Home / Financial Firm (Unknown - Insurer) / Determination 255116
Determination 255116
Storm damage claim for internal water damage denied
Summary
The insured's storm claim for internal water damage was denied by the insurer, which relied on storm-created opening and faulty workmanship exclusions. AFCA found a storm-created opening and ordered the insurer to pay 50% of internal repair costs, to be quantified by scope and quotes.
Raised roof screws evidenced a storm-created opening, so the water entry is covered, and the insurer's failure to properly investigate meant liability was shared equally.
Issues
- Claim denial primary · upheld
“I am satisfied, on the balance of probabilities, water inundation occurred as a result of the storm event.”
- Inadequate claim investigation secondary · upheld
“no action was taken by the FSP at this time and it maintained its position to deny the claim.”
- Poor communication secondary · upheld
“There is no indication the FSP sought to pursue this matter further by writing to the Applicant.”
Subjects and remedies
home or building damagenatural disasterpay claim
Text of the determination
Case No: 255116 Determination Page 1 of 10
Case number: 255116
General Insurance - Domestic Insurance - Home Building & Contents - FSP
Decision - Denial of claim-Exclusion/ condition
27 March 2012
Background
1. The Applicant is insured under a home building and contents policy with the
Financial Services Provider (FSP) to cover loss or damage to property
caused by insured events as described in the policy. The relevant period of
insurance is 11 January 2010 to 11 January 2011.
2. On 6 September 2010, the Applicant contacted the FSP to advise that
damage occurred to the property that day as a result of a storm event. It was
reported damage had been sustained to the west wall, ceiling, chimney, fire
place, antenna, roof, toilet floor, kitchen and bedrooms one and three.
3. It was also reported that a television situated in the living room was
damaged by the storm event.
4. The FSP arranged for a builder to attend the property on 8 September 2010
and to report on the damage. The builder noted damage to the flue pipe and
TV antenna. The builder also noted there were no flashings installed on the
verandah roof.
5. On 10 December 2010, the FSP wrote to the Applicant advising it would not
cover internal repairs and referred him to page 15 of the policy booklet
where it stated the FSP will not cover loss or damage when water enters the
property through an opening that was not storm created.
6. The FSP also referred the Applicant to the general exclusion regarding faulty
design and workmanship.
7. The Applicant disputed the FSP’s decision to deny his claim for internal
water damage. The Applicant also advised the roof had been damaged by
the storm. Although the FSP arranged for its builder to re -inspect the
property it still maintained its decision to deny the claim for internal damage.
8. The FSP cash settled the Applicant for repairs to the chimney flue and
antenna. The Applicant was paid $120.00 less the policy excess of $500.
Determination
Case No: 255116 Determination Page 2 of 10
9. In regards to the television the FSP says the Applicant has not established
this has been damaged by an event covered by the policy.
Summary of Applicant’s position
10. The Applicant says at the time he lodged the claim he advised the FSP there
was a hole in the roof.
11. In addition the Applicant says the roof was lifted during the storm event
allowing water inundation. He says the FSP accepted the chimney flue and
antenna have been damaged by the storm.
12. The Applicant says damage to the chimney flue and its supports opened the
roof in this area resulting in flooding of the roof, the ceilings, internal walls
and floor in the sunroom.
13. The Applicant says the FSP is fixated on the issue there was no flashings.
He says water did not enter the house because of the lack of flashings on
the verandah roof.
14. The Applicant says because of the way the FSP has handled the claim and
its attitude towards him it has failed its obligations towards him with
regarding the following:
A “Duty of Care” under Contract Law;
Misrepresentation of facts by its staff;
Unconscionable conduct;
Negligence in Tort;
The FSP’s records are incorrect / reconfigured.
Summary of FSP’s position
15. The FSP says given the Applicant has made serious allegations against it, in
particular:
breaching its duty of care in contract law;
was negligent in tort;
engaged in unconscionable conduct;
conspiring against him; and
made misrepresentation of facts
16. The FSP originally submitted that given the above, this dispute is more
appropriate for determination by a court and that FOS ought to exercise its
discretion and refuse to consider this dispute pursuant to Section 5.2 of the
FOS Terms of Reference.
Case No: 255116 Determination Page 3 of 10
17. The FSP subsequently withdrew that submission and relied on clause
8.7(a)(ii)B of the Terms of Reference. Under that clause FOS is empowered
to not make a determination if it believes it is not possible to reach a
conclusion as to the merits of the dispute.
