The applicants' home flooded in January 2011 and the FSP declined the claim as flood. AFCA found the river water was excluded flood but that stormwater runoff inundated the property to 150mm first, and ordered indemnity to that level, with interest if cash settled.

A creek was not a water course under the policy definition, so the earlier overland stormwater flow was not flood and is covered to the extent of 150mm.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 252780 Determination Page 1 of 11 Case number: 252780 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 29 October 2012 Background 1. The Applicants hold a Home and Contents policy underwritten by the Financial Services Provider (FSP). The policy covers a residential address in Charlton Victoria. 2. On or about 14 January 2011 the insured property was inundated by water. 3. The FSP assessed then declined the claim on the basis the inundation arose from flood which was an excluded cause of loss or damage under the policy. 4. The Applicants dispute the declinature on the basis inundation occurred from stormwater runoff. Summary of Applicants ’ position 5. The Applicants rely on a letter from a law firm which provides the following summary of an independent hydrology report:  Charlton‟s local drainage system is highly likely to have reached capacity and overflowed between 12am and 4am on 14 January 2011.  Rainfall after 4.00am 14 January 2011 is likely to have contributed to the overflow.  It is highly likely that the intensity of the rainfall and stormwater runoff would have caused damage.  Heavy rainfall between 10 and 14 January 2011 is likely to have caused saturation of soils in farmland surrounding Charlton and the additional rain was likely to have caused saturation overland flow or runoff.  Clear water indicates that the water was of a low sediment load and therefore is likely to be from local runoff and rainwater not from the Avoca River.  Every property owner‟s situation is different. The evide nce from each property owner is required to determine what caused the damage to their property. Any evidence relating to damage before 5.00pm on 14 January 2011 is in all probability a result of stormwater and local runoff. Determination Case No: 252780 Determination Page 2 of 11 It is noted that the Applicants were unable to obtain a copy of the hydrologist‟s report (as quoted above) as they were not a client of the solicitors. 6. The Applicants have provided photographs captioned with the street address and time the photographs were taken. The Panel notes that the photographs depict significant inundation as early as 8.12am on 14 January 2011 and a substantial depth of water around 12.00pm-2.00pm. The Applicants have labelled a photograph inside their property at 7.46pm and noted it was clear water. 7. The Applicants have enclosed a letter dated 26 August 2011 from a witness “TM”, from which the Panel notes the following:  On 14 January 2011, following heavy storms the previous day and overnight, the Yeungroon Creek sent an unprecedented “torrent towards Charlton”.  By midday the creek water had reached the south-east end of town and was rising in the gutters along High Street.  The Applicants‟ residence sits lower than the centre of the road because it is older.  After midday the creek water had begun to surround the house and seep under it.  It was not until some hours later that the Avoca River waters joined with the waters from Yeungroon Creek. 8. The Applicants have enclosed a letter from “GW” from which the Panel notes the following:  GW has 22 years of local experience with soil and water, gained from working in the catchment south of Charlton.  83mm of rain fell in an eight hour period between 13 and 14 January 2011.  The rainfall contributed to the stormwater runoff (clear water) entering houses from the south.  Water started entering houses around 5.30pm to 5.45pm; this water was clear. 9. The Applicants rely on an email dated 27 July 2011 from their broker, from which the Panel notes the following:  The FSP agreed to pay for any water damage that can be proven to have occurred prior to 2.00pm on 14th.  The latest hydrologist‟s report states that flooding east of Armstrong Street on the morning of 14 th can be attributed to stormwater and secondly at 2.00pm water began coming into the house. 10. The Applicants have obtained Bureau of Meteorology data from which the Panel notes the data indicates heavy rainfall towards the evening of 13 January 2011 and particularly in the early hours of 14 January 2011. Case No: 252780 Determination Page 3 of 11 11. The Applicants submit that the FSP‟s hydrologist provided inaccurate information and has not taken into account local flooding or stormwater runoff from the hills that lie to the south-east of the town. In particular the Applicants state:  The hydrologist stated the water inundation level was 0.5m when in fact it was 740-765mm above floor level, this being 960mm from ground level. The Applicants also note that the cellar is 1800mm deep.  