Home / Financial Firm (Unknown - Insurer) / Determination 257259

Determination 257259

Cash settlement amount for retaining wall repairs disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2012-12-31
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$1,058
Non-financial loss$1,000
Amount claimed$25,228
SourceAFCA PDF

Summary

This addendum determination follows the same retaining wall dispute: the applicants sought a higher cash settlement and $3,000 compensation. AFCA accepted their updated $32,945.55 repair quote, ordered the FSP to pay 50% less the $15,565 already paid, and awarded $1,000 for non-financial loss.

The original contractor quote was conditional on engineer's specifications that the FSP never obtained, so the updated costed quote is treated as fair and reasonable under the policy claim settlement.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 257259 Addendum Determination Page 1 of 6 Case Number: 257259 General Insurance – Domestic Insurance – Home Building – Storm damage – Collapse of retaining wall – Repair rectification 21 November 2012 Background 1. On 16 January 2006, the Applicants lodged a claim for damage to 8 metres of an 18 metre retaining wall that had collapsed following storms and heavy rain. The Financial Services provider (FSP) accepted liability and completed repairs at a cost of $3,118. 2. The FSP did not engage the services of a structural engineer and it was subsequently found that the original wall was not structurally adequate to withstand the applied loads. 3. In early January 2011, eight metres of the retaining wall, that had been replace d in 2006, collapsed due to what the Applicants, and FSP‟s experts believed, was as a result of poor workmanship and not following BCA standards. 4. The FSP accepted the claim to rebuild the eight metres of wall previously replaced due to it having accepted t he 2006 claim. However, the Applicants‟ requested the FSP obtain a quote to replace the entire 18 metres of the wall. 5. The FSP obtained a quote to replace the wall at a cost of $27,060 and made a cash settlement offer to the Applicants to pay 50% of that amount, that is, $13,530. Summary of Applicants’ Position 6. The Applicants seek to have replacement of the entire 18 metre length of the wall to comply with the Building Act 1993 and an engineer‟s design. 7. The FSP rejected the Applicant‟s request on the grounds that the original retaining wall had not been constructed according to the Building Code and the inadequate construction was the cause of the collapse of the wall. 8. The matter was referred to the FOS Ombudsman who found that the FSP „s offer of $13,530 was fair and reasonable with the proviso that the cost of Addendum Determination Case No: 257259 Addendum Determination Page 2 of 6 repairs was to include additional costs such as engineer‟s report, Council and Building permits. Summary of FSP’s Position 9. The FSP obtained quotes to complete repairs for the amount of $27,060 which was subsequently increased by $4,070 to include the cost of Engineer‟s design fee, Building surveyor‟s fee and Soil engineer‟s fee increasing the total amount to $31,130. 10. The FSP then made a cash payment of 50% of $31,130, that is, $15,565 to the Applicants. 11. However, the Applicants have rejected the amount of the cash payment on the grounds that it does not allow for price increases since the date of the original quotes and does not include possible additional costs that may be incurred in carrying out the repairs. 12. The Applicants are also claiming payment of $3,000 compensation under section 9.3 of the Service‟s Terms of Reference due to further delays in settling their claim and time and effort in reviewing the costs associated in replacing the wall. 13. The Applicants investigated the increases in material and labour costs and the possible additional overhead costs and found that the cost of repairs will possibly be $44,455.75. They submit that the FSP should increase its payment to 50% of $44,455.75, that is, $22,227.88. 14. The Applicants have referred this matter back to the Ombudsman as the FSP has maintained its position to pay the amount of $15,565. Issues 15. Whether the Applicants are entitled to have the cash payment of $15,565 increased. 16. Whether the Applicants are entitled to payment of compensation under the Terms of Reference. Reasons for Decision 17. There has been an exchange of material which the parties rely on. Each party has had access to the material on which the other party bases its case. As a consequence it is not necessary to go into all of this material other than when relevant. Case No: 257259 Addendum Determination Page 3 of 6 18. The Applicants have reviewed the costs involved in carrying out the repairs to the retaining wall with various contractors. A schedule of their increased costs is as follows: Item FSP ‟s Quote Applicants‟ Quote Steel channels $2,134 $2,400.75 Sleepers $3,850 $4,235.00 Concrete $4,400 $4,730.00 Labour $6,270 $6,583.50 Machinery hire & drilling $2,750 $2,887.50 Demolition $3,080 $3,234.00 Supervision & Overhead $4,576 $4,804.80 Engineers‟ reports $4,070 $4,070.00 Total $31,130 $32,945.55 50% = $15,565 $16,472.78 19. The Applicants have also included the following costs that may, or may not be, incurred: 1. Remove & reinstall fencing $300.00 2. Drainage aggregate $787.50 3. Drainage plumbing $375.00 4. Fixings & wedges $450.00 5. Porta-loo hire $165.00 6. Building permit $630.00 7. Lodgement fee $51.00 8. State government levy $85.35 9. Traffic management permit $1,912.50 10. Traffic management plan $404.25 11. Assets protection fee $210.00 12. Power line safety $2,250.00 13. Dogman $618.75 14. Electrical spotter $585.75 Case No: 257259 Addendum Determination Page 4 of 6 15. Traffic controller $1,607.10 16. Letter drop $200.00 17. Repair access and egress $500.00 18. Kennel for dog $378.00 Total $11,510.20 20. The Applicants are seeking 50% of $44,455.75 which is the total of $32,945.55 plus $11,510.20; 50% amounts to $22,227.88. 