18. In the alternative the FSP says:
the Applicant has not established the policy responds to his contents
claim;
it has established that internal building damage was the result of water
entering through an opening that was not created by the storm;
it has established the internal damage was as a result of faulty design
or workmanship which is excluded by the policy;
the Applicant’s failure to co-operate with it has undermined its ability to
assess the damage as a result of the storm. Thus pursuant to section
54 of the Insurance Contacts Act (the Act) it is entitled to reduce its
liability;
the Applicant has not established it acted in a manner consistent with
the serious allegations made by him.
19. The FSP relies on the followi ng policy provisions:
“ Storm
If your home or contents suffer loss or damage caused by
a violent wind, cyclone or tornado
thunderstorm or hail which may be accompanied by rain or snow, or
a sudden, excessive run-off of water as a direct result of a storm in
your local area
we will under contents insurance
► replace or repair your damaged contents
we will under buildings insurance
rebuild or repair that part of the home that was damaged
…
however under buildings insurance
► we will NOT cover loss or damage caused by storm to retaining walls, or
when water enters through an opening that was not created by the storm.
…
What you are not covered for – general exclusions
We will NOT cover
► loss, damage, injury or death that occurs as a result of
…
faulty design or workmanship
…
Case No: 255116 Determination Page 4 of 10
What you must tell us
We need information from you before we can process your claim
you must
► promptly pass on all information about the claim to us
remember that a claim made by any one of the persons named as the
inured is a claim made by all of them
► pass on any information that we request
otherwise
► we will be unable to process your claim
…
Your responsibilities
You have a responsibility to co-operate fully with us, even if we have
already paid your claim
you must
► provide us with all the information, documents and help we need to deal
with your claim
…
Things that may put your claim at risk
You may put your insurance claim or cover at risk if you do not meet
your obligations to us. We may refuse a claim, cancel your Policy, or do
both
if you
► are not truthful and frank in any statement you make in a claim or in
connection with a claim
►….
► do not take all reasonable care to protect your home and contents against
loss or damage
► do not maintain your home in good order and condition. This means your
home must be watertight, structurally sound, secure and well maintained
...
GLOSSARY
…
storm
is a violent wind, cyclone, tornado, thunderstorm or hail which may be
accompanied by rain or snow, or a sudden, excessive run-off of water as a
direct result of a storm in your local area. It does not include persistent rain by
itself.”
Case No: 255116 Determination Page 5 of 10
Issues
20. Whether the FSP has fulfilled its obligations under the policy in respect of
storm damage to property.
Reasons for decision
21. FOS has considered it is appropriate to expedite the dispute in accordance
with clause 8.6 of the FOS Terms of Reference. This is because of the
issues in dispute. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
22. There has been an exchange of material between the parties. It therefore is
not intended to recite material except where considered relevant.
Jurisdiction
23. The Applicant has raised allegations which the FSP considers to be of a
serious nature regarding:
a. breaching its duty of care in contract law;
b. was negligent in tort;
c. engaged in unconscionable conduct;
d. conspiring against him; and
e. made representation of facts
24. The Applicant has however, not provided any succinct argument to the
allegations but regardless the FSP contends the Financial Ombudsman
Service (FOS) should exercise its discretion to exclude the dispute.
25. I have read the arguments put forward by the FSP in this regard. I have also
taken into consideration the issue(s) in dispute which entails as to whether
the Applicant has suffered a loss which is covered by the policy.
26. FOS has successfully dealt with disputes of varying degrees of complexity
over a number of years, including those where an FSP has made an
allegation of fraud. I do not consider this matter to be overly complex nor is
there an allegation of fraud.
27. In addition, paragraph 8.2 of the Terms of Reference requires FOS, when
deciding a dispute and whether a remedy should be provided, to do what in
its opinion is fair in all the circumstances, having regard to:
legal principles;
applicable industry codes or guidance as to practice;
good industry practice; and
previous relevant decisions of FOS or a Predecessor Scheme (although
FOS will not be bound by these).
Case No: 255116 Determination Page 6 of 10
28. FOS’s processes and procedures, in addition to its experience in relation to
all types of disputes, means that the Service will provide a resolution of the
dispute, which is fair in all the circumstances.
