Home / Financial Firm (Unknown - Insurer) / Determination 254858

Determination 254858

Claim denied for river flood damage to home; carport stormwater damage

FirmFinancial Firm (Unknown - Insurer)
Decided2012-12-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$10,650
SourceAFCA PDF

Summary

The insured's home was damaged by Bundamba Creek floodwater in January 2011, and the FSP denied the claim under a river flood exclusion. AFCA upheld the denial for home damage but ordered the FSP to pay for carport items damaged by stormwater, subject to proof of loss, with interest.

The river flood exclusion was clearly informed under section 35(2) of the Insurance Contracts Act, but the hydrologist's evidence supported stormwater inundation of the carport.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 254858 Determination Page 1 of 12 Case number: 254858 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion/ condition 2 November 2012 Background 1. The Applicant entered into an insurance contract with the Financial Services Provider (FSP) to cover his residential property in North Booval. This policy was incepted on 24 February 2007. The relevant period of insurance operated for 12 months beginning from 24 Februa ry 2010. During this period, the building was insured up to a sum of $156,000 and contents for $63,000. Claims were subject to a basic excess of $100 for buildings and nil for contents. 2. The Applicant lodged a claim under this policy due to extensive water inundation damage following extreme weather events in Queensland. 3. The FSP denied the claim on the basis the damage was due to “river flood”. The Applicant, through his solicitors, has disputed this. 4. For the sake of simplicity, reference to the Applicant will include his legal representatives. 5. Both the Applicant and the FSP have provided detailed submissions on the relevant issues. For the sake of brevity, the Panel will summarise these submissions given all of the material made available has been exchanged with the other party. Summary of Applicant ’s position 6. The Applicant submits the following as alternative arguments in response to the FSP’s decision: a. The FSP’s policy failed to clearly inform him that “river flood” was excluded as required under Section 35 of the Insurance Contracts Act 1984 (the Act). b. The FSP breached its duty of utmost good faith as it allowed the Applicant to arrange a policy clearly unsuitable to his needs. c. The damage was solely due to stormwater run-off or flash flood. Determination Case No: 254858 Determination Page 2 of 12 d. The damage is covered under the insured event of “Water or Other Liquid”. e. The FSP is unable to discharge its onus in establishing the loss was caused by “river flood”. 7. The Applicant therefore seeks to be indemnified for his loss. Summary of FSP’s position 8. In response to the Applicant ’s arguments, the FSP submits the following: a. It has provided evidence from an appropriately qualified individual to corroborate that the building and contents policies were sent to the Applicant prior to the claim. Further, both these policies’ structure and layout in conjunction with this evidence enables it to rely on the exclusion clause of “river flood” pursuant to Section 35(2) of the Act. b. The duty of utmost good faith does not extend to an obligation to ensure a policy is suitable to the Applicant’s needs. 9. The FSP therefore relies on the following policy provisions (which, where relevant, are consistent in both), a site specific hydrology report and the reports commissioned by the Insurance Council of Australia (ICA) to substantiate its position: “ Definitions (The Meaning Of Some Words) … “ flash flood ” means what occurs when there are heavy, intense bursts of rainfall, usually during thunderstorms where so much water falls in a very short time that it cannot get away quickly enough and collects and flows into your building . but does not include when rainwater on the site :  cannot run-off into a water catchment system , because it is overflowing in flood; and  mixes with the flood water coming from the water catchment system and then flows into your building . … “ rain ” means water that has fallen from the sky on to your building and the site but not water from flash flood . “ river flood ” means when water that is normally contained in a water catchment system increases because of rainfall or snow melt (whether in the immediate region or elsewhere) or is deliberately released by an authority, and the water overflows onto land that is not normally covered by water into your home For example water may be deliberately released by an authority from a dam or reservoir. … Case No: 254858 Determination Page 3 of 12 “ storm ” means violent weather and high winds, sometimes accompanied by rain, hail or snow including a cyclone, tornado or willy willy. … “ water catchment system ” means:  a river, creek, other natural watercourse or lake, whether they are in their original state or have been modified, are named or unnamed, or normally dry land that only run during periods of rain;  a dam, reservoir, storm water channel or canal. … 1.12 Storm, Rain or Flash Flood You are insured for damage to your building caused by storm , rain or flash flood . … We will not pay for damage caused by:  …  river flood ;” Issues 10. Whether the FSP breached its duty of utmost good faith in allowing the Applicant to incept this type of policy. 