Home / Financial Firm (Unknown - Credit) / Determination 255104
Determination 255104
Denial of claim
Summary
The Applicant complained about his investment loan, progress payments and the FSP's conduct over selling his properties. AFCA found the FSP misled him about selling one property and overpaid the builder, and ordered a $2,578 reduction of his debt.
Misleading conduct is remedied by putting the consumer in the position they would have been in had they not been misled, and non-financial loss requires an unusual degree of inconvenience.
Issues
- Misleading conduct primary · upheld“FSP's statements misled the Applicant into believing it would not permit separate sale of his properties; reliance was reasonable.”
- Claim denial secondary · not upheld“FSP was not required under the loan terms to make progress payments to the builder.”
- Financial difficulty assistance secondary · not upheld“The FSP did meet its obligations to the Applicant as a customer experiencing financial difficulty.”
- Instructions not followed secondary · upheld“FSP was not authorised to pay an additional $1,078 to the builder and should compensate the overpayment.”
Subjects and remedies
financial hardshipdebt waiver or reductionpay compensationpay non financial loss
Related
All Financial Firm (Unknown - Credit) determinations · Find similar determinations
Text of the determination
Case No: 255104 Recommendation Page 1 of 7
Case number: 255104
Credit - Consumer Credit - Home Loans - FSP Decision - Denial of claim
11 December 2013
Summary
Description
This dispute concerns the FSP’s conduct in relation to a loan to the Applicant for the
purchase of two properties and construction costs.
Basis of Determination
On the information made available, the Applicant had not made out his
claim that the FSP told him it would not release the titles to the
properties individually or, if it had, that he had suffered financial loss;
The structure of the Applicant’s loan had no bearing on the FSP’s
conditions upon which it would agree to the Applicant selling one of his
properties;
The Applicant would have experienced stress while he was under a
misapprehension about the FSP’s conditions upon which it would
release the title to one of his properties, and $1,500 was an appropriate
amount of compensation;
The FSP did not have the Applicant’s authority to pay any more to the
builder than his loan amount and it should compensate him for its
$1,078 overpayment.
Determination
The FSP should reduce the Applicant’s current debt by $2,578 being the amount of
compensation awarded for his financial and non-financial loss.
If the Applicant and the FSP are not able to agree a mutually acceptable repayment
proposal for the Applicant’s debt within 14 days of the Applicant’s acceptance of this
Determination, the FSP is entitled to take recovery action to collect its debt from the
Applicant
Background
1. In December 2007, the FSP granted a loan to the Applicant to purchase the
O Street property and to construct a house on that property;
Determination
Case No: 255104 Determination Page 2 of 7
2. In March 2008, the FSP approved an increase to the loan in order to fund
the planned construction works on the O Street property.
3. In April 2008, the Applicant purchased the S Road property and entered into
a building contract for the construction of a house on that property. He
sought a further loan from the FSP to fund that purchase and construction.
4. On 28 May 2008, the FSP approved an investment loan for $399,371(the
investment loan) secured by the Applicant's mortgages over the O Street
property and the S Road property. The investment loan funds were used to
refinance the Applicant's existing loan, with the remainder used to fund the
purchase of the S Road property and for construction costs.
5. The Applicant claimed the FSP:
a. failed to make progress payments to his builder;
b. misled him as to the terms and conduct of the loan; and
c. prevented him from selling the properties described above.
6. The FSP denied the Applicant's claims.
Conclusions in Recommendation
7. The dispute was the subject of a Recommendation. A copy of the
Recommendation is attached to this Determination. It sets out the details of
the parties' respective positions in relation to the dispute. It also sets out the
case manager's reasons for his Recommendation. In summary, the case
manager said:
Progress payments
a. Before the FSP was obliged to release any loan funds towards the
builder's claim for construction costs, the Applicant was required to:
i) contribute his own equity;
ii) pay the interest accruing on his loan;
iii) make a written request for each progress payment; and
iv) continue to demonstrate that he could afford the loan;
b. The FSP made the first progress payment claim, even though the
Applicant had not contributed his own funds. This was the only
payment made while the investment loan was within its terms;
c. The Applicant never met all the obligations for the FSP to be
contractually obliged to make payments to the Applicant's builder and
therefore is not liable for any loss the Applicant suffered due to his
inability to pay his builder when progress payments became due;
Case No: 255104 Determination Page 3 of 7
Misleading conduct
d. The FSP was not obliged to clarify the terms of the investment loan
with the Applicant. Further, the FSP did not mis lead the Applicant
about those contractual terms;
e. The FSP's payment of the first progress payment did not mislead the
Applicant into believing all subsequent payments would be or were
being made. Neither did the content of his account statement mislead
him into this belief;
f. Even if the FSP's conduct in this regard could be said to be misleading,
it was unreasonable for the Applicant to rely on that conduct to form his
belief when other circumstances (such as the FSP's efforts to contact
him and the lack of specific progress payments showing on his account
statements) would lead to a contrary belief;
g. The loan amount was not reduced when the Applicant informed the
FSP that he would not be proceeding with building works on the S
Road property but there was no information to show that the FSP had
represented that it would reduce the limit;
Sale of properties
h. It was likely that the FSP told the Applicant that his plan to sell one
property would not leave sufficient security, but it did not follow that the
FSP prevented a sale. However, its failure to clarify its position led the
Applicant to believe he would not be permitted to sell his properties
separately;
i. Despite this, the Applicant did not have information to show that he had
suffered loss as a result of being misled by the FSP, as his properties
were never put on the market;
j. The confusion about the FSP's position regarding the sale of the
Applicant's properties would have caused him stress and he was
entitled to $1,500 compensation for non-financial loss; and
k. The FSP had met its obligations to the Applicant when he was in
financial difficulty.
8. The FSP accepted the Recommendation but it was rejected by the
Applicant.