29. I concl ude the dispute does in fact fall within FOS’s jurisdiction and that it
would not be appropriate for FOS to exercise its discretion under paragraph
5.2 to exclude it.
30. In passing, I note the Service is required and empowered under the Terms of
Reference to resolve disputes as between the FSP and the policy holder in
accordance with the Insurance Contracts Act (the Act) and the common law
in respect of insurance contracts. In my view, I am not empowered to apply
tortious remedies of the type claimed by the Applicant and set out in
paragraph 14 above.
Insured Event
31. The Applicant lodged a claim for storm damage to his property. The FSP
appointed a builder to attend the property on its behalf on 8 September 2010
and report on the damage. The builder’s report is not extensive. However
wind damage was identified to the TV antenna and flue pipe. At the time of
this inspection the Applicant alerted the builder to water entry to the lounge
room from the storm event. The builder noted there were no flashings on the
verandah iron roof.
32. Following receipt of the builder’s report, the FSP wrote to the Applicant
advising it was not accepting the claim for water damage to the lounge room
citing policy exclusions regarding “storm created opening”, faulty design and
workmanship.
33. The FSP advised the Applicant that damage to the chimney and TV antenna
was covered and that he should contact it to process this part of the claim.
34. According to the FSP’s claim files notes the Applicant lodged a second claim
on 10 September 2010 as a result of hail damage to the roof that occurred
on 9 September 2010. The FSP requested the builder to re-attend the
property to inspect the roof.
35. The builder attended the property on 14 September 2010. Again this report
is not extensive but I note the following commentary:
“… [Applicant] explained water had once again entered via the are a on the
verandah where no flashings are present also again through the heater flue &
overflow from spouting allowing water into the toilet. We recommend an
internal assessor be appointed for 1. As [Applicant] is indicating possible
structural damage as a result of the water entry overtime & 2. We believe
these issuers (sic) about the dwelling [Applicant] has will be ongoing problem
between ourselves, [Applicant] and Claims. Therefore we would like to stand
aside from this claim & have an assessor appointed.”
36. There is no indication in the report that the roof was inspected for hail
damage.
Case No: 255116 Determination Page 7 of 10
37. The Applicant contacted the FSP on 15 September 2010 to dispute the
denial of his claim for internal water dmage due to insufficient flashings. The
FSP advised it would review the file on receipt of the builder’s second report.
38. On 16 September 2010, the Applicant was advised the claim was denied
based on the builder’s inspection on 8 September 2010. The FSP confirmed
in writing that day that the claim was denied as damage was not caused by a
listed event as described in the policy.
39. The Applicant again disagreed with the FSP’s decision to deny his claim for
internal water damage. The Applicant also raised issue with the roof having
suffered storm damage in that it was lifted by the winds and water gained
entry because of this.
40. During the review, the FSP’s representative [GH] conceded the Applicant
was covered for storm damage to the chimney flue and TV antenna and
belatedly cash settled the Applicant for these repairs.
41. It was also during this review that GH contacted the builder who advised that
someone higher needed to deal with the situation as it was beyond him. GH
was not aware of t he builder’s second report. GH contacted the Applicant on
18 October 2010 to arrange for assessor to attend the property. However the
Applicant did not agree to this believing the FSP was too late in trying to
rectify the situation.
42. On reviewing the FSP’s claims file notes I note the level of telephone
communication between the FSP and Applicant. I acknowledge this may
have been a difficult matter for the FSP to resolve.
43. In addition I also note from the file notes the FSP sought, on several
occasions, a report from the Applicant as to the cause of damage to the
television.
44. Nevertheless, I do not have the benefit of knowing what correspondence
was issued, if any, to the Applicant following the telephone conversation of
18 October 2010.
45. I note the FSP has in its submission referred to the policy conditions
including providing information and co-operation. The FSP has established it
brought these policy conditions and consequences to the Applicant’s
attention during the claims process either by way of telephone contact or
correspondence.
46. The crux of this dispute is the Applicant is primarily seeking to have internal
water damage that occurred to various rooms accepted as storm damage.
47. The FSP has denied the claim for internal water damage on the grounds that
there is no storm created opening as well as referring to policy exclusions
relating to faulty design and workmanship due to the lack of flashings on the
verandah roof.
Case No: 255116 Determination Page 8 of 10
48. However the Applicant maintains that the lack of flashings on the verandah
roof was not the cause of water entry.