The hydrologist has not investigated the height „build up‟ of the old St Arnaud Road, as this „build up‟ would have prevented the water from the Yeungroon Creek from entering across the road.  The fact that 8-10 inches of clear rain water entered the property indicates that it is stormwater and nothing else. It is incorrect to suggest that the water from the Avoca River was filtered clear of debris when it travelled overland.  The level of the river cannot be fully taken into account as the river gauges failed at 8 metres.  The Applicants note that the parties interviewed by the FSP‟s hydrologist were all on higher ground.  The Applicants note the people interviewed in their street all indicated the approximate time of inundation was 7.00pm-8.00pm. The notations indicate water direction as coming from the west, south, north and the river. One interviewee stated that the backyard was flooded the day before.  The hydrologist misreported statements by the (male) insured regarding the timing of the inundation. 12. The cellar beneath the home became nearly full at 8.00pm on 13 February 2011. Further, there was water around the front and side verandah which was escaping into the vents around the base of the house. 13. The rear of the insured property consists of a bathroom, kitchen and spare room which sits lower than the rest of the house. When the female Applicant awoke around 7.30am (14 January 2011) the rear of the property had taken in about 3 inches of water. 14. The driveway and all the stormwater drains around the house were under water the night before, with the garage and rear shed full of water in the morning. 15. Family and friends of the Applicants came around to stack sandbags 2-3 metres high. The sandbags held back the water until early afternoon. Summary of FSP’s position 16. The FSP relies on the following policy terms and conditions: “Flood Case No: 252780 Determination Page 4 of 11 The inundation of normally dry land by water escaping from any water course, lake, canal, dam or reservoir. ... Additional exclusions applying this Policy These additional exclusions apply to cover for your home, contents, additional benefits and „options you can choose for an additional premium‟. This Policy does not cover: ... (e) flood, (unless your policy Schedule confirms that you have chosen optional flood cover and paid any additional premium we require)” 17. The FSP relies on a copy of the Home & Contents Insurance Schedule. The Panel notes the building is covered up to $233,000 and the contents up to $69,000. The policy is subject to an excess of $250 for building and $250 for contents. 18. The FSP relies on a Flood Assessment Report dated 21 March 2011 from which the Panel notes the following:  Charlton experienced heavy rainfall be tween 10 and 14 January 2011.  The rainfall data indicates that on Thursday 13 January 2011 Charlton received 66mm in the 24 hours to 9.00am on 14 January 2011.  The peak flood level of 8.05m was reached early morning on 15 January 2011 at least two days after the most intense rainfall.  The general mechanism of flooding of Charlton properties was overflow from the Avoca River and Yeungroon systems. The Avoca River peaked 700mm above the prior September 2010 event.  Any flooding after lunchtime can be directly attributed to the Avoca River and Yeungroon Creek systems.  Floor inundation that occurred east of Armstrong Street early morning on 14 January 2011 can be attributed to stormwater flooding.  The owner of the insured property provided the following information: i. At 9.00am on 14 January there was water in the street. ii. At 11.00am the road adjoining the property were becoming inundated. iii. At 2.00pm water began coming into the house. iv. At 4.00pm on 14 January 2011 the water was knee deep in the house. v. Water came from the south west along Wilson Street.  The house is almost level with the surrounding land and therefore has little freeboard when flooding occurs.  Depth marks on the house indicates a final flood depth of approximately 0.5m.  The property is outside the historical mapped extent of flooding within Charlton. Case No: 252780 Determination Page 5 of 11  The hydraulic model prepared to determine the source of various flood waters that entered the town indicates that the water that flooded the property at 2.00pm was from Yeungroon Creek, this was followed by flooding from the Avoca River.  Timing and depth on inundation is in line with the information provided by other residents throughout the town.  The clarity of the water, or otherwise, has little bearing on whether the water is classified as stormwater related.  The hydrologist concluded that flood damage at the insured property occurred as a result of flood flows from Yeungroon Creek followed by flooding from Avoca River.  The report has an attachment of interviews with other residents, some of which are in the same street as the Applicants. Most of the residents in the same street indicate inundation around 7.00pm-8.00pm. One of the residents indicated flooding in the backyard the day before. 