11. Whether the FSP has complied with the requirements under Section 35 of the Act to rely on the policy exclusion of “river flood”. 12. Whether the FSP is able to establish the Applicant ’s loss was caused by “river flood”. 13. Whether the FSP is able to rely on the “river flood” exclusion. Reasons for decision 14. Due to the nature of the dispute, the parties have been informed that the matter has been referred to the Panel for Determination in line with the Operational Guidelines to the S ervice’s Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 15. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the ins urance industry and a representative with extensive experience in consumer claims. 16. It is appropriate to consider the issues under the various headings. Case No: 254858 Determination Page 4 of 12 Clearly Inform 17. Section 35(2) of the Act states that when a claim is made under a “prescribed contract” for a “prescribed event”, an insurer cannot refuse to pay the claim unless it can establish that it clearly informed its insured in writing that it would not cover this event. Section 34 of the Act has defined the terms “prescribed contract” and “prescribed event” by referring to the Insurance Contracts Regulations 1985. 18. There is no dispute that contracts of insurance covering a residential building and contents are “prescribed contract s ” and damage due to flood is a “prescribed event” . 19. The onus is therefore on the FSP to establish that it has clearly informed the Applicant prior to the claim that it would not cover damage caused by “river flood”. This is generally done by an insurer providing a copy of its policy to its insured which is meant to set out completely the rights and obligations of both parties under the insurance contract. 20. Further, the Courts have supported this and particularly, in the case of Marsh v CGU Insurance Ltd [2004] NTCA 1, Mildren J provided the following comments that are particularly relevant to the operation of Section 35(2) of the Act: “In Hams & Anor v CGU Insurance Ltd(2002) 12 ANZ Insurance Cases 61 - 525, Einstein J held that the provisions of s 35(2) of the Insurance Contracts Act 1984 (Cth) could be met if the insurer provided to the proposed insured a document such as the proposed policy, which contained the relevant wording. I agree. … Whether the policy wording in fact "clearly informed" the insured that there was no cover for flood is a question of fact to be determined by an examination of the document in question. … Furthermore, the language of s 35(2) suggests that the proposed insured can be clearly informed merely by providing the insured with a copy of the policy which shows the exclusion in clear and unam biguous terms. … The answer to the question "is flood covered" is easily ascertainable by any person of average intelligence and education. ” (Panel emphasis) 21. In this regard, the Applicant has not disputed receiving the policy/PDS for both the building and contents. Instead, he stated that: “It was not received until well after the client paid for the Insurance.” 22. The Panel notes that although Section 35 of the Act requires an insured to be clearly informed in writing before the contract is entered into, Section 69(2) of Act provides an exception to this. This provision states: “Where, by reason of a provision of this Act: (a) information in relation to a contract of insurance is to be or may be given in writing to a person before the contract is entered into; and (b) it was not reasonably practicable for the information to be so given orally or in writing; Case No: 254858 Determination Page 5 of 12 the provision shall be deemed to have been complied with, and the information shall be deemed to have been given, if the information is given in writing wit hin 14 days after the day on which the contract was entered into.” 23. The Applicant has submitted it was reasonably practicable for the “river flood” exclusion to have been brought to his att ention when incepting the policies. The Panel does not accept this. 24. As evident, the policies are subject to numerous exclusions or limitations and it would be unreasonable to expect an insurer to highlight all of them or alternatively, attempt to identify which ones may be of most interest to a prospective insured. 