49. The Applicant says water entered into the house as a result of the roof being
lifted during the claimed event. This, he says, is supported by the damage to
the chimney flue.
50. The Applicant also reported roof nails were lifted. According to undated
correspondence from a plumber a section of roof tek screws were replaced.
51. The FSP has provided photographs with its submission showing the roof. I
note from the photographs that there are raised screws which confirm the
Applicant’s assertion the roof was lifted. I accept rainwater would be able to
penetrate into the roof through these raised screws. I also note water would
have been able to enter where there were no flashings.
52. The FSP in its submission stated:
it would be difficult, if not impossible, to assess the loss and damage
that occurred as a result of the storm due to the passage of time;
the Applicant’s actions have resulted in its not been able to investigate
the claim;
i t has been significantly prejudiced by the Applicant’s actions .
53. The FSP states, in the circumstances, that section 54(1) of the Insurance
Contacts Act (the Act) applies. As such it is entitled to limit is liability to nil.
54. In my opinion, S54 has no application to this case because the Applicant
does not seek to rely on an intervening causal act as requested by that
profession.
55. The FSP asserts the Applicant failed to cooperate with it and actively
prohibited it from properly assessing and investigating the claim.
56. The FSP also referred to various policy conditions as to why the loss is not
covered including the Applicant’s failure to keep the property in good repair
and condition. The FSP is not in the possession of a ny report that indicates
the Applicant failed to keep in house in good repair or condition. I accept the
there were no flashings on the verandah roof.
57. I note the FSP appointed a builder to attend the property on 8 September
2010 and 14 September 2010. Following his second attendance the builder
suggested an assessor be appointed. However no action was taken by the
FSP at this time and it maintained its position to deny the claim.
58. It was not until 18 October 2010 that when reviewing the Applicant’s
complaint about the denial of the claim that the FSP requested to send a
building assessor. However the Applicant would not agree to this believing
the FSP had left it too late to adopt this course of action.
Case No: 255116 Determination Page 9 of 10
59. There is no indication the FSP sought to pursue this matter further by writing
to the Applicant to advise him of his obligations under the policy and as to
why it considered a further inspection of the property was necessary.
60. It would have been helpful for the FSP to have advised the Applicant that it
needed to inspect the internal damage as the builder was only requested to
inspect the roof.
61. The FSP has also raised issue with the Applicant failing to provide an
electrician’s report to show the cause of damage to his television. However
the Applicant is not overtly pursuing this.
62. Even so, I accept the Applicant would need to provide some evidence as to
why the television was not working and whether this was storm related.
63. Nevertheless I accept both parties have contributed to the unsatisfactory
position that now exists. The FSP has indicated its prejudice is such that it its
liability is nil. It has indicated it would be difficult, if not impossible, to assess
the loss that occurred as a result if the storm due to the period of time since
the claimed event.
64. The FSP also referred to the application of the W ayne Tank principle in this
matter as although the “storm” is the insured peril, the excluded peril is no
“ storm created opening ” . In such circumstances, the exclusion applies if the
events are concurrent.
65. However, I am satisfied there is indication the roof was lifted by winds, as
evidenced by the raised screws, this being a storm created opening. As such
I am satisfied, on the balance of probabilities, water inundation occurred as a
result of the storm event.
66. Due to the passage of time since the claimed event I will consider as to what
is fair in all the circumstances in accordance with clause 8.2 of the Terms of
Reference. Although it may not be possible to establish as to how much
water inundation occurred through the storm created opening(s) I believe
that each part should be held equally liable for the cost of repairs of internal
damage.
67. The Applicant has indicated he has not undertaken any internal repairs as he
was not in a financial position to do so. However, he did indicate water
damaged carpet had been removed.
68. To establish quantum of the claim, I see no valid reason as to why a loss
assessor should not attend the property to report on internal water damage,
and arrange for a scope of works and obtain quotes on which settlement can
be considered.
Case No: 255116 Determination Page 10 of 10
Determination
69. On the basis of the available information I determine the FSP is liable for
50% of the repair costs of internal water damage.
70. The FSP is to arrange for a scope of works and quotes for the repair of
identified internal water damage. This is to be carried out within 21 days of
this determination. Once the quotes have been obtained the FSP is to
provide a copy to the Applicant and to advise him of the amount on which
settlement is to be based. I strongly urge the parties to act towards each
other in a spirit of good faith.