Home / Financial Firm (Unknown - Insurer) / Determination 254248

Determination 254248

Claim denied for building damage alleged to be caused by earthquake rather than soil movement

FirmFinancial Firm (Unknown - Insurer)
Decided2012-02-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$20,000
SourceAFCA PDF

Summary

A homeowner claimed for building damage he attributed to earthquakes in 2009. The insurer denied the claim, finding the damage was caused by reactive clay soil movement, which the policy excludes. AFCA found the applicant had not proven an insured event, so the denial stands.

The insured bears the onus of proving an insured event, and the weight of expert evidence attributed the damage to soil movement rather than earthquake.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 254248 Determination Page 1 of 7 Case number: 254248 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 29 February 2012 Background 1. The Applicant and his wife are insured under a home building and contents insurance policy that was incepted with the Financial Service Ombudsman (FSP) on 8 June 2000. The policy was renewed annually. 2. On 1 May 2009 the Applicant contacted the FSP to lodge a claim for damage to the building as a result of an earthquake. It was reported the earthquake had occurred three weeks earlier. 3. The FSP denied the claim as the damage to the building was not the result of an earthquake. Although the Applicant provided his own expert report to dispute the FSP ‟s denial, it maintained its decision. 4. The Applicant has referred this matter to the Service, with the assistance of a friend. The Applicant is seeking indemnity under the policy for damage to the building which he maintains was caused by an earthquake. Summary of Applicant’s position 5. The Applicant says his policy covers him for damage to the building caused by an earthquake. 6. He says the FSP first denied his claim on the grounds his home was outside the earthquake damage zone. 7. The Applicant says he relies on his own independent report to show that earthquake movements were the cause of damage to the building. Summary of FSP’s position 8. The FSP says the facts of this case are clear in that the Applicant has not provided evidence that establishes the damage was caused by an event covered by the policy. Determination Case No: 254248 Determination Page 2 of 7 9. It says it has been shown by its engineer that the damage occurred as a result of earth movement caused by reactive clay soils. 10. The FSP says the policy specifically excludes damage caused by soil movement, settlement and subsidence. 11. The FSP relies on the following policy provisions: “ What we cover – insured events … You are covered for damage or loss to your building occurring during the period of cover and caused by the following events: … Earthquake including subsidence and landslide caused by an earthquake. … What we do not cover – general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: … soil movement or settlement, subsidence or landslide unless caused by the insured event of earthquake, ” Issues 12. Whether the damage to the Applicant‟s home was caused by an event covered by the policy. Reasons for decision 13. FOS has considered it is appropriate to expedite the dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is because of the issues in dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 14. There has been on exchange of material which the parties rely upon. Each party has had access to the material on which the other party bases its case. As a consequence it is not necessary to go into all of this material in any great detail. 15. It is an accepted principle of insurance law that the onus rests with the Applicant to prove, on the balance of probabilities, that he has suffered a loss caused by an event covered by the policy. 16. The FSP says the Applicant has not provided evidence to show the damage was caused by an event covered by the policy. Whereas the Applicant is Case No: 254248 Determination Page 3 of 7 relying upon his own independent report to establish that the damage can only be explained as a result of an earthquake. 17. The Applicant‟s representative indicated to the Service‟s case manager the cost to repair the building maybe around $20,000. 18. I have considered the material relied upon. The reports provided by the parties are not extensive. 19. According to the information provided to the FSP at claim lodgement on 1 May 2009, the earthquake occurred on 10 April 2009 and the following claims description was transcribed onto the FSP‟s record s: “ 5-6 years ago there were gaps forming between the floor and skirting, I called a builder who repaired the problem, but then a few days later the gaps started to reappear. The builder came back and fixed it up and since then it has been fine. After the earthquakes that happened three weeks ago the gaps reappeared. I called the builder who advised me that I should lodge a claim with my insurance company.” 20. The FSP appointed a loss adjuster to attend the property and report on the damage. I do not have the benefit of a site specific report. 21. However, the loss assessor inputted his notes onto a computer claims assessment screen. He identified the following repairs needed to be undertaken:  Realign and block stumps throughout the house;  Readjust binding full height doors to suit;  Repair gaps to skirting as required;  Repair gaps to ornate cornice throughout;  Repair and paint ceiling and cornice throughout;  Cornice painted in contrasting colours. 