Home / Financial Firm (Unknown - Insurer) / Determination 247135

Determination 247135

Denial of flood inundation claim at Yeronga home and contents

FirmFinancial Firm (Unknown - Insurer)
Decided2012-10-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants' Yeronga home and contents were inundated in January 2011 and the FSP denied the claim as flood. The Panel found flash flood cover applies to damage to about 0.2m above floor level, subject to policy limits, with interest payable and the balance excluded.

Inundation within 24 hours of heavy rain at Wivenhoe Dam is flash flood covered by the policy only to the extent of the early inundation, and the later flood damage is excluded.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 247135 Determination Page 1 of 12 Case number: 247135 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 27 September 2012 Background 1. The Applicants insured their home and contents in Yeronga with the Financial Services Provider (FSP). The relevant period of insurance operated for twelve months beginning from 21 Dec 2010. During this period, the building was insured up to a sum of $430,000 and the contents for $269,000. 2. On 14 January 2011, the Applicants lodged a claim under the policy due to extensive water inundation following severe weather events in Queensland. 3. The FSP denied the claim on the basis the damage was due to “flood”. 4. Both the Applicants and the FSP have provided detailed submissions on the relevant issues. For the sake of brevity, the Panel will summarise these submissions given all of the material made available has been exchanged with the other party. Summary of Applica nts’ position 5. The Applicants are represented by legal representatives and for the sake of simplicity reference to the Applicants includes reference to their solicitors. 6. The Applicants submit the following as alternative arguments in response to the FSP’s d ecision: a. They accept that the FSP’s policy states that “flood” is excluded but say that the definitions for “Flood”, “Flash flood and stormwater run - off”, and “Storm” are contradictory and confusing and that the FSP has therefore failed to clearly inform them that “flood” was excluded as required under Section 35 of the Insurance Contracts Act 1984 (the Act). b. The damage was due to the insured event of “Flash flood and stormwater run- off”. In particular, the inundation was due to heavy rain that fell from 4am on 11 January 2011 which resulted in the Wivenhoe Dam operators elevating their strategy to W4. This decision resulted in massive discharges of water into the Brisbane River that ultimately inundated her property. Determination Case No: 247135 Determination Page 2 of 12 c. The FSP is unable to discharge its onus in establishing the loss was caused by “flood”. 7. The Applicants seek to be indemnified for their claim. Summary of FSP’s position 8. In response to the Applicants’ arguments, the FSP has provided evidence from an appropriately qualified individual to corroborate that a PDS was sent to the Applicants prior to the claim. Further, it says that the policy structure and layout in conjunction with this evidence enables it to rely on the exclusion clause of “flood” pursuant to Section 35(2) of the Act. 9. The FSP relies on a number hydrology reports authored by SC and the following policy provisions to deny the Applicants’ claim: Page 3 of the Certificate of Insurance (COI) “ What optional covers are included and not included Home Contents ... Flood and storm surge not included not included...” Pages 10-12 of the PDS “ Words / terms with special meanings Word / term Meaning ... Flood Rising water which enters your home as a result of it running off or overflowing from any origin or cause. This policy does not cover flood unless we have agreed and it is shown on your certificate of insurance. Flash flood and stormwater run - off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run - off . ... Storm A violent disturbance of the atmosphere associated with strong winds including a cyclone, lightning, heavy rain, hail or snow, but not continuous bad weather by itself. ...” Pages 17-18 of the PDS “ Insured events you are covered for Case No: 247135 Determination Page 3 of 12 Damage caused by weather... What is covered What is not covered Storm Loss or damage:  caused by rain, hail or snow after it has reached the ground... ... Flash flood and stormwater run-off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run - off Loss or damage caused:  by flood... ...” Page 27 of the PDS “ Your home The most we will pay you for home claims What is covered What is not covered Flash flood and stormwater run-off We will pay up to 50% of your home sum insured or $25,000, whichever is higher. ... ...” Page 32 of the PDS “ Your contents The most we will pay you for contents claims What is covered What is not covered ... ... Flash flood and stormwater run-off We will pay up to 50% of your contents sum insured or $25,000, whichever is higher, but not exceeding your contents sum insured. ... ...” Page 48 of the PDS “ Optional covers for extra peace of mind The covers outlined in this section are optional and do not apply unless you have asked for them and we agree to cover you. Additional premiums apply for each cover. Your certificate of insurance will show which covers operate. All optional covers are subject to the terms and conditions of this policy.” Case No: 247135 Determination Page 4 of 12 Page 53 of the PDS “ Optional covers for extra peace of mind What is covered What is not covered Flood and storm surge This policy