSP was drawing attention to the fact that in the event that
the PC report was accepted, it would still be the case that many areas of
damage, or in need for repairs, would be excluded under the policy this time
because of paragraphs 2(b) and 2(c) of the policy (see above). The FSP
suggested that if loss or damage to the property was caused by earth
movement etc, it would be excluded even in situations where the preceding
clause was an event which is itself the subject of cover under the policy,
such as rainwater runoff. The FSP stated “t he policy has been carefully
drafted to achieve this effect.” The Applicants’ argument – that the dominant
cause of land movement was rain water runoff which is covered under the
policy – is precisely the type of argument which the exclusion clause is
designed to overcome. Therefore even if P C’s opinion on the cause of
damage is preferred over that of Mr B’s, the loss would not attract cover ” .
157. In the event, the two scopes of works prepared at the instigation of the FSP
and carried out by M produced the following results:
Case No: 257846 Determination Page 24 of 31
a. Scope of works – Part 1(for damages for which the FSP admits
liability) produced two quotations, one from CS and one from BEB, in
the sums of $42,854.50 and $57,970 respectively.
b. Scope of works – Part 2 (said to describe items for which cover would
not be offered), produced quotations from CS in the sum of
$188,127.26 and from BE Building Services in the sum of $247,390.
All sums include GST.
158. These scopes of work were then referred back to the Applicants’ expert PC
for further comment. At the same time, the further response from the FSP to
which I have referred, dated 17 December 2012 was also referred to PC. In
an email to the Applicants, P C said: “earth movement, vibration, erosion,
landslide or subsidence (except where caused by an earthquake) – none of
these caused your damage. There was no earth movement circumstance, or
vibration event, or erosion causing the ground to split apart or landslide from
sloping ground or subsidence by earthquake or subsurface mine implosion
or rabbit burrow failure or otherwise. It was caused by stormwater runoff
which as the FSP said “does attract cover under the policy.” ”
159. He subsequently commented that “the building did not settl e, the building did
not shrink and the building did not expand to cause the damage.” None of
these potential causes preceded the stormwater runoff event. He said that
the building remains static for its entire life. The stormwater runoff damaged
the building in a one-off event. Without the runoff there would be no event,
no cause and no damage.
160. In commenting upon the claim by the FSP that it would not pay for settling,
shrinkage or expansion in the foundations or any walls or pavements, PC
commented “the fo undations have not settled in the preceding 80 or so
years, foundations did not shrink or expand to cause the damage and the
walls did not settle, shrink or expand to cause the damage. There was no
preceding damage in any evidence I saw on the building ins pection.” As
noted above, the stormwater runoff damaged the structure in a one -off event
cause. The policy does not presumably say stormwater run-off cover only
applies to the roof and not the walls, and the rest of the property.
161. PC then pointed out the FS P’s change of position whereby he considered it
was “distancing itself from the prior position that there was no solid
engineering evidence that proved the house was damaged by the 7
December 2010 event, whereas, the FSP now states “even if P C’s opinion is
preferred over that of Mr B, i.e. all the previous engineering effort was
pointless.”
162. In his final report dated 4 April 2013, PC commented that in his view the
Scope of Works No. 2 should be accepted by the FSP completely. In fact he
commented as to a number of areas in which he considers that the scope of
works was inadequate and pointed out that those responsible for drawing up
these scope of works were responding to a specific request from the FSP.
Case No: 257846 Determination Page 25 of 31
163. In his view, omissions to the scope of works included wall and ceiling
damage in the house, house roof damage causing leaks, repairs to the
cottage roof, walls and floors, termite barriers and slab moisture barrier
detailing, barn walls and floor and door slabs specifications.
164. Much of P C’s commentary in the final report relates to the other buildings
which he considered were not the subject of the Scope of Works No. 2, or at
least have not been dealt with adequately.
165. I must say that I cannot agree with this conclusion. Examining, for example,
the quotation from CA (for $188,127, some $26,000 has been included in
relation to the barn, the cottage and the basement.) Whilst the quotation
from BE does not list specific figures for all of these items, it is plain that in
the quote from BE amounting to $247,390, signi ficant allowance has also
been made for the barn, cottage and the basement.
166. In his final report, PC has also highlighted a number of inconsistencies,
several of which I have already referred to.
