Partial refusal of water leak claim for living room flooring under faulty workmanship exclusion
Text of the determination
Case No: 255057 Determination Page 1 of 9
Case number: 255057
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
22 May 2012
Background
1. The Financial Services Provider (FSP) is a not-for-profit organisation that is
member owned and specifically formed to address the needs of its
members. It is a discretionary mutual and all of its members are in the
automotive industry. It has been created to use the collective strength of its
members to spread their cost of risk.
2. Pursuant to this purpose, the FSP offers a choice of protection for a
member’s personal and business risks. The terms and conditions of this
cover are contained in a Product Disclosure Statement (PDS). Although the
protection cover is similar to that of an insurance contact, the significant
distinguishing feature is that claims are granted at the absolute discre tion of
the FSP’s Board of Directors. Accordingly, this type of product is described
as a discretionary risk product.
3. The Applicants arranged protection for their business and personal assets,
the latter which included a residential property. This cover was operable
when the Applicants lodged a claim for damage to the flooring in their
residential property caused by leakage.
4. The FSP has accepted a portion of the damage and denied cover for the
rest. In essence, the areas of damage being denied are the flooring in the
living room and other parts of the home attributable to the leak from the
ensuite in the main bedroom (ensuite one). The Applicants have disputed
the FSP’s decision.
5. Both the Applicant and the FSP have provided detailed and lengthy
submissions on the relevant issues. For the sake of brevity, I will only briefly
summarise these submissions given all of the material made available to me
has been exchanged with the other party.
Determination
Case No: 255057 Determination Page 2 of 9
Summary of Applicants ’ position
6. In relation to the damage around ensuite one, the Applicants submit the
following:
The cause of the water damage, as identified by GB (a plumber), was
the silicone failing due to shrinkage or movement.
An earthquake occurred on 16 April 2010 and this is a likely cause for
the silicone failing.
Accordingly the FSP should, at the least, consider a 50% payout for the
damages attributable to this.
7. With respect to the living area, the Applicants submit the following:
The failed breech in the ensuite of the second bedroom (ensuite two)
caused extensive and irreparable damage to the floorboards, which
included the living area.
This has essentially been corroborated in various ways by most of the
experts.
There was no issue with the flooring until the leak had been identified.
8. Accordingly, the Applicants maintain the FSP should cover the damage
around ensuite one and the living area.
Summary of FSP’s position
9. The FSP has relied upon all of the expert evidence and the following
provisions in its product disclosure statement to substantiate its position that
it exercised its discretion appropriately in offering $15,314.50 to settle the
Applicant s’ claim :
“ What is not protected?
We will not pay under this section 1 for:
1. Certain loss or damage
Loss or damage caused directly or indirectly by:
…
(c) evaporation, shrinkage, loss of weight, dampness, dryness, rust,
corrosion or a gradually operating cause;
(d) faulty design, plan, specification, materials, workmanship or built-in
faults;”
Issues
10. Whether the FSP has exercised its discretion appropriately regarding the
Applicant s’ claim.
Case No: 255057 Determination Page 3 of 9
Reasons for decision
11. Due to the nature of the dispute, FOS has considered it appropriate to
expedite the dispute in accordance with clause 8.6 of the FOS Terms of
Reference. This is due to the circumstances and complexity of the dispute.
This dispute has not been the subject of a FOS Recommendation and has
proceeded directly to Determination.
12. I am satisfied that a full exchange of information has taken place between
each party and that each party has had the opportunity to address any
issues raised.
Ensuite One
13. The plumber engaged to identify and repair the leaks from this part of the
home (GB) provided an email dated 15 September 2011 that stated the
following:
“The damage to the main bed room ensuite was caused by water running
down the tiles in the shower when is use then thru into the wall frame via the
tap spindle penetrations not from the shower breech piece as in the front
ensuite.”
14. Upon the Applicants seeking further clarification regarding this, GB
responded in an email dated 23 September 2011 stating:
“Yes there was silicone around the ensuite taps but it was not sealing either
thru shrinkage or movement.”