21. The FSP has included in its o ffer payment of 50% of the cost of an engineer‟s design fee, building surveyors fee, and soil engineers fee. 22. However, this only goes part of the way in arriving at a fair and reasonable settlement of the Applicants‟ claim. 23. The FSP submits that a report it received from a consulting engineer confirmed that the contractor‟s quote of $27,060 was fair and reasonable and complies with the Ombudsman‟s determination. 24. However, the FSP has ignored provisos to the quotes from the contractor in which he states: “ Quote No: 40560 – „Total estimated cost to complete these works $27,060 including GST. NB: these costs are subject to change, depending upon specifications by an engineer‟ Quote No: 40658 – „This quote would be subject to an engineer‟s report and approval of the method [my emphasis] we have quoted for.” 25. Further, the consulting engineer in confirming the contractor‟s quote was fair and reasonable also added a proviso when he stated: “ In our opinion, the Scope of Works detailed in the quotation appears fair and reasonable and the proposal put forward appears [my emphasis] to be adequate, however geotechnical investigation and engineers computations would need to be carried out to confirm this.” [my emphasis] 26. Therefore, because of these provisos I find that the FSP has not met the terms of the determination dated 22 March 2012. 27. The Applicants have stated that they contacted the landscape contractor, who was to perform the repair work and submitted the quote for $27,060 to the FSP‟s managing contractor and who confirmed that his quote was for only 30 days after 21 September 2011. 28. However, the FSP submits that the landscape contractor has confirmed that he will honour the quote of $27,060. 29. Neither the FSP nor the Applicants have submitted any evidence in support of their position in regard to the status of the quote. Case No: 257259 Addendum Determination Page 5 of 6 Compensation 30. The Applicants have submitted a request for FOS to determine whether compensation should be awarded under the FOS Terms of Reference. 31. 9.3(b)(i) of the Services terms of Reference state: “ 9.3 Other compensation ... b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services provider compensate the Applicant for non-financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind has occurred; or FOS Terms of Reference – 1 January 2010 (as amended 1 January 2012) page 19 to 43. ... The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute.” 32. During the course of the dispute, the FSP has not explored what possible costs would be incurred following any investigation by structural and/or soil engineers. 33. In the contractor‟s original quote under the heading “Scope of works‟ is the statement: “ Approval of engineer specifications & permits will be required before work can be carried out.‟ Notwithstanding this advice the FSP did not appoint an engineer to prepare the recommended specifications. ” 34. In September 2011, the FSP engaged a consulting engineer to „...determine the cause of partial collapse of a retaining wall.‟ However, the FSP did not engage a structural engineer to prepare specifications to repair the wall as recommended by the contractor. 35. At the request of FOS, the Applicants did have the cost of repairs reviewed and investigated other additional costs that may be incurred during the repair works. The Applicants submitted a schedule of these costs to FOS which were copied to the FSP. 36. The FSP did not offer any comment. I would have expected a detailed response. I do consider that the FSP‟s handling of the matter has been unsatisfactory and has caused unnecessary inconvenience as referred to in paragraph 9.3(b)(i) of the Terms of Reference. 37. Therefore, in view of the inconvenience and time taken to prepare the costings schedule, I consider that the Applicants should receive $1,000 as compensation under clause 9.3 (b)(i) of the Terms of Reference. Case No: 257259 Addendum Determination Page 6 of 6 Determination 38. In respect to the quote of $27,060, that is eleven months old, I determine the Applicants‟ increased quote of $32,945.55 to be fair and reasonable and supersedes the amount of $27,060. The FSP is to pay 50% of the $32,945.55, that is, $16,472.55 less the amount of $15,565 already paid to the Applicants. 39. If the amount of $32,945.55 has to be reviewed depending on the results of engineers‟ reports, a ny increase in the cost of repairs is to be shared on a 50:50 basis between the FSP and Applicants. 40. In respect to expense items numbe red 1 to18 I determine that item 1 „remove and reinstall fencing $300‟ is to be included. I therefore add the additional sum of $300 or 50% equalling to $150. 41. In respect to item 18 „Kennel for dog $378‟ I determine that this item is not relevant in respect to the repairs and is not to be included in the total cost. 42. Items 2 to 17 inclusive are items which may, or may not, be costs that will be incurred as repairs to the wall proceed. However, I determine that as any of these expenses are incurred the FSP is to pay 50% of the cost incurred at that time. 43. Alternatively, I determine that the FSP can make a full and final settlement of the Applicants‟ claim by payment of the amount of $ 21,849.88 (being $22,227.88 less the $378 for the dog kennel) less the amount of $15,565, as requested by the Applicants. In addition, the FSP is to cash settle 50% of any additional construction costs that may be incurred following the repair specifications recommended by the relevant engineers‟. 44. I also determine that the FSP must pay to the Applicants the sum of $1,000 pursuant to paragraph 9.3(b)(i) of the Terms of Reference of this Service.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.