167. In summary, in the final report, whilst PC recommends that the work set out
in Statement of Works No. 2 (SOW) would need to be carried out by the
FSP, it is his view that the SOW is far too brief and fundamentally flawed. He
summarises by saying that the higher of two SOW quotations should be
used and then with an e scalation of at least 25% to allow for “inappropriate
specifications, incomplete specifications, and their irregularities and
omissions in the specifications at FSP SOW.
168. Crucially, PC does also highlight the fact that over the period of time, in the
C&C reports, for a reason which is unstated, the sums insured for sheds and
barn, were deleted. As set out previously, the sum of $60,000 was provided
for sheds, and $20,000 for barns. Yet, by the time of the ninth report by
C&C, the only items which are referred to are the building homestead (which
must include the cottage) of $400,000, and fences of $5,000.
169. Bearing in mind that in November 2012, PC had expressed the view that the
“outbuildings” were clearly of economic value and that they were capable of
repair, I do find it extraordinary that no allowance has been made for these
items in the ninth report from C&C.
Previous FOS Decision 287408
170. Both PC, and in their final submission, the Applicants drew attention to a
previous FOS decision in case number 287408. Having read the decision, I
do agree that it relates to facts which are not dissimilar to those with which
we are dealing.
171. In Case 287408, the effect of stormwater runoff damaged the slab because
water flowed in the soil under the slab of the hayshed, thus causing material
loss in the soil under the slab. The Ombudsman allowed the claim in that
matter, rejecting the “earth movement exclusion”.
Case No: 257846 Determination Page 26 of 31
172. In this dispute, PC’s contention is that the extreme speed of the water
flowing over the ground caused a great deal of damage, such as that
sustained by the cottage basement, the pillars, balustrade walls, front
veranda slab and barn .
173. PC commented that a common feature of both this dispute and dispute
number 287408 was the loss of material in the surface sand y soils of this
site. In both cases, the soil had for the previous 80 years been a perfectly
good foundation base for the houses, including through numerous heavy
rainfall events that would have occurred through those 80 plus years.
174. PC summarises his view by saying the following: “ For a building that is at
least 80 years old, this illustrates how the idea that this was foundational
movement from a ground and water effect is not sound as this problem
would have occurred already which was demonstrably not the case for this
prior good condition building”.
175. He went on to say “t he damage to this property was due to this singular
extreme water event on 7 December 2010. Of course, so much of the
damage was just due to surface flooding of the site including the veranda
and pillar out of edge damage, the filling up of the cottage basement and
upper floor with running water and the damage to the barn floor and door by
surface flowing water and is unrelated in any way to foundational
movement.”
The Engineering Reports – Conclusions
176. I must say again that I have no reason to doubt the veracity of the comments
of Mr B and I am satisfied that his reports were written in a genuine attempt
to address the issue which arose following the storm event.
177. But I believe that the matters which I have set out above and specifically the
very detailed findings in the PC reports, are sufficient to establish that on a
number of matters, the initial report of Mr B from MP, was incorrect. I will not
list again the matters about which I consider he was in factual error.
178. However I again state that I am satisfied that some of these errors must
have been of fundamental importance in the decision making of the FSP. I
point specifically to the acknowledged error wherein Mr B suggested that at
the time of the storm, weeds had been growing out of one of the cracks on
the veranda. This was plainly incorrect, but it was 12 months before he
corrected that error which, was incidentally, entirely inconsistent with the
initial inspection of the property by MJ. Mr B was also incorrect in relation to
the suggestion that half of the slab had been replaced. His inspection of the
box guttering and the fascias was, to say the least, inadequate, and his
persistent in stating that he maintained his conclusions on that subject, is
hard to understand.
179. What is also important to stress is that the reports from MP, a most
experienced and reputed firms of engineers, did not suggest a partial denial
of the claim on the basis of the “earth movement” exclusion.
Case No: 257846 Determination Page 27 of 31
180. Rather, the reports from MP concluded that the property had not been in
good condition at the time of the storm event, and that therefore the
proximate cause of much of the damage was the pre-existing state of
various parts of the property.
181. To rely on such an exclusion, the onus of proof is on the FSP. It is clear that
the FSP has failed to discharge that onus, having regard to the various
errors to which I have referred. The evidence regarding the pre-storm
condition of the property is wholly adverse to the FSP’s contention that there
were significant faults at the property, whether to the slab, the pillars, the
balustrades, or particularly to the box guttering and fascias.