15. The Applicant s note that this contradicts the FSP’s comment that there was
no silicone around the taps. Further, they have theorised that this shrinkage
or movement could have been due to an earthquake that occurred on 16
April 2011.
16. In relation to the latter argument, I am persuaded by the FSP’s rebuttal,
namely that is not probable that the damage caused by a quake would be
isolated to this silicone. Instead, if I accept GB’s finding that the damage was
due to shrinkage, this falls within a specific exclusion under the protection
cover that was highlighted in the “Summary of FSP’s Position” .
17. Given this, I am satisfied that the FSP has appropriately exercised its
discretion in denying cover for all of the damage attributable to this leak.
Living Room
18. The parties do not dispute that there was a leak identified in the area
commonly referred to as ensuite two. Further, neither party disputes that the
damage which was substantively caused by this leak would be covered
under the protection cover.
19. In addition to this, both parties agree that no other leak (excluding ensuite
one) has been identified. This was corroborated by a report provided by
Case No: 255057 Determination Page 4 of 9
another plumber (JH) dated 6 July 2011 after he tested the plumbing at the
property.
20. Following this position, the FSP has attempted to settle the claim based on
the damage it considers is substantively attributable to this leak. This
includes damage sustained to the flooring of the games room (or the dining
room as referred to by some of the experts).
21. However, the FSP has relied on two experts (PH and RL) in substantiating
its decision not to pay for the repairs to the living room flooring. The
Applicants have contested this on a number of bases, including relying on a
report provided by a builder they commissioned (CMT).
22. The damage to the living room flooring has formed the substance of the
parties’ dispute.
Expert Evidence
23. PH provided an initial report dated 26 July 2011 that contained the following
conclusions:
Both the timber flooring installation and the process of adhering the
timber to the slab were inadequate and a “disaster waiting to happen” .
The extent of travel of the water seepage from the plumbing leaks
cannot be determined. The early indication of slab wetness from a slow
water leak is the cupping of the timber that will occur when the base
level moisture is higher than that of the surface. This was not reported
nor is evident. If the bond of the timber to the slab is very low then
cupping may not occur but delamination or bond failure with associated
tenting might.
The dry slab in the dining room indicates that the water may not have
travelled the full distance across the room. However, due to an
apparent very low bond strength from the poor floor installation, a slight
increase in dampness could expand the poorly installed floor causing
delamination and bond failure.
The 11 metre span with no installed expansion gap is the likely cause
of the tenting in the living room. If an expansion gap had been installed
and correct MVB (Moisture Vapour Barrier) and adequate adhesive
used, the tenting failure in the living room would not have occurred
despite the slow leak.
The water leaks are the probable trigger for the tenting in the living
room.
If the installation was conducted to best industry practice, the slow
water leaks may have caused floorboard cupping but not major
delamination or tenting issues. This would not have necessitated board
removal.
Case No: 255057 Determination Page 5 of 9
24. PH provided an email dated 15 September 2011 that added the following to
the above:
He cannot determine if incorrect glue was used. However, the
application was in contravention of the glue manufacturer’s instructions
and the quantity used was totally insufficient.
Polyurethane had been used instead of epoxy to seal the slab for
moisture. No adhesive manufacturer would condone this.
The poor installation was reflected by the fact he could lift the timber
without the use of a crowbar.
Since the end of the drought, incidents of tenting failures have
significantly increased.
25. The Applicants provided a report by CMT dated 4 November 2011 that
contained the following conclusions:
The damage to the flooring in all areas is not attributed to faulty
workmanship as the installation was in accordance with industry
standards.
The flooring boards were installed with expansion gaps at all skirting
boards and along the underside of the door frame, which exits to the
outside pergola area.
The zone of influence from the moisture has been proven and includes
the living room.
26. The FSP also engaged RL to investigate the extent and source of damage to
the timber floor. This report was dated 26 September 2011 and contained
the following relevant comments:
The flooring has been coated with a solvent-based polyurethane
treatment which does not readily permit moisture in the flooring to
evaporate. As a result, the moisture is contained within the flooring and
tends to cause cupping.
In the lounge area, there is evidence of moisture damage and cupping
to the timber floor. This has led to expansion of the timber and tenting.