25. In addition, the policy provides a 21 day cooling off period. This enables a prospective insured sufficient opportunity to read the policy and seek any advice from a professional adviser (such as a broker) to ensure it is suitable to his needs. 26. Accordingly, the Panel accepts that Section 69(2) of the Act applies. In this regard the FSP has provided a statutory declaration from HW, who is responsible for the administration of daily processing of notices. HW’s evidence states:  The policies were sent to the Applica nt shortly after inception.  There is no record of the Applicant ever advising the FSP that he did not receive either policy. 27. The Applicant has not provided any evidence to refute any of this. Accordingly, the Panel accepts the FSP sent, and the Applicant received, a copy of both the building and contents policies within 14 days of the policy being incepted and well before the claim arose. 28. The Applicant has also argued the FSP failed to inform him of the changes to the policies in November 2010. The FSP has responded indicating the policies have remained unchanged since 2004. 29. There is no evidence of there being an updated policy which the FSP is relying upon. Instead, the FSP is relying upon the version of the policies it has sent to the Applicant at or around inception to deny the claim. Accordingly, the Panel does not accept the Applicant ’s argument in this regard. 30. The Panel therefore accepts the Applicant received the building and contents policies in accordance with the requirements under Sections 35(2) and/or 69(2) of the Act. Whether the policies are clear 31. The Applicant’s insurance policies regarding the building and contents are set out in two different policy documents. However, the relevant terms and structure are essentially identical. Case No: 254858 Determination Page 6 of 12 32. The Applicant has provided numerous submissions arguing that the terms and conditions in the policies are confusing, complex and unclear. In particular, the Applicant has referred to the defined terms of “storm”, “flash flood”, “rain” and “river flood” to argue that the distinctions are ambiguous, unclear and confusing and therefore should not be relied upon. 33. These specific issues and arguments have been raised by the Applicant ’s solicitors in a number of other disputes, and particularly case number 254731, involving a policy with almost identical definitions. These arguments were reviewed at length by the Panel in that case. In particular, paragraphs 28 to 38 sets out that Panel’s rationale in finding that the definitions of “rain”, “storm”, “flash flood” and “river flood” being used in that policy were clear and unambiguous. 34. These arguments were also raised by the Applicant in a dispute involving his investment property that suffered damage associated with this e xtreme weather event and insured under the same policy wording. 35. Pursuant to clause 8.2 of the Terms of Reference, the Panel intends to adopt the reasoning in Determination 254731 for the following reasons:  It is contemporaneous,  It involves policy provisions that are essentially identical to the policy in this dispute,  It considered arguments that are substantively similar to the Applicant’s submissions,  The reasoning and analysis contained in the previous Determination has clear applicability to this dispute, in particular paragraphs 28 to 38, and  The Applicant has not introduced any new substantive arguments that would imply the Panel’s previous reasoning is incorrect either in law or fact. 36. Given this, the Panel finds that the policies clearly informed the Applicant that he was not covered for “river flood” pursuant to Section 35(2) of the Act. Utmost Good Faith 37. The Applicant has alleged the FSP breached its duty of utmost good faith by failing to ensure the policy provided adequate coverage or that it was suitable to his needs. 38. The Panel considers the Applicant ’s arguments regarding the duty of utmost good faith are misconceived. There is no legal principle that supports the Applicant ’s argument that an insurer’s duty of utmost g ood faith extends to enquiring and ensuring its policy is appropriate to the insured’s needs. Such a duty is generally associated with insurance brokers or other authorised parties where case law makes it clear these professionals have a duty to ensure the policy they procure is suitable to their client’s needs. Case No: 254858 Determination Page 7 of 12 39. Further the FSP’s polic ies, which the Panel has found the Applicant received before the policy commenced:  Are standard building and contents policies that appear to be available to the general publ ic as opposed to being tailored to the Applicant’s needs, and  Both have a 21 day cooling off period which provided the Applicant ample opportunity to review the contract and obtain advice on it to ensure it was suitable to his needs. 