Further submissions
9. The Applicant made further submissions that can be summarised as follows:
The FSP had already made several written offers which far exceeded
the case manager's recommended compensation of $1,500. He had
lodged his dispute with FOS because the FSP's offers had been
unacceptable and he had approached FOS to obtain a fairer
determination exceeding the FSP's previous offers which he had
rejected;
Case No: 255104 Determination Page 4 of 7
He never marketed the properties because the FSP would not have
released the titles individually. If he had been given the correct
information by the FSP, he would not have incurred the interest on his
loan because he would have sold the O Street property on which a
house had been constructed. He therefore should not be liable for
accumulated interest, particularly since the date he lodged his dispute;
$1,500 was inadequate compensation for the stress he has incurred
over the five years spanning the circumstances of his dispute;
In summary, the FSP said it would not "split" the investment loan to
separate the properties so they could be sold. It stopped him selling
his properties and kept charging interest on his loan; and
In March 2010, the FSP overpaid the builder by $1,078 and added that
amount to his loan rather than recovering it from the builder.
10. The FSP provided the following further information:
a. Builder’s progress payment record form ;
b. FSP internal e-mail dated 13 April 2010;
c. Builder’s invoice dated 8 April 2010 for $5,102.25;
d. FSP’s letter to the Applicant dated 13 April 2010; and
e. FSP’s systems notes regarding the Applicant’s loan applications.
Ombudsman’s consideration
11. I have decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions. I have
taken into account all the material submitted by the parties, both before and
after the Recommendation. I am satisfied that the documentation I have
relied on has been provided to both parties.
12. I have carefully considered the case manager ’s Recommendation, together
with the pa rties’ further submissions.
13. I am satisfied that the case manager’s Recommendation contains an
accurate summary of the background to this dispute, the parties’ positions,
the issues to be determined, any applicable paragraphs of the Terms of
Reference and any relevant law.
FSP’s previous offers
14. Contrary to the Applicant’s expectations, FOS is not an advocate. FOS is an
external dispute resolution scheme alternative to the courts. We are
required under FOS’s Terms of Reference to form a view on a fair outcome
to a dispute between a financial services provider and its customer, having
regard to legal principles, industry codes and guidelines, good industry
practice and FOS’s approach to similar issues in dispute.
Case No: 255104 Determination Page 5 of 7
15. This means that, if required to provide our view about the merits of an
applicant’s dispute, we may conclude that the applicant is entitled t o less
compensation than the financial services provider may have previously
offered, as the financial services provider may also have had regard to the
value of its relationship with the applicant and its reputation when making its
offer, whether in admission of liability or on an ex gratia basis.
Misleading conduct
16. On the information made available, I am not satisfied that the FSP told the
Applicant it would not release the titles individually. The FSP’s system notes
include a record of a meeting between the Applicant and one of its branch
officers on 26 November 2008 which says:
“Spoke with [the Applicant] at [branch location], plans to sell [the S Road
property] auction this weekend, expects $127000 less agents fees . Existing
valuation for remaining security property (on completion) is $190000. Client
still needs to draw $96000 from home loan to complete the building. Client
advises that his estimate of value once home on [the O Street property] is
$265000. Currently at fixing stage. Have explained to [the Applicant] that
until valuer provides a higher valuation for on completion, his loan would need
to be reduced to $180,000 in total (using 95% lend).”
This shows that the Applicant was made aware that release of the S Road
property would be possible on the condition that his residual debt was
reduced. The Applicant’s subsequent misunderstanding may have arisen
from the FSP’s subsequent refusal to allow the S Road property to be sold
without an agreement about his residual debt.
17. Even if I was satisfied that, by failing to reinforce the basis upon which it
would not agree to the sale of the S Road property (that is, that it was
conditional upon an agreed strategy regarding his residual debt), the FSP
misled the Applicant, the Applicant’s claim for inte rest is not the appropriate
outcome, nor is its amount ascertainable.
18. As the case manager noted, the remedy for misleading conduct is to put the
Applicant into the position that he would have been in had he not been
misled, it is not to make the misleading representation come true. As the
Applicant never put the properties on the market in the period of time he may
have been misled, any difference in the market price is purely speculative.
Similarly, his claim for interest he paid is speculative as I could not ascertain:
when he would have sold the S Road property;
What price he would have obtained;
What his residual debt would therefore have been, upon which interest
would have been payable in any event.
I however agree with the case manager that the Applicant would have
experience stress in this period. I address the case manager’s award of
$1,500 for non-financial loss below.
Case No: 255104 Determination Page 6 of 7
Loan structure
19. I do not consider that the loan structure had any bearing on the FSP’s
conditions upon which it would agree to the Applicant selling one of his
properties. Whether the Applicant had one loan or the debt was split
between two loans representing his investment in each property, the FSP
would reasonably have required each property as security for all the
Applicant’s deb t. Therefore, it would reasonably only have released its
security over one property when it was satisfied that the Applicant’s residual
liability was adequately secured, or it made a commercial decision to assist
the Applicant in his financial difficulty in a way that its usual loan to security
ratio was exceeded.
Non-financial loss
20. The Applicant considers $1,500 is inadequate for the stress he has
experienced from his relationship with the FSP over the last five years.
21. As the case manager observed in his Recommendation, the maximum we
can award for non- financial loss under FOS’s Terms of Reference is $3,000.
We will only award compensation for non-financial loss if there has been an
unusual degree or extent of inconvenience. In doing so, we will have regard
to
the degree or extent of physical inconvenience suffered
the general time taken to resolve the dispute
the extent to which the FSP’s actions interfered with the
Applicant’s expectation of enjoyment or peace of mind.
If we do award compensation, it is unlikely to be substantial.
22. In my view, noting that
the period of time in which the Applicant may have been under an
erroneous belief that the FSP would not let him sell his properties was
at most just over one year (from November 2008 to December 2009
when the Applicant’s father dealt with the FSP on his behalf); and
our maximum compensation is more often awarded when an applicant
has experienced a substantial degree of stress and personal
inconvenience, such as being evicted from their home;
I consider that $1,500 is adequate.
FSP’s payment to the builder
23. The Applicant says that he had an agreement with his builder for the final
costs of construction and his builder should have claimed $4,024.25 in one
progress payment claim. He says the builder provided his invoice for
$5,102.25 in breach of their agreement and the FSP mistakenly paid this
Case No: 255104 Determination Page 7 of 7
amount to the builder without his authority. If he had been contacted he
would have disputed the builder’s claim.