182. It was as recently as December 2012 that the FSP first suggested that it
might rely upon the exclusions contained in paragraph 2(b) and (c), which I
will loosely describe as the “earth movement exclusion”.
183. The opinions of PC strongly negate such a conclusion. I refer to the
commentary which P C forwarded to the Applicants after he saw the FSP’s
contention of December 2012.
184. Whilst, as the FSP suggests, the earth movement exclusions in paragraphs
b & c are drawn very widely, they must be subject to some limitations.
185. To provide an example, if a flag pole is situated immediately adjacent to the
corner of a veranda and, if the flag pole is blown over during the course of a
storm, the “inground portion” of the flag pole will lift. If it lifts under the
veranda causi ng damage to the veranda, can it be said that the proximate
cause of the damage to the veranda is earth movement? The immediate
pressure upon the veranda would be caused by earth movement. But it
utterly defies good sense to suggest that in such circumstances the
proximate cause of the damage to the veranda would be earth movement.
Plainly in the circumstances set out above, the proximate cause was the
storm which caused the flagpole to blow over.
186. In this dispute, PC is overwhelmingly of the opinion that it is the force of the
inundation of the property by the water which has caused the damage. It has
caused certain soils to move. It caused quite plainly a 9 metre portion of the
veranda to lift. The movement of the water, of itself, has caused a huge
proportion of the damage. In most circumstances, it is difficult to imagine that
this may be the case, and difficult to accept that, for example, pylons or
balustrades would be affected by the rain storm.
187. But this was a rainstorm of a kind never previously experienced (as Mr B
very appropriately comments). A rainstorm causing runoff (as opposed to a
flood emanating from a water course) which causes a vehicle to turn on its
side or which picks up all of the fencing on the property and sweeps it away,
is, one would imagine, at least a one in one hundred year event, and
hopefully is even less likely.
188. As to the “earth movement exclusion , ” first I am of the opinion that the onus
is upon the FSP to establish that the damage to which PC refers is in fact
Case No: 257846 Determination Page 28 of 31
due to earth movement or the other matters described in sub-paragraphs (b)
or (c). Because of the extraordinary effect of the inundation, I am satisfied
that the FSP has not discharged that onus.
189. If it is the case that some parts of the damage have been caused by
lingering effects of water permeating the soils and causing movement, I
remain of the opinion that the proximate cause of the damage to this
property was not earth movement, but rather the storm on 7 December
2010.
190. As PC commented, if this were not the case, why has the property remained
so successfully intact for so long. Mr B also stated, upon his inspection of the
interior of the property, that the interior of the property was in remarkably
good condition. For a house of its age, in a country area, this is a quite
significant finding.
The Position of the Applicants
191. From time to time during the conduct of this matter, the Applicants drew
attention to their plight, pointing out that they did not have the funds to carry
out repairs which were necessary (if the FSP was not prepared to pay for
them).
192. The FSP obtained an original scope of works for approximately $13,000, and
then a subsequent scope of works in November 2012 (for a minimum of
$43,000). It appears that neither of these sums has been paid to the
Applicant. Perhaps, had the FSP’s chosen adjuster been inclined to deal
more directly with the Applicants, it might have been realised that the
payment of such sums might enable the Applicants to “hold the fort” until the
matter could be determined.
193. Ultimately, I am satisfied that until the Applicants obtained the two reports by
PC, it was not possible for the Applicant to rebut the evidence provided by
Mr B.
194. Regrettably, the position has now been reached that the Applicants have left
the property. This ensures that the Determination I make may only apply to
the payment of a monetary sum, rather than the effecting of the repairs,
which would have been by far the preferred option.
195. PC commented that the full SOW No. 2 quote must be accepted by the FSP.
He adds that figure to the sum for which a tender was provided for SOW No.
1 and produces a figure of $305,000.
196. I note that the FSP has already agreed to payment of the works contained in
Scope of Works No. 1. There has been no attempt to challenge the figures
contained in the quote from CA in respect of Scope of Works No. 1. I
therefore treat the value of the work described in Scope of Works No. 1 as
not being in dispute. The only dispute therefore remains as to the sums
necessary to compensate the Applicants for the expense which would have
been incurred in Scope of Works No. 2.