22. The loss assessor noted he was advised by the Applicant that the stumps had been attended to twice since the house was built and are now twisted and that he had attended to previous cornice repairs. 23. The loss assessor reported he did not believe the damage was the result of an earthquake but was related to a pre-existing soil movement issue. He noted: “the area is clay based soil and very reactive: 24. During the claims process the FSP obtained a report from an environment service (ES&S) regarding the earthquake on 6 March 2009 and on 18 March 2009. The claims screen notes: “…. PEAK VE LOCITY FOR THIS SITE WHICH IS APPROX 76 KLM FROM EPICENTER ONLY ATTAINED A MAX 20% OF THE VELOCITY REQUIRED TO CAUSE DAMAGE TO DWELLINGS. DAMAGE NOT DUE TO EARTHQUAKE: Case No: 254248 Determination Page 4 of 7 In short, the FSP concluded these earthquakes did not cause damage as the Applicant‟s ho me was outside the earthquake damage radius. 25. Following the FSP‟s initial denial of his claim , the Applicant obtained a geotechnical report. According to the information contained within the geologist‟s report the property has been subjected to three earthq uakes, occurring in the years 2003, 2005 and 2009 following a discussion with the Applicant. I have concerns with such a generalised comment based on a discussion with the Applicant particularly as the onus is on the Applicant to establish an insured event has occurred. 26. In any event, the geologist noted: “Foundation movement is evident as a result of earthquake activity. The Beaumaris Fault and Melbourne Warp intersect within 10 Kilometers of Tyara Close, and are the probable source (epicentre and focus) of the causal earthquake” … “Soils in this area consist of still clays over weathered Silurian/Devonian bedrock which occurs at approx 1.5 – 2.0 m below the surface” “H orizontal movement of footings seen at the site are the result of ground movement in response to a minor earthquake. This type of earthquake is known as strike slip, in response to movement along a fault as shown in Figure 1. The Beaumaris Fault and Melbourne Warp intersect within 10 Kilometers of Tyara Close, and are the probable source (epicentre and focus) of the causal earthquake. Refer to Appendix 1. By inference, the lower portion of the house moved north and west following the first earthquake while the upper portion remained in its original position. ” 27. I can only assume when the geo logist refers to „first earthquake‟ he is referring to an unidentified earthquake that occurred in 2003 based on the discussion he had with the Applicant. 28. Nevertheless the Applicant‟s claim was for damage that occurred following an earthquake that occurred around 10 April 2009. The geologist‟s report makes no mention of the building suffering damage from any earthquake that occurred in 2009. 29. The geologist did recommend a structural engineer should attend the site to assess the damage. 30. The FSP appointed a structural engineer to attend the property and report on the cause of damage. The engineer advised he was unable to source from the Geoscience Australia website any earthquake that would have impacted the Applicant‟s property. 31. The engineer reviewed Geological Survey maps which indicated the clay soils at the site are “expected to be moderately reactive.” Case No: 254248 Determination Page 5 of 7 32. The engineer listed the damage and was told the house was built in 1999 and “distress to the residence was first noticed following the earthquake event in 2 003 and has increased since then.” 33. A floor level survey was conducted and the engineer concluded: (iii) “There is a general pattern of relative settlement towards the central region of house. The average magnitude of this relative settlement is approximately 30-40mm. This pattern of the relative movement is common for a strip and stump footing system and is expected be caused by long term drying of the sub- floor soils…” 34. The engineer made extensive comments about the relevant earthquake events. He said the damage to the house was not caused by the earthquakes on 6 & 18 March 2009. “…there were only two significant earthquake events which affected Melbourne and its suburbs for last 10 years, i.e., 6 and 18 March 2009. The review further indicated that there were only 4 minor earthquakes which occurred between 2003 and 2005 in Victoria. Among the four earthquakes, the most severe earthquake had occurred on 12 April 2004 and had a magnitude of 2.8 on the Richter scale, and its epicentre was locate in Lake Eildon, which is approximately 75 km away from the subject site. Considering the distance and magnitude of this earthquake, in (expert‟s) opinion, none of the observed distress to the subject residence has been caused by this earthquake event. The subject site is located approximately 70 km from the epicentres of the earthquakes which occurred on 6 and 18 March 2009. These earthquakes both had a magnitude of 4.6 on the Richter scale, and their epicentres were located north of Korumburra. Maps of the earthquakes on 6 and 18 March were obtained from the Australian Government website… The maps of the earthquakes on 6 and 18 March 2009 are very similar, and both indicate a „damage radius‟ of 9 km and „felt radius‟ of 113 km. The subject site is within the „felt radius‟ of th ese earthquakes. As isoseismal map, which graphically shows the Modified Mercalli (MM) values experienced in zones around the epicentre on 6 March 2009 has been prepared by the Seismology