24. The FSP’s inf ormation shows that the builder provided an invoice for
$5,102.25 and the FSP paid this amount. There is no information to show
that the FSP obtained the Applicant’s authority to pay this amount, or to incur
any liability to the FSP greater than the maximum amount available under
his loan. Neither has the FSP shown that the Applicant obtained any benefit
from the additional $1,078 being paid to the builder, as there is no
information showing the Applicant obtained any greater value from the
services rendered by the builder.
25. Therefore, on the information available, I consider that the FSP was not
authorised to pay an additional $1,078 to the builder and, as it has not
shown that the Applicant derived any benefit from the additional payment, it
should compensate the Applicant for the $1,078 overpayment.
Conclusion
26. I otherwise agree with the case manager’s reasons for the Recommendation
and the recommended outcome.
27. I have considered the Applicant’s further information, but it does not change
my view that the case manager’s Recommendation was correct.
Determination
28. I determine that:
a. The FSP should reduce the Applicant’s current debt by $2,578 being
the amount of compensation awarded for his financial and non-financial
loss.
b. If the Applicant and the FSP are not able to agree a mutually
acceptable repayment proposal for the Applicant’s debt within 14 days
of the Applicant’s acceptance of this Determination, the FSP is entitled
to take recovery action to collect its debt from the Applicant
Case No: 255104 Recommendation Page 1 of 19
Case number: 255104
Credit - Consumer Credit - Home Loans - FSP Decision – Failure to follow
instructions - Denial of claim
20 June 2013
Background
29. It is not disputed that:
on 21 December 2007, the Applicant purchased the O Street property
(the O Street property) with a loan from the FSP secured on the O
Street property (the O Street loan);
on 29 January 2008, he signed a building contract for the construction
of a house on the O Street property;
on 28 March 2008, the FSP approved an increase of $305,601 to the O
Street loan in order to fund the planned construction works;
on 6 April 2008, the Applicant purchased the S Road property (the S
Road property) and entered into a building contract for the construction
of a house. He sought a further loan from the FSP in order to fund the
purchase and development of the S Road property.
On 28 May 2008, the FSP approved the investment loan (the
investment loan) for $399,371 secured on the O Street and S Road
properties. The investment loan funds were used in part to refinance
the O Street property loan, with the remainder used to fund the
purchase and development of the S Road property.
30. This dispute arises from the way in which the Applicant’s investment loan
was structured. The Applicant claims that the FSP:
a. failed to make progress payments to his builder;
b. misled him as to the terms of the loan; and
c. prevented him from selling the properties described above.
Summary of Applicant’s p osition
31. On or around 30 June 2008, the Applicant informed the FSP that additional
foundation works would increase the construction costs of the O Street
property by $16,814.60.
Recommendation
Case No: 255104 Recommendation Page 2 of 19
32. On 1 September 2008:
the FSP made the first progress payment in respect of the O Street
property; and
wrote to the Applicant confirming that further progress payments would
be made during construction of the O Street property.
33. In February 2009, he wrote to the FSP seeking a deferment of his
investment loan repayments due to ill health, and sent it medical certificates
confirming his ill-health for the period from 1 November 2008 to 16 February
2009.
34. On 27 May 2009, he received a letter from lawyers acting for the builder of
the O Street property (the builder) stating that the property would not be
handed over until the final balance of $91,508.61 for the constructio n works
was paid. It gave him until 12 June 2009 to make payment, failing which the
builder would commence legal proceedings for this debt plus interest.
35. The FSP agreed to “forward all the funds needed” to the builder provided he
cleared the $3,847.57 arrears on the investment loan. On 10 June 2009, the
FSP paid the builder $79,200.61, a sum equal to the total of the un-paid
progress payments. The FSP refused to make payment of the remaining
$12,308.01 due to the builder.
36. On 14 September 2009, the Applicant provided the FSP with a letter of
authority authorising his father to negotiate with it and put forward a written
calculation of the repayments which could be made if it approved the sale of
both properties. On 17 October 2009 the FSP refused this offer a nd sent a
notice of arrears of $6,109.95.
37. On 20 November 2009, the builder lodged a caveat on the O Street property
for the $13,307.99 which remained owing to it for the construction of that
property. On 8 December 2009, the FSP paid $13,308 to the builder .
38. On 18 March 2010 he sold the S Road property and repaid $102,818.45 of
the investment loan using the sale proceeds. On 11 April 2010, the O Street
property was completed and advertised to rent.
39. On 24 April 2010, he wrote to the FSP to outline his complaint. It responded
by phone denying his claim. However, on 15 July 2011, he received the
FSP’s letter containing two options for compensation, the higher of which
was for a total of $14,418.08. He rejected this offer. On 22 August 2011, he
received a further compensation offer from the FSP of $19,418.08. The
offers do not adequately compensate him for his loss.
Summary of FSP’ s position
40. In July 2008, the Applicant advised it that he was no longer intending to build
at the S Road property and that it was listed for sale. It did not receive
confirmation that this sale was proceeding.
Case No: 255104 Recommendation Page 3 of 19
41. On 14 August 2008, it received a request for the first progress payment of
$19,796.80 in respect of the O Street property. On 20 and 21 August 2008, it
attempted, without success, to contact the Applicant, as he was required to
fund the first progress payment.
42. On 1 September 2008, it “...elected to pay the first progress payment to
ensure building progressed...”. Subsequently, it received a variation to
construction costs on the O Street property which increased the construction
costs to $115,744.00.
43. On 9 December 2008, it carried out a valuation of the O Street property in
the light of these increased construction costs, and on 15 December 2008, it
told the Applicant that he would have to pay the costs increase of
$12,308.61 before further progress payments were made.
17. On 9 February 2009, the Applicant contacted it to request a deferment of
repayments as he was unable to work due to an injury. It asked him to
complete a personal money plan and to supply a medical certificate.
18. On 21 March, it received the medical certificate, but this was dated 16
February 2009 and covered the period from November 2008 to 16 February
2009. It therefore requested an updated medical certificate from the
Applicant. He told it that he would not provide this as he would be re-starting
work. It requested confirmation of his employment, but he did not provide
this.