does not cover flood unless we have agreed and it is shown on your certificate of insurance. Home and/or contents cover We cover you for loss of or damage to your home or contents caused by flood or storm surge which happens during the period of insurance at the property address. We will pay up to the:  home sum insured, if your home is insured;  contents sum insured, if your contents are insured for damage caused by flood or storm surge, We will pay for loss or damage in the same way and in the same amounts as we do under insured events cover. We will not pay for loss or damage to:  paths, driveways, paving, retaining walls (whether or not part of the home), tennis cou rts or other playing surfaces;  shade or sail cloth;  fabric awnings, swimming pool and spa covers or liners and the like;  glasshouse whether or not constructed principally of glass;  water in swimming pools or spas... ...” Issues 10. Whether the Applicants were “clearly informed” about what the policy did and did not cover. 11. Whether the cause of the Applicants’ loss was covered under the policy. Reasons for decision 12. Due to the nature of the dispute, the parties have been informed that the matter has been referred to the Panel for Determination in line with the Operational Guidelines to FOS’s Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 13. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 14. It is appropriate to consider the issues under the various headings. Case No: 247135 Determination Page 5 of 12 Consideration of "Flood" Definition in PDS 15. The Applicants have argued that the policy fails to clearly inform as to the derogation from flood cover and the limitations on the extent of cover for flash flood. There is no dispute that the Applicants had received the policy documentation and Certificate of Insurance. 16. It is established law that in order to satisfy the requirement to clearly inform, the language of section 35 (2) allows for a proposed insured to be clearly informed by providing the relevant documentation in writing and that the relevant exclusion and/or limitation in this case is clear and unambiguous and presented in a manner which a person of average intelligence and education is likely to have little difficulty in finding and understanding if that person reads the policy in question. 17. The Panel has reviewed the FSP’s policy on a number of occasions. The policy is indexed with relevant sections covering the insured events. The policy sets out the definitions of storm and flash flood and stormwater run- off. The policy clearly identifies that flood and storm surge is an optional cover but otherwise flood is excluded from cover. The Certificate of Insurance also clearly identifies that with respect to the Applicants’ policy flood and storm surge is not covered. 18. Having considered the Applicants’ submissions and the FSP’s policy documents, the Panel is satisfied that the FSP has met its obligations to clearly inform the Applicants of the extent of the exclusions and limitations in accordance with the requirements of the Act. Water Inundation The Evidence 19. The Applicants say that right outside their front gate there is a stormwater drain which regularly backs up if there is a heavy storm. 20. In her 12 March 2012 submission, the female Applicant states that she left the property at approximately 2-3am on Wednesday 12 January 2011 and at that stage, water had started coming out of the stormwater drains. She believes that it is likely her property was inundated shortly after she left the property. 21. After the lodgement of the claim, the FSP appointed a loss adjuster (MY) to investigate and report on the damage caused to the Applicants’ property. The report stated that the Applicants’ home was inundated to a depth of 1730 mm. 22. Amongst the factual information, MY suggested that water first e ntered the property at approximately 2pm on 11 January 2011. This does not accord with the female Applicants’ statement or the report from the hydrologist. MY also states that the loss was discovered on 11 January 2011, but has noted that the date of loss was 12 January 2011, this is clearly incorrect. Case No: 247135 Determination Page 6 of 12 23. MY stated that the Applicants’ property is located 100m from the Brisbane River and considered that the cause of the loss was the river “breaking its banks” and “the backup of the stormwater drainage which could discharge” (sic). 24. Given the inconsistencies and lack of clarity the Panel is of the view that MY’s report has little value and cannot be relied upon. 25. The FSP subsequently engaged a hydrologist, SC, to provide a report as to the damage. 26. SC provided a statutory declaration dated 6 October 2011 to evaluate the cause of the loss in the region surrounding and specifically affecting the Applicants’ home. He found that:  A substantial amount of rain fell in the greater Brisbane area from 9 January 2011 and over the subsequent two days, which caused significant inflows into the Wivenhoe Dam, which peaked on the evening of 11 January 2011;  Rain also fell in the area of the Bremer River from 6am on 11 January 2011. This rain travelled along the Bremer River to the junction of the Brisbane River and ultimately contributed about 15-25% of its peak flow;  A “small proportion” of the overall depth of the Brisbane River “may be partially attributable to the rain that fell in the Bremer River catchment on 11 January 2011”, although the “overwhelming influence” was the rain that had fallen in the previous days.  