19. The FSP contends that the site specific hydrology report together with the timing of the inundation and the amount of water demonstrates the proximate cause of water inundation was flood. Further, the hydrologist has the appropriate expertise to determine the cause of inundation. 20. The damage falls within the definition of flood under the policy and is specifically excluded from cover. 21. The FSP maintains that it was entitled to decline the claim as flood is excluded under the policy. Issue 22. Whether the FSP was entitled to decline the Applicants‟ claim for loss or damage arising from flood inundation. Reasons for decision 23. As advised to the parties, FOS has considered it appropriate to elevate the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the complex nature of the issues. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination by an Ombudsman Panel. 24. The Panel is comprised of an Ombudsman, an insurance representative appointed by the Financial Ombudsman Service Board, and a consumer representative appointed by the Financial Ombudsman Service Board. 25. The Panel Chair Ombudsman and a Panel Member attended on site where they met with the Applicants and a representative of the FSP. Case No: 252780 Determination Page 6 of 11 26. There has been an exchange of material between the parties. Each party therefore is aware of the issues and has had the opportunity to comment. 27. Prior to arriving at a determination the Panel has read and considered all the material submitted by the parties to FOS. 28. There appears to be no dispute between the parties that the Applicants‟ residence was subject to heavy rainfall from the evening of 13 January 2011 to early morning on 14 January 2011. 29. The Panel notes that the Applicants have disputed the FSP‟s summary of information allegedly provided by them to the hydrologist. 30. The Applicants have provided a timing of inundation as early as 8.00pm on 13 February 2011. This being the time that the property‟s cellar became full of water and the driveway and storm drains were submerged. The Panel notes this matches a description of an individual interviewed in the street who stated water had inundated his backyard the day before. 31. The Applicants have stated that the rear of the property became inundated up to 3 inches around 7.30am on 14 January 2011. Further, the garage and rear shed were also full of water at this time. 32. The Applicants confirmed with the Panel Chair Ombudsman and Panel Member that the inundation of the house occurred at approximately 2.00pm. 33. It is unclear from the hydrological evidence precisely when the river broke its banks. However, given the evidence presented, the Panel is satisfied that ultimately the property was impacted by flood waters which had escaped from the Avoca River. The Panel accepts that flood is an excluded event under the policy. 34. On the other hand, the relevant policy pro vides coverage for storm damage. The Panel notes that the policy does not include a definition of “storm” but does include coverage for rain and as such, the Panel accepts that coverage will include stormwater runoff. 35. It is appropriate for the Panel to determine the potential extent of inundation that could properly be described as having arisen from stormwater runoff as distinct from flood water. 36. Subsequent to the attendance on site by the Panel Chair Ombudsman and Panel Member, the further exchanges between the parties have been voluminous. Given that there has been an exchange of all submissions between the parties and the parties have had the opportunity to respond, the Panel does not propose to recite the full details of the various submissions exchanged but rather to summarise and to refer to specific submissions where appropriate. 37. The exchanged submissions include but are not limited to the FSP‟s hydrology report dated 16 August 2012. The Applicants have provided a Case No: 252780 Determination Page 7 of 11 detailed response to the hydrology report and there have been further exchanges between the parties subsequent to that time. 38. In respect to the FSP‟s hydrology report, the Panel notes that the report refers to and responds to a report from Dr PM dated 3 November 2011. 39. It is interesting that the FSP has had their hydrologist respond to that report when that report of Dr PM does not appear to form part of the Applicants‟ material. 40. However, the Panel recognises that the Applicants‟ claim is one of ma ny made by residents of the Charlton area arising from the weather events of January 2011. 41. The Panel has considered a number of the claims arising from these weather events and is aware of the report from Dr PM, as that report forms part of the material submitted in respect of a number of the other claims. 