19. On 4 June 2009, it received a further payment request from the Applicant’s
builder for the sum of $91,508.61. It told the Applicant it would pay
$79,200.00 once the arrears had been cleared, and that he would have to
pay the balance of $12,308.61. The Applicant subsequently paid the $3,847
arrears on his investment loan.
44. On 10 June 2009, it released the progress payment of $79,200.00. On 21
June 2009, and on 12 August 2009, the Applicant informed it he intended to
sell one of his properties. It requested a copy of his agreement with a real
estate agent as proof that the property was listed for sale . The Applicant did
not provide this.
20. On 15 September 2009, the Applicant wrote to it proposing the sale of both
properties, and stating that he anticipated a profit from the sale of $7,000. He
did not provide it with the requested real estate agency agreement or proof
that the property was listed for sale. It has no records to show that it told him
it would not agree to a sale.
21. On 2 November 2009, the Applicant asked it to make a final payment to his
builder for the completion of the O Street property and advised that he no
longer intended to sell the O Road property but would be recommencing
employment in January 2010.
22. Because a further release of funds would mean the loan to value ratio would
exceed 100%, it required updated valuations and authorisation from its
Case No: 255104 Recommendation Page 4 of 19
mortgage insurer for release of payment. It therefore requested that the
Applicant send it:
the final progress payment figure;
confirmation of income and employment; and
a current medical certificate.
23. On 2 December 2009 its mortgage insurer agreed it could release the final
progress payment and fund for completion of the O Road property, as well
as capitalising the Applicant’s arrears and deferring his payments for three
months to allow him time to return to work.
24. However, this was on the condition that the Applicant provided a real estate
agency agreement for the sale of the S Road property by 15 January 2010.
The balance of the investment loan was to be secured by a continuing
mortgage on the O Street property. On 15 February 2010, the Applicant
informed it that he had sold the S Road property and that settlement was
planned for 12 March 2010.
25. The FSP does not accept that it caused the Applicant loss as:
the valuer’s report of November 2009 confirmed that the O Street
property was not completed and fit for lease;
there is no information to show that the FSP refused to permit the
Applicant to sell his properties; and
it provided substantial assistance in respect of the Applicant’s financial
difficulty by approving payments outside the terms of the bu ilder’s
contract, capitalising his arrears, and deferring his repayments.
45. It has therefore not made any error which has caused the Applicant loss and
is not liable to compensate him. His loss has been caused by the property
market dropping and the impact this had on the value of his properties.
26. It has withdrawn its offer of 15 July 2011 to resolve his dispute, but it is
willing to discuss options for bringing the Applicant’s loan account into order.
Issues
27. In the circumstances, was the FSP required to make progress payments to
the Applicant’s builder?
28. Did the FSP mislead the Applicant:
a. as to the terms of the loan?
b. it would make progress payments to his builder?; or
c. into believing that it would reduce his loan to take account of his
decision not to proceed with the development of S Road.
Case No: 255104 Recommendation Page 5 of 19
29. Did the FSP prevent the Applicant from selling one or more of his
properties?
30. Did the FSP respond appropriately to the Applicant as a customer
experiencing financial difficulty?
31. What loss has the Applicant suffered for which the FSP should compensate
him? And
32. What is an appropriate resolution of this dispute?
Reasons for Recommendation
How we assess disputes
46. When we assess disputes, we consider the available documents, the
recollections of the parties, and all relevant circumstances. Because of this, I
have given more weight to contemporaneous documentary information than
to unsupported recollections of events. Where there is no relevant
documentation, I have decided what is most likely to have occurred based
on the information provided to us. Where there are conflicting unsupported
recollections and these are evenly weighted, I have decided what is most
likely to have occurred in all the circumstances.
In the circumstances, was the FSP required to make progress payments to the
Applicant’s builder?
33. The Applic ant’ position is that, in breach of his loan agreement, the FSP
failed to make the required progress payments to his builder. The FSP’s
position is that the Applicant was required to make payment to his builder out
of the equity which he was placing in the property, prior to any release of
funds by it. I have therefore considered whether, under the terms and
conditions of the investment loan, the FSP was in fact required to make
these payments.
Analysis
34. I find that the FSP’s position is supported by the “notes for borrowers” it
provided to the Applicant. In particular, these state:
“...It is your responsibility to enter into a satisfactory building contract with your
builder. The contract should provide for progress payments to be made on the
basis set out below. The Bank will not become involved in any discussion
concerning a particular contract nor will it become involved in any disputes
between yourself and your builder...”
“...Prior to the release of any loan funds, your equity is to be fully utilised...”
“...Progress payments will be made on your written authority only. Please
inform the builder that all requests must be made though yourself and the
builder’s estimate of the value of the work completed and the stage reached is
Case No: 255104 Recommendation Page 6 of 19
to be included in your written authority. This should be forwarded to the bank
for release of funds to your builder...”
35. The “notes for builders” provided to the Applicant are also supportive of the
FSP’s position. These notes state:
“...Progress payments will be made on the owner’s w ritten authority only.
Please make all such requests through the owner with your estimate of the
value of the work completed and the stage of construction reached...”
“...Your written instructions as to how you would like progress payments to be
made (i.e. by cheque or payment direct to your bank account) are also
required. The owner will provide you with an authority form from the bank for
your instructions and signature. This form must be completed and handed to
the owner prior to release of funds...”
36. The terms of the loan contain further conditions applicable to the FSP’s
obligation to make progress payments to the builder. These terms are
contained in the provisions of the FSP’s usual terms and conditions for
consumer mortgage lending, and in the terms of the conditions for the
investment loan. I reproduce the relevant terms and conditions below:
“...We make the full amount of the Loan available to you by progressive Loan
drawings in accordance with progress of the Building Works...and as we see
fit...”
“...You must pay us the interest debited to the Loan Account...during any
period of progressive loan drawings...”
“...We will not fund the Loan if:
(a) you are in default under the Contract...
(b) you fail to satisfy our conditions for the provision of credit...
...
(d) we believe you may not be able to repay the Loan due to a change in your
financial position since the date you applied for the Loan... “
“...If the Loan is to be funded by progressive Loan drawings, you must also
satisfy our requirements for the funding of each Loan drawing...”
