Determination 250614
Declined cost of preventative works for recurring water ingress
Summary
Water repeatedly entered a bedroom and the FSP declined to pay for preventative works the applicants carried out on its advice. AFCA ordered the FSP to locate the source of the damage and pay $1,000 for consequential loss.
Where the cause of storm damage is uncertain and the insurer directed the insured to carry out works, the insurer must locate the source and may compensate consequential loss under the Terms of Reference.
Issues
- Claim denial primary · upheld
“I determine that the FSP is required to locate the source of the damage arising from the insured event of storm.”
- Inadequate claim investigation secondary · upheld
“The claim file records provide reasons for concern given the high degree of uncertainty as to whether the cause of loss ... was correct.”
- Poor communication secondary · upheld
“but for the statements made by the FSP the Applicants were unlikely to have undertaken the works they did.”
Subjects and remedies
home or building damagepay compensationreassess claim
Text of the determination
Case No: 250614 Determination Page 1 of 9
Case number: 250614
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
30 January 2012
Background
1. The Applicants hold a Home Building Insurance Policy with the Financial
Services Provider (FSP). The policy covers the building up to $519,646 and
is not subject to an excess.
2. The dispute arises from two incidents. The first occurred on 13 February
2010 and resulted in stormwater run-off entering a wall cavity into the
downstairs bedroom and onto a carpet. The FSP engaged a building
assessor who stated there was a lack of controls in place to accommodate
ground water that is entering from outside into the sub-floor area. The FSP
paid for the resultant damage and the Applicant engaged a builder “G” to
perform works to prevent a recurrence of the water inundation.
3. The second claim occurred on 25 March 2011 in which water entered the
downstairs bedroom resulting in damage to the carpets and walls. The FSP
again engaged an assessor who opined that the weep holes were lower than
ground level to front elevation and side elevation of bedroom which would
allow water ingress to cavity and contributed to damage sustained. As a
result, the FSP paid for the resultant damage.
4. The FSP has declined to make any payment for the preventative measures
required to be taken by the insured to avert any further water damage to the
home.
5. The Applicants dispute the FSP declinature on the basis they took the steps
the prior assessor suggested that they should take. The Applicants seek
financial assistance from the FSP for the new works to prevent inundation
damage.
Summary of Applicants ’ position
6. The Applicants‟ rely on the assessment report dated 25 March 2011 from
which I note the following:
Determin ation
Case No: 250614 Determination Page 2 of 9
The damage to lower bedroom has been occurring for quite some time
and there may be issues with stormwater drainage to external wall area
to lower bedroom.
The weep holes are lower than ground level to front elevation of
bedroom, which would allow water ingress to cavity and contributed to
damage sustained.
The issue should be rectified by the Applicants prior to any internal
works being carried out.
The assessor notes that if damage is present to timber wall frames
once wall lining are removed that a variation request will be submitted.
7. The Applicants rely on the assessment report dated 15 February 2010 from
which I note the following:
Inspection of the downstairs bedroom revealed that it was part of an
extension built some time ago and is adjacent to the sub-floor area.
The sub-floor area had been dug out to create a storage area this
excavation has been taken down below the footing of the main house
with no visible evidence of a drainage system to collect ground wat that
naturally flows to this area.
At the time of inspection there was water seeping through the bricks
that would be below outside ground level.
Inspection of the outside of this wall revealed the outside ground level
to be 700mm higher than the ground level of the sub-floor storage area.
The damage to the downstairs bedroom is from water.
The contributing factor to this is the lack of controls in place to
accommodate ground water that is entering from outside into the
subfloor area.
8. The Applicants rely on a report dated 3 May 2011 from their builder “G”. I
note G provided the following information:
“Our company carried out concrete works at [Applicants‟ address]. The work
involved removing existing brick pavers, stepping stones set in with pebbled
borders. This was on the eastern side of the residence and was not layed (sic)
out in a way which stormwater would run out and away from the adjacent
brick wall. The work we carried out as instructed by the owners of the property
was to remove the existing footpath and stepping stone path and replace with
a new concrete footpath which was to fall away from the eastern side of the
house and to an adjoining stormwater system in the rear area of the house.