40. Given this, the Panel does not accept the FSP breached its duty of utmost good faith with respect to offering its standard building and contents policies to the Applicant. Water Inundation 41. The FSP is relying on a site specific report dated 30 April 2012 that contains the following of relevance:  The property is located approximately 100m from Bundamba Creek and 2km upstream of the Bremer River. Runoff from the property would drain to Bundamba Creek within a few minutes. There is virtually no external catchment draining to the property.  The estimated ground level around the property is approximately 15.5m AHD. Based on the reported depth of inundation of the upper floor level (1.3m), the upper floor would be approximately 18.1m AHD.  Recorded hourly rainfall data was obtained from Bundamba (Hanlon Street) Alert station, located approximately 400m northeast of the property. A total of 123mm of rainfall was recorded between 0000 hours on 9 January 2011 and 1800 hours on 11 January 2011. No significant rainfall was recorded after 1400 hours on 11 January 2011. For durations up to 24 hours, recorded rainfalls had Average Recurrence Intervals (ARIs) of less than 1 year.  The peak hourly rainfall intensity of 16.3 mm/hr was recorded by Bundamba (Hanlon Street) Alert at 1400 hours on 11 January 2011. The peak stormwater runoff at the property would have occurred within 15 minutes of the peak intense rainfall.  Recorded water levels of Bundamba Creek were obtained from the Bundamba (Hanlon Street) Alert. Bundamba Creek peaked at 19.39m AHD. Based on the recorded water levels, water would have reached the ground level at approximately 2200 hours on 11 January.  The lower level includes a carport area which is below the surrounding ground level and approximately 0.5m below the floor level of the lower level of the house. It is possible stormwater runoff and water from the property accumulated in the carport area. This water could have ponded to a depth of approximately 0.3m. 42. The hydrologist therefore concluded the following: Case No: 254858 Determination Page 8 of 12 “The carport area under the house at the subject property is below the surrounding ground level and below the floor level of the house. It is possible that the carport could have been inundated to a maximum depth of approximately 0.3m above floor level by roofwater and stormwater runoff prior to inundation by floodwaters. Note however that the local rainfall intensities during the January 2011 event were not exceptional and hence, if such inundation occurred, it would be a regular occurrence at the property. The lower and upper floor level and the sheds at the subject property would not have been inundated by stormwater runoff. The initial and peak inundation of the lower and upper floor levels of the house and the sheds at the subject property was caused by floodwaters from the Bremer River backing up along Bundamba Creek and overflowing to inundate the subject property. Initial inundation of the lower floor level at the subject property by floodwater from Bundamba Creek would have occurred at about 2200 hours on 11 January, about 5 hours after rainfall in the area had ceased. The inundation of the upper floor level would have commenced around 0600 hours on 12 January. 43. The ICA hydrology report relied upon by the FSP is titled “Flooding in the Brisbane River Catchment January 2011, Volume 3 – Flooding in Ipswich City LGA”. The following information is available within the sub - heading “9.3 Releases from Wivenhoe Dam”:  Large releases were made from Wivenhoe Dam over the period from 0600 hours, possibly as early as 0300 hours on 11 January 2011, until around 0300 hours on 12 January 2011.  Releases from Wivenhoe Dam caused a flood wave in the Brisbane River. As the flood wave moved downstream, backwater flooding occurred along the lower reaches of the Bremer River and its tributaries.  Floodwaters moving down the Brisbane River were made up of dam release floodwaters from Wivenhoe Dam and floodwaters from Lockyer Creek and the Bremer River.  It was concluded that the dam release flood from Wivenhoe Dam was the immediate cause of flooding alo ng the reaches of the Brisbane River downstream of the dam and along tributaries through the Ipswich City LGA. 44. The Applicant has not provided any hydrological evidence. Although the Applicant raised a number of arguments stating that little to no weight s hould be given to the ICA report, he has not done so with respect to the site specific report. 45. Instead, it appears the Applicant accepts in principle this report to the extent it found that the carport was inundated by stormwater up to 0.3 metres . The FSP, despite relying on the report with respect to the damage to the house, appears to disagree with the findings regarding the potential stormwater inundation to the carport. 