The flooring within the walk-in robe, dining area and living area are all
related to the failure of the breaching piece found in ensuite two.
An increase in moisture in both the eastern wall and the south-eastern
bedroom (where ensuite two is located) was attributed to “Slab Edge
Dampness”.
27. Both PH and RL provided additional comments regarding CMT’s repor t. PH
in particular disputed CMT’s finding that the timber flooring was installed
appropriately. RL’s comments did not add much to the report dated 26
September 2011.
Case No: 255057 Determination Page 6 of 9
Analysis
28. I am not inclined to accept CMT’s findings that the flooring was installed
pursu ant to appropriate standards. PH’s comments in this regard are more
persuasive and detailed and he has corroborated his position by making
specific reference to the Australian Standards.
29. Further, CMT ’s report did no t substantively rebut PH’s comments about the
insufficient application of the glue and the use of polyurethane rather than
epoxy. Instead, CMT’s comments on these salient points are more general.
30. A s such, I am more inclined to accept PH’s comments that these two issues
corroborate that the flooring in the lounge room was incorrectly installed,
particularly as these two issues were also corroborated by RL in his report
dated 26 September 2011.
31. Despite this, I note much of the expert evidence does corroborate that the
leakage from ensuite two has, at the least, contributed to the damage in the
living room. RL particularly made the following comment in this regard in his
report dated 26 September 2011:
“In the lounge area of the western side of this particular bathroom, there is
evidence of moisture damage and cupping to the timber floor beneath the
original location of the lounge itself. This, in the writer’s opinion, has led to the
expansion of the timber and resulted in tenting adjacent to the television
cabinet on the north-western corner of this room adjacent to the indoor pool
room.”
32. Although RL provided comments regarding “Slab Edge Dampness”, these
were mainly focused on the eastern perimeter of the home. The living area is
more central and the tenting is almost midway between the eastern and
western boundaries of the home. Accordingly, it is unclear whether RL was
attributing the tenting and other damage to the living room floor to this
concept.
33. PH’s comments , despite being substantively focused on the inadequate
installation methods, did accept that the water leak played a contributing part
as evident in the following conclusions of his initial report:
“While damage to this floor is evident, it is not possible to apportion the
relative contribution of the damage to the flooring between the slow leaks in
the premises wet areas and the obvious inadequacy of the flooring
installation.
The water leaks are the probable trigger for the extensive failure in the dining
room, the tenting in the living room and the delamination and tenting in the
master bedroom.
… If the installation was conducted to best industry practice then the slow
water leaks may have caused floorboard cupping but not major delamination
or tenting issues. This would then have not necessitated any board removal
rather just sanding flat and recoating after the slab and timber had dried out.”
34. CMT’s report corroborated this as he ascertained that the moisture readings
were higher than expected in the living room.
Case No: 255057 Determination Page 7 of 9
35. Further, as the Applicants have highlighted, these issues to the flooring only
became evident when the leak occurred. Prior to that, the flooring had
maintained its integrity and as PH acknowledged, the leak was the trigger for
the damage now evident.
36. As such, I am persuaded that the leak in ensuite two has , at the least,
contributed to the damage caused. As a result, I am not satisfied by the
FSP’s position that all of the damage to the living room can be attributed to
poor and/or faulty installation.
FSP’s Decision
37. As indicated previously, the Applicants ’ protection plan is not an insurance
contract. Claims are not automatically payable but instead are subject to the
FSP’s discretion, which is ultimately vested in its Board of Directors.
38. In exercising this discretion, the FSP has provided the following conditions
as to how a member would expect this to be applied for claims:
“The Board’s discretion to refuse or reduce a claim will only be exercised in
circumstances where the Board believes that the members of [FSP] would
expect it to do so. The Board also has the power to pay claims that are
specifically excluded under the protections.
The exercise of the Board’s discretion will be based on, amongst other things,
the summary of what protection is given and what is not given, as set out in
the Business and Per sonal Protections section of this PDS.”
39. In this regard, the FSP has exercised its discretion to refuse the Applicant s’
claim regarding the damage to the living room on the basis that the damage
was directly or indirectly due to faulty workmanship.