“...If we make the Loan available to you by progressive Loan drawings and
there is an interest only period...you must continue making your interest
payments until the end of the interest only period...”
“...Borrowers must have a r elated account from which the Bank is available to
draw both the monthly and final interest charges...They must ensure that
adequate funds are held in their nominated account on 15 th of each month
and on the day of final loan drawing to cover these payment s...”
“...The customer’s equity is the amount of money that [the customer] will
contribute to complete the transaction...The equity may be collected as
required when progress payments are authorised...All of the borrower’s funds
and funds from other source s must be used before the Bank’s loan funds...”
Case No: 255104 Recommendation Page 7 of 19
Conditions under which the FSP was obliged to make loan repayments
37. In summary, the information provided indicates that the FSP was required,
under the terms on which it advanced the investment loan, to make the
progress payments if the following conditions were met by the Applicant:
a. the Applicant first used his equity and non-loan funding to satisfy these
payments;
b. paid the interest accruing on the loan out of a designated account
which he kept in funds for this purpose;
c. made a written request for each progress payment at the time it was
required and in the form required by the FSP; and
d. continued to demonstrate to the FSP that he was able to service the
investment loan.
Did the Applicant meet the conditions for the FSP to make loan repayments?
38. On the information provided, I am satisfied that:
the FSP made the first progress payment of $19,786 on 1 September
2008. This was the only progress payment made while the investment
loan was within terms;
the Applicant made a subsequent request for the release of further
progress payments on 26 September 2008; however
I can find no sign of further repayments requests from the Applicant in
the required form;
there is no information to show that the Applicant, at this or any other
time, in fact applied his own funds to the development costs of his
properties in advance of seeking release of progress payments;
the investment loan fell into arrears in March 2009, and from this point
on, it does not appear that the Applicant’ s designated account
contained sufficient funds to make the interest payments on the
investment loan when they fell due.
39. From the information provided, it is not clear why or on what basis the FSP
made the first progress payments. In my view, it was not in fact required to
do so as the Applicant had failed to comply with the requirement to first use
his equity to fund the development costs he was incurring.
40. This was also the case when, on 26 September 2008, he made the only
formal payment request revealed b y the information provided. There is no
sign that the Applicant ever in fact applied the required equity to the
development as required by the terms of the investment loan. In the
circumstances, I am satisfied that the Applicant never complied with his
obligation to make payments out of his equity before seeking the release of
loan funds.
Case No: 255104 Recommendation Page 8 of 19
41. The subsequent progress payments toward development costs became due
(according the later demands of the Applicant’s builder) at a time after which
the loan had fallen into arrears. Irrespective of the other requirements
imposed by the terms of the investment loan, I am satisfied that from March
2009 onwards, the Applicant was in breach of the requirement to maintain
sufficient funds in a designated account from which the i nterest only
investment loan repayment could be made. He subsequently confirmed his
altered financial position to the FSP.
42. In the circumstances, the FSP would have been entitled (under the relevant
terms and conditions) to reach the conclusion that it did not have to make
progress payments while the Applicant’s financial position had deteriorated
to this extent compared his position when he applied for the loan.
Conclusion
43. On the basis of the information provided, I am satisfied that:
the Applicant never in fact met all of the conditions which he was
required to fulfil for the FSP to be required to make progress payments;
the FSP was therefore not required, under the terms of the investment
loan, to make any progress payments to the Applicant’s builder; and
The FSP is not liable to the Applicant for any loss he suffered due to his
inability to pay his builder when the progress payments became due.
Did the FSP mislead the Applicant?
What is misleading conduct?
44. Our approach to misleading conduct is based on the Australian Securities
and Investment Commission Act (Commonwealth) 2001 (the ASIC Act).
Section 12DA of the ASIC Act states:
“A person must not, in trade or commerce , engage in conduct in relation to
financial services that is misleading or deceptive or is likely to mislead or
deceive.”
45. Section 12DA is not dependent on proof of knowledge, fault, and intention to
mislead or benefit accruing to the person engaging in the misleading
conduct. This means that it is not necessary for the Applicant to show that
the FSP was negligent or blameworthy; he is required only to show that the
information he was given was “misleading” and may recover damages if he
placed reasonable reliance on that information and suffered loss as a result.
46. The first issue we must determine is whether the conduct of the FSP was in
fact misleading. This requires an assessment of the facts as presented by
each of the parties to this dispute. If we find that the FSP provided
misleading advice, or engaged in misleading conduct, the Applicant must
establish that she relied on the misleading advice or conduct to his
detriment, and that it was reasonable for him to do so .
Case No: 255104 Recommendation Page 9 of 19
Did the FSP mislead the Applicant as to the terms of the loan?
47. The Applicant has not disputed that he signed the loan contract and the loan
terms and conditions were provide to him. He has also confirmed that he
read these documents. However, he claims that that although he believed
that he could afford the investment loan at the time at which he applied for it,
the FSP’s failure to clarify the terms of the investment loan amounts to
“maladministration”.
Analysis
48. Our approach is that if a person signs a document that they know contains
contractual terms and which they understand will affect their legal
relationship with their financial services provider, then the person is legally
bound by those terms. It is irrelevant whether or not the person read the
document before signing it.
49. The only exception to this is if there are extenuating circumstances, for
example if the person was misled into signing the document. I have
therefore considered whether, in the circumstances, the FSP misled the
Applicant into signing the investment loan contract so that he was bound by
its terms.
50. However, the Applicant has not provided any information to show that the
FSP misled him as to the terms of the loan, or their meaning. There is no
information to indicate that the Applicant was not capable of understanding
the written loan terms, or under a disadvantage which would prevent him
from doing so when these were provided to him.
51. In the circumstances, the FSP did not have a special duty to explain the
investment loan terms other than providing these to the Applicant. There is
no indication that it failed to do this, or that the Applicant was given
insufficient time to read and consider these documents when he obtained the
loan.
Conclusion
52. On the basis of the information provided, I am satisfied that the FSP did not
mislead the Applicant as to the terms of the loan, and did not mislead him
into signing the investment loan contract.
Did the FSP mislead the Applicant into believing that it would make progress
payments to his builder while he maintained repayments on the investment
loan?