46. The carport inundation will be addressed later. Case No: 254858 Determination Page 9 of 12 Damage to the home 47. According to the FSP’s loss adjuster’s report, the Applicant had evacuated the property before it was inundated. It is unclear when he evacuated. Further, the Applicant had apparently informed the loss adjuster that he believed the water that inundated the property came from stormwater and Bundamba Creek back-up. 48. In his submissions, the Applicant has relied on this report to argue that the water which inundated the property was either stormwater or water discharging from the drains. 49. The Panel has reviewed the site specific hydrology report and prefers the hydrologist’s findings contained therein based on the following:  It relies on rainfall data recorded from a station proximate to the Applicant’s property which would therefore, on balance, be reflective of the local rainfall characteristics affecting the property.  His reasoning about why the rainfall recorded was not s ufficient to inundate the property is reasonable on the face of it given the fact the ARI was less than 1 year and the property is elevated approximately 2.2m from the ground.  His estimated time of inundation is consistent with the elevated levels of the Bundamba Creek, which is located approximately 100m from the property.  His opinion about the elevated waters of the Bundamba Creek being due to waters from the Bremer River backing up into it is corroborated both by the ICA report and general public knowledge of the events that occurred in the region around that time.  His findings are not inconsistent with any eyewitness evidence presented.  He has acknowledged the possibility that the carport would have been inundated, indicating he has clearly turned his mind to this issue, giving the Applicant any benefit of doubt with respect to the issues he was asked to review.  He is appropriately qualified to examine and report on the likely source of inundation. 50. Given this, the Panel accepts that the water which inundated the property escaped from the Bundamba Creek and was not due to stormwater runoff. 51. The Applicant has attempted to argue that even if this is the case, this water could have escaped from a stormwater drain or road gutter, thus falling within the insure d event of “Water or Other Liquid”. 52. However, the Panel does not accept this argument. The Applicant, in advocating this position, referred to the loss adjuster’s report as supportive Case No: 254858 Determination Page 10 of 12 evidence despite having previously argued that loss adjusters cannot make assertions as to hydrology. 53. The Panel accepts the Applicant’s argument that loss adjusters are not appropriately qualified to examine and report on matters involving hydrology. Furthermore, the evidence referred to by the Applicant was information he himself provided as the possible source of inundation. It is not the loss adjuster’s opinion as to the likely cause of inundation or eyewitness evidence. 54. Accordingly, the Panel does not accept the loss adjuster’s report is probative. Instead, for the reasons already outlined, the Panel accepts the findings contained in the site specific hydrology report, which states the water escaped the confines of the Bundamba Creek, overflowed onto normally dry land and then inundated the property. 55. Given this, the Panel therefore finds the following with respect to the water inundation to the property:  The damage was due to “river flood”, and  The circumstances of the loss do not fall within the insured event of “Water or Other Liquid”. 56. The FSP is therefore entitled to deny liability with respect to the damage to the home. Carport 57. The FSP ’s hydrologist raises the possibility that the carport may have been subject to stormwater runoff to a height of approximately 0.3m. 58. Although the FSP submits; “ ho wever, given the low amount of rainfall that fell, (hydrologist) states that if it was subject to runoff in January 2011, it is likely to be subject to inundation at regular intervals.” 59. The FSP does not provide any evidence one way or the other as to whether the carport was subject to inundation at regular intervals. 60. Upon reading the report from the hydrologist, the Panel is satisfied that the conclusion of the hydrologist is not that the carport was not subject to stormwater runoff prior to inundation by flood waters , but rather, given the unexceptional nature of the rainfall intensities, if such inundation occurred, it would be a regular occurrence at the property. The Panel is satisfied that this is very different from saying that stormwater runoff did not occur. 