40. To an extent, I am satisfied that the FSP has established this on the
evidence. That is, it is clear faulty workmanship has indirectly led to some of
the damage to the living room.
41. However, I also note that the water leak itself was sufficient to cause
damage alone. This was acknowledged by PH who, out of the three experts,
was the most conservative in attributing the damage to the leak. This was
evident by his remark in his report dated 26 July 2011:
“If the installation was conducted to best industry practice the n the slow water
leaks may have caused floorboard cupping but not major delamination or
tenting issues. This would then have not necessitated any board removal
rather just sanding flat and recoating after the slab and timber had dried out.”
42. Further, RL provided greater support to the damage being attributable to the
leak and was supported by CMT.
43. In my opinion, based on a review of the evidence and applying my discretion
under clause 8.2 of the Terms of Reference to do what is fair in all the
circumstances, I consider a 50/50 apportionment between the water leak
Case No: 255057 Determination Page 8 of 9
and the faulty installation would be appropriate for the damage to the living
room flooring.
FSP’s Offer
44. The FSP’s offer, which was contained in its letter dated 3 October 2011, is
broken down as follows:
Repairs to ensuite 2 $4,059.00
15% of flooring (per U quote) $11,005.50
Allowance for furniture removal $250.00
Total $15,314.50
45. U’s total quote was for the total removal and replacement of all the timber
flooring in the house. This floor space equated to 290 square metres. It
appears this quote was provided on the basis the specie of timber used
previously is no longer available and it was not economical to replace
sections of the damaged floor with the nearest equivalent.
46. I note the protection terms and conditions contain the following provisions
regarding the cover:
“ What is protected?
You have the right to have a claim considered for loss or damage to home
buildings at the premises caused by an event during the period of
protection .
If your claim is successful
…
We will repair the home building or pay the costs of repairing the home
building to a condition substantially the same as but not better or more
extensive than new.”
47. The Applicants believe that this provision entitles them to the total cost of
replacing all of the flooring. However, I would disagree.
48. As set out previously, it is expected from the FSP’s members that the FSP
would exercise its discretion to refuse a claim in circumstances where
members would expect it to.
49. Having reviewed the terms and conditions of the protection cover, it is clear
this type of arrangement is akin to an insurance contract. As such, it is
expected that in normal circumstances, an FSP would decide claims in line
with the terms and conditions of the protection cover and only deviate from
this if prevailing circumstances compels it to so.
50. I accept it would be consistent with the FSP’s member s ’ expectation that the
FSP would limit any settlement to the reasonable costs involved in repairing
the damage caused by a covered event.
Case No: 255057 Determination Page 9 of 9
51. Following from this rationale, I accept the repairs to ensuite two and the
flooring in the games room are clearly payable by the FSP. The FSP has
acknowledged this in its decision.
52. In regards to the living room, I accept that at the least, an apportionment
should be allowed that reflects the fact that the leak played a contributing
factor to the damage. The FSP’s settlement offer with respect to the flooring
allowed 15% of the total cost of replacing all of the flooring as quoted by U.
Further, I note the FSP opted to base its settlement on this quote instead of
a more competitive quote available for the sum of $39,500.
53. According to the floor plans submitted by the Applicants regarding the home,
the total floor space for the living (6.3 x 5.1) and games rooms (4.7 x 5.4)
total approximately 60 square metres. This calculates to approximately 20%
of 290 square metres. If I was to accept 50% of the damage to the living
room flooring should be covered, this would calculate to approximately 15%
of 290 square metres.
54. Given this, I therefore accept that the 15% allowed by the FSP for the
replacement flooring costs based on U’s quote is fair in all the
circumstances, particularly given there was an alternative quotation available
for almost half this amount.
55. Accordingly, I am satisfied the FSP has appropriately exercised its discretion
regarding the costs of repairing the flooring .
Determination
56. On the basis of the available information I determine that:
The FSP is entitled to refuse to pay any of the costs involving in
repairing the damage attributable to the leak in ensuite one.
The amount it has allowed for the damage to the flooring caused by
ensuite two is fair in all the circumstances.