53. I have considered the facts as presented by each of the parties to this
dispute in order to determine whether the conduct of the FSP or any
statements made by it were misleading in regard to this issue, and if so,
whether it was reasonable for the Applicant to act in reliance on the mistaken
belief to which the misleading statements/conduct may have led.
Case No: 255104 Recommendation Page 10 of 19
Positions of the parties
The Applicant
54. The Applicant has said:
“I believe that the FSP was required to make progress payments to my builder
as per our construction loan agreement while my payments were up to date. I
believe [the] FSP was in breach of our agreement by not doing so. I’m not
sure how the payments made to the builder would be reflected on my bank
statements so I was unaware that the builder was not being paid...
“I don’t [accept] that the bank made a proper effort to contact me regarding
the first progress payment that they believe I needed to make....why did the
bank make the first progress payment if the bank really though it was my
obligation to pay that?...”
The FSP
55. The FSP denies that it breached the investment loan agreement, and
maintains that it attempted to contact the Applicant to make clear that he had
to make the first payment(s) to his builder out of his equity. It has also stated
that when this did not occur, it made payments in order to enable
construction to progress.
56. In support of its position, it has provided copies of the loan documents, notes
of its contact with the Applicant, and internal communications between its
officers which relate to the App licant’s investment loan.
Analysis
57. As I have concluded above, under the terms of the investment loan, the FSP
was not required to make any progress payments to the builder because the
Applicant was in breach of the conditions under which progress payments
were payable by the FSP. On the basis of the information provided, I am
also satisfied that the FSP made no statement to the Applicant that (in the
circumstances of his lack of equity contribution and his subsequent financial
difficulty) these payments would be made regardless of these conditions.
58. I have therefore considered whether, given the above, the FSP’s conduct led
the Applicant into the mistaken belief that it would make the progress
payments as they were requested. On the information provided, and given
the statements made by the Applicant, I satisfied that the only basis on
which the Applicant could form this view was the FSP’s decision to make the
first progress payment.
59. The FSP claims that this payment was made in order to enable the project to
move forward, and was not an indication that further payments would be
made without the relevant conditions being fulfilled.
60. However, a review of the FSP’s internal communications relating to this
payment reveals considerable confusion as to the Applicant’ s intentions and
his contribution to development costs at the time the first payment was
Case No: 255104 Recommendation Page 11 of 19
made. I have reproduced the relevant aspects of these email conversations
below. These email conversations take place between FSP officers, Ms F,
Ms B, and the FSP’s m ortgage services department. They are, in my view,
determinative of this issue.
14 August 2008
From mortgage services department to Ms S
“...I am trying to set up the above loan because we have a payment request...I
am...unable to find [a] proper contract for either property (there appears to be
two constructions [the O Street property and the S Road property])...I do not
seem to have complete paperwork for either property...We have received...a
signed payment request...Are you holding any paperwork for this file, because
image does not seem to have what I need. I cannot work out what the
contract amounts etc are supposed to be and if variations, quotes etc. Please
[advise] because we need to make this payment.
Ms S to mortgage services department
“...I will contact the builder to fax me the contract as soon as I can
today...Going by what the client has told me the [S Road property] is no
longer being built and he is selling the land...I haven’t received any discharge
instructions as such...”
1 September 2008
From Ms F to Ms S
“...we are ready to make the first progress payment. It appears that this file
was originally approved as the construction of 2 properties and rental income
for 2 properties was included. Would you please confirm by email that [the O
Street property] is now the only property being constructed with funds from
this loan?”
3 September 2008
From Ms S to Ms F
“...I have [left] two messages for the client to call me and he hasn’t. The last
time I spoke to him he told me that only 1 building was going to happen and
that he was selling the other block. Has the builder contacted you in regards
to this payment?”
From Ms F to Ms S
“...We made the first payment to the builder on [the O Street property] on
Monday but need you to confirm that the surplus funds are not required for the
construction of another property and can be released to customer when either
building is finished or you authorise us to. We would assume your branch has
reassessed and reapproved the loan for only 1 construction property?..."
From Ms S to Ms F
“...The application has not been changed yet as client has not formally
confirmed the sale of the property. The second time I contacted him I told him
that he had to pay for the invoice out of his own funds and he did not return
my call...
From Ms F to Ms S
“...Ok, so maybe we don’t make any more payments until you confirm what is
happening with the builder and the loan...”
Case No: 255104 Recommendation Page 12 of 19
17 October 2008
From mortgage services department to Ms S
“...We have received a progress payment [request] for w all and roof frames
for $24,733.50 signed by client to make payment. There is an email on file by
Ms F requesting we don’t make any more payments until you confirm with the
builder what is happening. Please advise whether you want payments to go
ahead...”
From Ms S to mortgage services department
“...Don’t pay at this stage, I will attempt to contact client once again!!! He
needs to pay with his own equity first...”
21 October 2008
From Ms S to mortgage services department
“...still trying to contact client . Can you please advise the amount required to
be paid by client, is the second building...proceeding...”
61. On the information provided, I am unable to accept that the FSP made the
first progress payment with the intention of allowing the Applicant’s
development project to progress. Rather, the information supports a
conclusion that this payment was made outside the terms of the investment
loan, maybe to assist in progressing construction, and in the absence of the
full facts as to whether the Applicant had contributed the required equity, or
in fact was going ahead with the construction project for which, in part, he
obtained the investment loan. This view is further supported by a post-it note
attached to the email correspondence which reads “Do not make any further
payments until instructed by lender.”.
62. However, I am also unable to accept that this payment was sufficient, of
itself, to mislead the Applicant into believing that all subsequent payments
would be or were being made. This payment is clearly shown on the loan
statements provided to the Applicant, and the Applicant has not been able to
give any persuasive reason that these statements would not disclose to him
which payments had or had not been made going forward.
63. It is also clear from the above that the FSP made repeated attempts to
contact the Applicant to alert him to the need to use his own equity (as was
made clear in the loan conditions which he has confirmed that he read)
before further progress payments could be made. There is no indication t hat
the Applicant provided the FSP with the information sought. There is also no
indication that, at the time the relevant repayments requests were made, the
Applicant in fact contributed the required equity to the constructions costs.