Research Centre… An isoseismal map has not yet been compiled for the earthquakes which occurred on 18 March 2009, however, it is expected to be similar to the map for 6 March 2009 Based on the 6 March isoseismal map, the subject site is expected to have experienced an intensity of MM IV…This intensity is described as follo ws:- “ MM IV Generally noticed indoors, but not outside, Very light sleepers may be awakened. Vibrations may be likened to the passing of heavy traffic, or to the jolt of a heavy object falling or striking the building. Walls and frame of building are heard to creak. Doors and windows rattle. Glassware and crockery rattle. Liquids in open vessels may be slightly disturbed. Standing motorcars may rock and the shock can be felt by their occupants.” Structural damage to buildings is not expected for an earthquake with intensity MMIV. The MM scale suggests that damage to Masonry D type Case No: 254248 Determination Page 6 of 7 structure commences with intensity MMVI ( “Slight damage to masonry D. Some plaster cracks or falls. Isolated cases of chimney damage”). We note that that MMV is the highest category identified for the isoseismal map for the earthquake on 6 and 18 March 2009. This category was limited to sites located less than approximately 15 km from the earthquake. It therefore does not appear possible for the subject site to have experienced an intensity of MMVI, which is the minimum intensity level required to cause damage to masonry buildings. In (expert‟s) opinion, none of the observed distress to the house has been caused by the earthquake events on 6 and 18 March 2009. As noted above the clay soils in this site are expected be moderately reactively….. Moderately reactive clay soils have significant volumetric changes with relative changes in moisture content, i.e. if moisture content increases, the clay soils will swell, and if moisture content decreases, then the clay soils will shrink. 35. He did however say the type of soil was relevant. He said: “The locations and patterns of the wall cracks and distressed brickwork observed in the subject residence is typical of distress caused by differential foundation movements in this type of soils. In this case, the floor levels survey identified a relative settlement of the internal (central) region of the house of approximately 30- 40mm… This pattern of movement (“dishing shape”) commonly occurs to strip and stump footing systems, and is caused by differential foundation movements as a result of long term drying of the soils within the sub-floor space and subsequent differential changes in the moisture contents of the highly reactive clay soils at this site. Furthermore, the distress to this house does not appear to be recent, and it is evident that previous repairs have been carried out. In (expert‟s) opinion, movement and distress to this house has been occurring for many years. The owner advised that he was aware of the on-going movement of the house over the past years and had the floor re-packed and re-levelled and carried out repairs to the plasterboard walls and ceilings in the past.” 36. The engineer concluded: “ .. the observed distress in the subject p remises is most likely caused by the foundation movement as a result of the long term drying of the soils within the sub-floor space and none of the observed distress to the house has been caused by the alleged earthquake events in 2003, 2005 and 2009. We also note that an earthquake event could not have caused relative settlement in the internal region of the house identified by the floor levels survey.” 37. In response, the Applicant‟s geologist maintained his opinion. He said the horizontal movement in one direction is, nor consistent with clay shrinkage and the testing of clays at the site was not consistent with large scale movement seen. He concluded: “As this site movement is all in the same horizontal direction which can only be explained by earth movement as previously documented. The writer has never seen this type of foundation movement in 30 years of business as a geo- technical engineer.” Case No: 254248 Determination Page 7 of 7 38. As previously advised the onus is on the Applicant to establish the damage has resulted from an insured event covered by the policy. 39. A ccording to the geologist‟s initial report the damage resulted from the „ first earthquake ‟ . This has not been qualified but is an approximation based on a discussion he had with the Applicant. However, this in itself is not evidence to support the claim. 40. Nevertheless, the Applicant is claiming for damage that is reported to have occurred as a result of an earthquake in 2009. The geologist‟s report makes no mention of damage occurring to the building from any earthquake in 2009. In any event, even if the geologist intends to say the earthquakes in March 2009 caused the damage, I am not persuaded the Applicant has overcome the onus he has when three experts engaged by the FSP disagree. Two identify soil movement as a cause of damage, and two go on to say that the size of the earthquake was such that it would not have caused the damage noted at the site of the Applicant‟s house. 41. In short, after analysing the material, I am not satisfied the Applicant has, on the balance of probabilities, established the damage claimed was caused by an earthquake or any event covered by the policy. Determination 42. On the basis of the available information I determine the FSP was entitled to deny the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.