61. The Panel notes bot h the hydrologist and the FSP’s comments in respect to the low amount of rainfall that fell. 62. The FSP submits that the rainfall data does not support the proposition that stormwater inundation occurred. However, the Panel notes that the Case No: 254858 Determination Page 11 of 12 hydrologist has not speculated as to the time that the stormwater runoff occurred, prior to the inundation by flood waters. 63. The hydrologist believes that the flood waters arrived at 10.00pm on 11 January 2011, about five hours after rainfall in the area had ceased, but does not provide an estimate of the timing of the stormwater runoff. 64. In the Panel’s view neither the hydrologist nor the submissions of the FSP exclude the possibility that the stormwater runoff to a depth of approximately 0.3m above the floor level occurred at or about the time of the rainfall detailed within the hydrologist report. 65. The Panel accepts the inundation from storm water runoff could have occurred between 1400 (maximum intense period of rainfall) and 1800 hours, given this is one hour after continuous and sustained rainfall had ceased and is consistent with the hydrologist’s findings. 66. As such, the Panel is satisfied that the FSP has not adequately demonstrated why the hydrologist report should not be accepted. 67. The Panel accepts that the hydrologist is an expert who is appropriately qualified to examine and report on hydrology and has accepted the possibility that the rainfall data and the topography of the carport could have resulted in the carport being inundated by stormwater. 68. Given this, the Panel a ccepts the hydrologist’s evidence that the carport was likely inundated by stormwater up to 0.3 metres. 69. The extent of the loss is also in dispute. 70. The Applicant has provided a list of items he states would have been damaged and has conservatively estimated the loss at $10,650. He notes all receipts were lost and destroyed due to the flood. The FSP has queried the extent of this loss based on the following:  It is unreasonable to contend that a person would store approximately $11,000 worth of power tools and building supplies in a carport that has no walls, no lock and is unsecured.  As the inundation was only 30cms, all of these items would have had to be on the floor in order to be claimable.  The Applicant has not provided any evidence in respect of these items 71. The Panel accepts the FSP’s concerns have foundation, particularly given that this area would have been exposed to rainwater collection, probably over an extended period of time, yet no previous instances appear to have been reported. This is particularly so at least with respect to some of the power tools being claimed (e.g. the chainsaw). In relation to building supplies though, there appears to be scope to accept these could have been stored and damaged in the carport given the hydrologist’s report contain photographs of the carport with building supplies stored in similar locations. Case No: 254858 Determination Page 12 of 12 72. However, without any supporting documentation about the items and value, the Panel is not in a position to provide any monetary award. Instead, the Panel directs the Applicant to provide the FSP with the following to establish the extent of his loss:  An explanation as to where and why all of these items were stored in the carport and how they would have been damaged by 30cm of rainwater. This should include an explanation as to why these items were not stored elsewhere given the unsecured nature of the carport.  If there is any eyewitness evidence regarding the storing of these goods in the carport, this should be obtained as well.  A complete list of all items claimed together with any receipts or other proof. Although the Applicant states he has lost all receipts, he should endeavour to contact suppliers, obtain credit card statements, photographs and/or statements from witnesses to establish ownership and value. 73. Upon receipt of this information, the FSP is directed to settle items in an appropriate and fair manner taking into consideration the timeframe that has lapsed and the limitation the Applicant is working under in providing proof of ownership for items lost more than a year and a half ago. Determination 74. On the basis of the available information the Panel determines that the FSP is entitled to deny liability for the damage sustained to the Applicant’s home . 75. The Panel determines the FSP is liable to pay for the items damaged in the carport based on stormwater inundation of up to 0.3 metres in line with the requirements set out in paragraphs 72 and 73 of this Determination. 76. Insofar as the FSP is to cash settle the claim or reimburses the Applicant for cost or expenses already incurred, the FSP is to pay interest from 22 March 2011 (being the date of rejection of the claim) to date of payment of the claim, in accordance with Section 57 of the Act.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.