42. In respect to the report from the FSP‟s hydrologist, the Panel notes the following conclusion: “ It is our opinion that, based on the reported timing, parts of the property and cellar of the dwelling at (A pplicants’ address) Charlton were flooded firstly by local runoff and overflows from the rain water tanks. The property and dwelling were then later flooded by overflows in the (C) highway tributary caused by breakouts from Yeungroon Creek and the Avoca River farther upstream. The property and dwelling were then flooded later again by breakouts from the Avoca River directly.” 43. The FSP provided a copy of the supplementary report of the hydrologist dated 12 September 2012. The FSP‟s hydrologist concluded that the initial inundation reached a height of approximately 50-75mm above the surrounding ground level. Further, the hydrologist was of the view that this was sufficient for water to enter the cellar through the ventilation holes but insufficient to cause flooding of the main part of the house. 44. Further, the hydrologist‟s supplementary report confirmed that any subsequent inundation and any inundation above the 75mm level was caused by river flood water. 45. As previously stated, the Panel is satisfied that ultimat ely the Applicants‟ property was inundated by waters which came from the Avoca River. 46. Given the policy provisions relevant to this claim, the Panel is also satisfied that the water that ultimately came from the Avoca River is properly categorised as flood water and excluded under the terms of the policy. 47. However, as stated, consideration needs to be given as to whether the inundation of the property as described within the FSP‟s hydrologist report as being overflows in the Calder Highway tributary caused by breakouts from Yeungroon Creek can be described in the same way. Case No: 252780 Determination Page 8 of 11 48. Having dealt with a number of different disputes arising from the weather events in Charlton in January 2011, the Panel notes the undisputed evidence that water which inundated parts of Charlton, approached Charlton from the south and south east. The hydrology evidence is also consistent in that this water was caused by overflows from the Charlton/St-Arnaud tributary waterway of the Calder Highway and overland flows from the breakouts from Yeungroon Creek and later from the Avoca River upstream. 49. The question arises as to whether the Yeungroon Creek and the landscape over which the water flowed was a „water course, lake, canal, dam or reservoir‟ as described by the policy provision under the definition “flood”. 50. In this regard, the Panel has been greatly assisted by its visit to the area and the ability it has had to familiarise itself with the topography and relevant sites. 51. Within the report submitted by the FSP‟s hydrologist, the hydrologist re fers to descriptions of “ waterways ” contained within [a named publication] and reaches the conclusions that Yeungroon Creek and the two Avoca River tributaries are defined as “ waterways ” and based on stream flow and channel definition would be considered ephemeral streams. 52. Within [the named publication], referred to above, ephemeral stream is referred to as “those waterways with (often) poorly defined channels that generally flow unpredictably and only after heavy rainfall”. 53. However, the Panel notes that t he policy definition of “flood” includes reference to “water course” and not “waterway”. 54. The Panel also notes that the relevant policy does not contain a definition of “ water course ” . 55. In these circumstances, the Panel is not satisfied it is sufficient for the hydrologist to refer to a definition of “waterway” when the relevant wording in the policy is water course. 56. For the sake of completeness, the Panel notes that the FSP‟s hydrologist appears to agree with what the FSP‟s hydrologist says i s the finding of Dr PM that “Yeungroon Creek is a named water course”. 57. As stated, although familiar with the report from Dr PM, the Panel has not, within this dispute, been provided with a copy of that report or details of the basis on which the FSP‟s hydro logist finds that Yeungroon Creek is a named water course. It is also unclear to the Panel the context in which the FSP‟s hydrologist has used the term “water course”, given that the hydrologist appears to be addressing the concept of a waterway. 58. Having had the opportunity to review the report of Dr PM in other disputes, the Panel is not satisfied that the phrase “named water course” is sufficient to satisfy the definition within the policy provisions. The Panel does not Case No: 252780 Determination Page 9 of 11 accept that simply because the Yeungroon Creek, is so named, that that of itself, makes it a water course. 59. In this regard, the Panel considers it appropriate to consider the definition of water course. 