The new footpath was layed (sic) out so that stormwater run-off would fall
away from the house brickwall and across to the eastern boundary fence then
fall out to the back yard area into a 90mm stormwater pipe and into adjoining
stormwater pipes. All this work was carried out in a professional manner and
completed as per the instructions we had been set to achieve.”
9. The Applicants were informed verbally by the assessor for the 17 February
2010 incident that the damage was caused by „surface water and drainage‟
but were never provided with his report. The Applicants accordingly spent
Case No: 250614 Determination Page 3 of 9
$6,000 laying a new concrete path based on the verbal information provided
by the first assessor.
10. On 28 March 2011 a second claim was made for further water damage
occurring to the same room. The FSP‟s new assessor provided a different
opinion as to the cause of damage.
11. The Applicants submit that the first report was misleading and caused a
financial detriment to them. In particular, the first report from 2010 stated
there was a problem with surface and ground water. The second report
states a different reason for the inundation.
12. The crushed stone pathway was damaged by the water and is not the cause
of water inundation, it is actually a separate claim.
13. As a result of the second report the Applicants must now remove part of the
concrete pathway and have to engage an independent builder and plumber
to rectify the problem at considerable cost to them.
14. The Applicants seek assistance with the costs to be incurred by them.
Summary of FSP’ s position
15. The FSP relies on the following policy terms and conditions:
“Storm
If loss or damage is caused by a storm.
For example, hail damages your roof or a storm in your local area may cause
water to build up in your street gutters.
Covered
- Violent wind, cyclone or tornado
- Thunderstorm, hail, rain or snow
- Sudden, excessive run-off of water as a direct result of a storm in your
local area.”
16. The FSP relies on its claim file records from which I note the following:
On 22 February 2010 the Applicants were told that the contributing
factor to the damage was the lack of controls in place to accommodate
ground water that is entering from outside into the sub-floor area. The
Applicants were also told to have the matter attended to.
I note that the second assessor is questioned carefully by the FSP on
21 April 2011. The assessor was informed the damage was fixed and
responded that the Applicant knew of the ongoing issue. However the
assessor then states that “we do not know exactly where the water is
entering however at our discretion whether we accept the internals or
not.”
Case No: 250614 Determination Page 4 of 9
After being informed of the first assessor‟s opinion, the second
assessor advised the FSP that it may be a combination of issues. The
Applicants have rectified one problem but there is still another issue.
The only method to properly determine the issues would be a dye test.
The second assessor stated there was an issue with the weep holes as
they should be situated higher. However, when told that the Applicants
had inserted a hose in one of the weep holes with nothing occurring,
the assessor noted that there was no guarantee there was an issue
with the sub-drainage that the Applicant had repaired.
After being informed of the second assessor‟s opinion, the first
assessor stated the builders have done preventative repairs to control
the storm water run-off but that is not controlling the sub-surface water.
The Applicants would need to excavate the side of the home and have
waterproofing membrane installed to control subsurface water. The first
assessor did not believe a dye test would assist.
17. The FSP submits that it has accepted resultant damage but the preventative
measures in relation to the property are the responsibility of the Applicant.
18. The first report clearly states that the contributing factor to water ingress is
the lack of controls in place to accommodate ground water entering from
outside into the subfloor area.
19. The second report concurs with the first report and adds that there are weep
holes lower than ground level to front elevation and side elevation of the
bedroom which would allow water ingress to the cavity and contributed to
damage sustained.
20. The preventative damage required to the property is not an insured event
within the policy and accordingly the policy does not respond.
21. There is no evidence that the first assessor provided the wrong advice to the
Applicants. It was for the builder G to responsibly advise the Applicants. The
FSP has noted that the Applicants instructed G regarding the works.
22. The Applicants have not provided any documentation or independent
assessment to disprove the assessors ‟ findings regarding the damage.
Issue
23. Whether the FSP is required to make payment for the Applicants‟
consequential losses.