The terrain data for the Applicants’ home suggested that it was unlikely that the Applicants would have experienced significant stormwater or run- off problems during the period;  Inundation from stormwater run- off requires “intense levels of rain” which is sufficient to overcome the stormwater drainage system. Any such run-off generally occurs during or very shortly after such an intense period of rainfall;  A review of the rainwater gauge at Corinda High Alert Station, approximately 4 km from the Applicants’ property and representative of its rainfall in the expert’s opinion, revealed that 81 mm of rain fell between 9 and 10 January 2011, with a further 47 mm falling on 11 January 2011 and the most intense rainfall on 11 January 2011 occurring at approximately 11am. From 6pm on 11 January 2011 until 15 January 2011, a total of 2mm of rain was recorded;  The overall intensity of the rainfall was very low and unlikely to result in run-off or stormwater inundation to the property;  The water level of the Brisbane River at 2pm on 11 January 2011 (the time of the inundation of the Applicants’ property according to the MY Case No: 247135 Determination Page 7 of 12 report) was well below the minimum level of the property as shown in the Brisbane City Council Floodwise Report. As neither the rainfall intensity nor the river water level at that time would have been sufficient to cause inundation of the property, SC believes that the time of inundation included in the MY report is incorrect;  By comparing the Brisbane River water level information to the height of the Applicants’ property, SC says that the inundation of the property would have occurred at about 3am on 12 January 2011.  Given the low intensity rainfall over the pe riod, any backflow from the stormwater drains outside the front of the property would have been due to the rising level of the Brisbane River rather than stormwater or other local runoff. 27. Based on the evidence submitted the Panel concludes that on the bala nce of probabilities that Applicants’ premises would not have been inundated by stormwater runoff. Releases from Wivenhoe Dam & Proximate Cause 28. Although flood is generally excluded under the FSP’s policy, cover is provided for a particular type of flood, being flash flood. In order for a claim to fall within the insured event of Flash flood and stormwater runoff, the following elements must be established: a. There was a sudden flood; b. There was a heavy rain that occurred within 24 hours prior to that flood; c. The sudden flood was caused by that heavy rain. 29. Therefore, the central issue for Determination in this dispute is whether the inundation of the Applicants’ home on 12 January 2011 was due to flash flood as defined within the terms of the policy, that is whether rain that fell no more than 24 hours prior to the inundation of the Applicants’ property was the proximate cause of the inundation. 30. On 21 May 2012 FOS issued a memorandum to all relevant stakeholders advising that after considerable deliberation of all material available to it, the Panel formed a view that the heavy rain occurring from approximately 4.00am on 11 January 2011 and in particular the heavy rain between 4.00am and 8.00am on 11 January 2011 was a proximate cause of the W4 strategy being invoked and therefore a proximate cause or trigger that led to the flooding of many of the properties along the Brisbane River. 31. At that time, the Panel noted that in relation to the approach that each dispute would depend upon the individual and unique factors relevant to the dispute and in that regard the parties were invited to make further submissions in relation to disputes before FOS. Case No: 247135 Determination Page 8 of 12 32. In view of this, the FSP provided detailed further submissions to FOS on 18 June 2012 in relation to this dispute. Included with the submissions were the following documents:  A Reference document for disputes relating to Queensland Floods (this is a general reference document) relating to the various submissions the FSP makes in relation to a number of issues. Not all issues raised in the reference document appear in the current dispute;  Letter from the FSP’s hydrologist attaching a key information sheet for the Applicants’ property;  Hydrologist report “Investigations of January 2011 inundation event – Brisbane” dated March 2011;  Statement from hydrologist dated 7 June 2012. 33. The FSP has since provided revised Reference documents the latest dated 28 August 2012. 34. In summary the FSP argues that the proximate cause of the inundation of the properties, that is the real or effective cause of the damage caused to the properties downstream of the dam, is not simply the rain that occurred from 4.00am on 11 January 2011 but the combined effect of all of the rainfall and not just the rain that had fallen from 4.00am on 11 January 2011 leading to the implementation of the W4 strategy from 8.00am that day. 35. There is no dispute that heavy rain fell over the Wivenhoe Dam catchment area and in fact parts of the Brisbane River from approximately 4.00am on 11 January 2011. It is not disputed that in addition to this there was heavy rain over the Bremer River which influenced the level of the Brisbane River and that rain commenced at approximately 6.00am on 11 January 2011. 36. The FSP’s hydrologist relied on data from SEQWater dated 2 March 2011 which confirms the rapid increase in releases from the Wivenhoe Dam from 8.00am on 11 January 2011. Examination of the SEQWater report identifies the rapid increase in the inflows to the Wivenhoe Dam commencing from about 4.00am, 11 January 2011. The report confirms the inflows into the dam had been decreasing from as early as 8.00am from 10 January 2011 with steady decreases from approximately 3.00pm on 10 January 2011 to 2.00am on 11 January 2011. 