Home / Financial Firm (Unknown - Insurer) / Determination 255889
Determination 255889
Denial of storm-related home water damage claims
Summary
The applicant's two storm-related water damage claims on his home were denied by the FSP. AFCA found the gradual deterioration, poor maintenance and faulty design exclusions applied.
The FSP's engineering evidence established on the balance of probabilities that the water damage resulted from excluded deterioration, wear and tear, lack of maintenance and faulty design.
Issues
- Claim denial primary · not upheld“I determine that the FSP was entitled to deny liability for the Applicant's claims.”
Subjects and remedies
home or building damageno remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 255889 Determination Page 1 of 6
Case number: 255889
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
24 April 2012
Background
1. The Applicant arranged a home insurance policy with the Financial Services
Provider (FSP) for his residential home and contents. This policy was initially
arranged on 15 March 2002 and then renewed annually. The relevant
periods of insurance are 15 March 2009 to 15 March 2010 a nd 15 March
2010 to 15 March 2011.
2. This dispute results from two claims lodged on the policy regarding storm
damage. The first storm claim occurred on 6 March 2010 and the second on
4 February 2011.
3. Upon reviewing the claims, the FSP denied liability on the basis the damage
was due to factors excluded from the policy. The Applicant has disputed the
FSP’s decision.
4. After the denial of the claim by the FSP the Applicant referred the matter to
this Service. On 6 February 2012, after carefully considering all of the
material and the submissions by the parties, a Senior Case Manager
recommended that the FSP was entitled to deny liability for the Applicant’s
claims.
5. The Applicant has not accepted this Recommendation and has sought this
Determination. When doing so he stated that “I did all I could to rectify the
matter in an honest and businesslike manner ” a nd “what is the point of
insurance if customers are not covered – people are not aware of the
technicalities that allow companies like (FSP) to side step their
responsibilities ” .
Summary of Applicant ’s p osition
6. The Applicant says that in relation to the storm on 6 March 2010 and his
failure to follow this up or repair any of the damage before the second storm
on 4 February 2011, he was awaiting advice from his plumber regarding the
scope of works before undertaking any repairs or renovations. He has
Determination
Case No: 255889 Determination Page 2 of 6
provided a letter from his plumber to corroborate this and this letter stated
the following:
“I was engaged by [ Applicant] on 19/07/2010 after inspection of house at
[address] to remove old and completely replace surface upstairs balcony and
put in extra outlets and downpipe from roofs to allow excess water to escape.
I needed an extended dry period for the removal and replacement of balcony
flooring – this I was unabl e to achieve before the flooding of February 2011.”
7. He has owned the home for approximately 50 years and has not had any
issues with water penetrating the home prior to these storms. Further, it is
clear the storm has caused the damage.
8. The Applicant also says that if the property was such a poor risk, then he
queries why the insurer continually offered renewal.
9. Given the above, the Applicant believes some form of cash settlement would
be appropriate in the circumstances.
10. This Service contacted the Applicant to point out that if there was additional
evidence which could be supplied whether from his plumber or any other
tradesman, it should be supplied before a Determination was made.
11. In a report dated 11 April 2012 the Applicant’s plumber “BP” stated that “ I
was asked by (Applicant) to inspect his property at (Address) after a big
storm in March 2010 to find the source of water leakages in upstairs areas of
the house. My findings were that the existing overflows were not adequate to
carry away excess water and that the roof top balcony area had severe
cracks in the concrete and bitumen surface. ”
12. BP then commented as to the steps which needed to be carried out to
resolve the problem and estimated a scope of works between $35,000 to
$40,000.
13. Finally, he commented that “I need an extended dry period for the removal
and replacement of balcony flooring – this I was unable to achieve before the
flooding of February 2011”.
Summ ary of FSP’ s position
14. The FSP is relying on its engineer’s report dated 8 June 2011 which
identified that the basis of the water damage was due to lack of
maintenance, gradual deterioration, wear and tear, inherent defects, faulty
workmanship and faulty design. These causes are all excluded under its
policy.
15. Further and in the alternative, the FSP notes the Applicant initially lodged a
claim on 19 March 2010 for the first storm damage yet made no effort to
repair any of the damage or rectify the issues with the roof. Accordingly, the
Applicant has breached his contractual duty of care to exercise all
reasonable precautions and his failure to do so has resulted in further
Case No: 255889 Determination Page 3 of 6
deterioration. As a result, the FSP is prejudiced by the Applicant ’s breach
regarding the damage from both storms.