60. The following comments were made by the High Court in Gartner v Kidman [1962] HCA 27: 108 CLR 12 (30 May 1962): “This distinction between water course and depression follows the language of Hood J in Lyons v Winter (1899) 25 VLR 464, who in that case held that a depression which took rainwater for about three months of a year fell short of the legal definition of a natural water course. To constitute such a water course as a matter of law, there must be a stream of water flowing in a defined channel or between something in the nature of banks. The stream may be very small and need not run, nor need the banks be clearly or sharply defined. But there must be a course, marked on earth by visible signs, along which water usually flows in order to constitute a water course such as creates riparian rights (1899VLR at p485 (at p16). 61. Following its visit to the area, the Panel considers the area of land over which the water flowed from the south and south east of the town cannot be regarded as a water course. 62. The landscape to the south and south east of the town does not have evidence of visible banks between which water flows. The landscape may best be described as a flood plain over which water flows in a direction determined by the rise and fall of the land. 63. This view is further supported by the description given by Dr PM who observed Yeungroon Creek has been infilled with flood deposits over many years. The course of the creek to the south of the town is marked by linear depressions and vegetation. 64. In addition, the Panel has regard to the area on the Charlton/St-Arnaud Road and the flood expanse of land in the area of that road. In respect to their visit to the Charlton/St-Arnaud Road it was noted that the road had been raised to allow access to the airport during floods. It was noted that the road dissects the natural flood plain which was in the direction of the Yeungroon Creek and Avoca River. 65. A number of pipes/culverts have been positioned under the road, but the evidence from the locals who also attended, is that they were insufficient to cope with the overland flow of water and thus the flow of water is diverted initially east of Armstrong Road and eventually through the town. 66. This evidence was confirmed by observation of the section of the Charlton/St-Arnaud Road which had to be dug up during the course of the flooding of Charlton in order to release the water building up on the east side of the Charlton/St-Arnaud Road. The FOS Panel representatives were able to observe the new bitumen laid subsequent to the road being rebuilt. Case No: 252780 Determination Page 10 of 11 67. Having considered all of these matters and with the benefit of having attended on site in the area, the Panel has gained a greater understanding of the local topography and its impact on the stormwater runoff in the area, prior to arrival of the flood water from the Avoca River. 68. The Panel has also had the benefit of the evide nce presented in numerous cases arising from the weather events in Charlton in January 2011. 69. In considering all these matters, the Panel is satisfied that the Yeungroon Creek referred to in the various hydrology reports and evidence in the submissions presented by the parties, is not a water course as defined under the terms of the policy. 70. As such, the Panel is satisfied that the flow of water which entered the town from the south and south east, prior to the water from the Avoca River cannot be regarded as flood water as defined by the policy but rather the overland flow of stormwater runoff. 71. The result is that the Panel is satisfied that the property was initially inundated by stormwater during the afternoon/evening of 13 January 2011 and then inundated by stormwater runoff from the south and south east during the course of the day on 14 January 2011 and only then ultimately inundated by flood water from the Avoca River later in the day on 14 January 2011. 72. Unfortunately, because of the absence of eye witness evidence, it is not possible to precisely differentiate the inundation arising from the second and third events. 73. Having regard to clause 8.2 from the Terms of Reference, the Panel proposes to do what is fair in all the circumstances, after being informed by the evidence submitted and the conclusions of the various Determinations, both in the same street and in the same area as the property, the subject of this dispute. 74. The Panel is satisfied that an inundation to a level of 150mm above the ground across the property is fair in all the circumstances when considering the storm damage inundation. The FSP is not responsible for damage arising from any inundation above 150mm from the ground. 75. The Panel enjoins the parties to work together to agree upon and forma lise a scope of works which appropriately represents the damage which would have been caused by an inundation to 150mm above the ground of the risk address. Determination 76. The Panel determines that the FSP must indemnify the Applicants for their loss arising from an inundation to the level of 150mm above the ground at the property. Case No: 252780 Determination Page 11 of 11 77. In the event that the FSP is to cash settle any part of the Applicants‟ claim the FSP is to pay interest pursuant to the Insurance Contracts Act 1984 from the date that the claim was rejected to the date that it is settled.