37. The Queensland Flood Commission of Inquiry report confirms that prior to 4.00am on 11 January 2011 and in fact prior to 8.00am of 11 January 2011 the dam releases were being managed at the W3 strategy. Whilst it is accepted that the W3 strategy had led to an increase in the levels of the Brisbane River, the W3 strategy was designed to avoid where possible inundation of the properties below the Wivenhoe Dam by flooding from the Brisbane River. 38. There is no dispute that there were two significant rainfall spikes with rain that fell from 9 to 10 January 2011 being considered the first spike and rain Case No: 247135 Determination Page 9 of 12 that commenced falli ng from approximately 4.00am on 11 January 2011 being the second spike. 39. There is no dispute that following the second spike that the W4 strategy was adopted. The FSP has argued that the switch to strategy W4 was not the natural and ordinary consequence of the rain that fell and in fact the move to W4 strategy was not taken in accordance with the Wivenhoe Dam manual. In the Panel’s view, the Queensland Flood Commission of Inquiry final report does not find the adoption of W4 strategy at 8.00am on 11 January 2011 was inconsistent with the manual. Although there may be issues as to how the Wivenhoe Dam had been managed prior to this time, there is nothing in the material that has been provided to the Panel to suggest that the earlier management of the Wivenhoe Dam influenced to any significant degree, the adoption of the W4 release strategy at 8.00am on 11 January 2011. 40. The Insurance Council of Australia (ICA) hydrology report and the information provided by the FSP’s hydrologist confirms that the increased releases from the Wivenhoe Dam after the adoption of the W4 strategy led to the development of a flood wave that ultimately caused the flooding of many properties downstream of the Wivenhoe Dam. 41. In determining the proximate cause of the inundation it is necessary to look at the effective or dominant cause of the inundation. The Panel agrees with the FSP’s general submission that the proximate cause is a cause determined by common sense evaluation of the relevant facts. In the event that there are two or more proximate causes, one within the policy and the other excluded, the policy does not respond. The proximate cause is not determined by identifying the last event or final trigger but by determining what is the dominant, effective, direct or efficient cause of the loss. 42. The FSP has maintained that the impact on the Wivenhoe Dam from the rainfall that fell in the early hours of 11 January 2011 was only 29% while 71% of the volume of the inflow came from the rain that fell on 9 and 10 January 2011 or earlier. The FSP maintains that to find the rainfall which had fallen from 4.00am on 11 January 2011 is the proximate cause is without foundation as such an approach produces an entirely artificial outcome. 43. With due respect to the FSP’s argument the Panel disagrees. W hilst the Panel accepts there has been a significant impact on the levels of the Wivenhoe Dam by the rainfall that commenced falling on or about 9 January 2011 or earlier, the Panel is satisfied having regard to the information that has been exchanged and the relevant legal principles, that the heavy rain which commenced falling on or about 4.00am on 11 January 2011 was a proximate or effective cause of the adoption of the W4 strategy. 44. The Panel accepts that the heavy rain that commenced falling around 4.00am on 11 January 2011 over the Wivenhoe Dam and Brisbane River combined with the heavy rain that commenced falling over the Bremer River at 6.00am that day was the cause of the inundation of the Applicants’ property. Case No: 247135 Determination Page 10 of 12 The Applicants’ Inundation 45. The FSP’s hydrologist SC provided a summary “Key Conclusions Statement ” on 7 June 2012 which provides a basis for determining the impact of the river levels on the Applicants’ home. 46. SC’s statement indicates the effect of the W4 releases first reached the vicinity of the Applicants’ property at 2.44pm on Tuesday 2011. He estimated that the property was first inundated by the Brisbane River to the bench mark level at 2.57am on 12 January 2011 and by 4am the same day, the property was inundated up to 0.2m above the relevant benchmark level. 47. According to the Key Conclusions Statement, the minimum land of the Applicants’ property was 6.3m AHD with the approximate benchmark level at 6.6m AHD. According to the Key Conclusions Statement W4 releases first reached the vicinity o f the Applicants’ property at 2.44pm on Tuesday 11 January 2011 although the Statement does not indicate what is meant by the vicinity. By 4am on 12 January 2011 the river level was approximately 6.8m AHD which is approximately 0.2m above the benchmark level. 48. The Panel has some concern as to the calculation of these estimates and accepts the possibility that these estimates may not be entirely accurate. The Applicants have described leaving the property around 2-3am with water coming up through the drains at that time. Given this is relatively consistent with the hydrology information, the Panel most likely accept that the Applicants’ property was first inundated above floor level at some stage prior to 4am on 12 January 2011 and at 4am on 12 January 2011 was inundated to a height of approximately 0.2m above floor level. 