16. The FSP relies on the following policy provisions to substantiate its position:
“ Your Duty of Care
You must exercise all reasonable precautions:
for the safety and protection of the insured property
to prevent personal injury or damage to property
to maintain your home and contents in good condition
…
General Exclusions
These General Exclusions apply to all sections of the policy. …
This Policy does not cover: …
Loss, damage, destruction, consequential loss or liability directly or indirectly
caused by, contributed to by, resulting from, or arising out of or in connection
with:
…
gradual deterioration, wear and tear … or lack of upkeep or maintenance
…
inherent defects , faulty workmanship, structural defects, or faulty design
…
The Insured Events You Are Covered For …
9. Storm and/or rainwater
including loss or damage from:
the escape of rainwater from any water pipe, drain or gutter
surface run-off rainwater from surrounding areas, or
flood.
We will not settle losses relating to:
Loss or damage:
…
from water seeping into or entering your home due to:
- poor attention to maintenance
- building additions and alterations
- structural defects, faulty design or faulty workmanship.”
Issues
17. Whether the FSP is entitled to deny liability towards the Applicant ’s claims.
Case No: 255889 Determination Page 4 of 6
Reasons for Decision
18. In this matter there has been an exchange of material between the parties
and I have had the opportunity to consider the submissions made by each
party.
19. The initial onus of proving that the damage of which he complains, is storm
related, falls upon the Applicant.
20. As considerable water damage has been established throughout the house,
and as no one has contradicted the Applicant’s statement that the damage
was first exhibited after 6 March 2010 storm, a nd then again after 4 February
2011 storm, I consider that the Applicant has discharged the onus.
21. Once I am satisfied as to this, I note that the FSP is seeking to rely on an
exclusion clause and therefore has the burden of establishing on the balance
of probabilities that it applies. In this regard, the FSP is substantially relying
upon its engineer’s report dated 8 June 2011.
22. In the Recommendation the Senior Case Manager summarised findings of
the FSP’s engineer in paragraph 14. That summary was accurate and I set it
out below:
“There is considerable water damage throughout this house. Practically all of
it has been caused by water infiltration from both the flat metal deck roof and
box gutters over most of the front section of the house and the flat courtyard
over the rear section.
There is little doubt that the storms in February and March would have caused
water to flow into the house. It is obvious however that the water infiltration
has been happening over a long time, probably years.
The metal deck and box gutters are a poorly conceived design and have been
penetrated many times – some of these penetrations have occurred in the
gutters themselves. They are highly susceptible to over flow and are in urgent
need of rebuilding.
The courtyard covering has been damaged and is in urgent need of
maintenance.”
23. I agree with the Senior Case Manager’s conclusion that the engineer’s report
together with photographs supplied by him show evidence of:
The waterproofing material in the courtyard deteriorating with weeds
growing through it,
The box gutters containing rust and being too flat, and
Roof sheets lifted, thereby disturbing potential rain flow.
24. The FSP’s engineer’s report is consistent with the report of the Applicant’s
plumber BP, from his report of 9 December 2011.
Case No: 255889 Determination Page 5 of 6
25. In these circumstances, prima facie the FSP’s reliance upon the exclusion
would succeed. In simple terms the FSP is not obliged to pay a claim if water
seeping into the home is due to poor attention and maintenance, building
additions and alterations, or structure defects, faulty design or faulty
workmanship. If the FSP can establish any of these matters, then it is
entitled to deny liability.
26. In the circumstances, I invited the Applicant to consider whether he had
made available all material which was available to him and which supported
his claim. The Applicant was specifically alerted to the need to establish that
the damage for which he seeks compensation was caused by one or other of
the storms and that it was not due to failure of maintenance or faulty design
and wear and tear.
27. The Applicant has now provided further report from BP but regrettably it
does little more than set out the position that BP had previously advised.
Nowhere in the report does BP deal with the issue of the suggestion from the
FSP’s expert that water infiltration had been happening over a long time,
probably years, or that the metal deck and box gutters were poorly
conceived or that the photographs showed water proofing material in the
courtyard deteriorating with weeds growing through it, or that the box gutters
contained rust and were too flat, or that roof sheets lifted thereby disturbing
the potential rain flow.
28. In short, the later report by BP, does not address any of the problems
highlighted by the Senior Case Manager in the Recommendation.
29. I sympathise with the Applicant, and note that he lives a considerable
distance from the subject property and that this combined with his age, make
it more difficult than what otherwise would be the case for him to present a
coherent picture of all that has happened.
30. But I am unable to reach a conclusion that once damage had been evident
following the 2010 storm, it was impossible to have any remedial action
carried out before the storm of March 2011. I appreciated the comments
made by BP but he was not the only plumber to whom the Applicant could
have turned to for assistance.
31. Having considered all of this material, I consider that the FSP is able to
establish, on the balance of probabilities that the Applicant’s loss with
respect to the two claims arose from or was indirectly caused by the
deterioration of the water proofing material in the courtyard and the faulty
design and wear and tear of the flat metal roof. I consider that there is also
abundant evidence of a general failure to maintain the property in
reasonable condition.
Case No: 255889 Determination Page 6 of 6
Determination
32. On the basis of the available information I determine that the FSP was
entitled to deny liability for the Applicant’s claims.