Reasons for Determination
24. There has been an exchange of material between each party, and I am
satisfied each party has had an opportunity to reply to the issues raised.
Case No: 250614 Determination Page 5 of 9
25. I have read each party‟s sub missions and materials and will only refer to the
relevant submissions and materials raised.
26. I consider the following Terms of Reference relevant to this Determination:
“8.2 Dispute resolution criteria
Subject to paragraph 8.1, when deciding a Dispute and whether a remedy
should be provided in accordance with paragraph 9, FOS will do what in its
opinion is fair in all the circumstances, having regard to each of the following:
legal principles;
applicable industry codes or guidance as to practice;
good industry practice; and
previous relevant decisions of FOS or a Predecessor Scheme (although FOS
will not be bound by these)
...
9.3 Other compensation
Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential
financial loss or damage up to a maximum amount of $3,000 per claim made
in the Dispute
...
Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the
Financial Services Provider Compensate the Applicant for non-financial loss
but only where:
An unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant‟s expectation of enjoyment or
peace of mind has occurred; or
In the case of a Dispute pertaining to an individual‟s privacy rights – injury has
occurred to the Applicant‟s feelings or humiliation has been suffered by the
Applicant.
The maximum amount of compensation for non-financial loss will be $3,000
per claim made in the Dispute.
Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation
for:
Consequential financial loss; or
Non-financial loss,
In a Dispute arising as a result of a claim on a General Insurance Policy that
expressly excludes such liability
...
9.6 Other types of damages
Punitive, exemplary or aggravated damages may not be awarded.”
27. I consider the following policy terms and conditions relevant to a
consideration of this claim:
“Locating the cause of damage
Case No: 250614 Determination Page 6 of 9
If a listed event causes loss or damage to your home and you need to confirm
that it was confirmed by a listed event:
Covered Under Buildings Insurance
- The reasonable costs you have paid to find the cause of damage if we
agree that the loss or damage was caused by a listed event.
...
Meeting building regulations
If a listed event causes loss or damage to your home and you need to meet
current building regulations to rebuilt or repair part of your home that was
damaged
Covered under Buildings Insurance
- The costs to meet current building regulations to repair or rebuild the
part of your home that was damaged.
Not covered
- Costs to meet building regulations:
- that were already in place when your home was built, renovated or
altered.
- for undamaged parts of your home – for example installing insulation in
ceilings that were not damaged.
...
General exclusions
...
Faulty design or workmanship that you knew about or should have reasonably
known about.”
28. There is no dispute regarding payme nt for the internal damage. The dispute
centres on whether the Applicants are entitled to consequential loss as a
result of the information provided by the first assessor, being works which
failed to prevent a recurrence of the loss and requirement of additional
works.
29. It is the FSP‟s contention that the reports did not provide incorrect
inf ormation, it was the Applicants‟ responsibility to arrange works to prevent
inundation and the Applicants‟ builder was responsible for performing the
works.
30. The Applicants state that they were not provided with the first assessor‟s
report until after the second event in 2011. The Applicants state they were
verbally informed of the works which needed to be completed. That is, the
damage was occurring from surface and ground water.
31. The first assessor report confirms the insured has been advised of the next
steps in the process but then there is a statement that the insured was not
aware of any repairs they are responsible for. I also note with concern that
the first assessor provides only general information in the scope of works
which is „lack of controls i n place to accommodate ground water that is
Case No: 250614 Determination Page 7 of 9
entering from outside into the sub- floor area‟ . There are no suggested
controls which should prevent the reoccurrence of the loss.
32. I further note that there is no statement from the first assessor stating his
recall of the conversation with the Applicants which would rebut their
submission they were informed it was a surface and ground water issue.
33. There are notes in the claim file records indicating that the Applicants were
directed to attend to works by the FSP. The FSP did inform the Applicants
that it was ground water entering from outside into the sub-floor area.
34. The Applicants have then engaged G and instructed him to perform works
presumably to prevent surface run-off and/or ground water from this area
inundating the property. This would explain the change to the fall of the path
away from the home and supporting plumbing work. It is unclear from their
submissions however what precisely the Applicants have instructed G to do.