49. On this basis, damage caused by the inundation up to 0.2m above floor level occurred within 24 hours of the rain which fell from 4am on 11 January 2011 and as such the FSP has required to indemnify the Applicants for such damage. 50. The Panel notes that the peak level of inundation of 2.4m above benchmark occurred well outside of the 24 hour flash flood period and therefore outside the coverage provided by the policy. As such the FSP is not liable for damage incurred by the inundation after 4.00am 12 January 2011 as this is outside the relevant 24 hour period. Quantum 51. The Renewal Certificate of Insurance provides a sum insured of $430,000 for the home with contents of $269,000. The Panel notes that damage caused by flash flood is subject to the policy limit of 50% of the sum insured or $25,000 (whichever is the greater) for each of the building and contents. Pursuant to the policy cap, the FSP is liable up to an amount of $215,000 for the damage to the building and $134,500 for the contents. Case No: 247135 Determination Page 11 of 12 52. Given the time since the loss was sustained, the Panel accepts that the parties may be unable to provide an exact estimate of the total loss sustained, or a breakdown of that loss. 53. The Panel accepts that significant damage to contents would have occurred as a result of inundation up to 0.2m above floor level and significant damage to the building would have also have occurred. It is likely that inundation at that level would have caused damage to the flooring, cupboards, appliances both internal and external, electrical wiring, etc. It is however impossible to assess the extent of this damage and the parties are asked to work cooperatively together to establish the extent of the loss sustained to the property and reach agreement as to the cost of the repairs to the home and replacement of the various contents lost or damaged as a result of inundation to a level of 0.2m above floor level. 54. Insofar as the FSP may have made payment of a compassionate sum to the Applicants, FOS does not have jurisdiction to deal with this payment but acknowledges that the FSP, given the terms on which the compassionate payment was made, may be entitled to deduct this payment from any settlement sum. 55. The Panel has also considered the issue of interest. 56. The FSP has argued that interest is only payable from the date from which it was unreasonable to withhold payment. The FSP maintains that it is entitled to a reasonable period to investigate and determine its position, and given the complex nature of the flood disputes, the delays are not unreasonable. Further complex situations require substantial periods of time for independent bodies such as the Queensland Flood Commission of Inquiry and FOS, to make conclusions on the issues in dispute. 57. The FSP maintains that it did not act unreasonably in this dispute and therefore interest is not payable. Alternatively if some period of interest is to be awarded it should be reduced to account for the substantial delays through the course of the proce ss which were not the FSP’s fault. 58. Section 57 of the Insurance Contracts Act requires interest be paid when it becomes “unreasonable for the insurer to have withheld payment”. An examination of relevant case law indicates that most probably, interest will be awarded from either when an insurer first emphatically denied liability or disputed a matter, or from when in the normal course of events the claim should have been paid if liability had not been disputed. 59. In this dispute the Panel accepts that the FSP was entitled to withhold payment of the settlement monies until such time as it had properly investigated the dispute and made its decision as to liability. 60. The FSP made its original decision to deny the claim after receiving relevant assessment reports, hydrology reports and other information. The FSP was aware of the terms of its policy and aware of the relevant provisions under Case No: 247135 Determination Page 12 of 12 which liability might arise and chose to deny the claim having reviewed those relevant provisions and the evidence available to it. 61. In the Panel’s view, at that point the FSP has made its decision on the claim and it is appropriate that from that time interest be paid unless it can be established that the Applicants had withheld information from the FSP that would have led to an alteration of its decision. 62. Accordingly, the Panel determines that it is appropriate that the FSP in this dispute pay interest from day upon which the FSP determined to deny liability of the Applicants’ claim, until payment of the claim. Determination 63. On the basis of the available information the Panel determines that the FSP is to meet the cost of repairs incurred by the Applicants and the cost of the replacement of items damaged as a result of the inundation of the property. Any payment is subject to the limitations of the policy and agreement as to the extent of loss attributable to flash flood throughout the Applicants’ home to a level of approximately 0.2m above floor level. 64. In the event that the parties are unable to agree as to the extent of the loss attributable to flash flood, the parties may make further submissions to the Service and the Panel will determine the quantum of the claim. 65. Insofar as the FSP is to cash settle the claim, the FSP is to pay interest from 24 March 2011 (being the date of rejection of the claim) to date of payment of the claim, in accordance with Section 57 of the Act.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.