Case No: 257846 Determination Page 29 of 31
197. Whilst PC comments that it should be escalated by 25% to allow for all the
omissions which he has identified, as I have commented already, I do not
consider that he is correct on this subject. In my opinion, the two quotations
supplied in respect to Scope of Works No. 2, in the sum of $188,127.26, and
$247,390, do make significant allowance for the other buildings which PC
believed had been, essentially overlooked. Accordingly, as the quotations
were provided reasonably recently, I do not propose to provide an escalation
percentage to them. Whilst PC comments that the higher of the two
quotations should be accepted, in the absence of any specific commentary
as to why the lower quotation may not be acceptable, I consider that the
appropriate step is to average the two quotations. This produces a figure of
$217,750.
198. I accept the evidence of PC that for a period had the repairs been carried
out, the FSP would have been obliged to pay for alternative accommodation
nearby. I consider that six months would have been adequate, and I make
an allowance of $6,000.
The Costs of the Reports from PC
199. The FOS Terms of Reference provide that allowance may be made for the
fees of professional advisers but that save in exceptional circumstances, an
allowance should not be made of more than $3,000. The FSP has submitted
that, indeed, no greater sum should be awarded.
200. I have to determine whether special circumstances exist in this case.
Ultimately I have decided that they do. I have noted the extremely large
sums which the FSP has paid in fees to MP and C&C, and ultimately a fee in
excess of $8,700 to M, for preparation of the scope of works.
201. These matters highlight the extraordinary complexity of this matter. I am not
critical at all of the FSP’s actions in obtaining the various reports from MP,
and I consider that the course they followed in obtaining the two separate
quotes arranged by M, was absolutely appropriate. It has enabled a
resolution of this matter (albeit in a manner which may not have been the
preferred solution for the FSP). But in my view this case did present
exceptional circumstances. A vast amount of material had to be considered.
The quantum of the claim was large. There was a huge variance between
t he opinions of the FSP’s expert , and the Applicants which PC had to
comment on.
202. I was initially surprised about the quantum of the fees charged by PC but
note that his first report did involve an analysis of all of the documentation,
and upon reflection it was utterly appropriate that this took place. Much of his
first report has consisted of an analysis of the various contentions advanced
by the FSP, and it is for this very issue that the Applicants most required his
assistance. Ultimately, I have reached the conclusion in respect to his first
report for which a fee of $11,803 was charged, an allowance should be
made of $9,000.
Case No: 257846 Determination Page 30 of 31
203. Once the M scopes of works were provided, it was obviously essential for
the Applicants to seek expert opinion as to these scopes of works, and the
quotations which had been provided. Without the assistance of PC, they
would have been in a very unequal position in dealing with quo tations for
considerable sums of money. I do not think that the second report was of
such significant value, but I am still satisfied that exceptional circumstances
apply and that in the circumstances a figure of $5,000 should be allowed in
respect to the second report for which PC charged $9,305. I will therefore
include a total sum of $14,000 in respect to the reports for PC.
Interest
204. Upon the sum which I consider the FSP must pay to the Applicants, interest
must be calculated. The normal principle is that interest runs from the date
upon which the FSP’s IDR response was furnished to the Applicants, which
in this case is August 2011.
205. I have given thought to the question as to whether this date is too early,
having regard to the fact that there was increasing evidence of damage at
this time.
206. I consider that the normal principle should apply. Essentially what has
happened is that the FSP has disagreed with the proposition that all of the
damage should be recognised as being carried by the storm. It was this
decision which has given rise to the dispute thereafter.
207. The Determination which I make will therefore apply the usual principle.
Determination
208. I determine that the FSP must pay to the Applicants the sum of $217,750 in
compensation for the damage that w as caused to the Applicants’ property by
the storm on 7 December 2010. (I note that this sum is to be paid in addition
to the sum of $42,854.50 being the cost of the work referred to in Scope of
Work Part 1, for which the FSP has already accepted liability).
209. I further determine that the FSP should pay to the Applicants interest upon
the above sums ($42,854.50 and $217,750, respectively), from 30 August,
2011, at the statutory rate, until the date of settlement.
Case No: 257846 Determination Page 31 of 31
210. I further determine that pursuant to the FOS Terms of Reference, the FSP is
to pay to the Applicants the sum of $14,000 in partial recompense of the fees
owing by the Applicants to PC Engineers.
211. I further determine that the FSP pay to the Applicants the sum of $6,000 to
compensate them for a period of six months during which they would have
been obliged to vacate their property while repairs were carried out.