64. Even if he did not r eceive the multiple messages described in the FSP’s
contemporaneous emails, it is reasonable to conclude that, lacking a
confirmation that progress payments were being made when requested, and
without any sign of these payments on the loan statements, the Applicant
should have made enquiry as to the correct position, either from the FSP or
from the builder. He did not do so, and says he assumed that progress
Case No: 255104 Recommendation Page 13 of 19
payments were being made. In my view, this was not a reasonable
assumption in the circumstances.
Conclusion
65. On the information provided, the Applicant has not established that the
FSP’s statements or conduct was enough to mislead him into assuming that
future progress payments would be made. Even if the FSP had engaged in
such conduct, in the circumstances, it was not reasonable for the Applicant
to rely on this assumption. Given the above, the Applicant has not
established that he was misled.
Did the FSP mislead the Applicant into believing that it would reduce his loan
to take account of his decision not to proceed with construction of the second
property?
Analysis
66. The Applicant states:
“...Even though I was not proceeding with the building work at [the S Road
property] and had advised the bank of this...the loan amount was never re-
adjusted to remove any building funding costs...”
67. The FSP does not dispute that the loan amount was not reduced in this way.
68. In my view, the email conversations reproduced above are also
determinative of this issue. It appears from these that despite repeated
efforts, the FSP was never able to obtain, from the Applicant or his builder,
definitive information as to his construction plans and how these altered after
the loan was granted. This led to administrative confusion which the FSP
failed to manage well.
69. However, this does not mean that the FSP misled the Applicant. I can find no
indication that:
a. the FSP confirmed to him that his loan was adjusted in the light of
these altered plans;
b. that the FSP instructed him that it would adjust the loan in the absence
of the information required from him;
c. that he in fact submitted the relevant information to enable the
recalculation of his loan and security requirements; or
d. that the Applicant sought to obtain the FSP’s confirmation of this
adjustment at the time.
70. In the circumstances, there was no basis (either in the form of an express
statement, or course of conduct by the FSP) on which the Applicant could
reasonably conclude that the investment loan had been, or would be
adjusted.
Case No: 255104 Recommendation Page 14 of 19
Conclusion
71. On the basis of the information provided, the Applicant has not established
that the FSP misled him into believing that it would reduce his loan to take
account of his decision not to proceed with construction of the second
property.
Did the FSP prevent the Applicant from selling one or more of his properties or
mislead him into believing that it would do so?
72. The Applicant has stated that after he began to experience financial
difficulty, he proposed the individual sale of his properties so that the sale
proceeds could be used to reduce his debt. He claims the FSP informed him
that he would not be able to carry out this plan because the investment loan
was secured over both of them. In support of his position, he had supplied a
copy of the letter dated 14 September 2009 in which there is a note which
says:
“...I have spoken to [FSP officer at branch] but her requirement of only 80% of
valuation left on land means that this would not work...”
73. The FSP denies that he was told this and says it can find no record of such a
statement being made. It points out that despite its requests; no information
was received to indicate that the property was on the market, or that a sale
and purchase contract had been signed. It adds that:
The staff member who took the Applicant’s call of 21 September 2009
requesting the individual sale of his properties did not have authority to
approve or decline this request;
It is likely that she would have informed him that under normal
circumstances, the FSP would need to consider residual security
against the debt remaining after any such sale in order to approve or
reject the sale; and
it is also possible that the staff member would have stated that the FSP
would not consider this proposal without a purchase offer which it could
consider and either reject or accept.
Analysis
74. The FSP has not been able to provide any contemporaneous information to
support its position. However, it is clear from the internal email conversations
already reproduced above that the FSP was aware of the Applicants plan to
sell at least one property in isolation at least one year before the
conversation and letter above. There is no indication that it raised any
objection to this proposal in this earlier period. There is also no indication
that the FSP took any steps or issued any communication to prevent the
Applicant from putting the properties on the market on the basis he
described in his letter of 14 September 2009.
Case No: 255104 Recommendation Page 15 of 19
75. In the absence of contemporaneous written information and in the face of the
conflicting recollections of the parties in regard to this issue, I must follow our
approach and decide what is most likely to have happened on the facts.
76. In my view, it is most likely that the Applicant was told that his plan would not
leave sufficient security for the remaining debt in order to be acceptable to
the FSP. This is not the same as being prevented from selling the property;
as the FSP points out, it would not able to decide whether to accept a sale or
not unless a sale contract had been provided indicating a sale price.
77. However, I am satisfied that th e Applicant’s understanding of the FSP’s
position was that he would not be permitted to sell his properties separately.
Whether or not this understanding was correct, it was one which the FSP did
nothing to correct until it authorised the separate sale of the property some 3
months later. I am satisfied that the effect of the FSP’s conduct in this regard
was to mislead the Applicant.
Conclusion
78. On the basis of the information provided, the Applicant has not established
that the FSP prevented him from selling his one or more of his properties.
However, I am satisfied that its statements misled him into believing it was
doing so, and in the circumstances, it was reasonable for him to rely on this
mistaken belief.
79. As set out above, where we find that there is misleading conduct, our
approach is not to make the mistaken belief come true, but to put the
Applicant in the position he would have been had he not been misled. I
consider below (after my analysis of the remaining issues in this dispute)
whether, as a result of being misled, the Applicant has suffered loss for
which the FSP should compensate him.
Did the FSP respond appropriately to the Applicant as a customer
experiencing financial difficulty?
80. The Applicant has said:
“...Even though [the FSP] assisted in changing payments the proper help
would have been to let me dispose of the [second property] when I needed to
and to pay the builder so that there was no delay in me finishing and renting
out [the O Street property].”
81. I understand from the above, that the Applicant does not dispute that the
FSP provided him with assistance with his financial difficulty, but challenges
whether this assistance was appropriate.
Our approach to financial difficulty
82.
A financial services provider is not obliged to provide assistance to a
customer (applicant) in financial difficulty. However, it has an obligation to
Case No: 255104 Recommendation Page 16 of 19
consider a request to provide such assistance. FOS is able to review a
financial services provider’s decision about whether to agree to a customer’s
request for a variation to a credit contract.