However, G does states “works... completed as per the instructions we had
been set to achieve.” I do consider from the works performed by G and the
amount expended by the Applicants that they undertook the works in good
faith and in the belief that the works would prevent the recurrence of
damage.
35. The second assessor has stated the cause of damage may be to do with
issues with stormwater drainage to the external wall area to lower bedroom.
Further that the weep holes are lower than ground level. The assessor
considered that these works should be completed prior to internal works
being carried out.
36. It becomes apparent from the claims file records that the assessors not only
disagree as to the cause of the loss but that further investigation is required
given there is uncertainty regarding the cause of the loss. This is reflected in
the assessment reports which provide no firm scope of works to rectify the
issue(s). I do not consider that the reports necessarily support one another,
particularly given the statements by the assessor in the claim records that
they are uncertain as to the cause of the loss.
37. I note that the Applicants believed that they were carrying out works at the
direction of the assessor and/or FSP. The works directed surface run-off
away from the building. Given that a new claim has arisen it now appears
that the works have not affected the recurrence of water inundation.
38. It seems to me quite unreasonable to have required the Applicants to repair
an issue at some expense and at the FSP‟s direction when the source of
inundation had not been properly identified. It is for this reason the
Applicants have sought financial assistance or compensation from the FSP.
39. The policy further allows for the costs to locate the cause of the damage for
an insured event. There is no dispute between the parties that the damage
occurs during heavy rainfall from stormwater run-off as well as potential
ground water. An insured event is therefore causing the damage; it is the
Case No: 250614 Determination Page 8 of 9
mechanism of the inundation which is still unknown. The Applicants are
entitled to claim for the cost of locating the cause of the damage.
40. The damage would not be excluded as the Applicants could not reasonably
be declared as being reasonably aware of the cause of the loss considering
the assessors have not been able to firmly ide ntify the cause of the loss and
in fact the claim records suggest that further testing may be required in order
to do so. Further, the Applicants believed that they had fixed the issue.
41. I further note that the policy covers costs to meet building regulations to
repair or rebuild part of the home that was damaged. Accordingly, if the
timber walls are damaged, and the building was built to appropriate
standards as of the time of construction, then the Applicants are entitled to
this loss and any costs to meet current building regulations.
42. The claim file records provide reasons for concern given the high degree of
uncertainty as to whether the cause of loss stated by the assessors, on
which the declinature of the building damage was based, was actually
correct.
43. Despite this the Applicants were still directed to conduct repairs for this
mechanism of inundation. Given this, I consider the application of Terms of
Reference 9.3 and 8.2 should be considered.
44. The policy does not provide an exclusion for consequential loss under the
General Exclusions. Accordingly, it is open to me to consider the loss
requested by the Applicants.
45. I consider that but for the statements made by the FSP the Applicants were
unlikely to have undertaken the works they did. The works performed and
the subsequent failure of these works to prevent a recurrence of the damage
would cause a great deal of frustration and upset to the Applicants. I note
that some accountability does rest with G for the works to be completed
appropriately however there is no suggestion G has improperly performed
the works. I am not minded to order the FSP bear the entire cost of the
works because if the building works has ameliorated the occurrence of the
damage then the Applicants have received a benefit from these works.
46. I consider a contribution in the order of $1,000 is fair and reasonable in all
the circumstances. I should add that on 11 January 2012, I invited the FSP
to respond as to whether an award under para 9.3 of the Terms of
Reference might be made. On 12 January 2012, the FSP replied saying that
it wished to make no further submission.
Determination
47. On the basis of the available information, I determine that the FSP is
required to locate the source of the damage arising from the insured event of
storm.
Case No: 250614 Determination Page 9 of 9
48. If the cause of damage is covered under the policy terms and conditions, the
FSP will be responsible for meeting the cost of compliance with current
building regulations, as to the area the subject of the damage.
49. The FSP make payment of $1,000 to the Applicants in compensation for
their consequential loss.