83. I have therefore considered below the extent to which the FSP met its
obligations to the Applicant as a customer experiencing financial difficulty. In
doing so, I have taken into account the Applicant’s financial circumstances,
ability to meet a variation to the credit contract, and the extent to which the
FSP and the Applicant each met the expectations set out below.
Our Expectations of the financial services provider
84. We consider that:
the financial services provider should give genuine consideration to any
repayment proposal and any reasonable alternatives that will help its
customer overcome their financial difficulty
if the financial services provider rejects a proposal made by its
customer, it should give reasons and ensure that those reasons reflect
legitimate considerations that relate to the customer’s specific
circumstances
a financial services provider that subscribes to the Code of Banking
Practice (COBP) should also inform their customer if the hardship
variation provisions of the National Credit Code (NCC) could apply to
them
financial services providers should comply with the ASIC/ACCC Debt
Collection Guidelines
in their dealings with their customer, clause 2.2 of the COBP requires a
subscribing financial services provider to act fairly and reasonably in a
consistent and ethical manner, taking into account the conduct of the
parties and the contract.
Our expectations of the customer (Applicant)
85. Under the COBP, the aim is to assist the customer to overcome their
financial difficulty. Under the NCC, the customer must reasonably expect to
be able to repay the debt if the terms of the contract are changed. Therefore,
we expect the customer to:
be willing to work with their financial services provider – for example, by
responding promptly to reasonable requests for information
provide current and accurate details of their financial position when
requested
propose a realistic repayment plan that will result in the eventual
repayment of the debt
Case No: 255104 Recommendation Page 17 of 19
make whatever payments they can while the financial services provider
is considering their application and/or while FOS is considering any
subsequent dispute.
86. However, it should also be noted that:
a. the FSP was not obliged to provide the Applicant with ongoing financial
assistance; and
b. the FSP was not under a general duty or responsibility to advise the
Applicant that a service or product was not in her interests or that there
may be other services that would better suit her needs; and
c. the FSP is entitled to continue to charge interest on a loan product
during a period of assistance.
87. In reaching my conclusions on this issue, I take account of:
the financial information provided by the Applicant to the FSP and to
FOS;
additional medical information provided by the Applicant to the FSP;
the contact notes provided by the FSP in regard to its conversations
and correspondence with the Applicant; and
copies of the financial difficulty responses which it sent to the Applicant.
Analysis
88. As I conclude above, the FSP did not in fact prevent the Applicant from
selling the second property. I have also concluded that, in the
circumstances, it was not obliged by the terms of the investment loan to
make further progress payments. It is also the case that its financial difficulty
obligations to the applicant did not require it to make such payments.
89. On the basis of the information provided, I am satisfied that:
the contact notes between the FSP and the Applicant indicate that it
sought specific information as to his health, current and projected
financial circumstances in order to consider his request for assistance
with financial ;
the FSP often had difficulty obtaining a response from the Applicant or
timely provision of the requested information;
the FSP wa s entitled to conclude that the Applicant’s financial difficulty
was long term;
nevertheless, the FSP provided amended repayments terms and
obtained authorisation for the release of funds to enable progress
payments to be made.
90. The information provided by the Applicant supports the view that his financial
difficulty was long term, and the only realistic prospect for over -coming this
was completion of the properties to sale or rental standard.
Case No: 255104 Recommendation Page 18 of 19
Conclusion
91. In the circumstances, I am satisfied that:
the FSP di d give genuine consideration to the Applicant’s request for
assistance with financial difficulty in relation to his investment loan, and
pursuant to this, provided a longer period of financial assistance than
its obligations under the COBP and applicable legislation required;
in the circumstances, it did not have an obligation to permit the
separate sale of the security properties to the detriment of its security
obligations, nor to release further funds, as the Applicant has
suggested, to fund development and completion of the properties.
92. On the information provided, I find that the FSP did meet its obligations to
the Applicant as a customer experiencing financial difficulty.
What loss has the Applicant suffered for which the FSP should compensate
him?
93. The Applicant has claimed compensation for the following losses:
waiver of all interest which has accrued since the start of this dispute;
a payment $19,525 representing profit had he been permitted to sell
the O Street property when it was completed compared to its likely
current sale price;
$3,000 for the stress and inconvenience which this dispute has caused;
and
retention of all rental income received to date.
Analysis
94. An applicant’s contractual obligations to repay their loan facilities remain on
foot whilst we are considering the dispute, and a financial services provider
is entitled to charge interest and fees on the sums outstanding. In the
circumstances, there is no basis for the waiver of interest requested by the
Applicant. Similarly, there is no basis for me to recommend that the FSP
refunds rental income which the Applicant has used to service his loan
repayments.
95. I have concluded that the FSP misled the Applicant into believing that he
was not permitted to sell his properties when he sought do so. However, as
we outlined above, the remedy for misleading conduct is to put the Applicant
into the position that he would have been in had he not been misled, it is not
to make the misleading representation come true. This means:
As the properties were never put on the market, the lost profit figure set
out by the Applicant is purely speculative;
Case No: 255104 Recommendation Page 19 of 19
there is no guarantee of the time they would have taken to sell (and
during which the Applicant would have remained liable to pay interest
on the investment loan; and therefore
the Applicant has not established that he suffered direct financial loss.
96. However, I am satisfied that the Applicant has suffered non-financial loss in
the form of stress and inconvenience as a result of the FSP’s conduct in this
regard.
97. Our terms of reference allow us to make an award of up to $3000 for non-
financial loss. We will only make an award if there has been an unusual
degree or extent of inconvenience. We will not award compensation for loss
that an Applicant may incur as a result of pursuing a dispute or rectifying an
FSP’s error. If we do award compensation, it is unlikely to be substantial.
98. In the circumstances, an award of $1,500 is appropriate compensation for
the stress inconvenience suffered by the Applicant for the FSP’s mi sleading
conduct.
Recommendation
47. On the basis of the available information I recommend that:
The FSP pay the Applicant compensation of $1,500 for his non-
financial loss by way of reducing his current debt;
It the Applicant and the FSP are not able to agree a mutually
acceptable repayment proposal in respect of this debt within 14 days of
the date of this recommendation, the FSP is entitled to collect its debt
from the Applicant.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.