Text of the determination
Case No: 247135 Determination Page 1 of 12
Case number: 247135
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
27 September 2012
Background
1. The Applicants insured their home and contents in Yeronga with the
Financial Services Provider (FSP). The relevant period of insurance
operated for twelve months beginning from 21 Dec 2010. During this period,
the building was insured up to a sum of $430,000 and the contents for
$269,000.
2. On 14 January 2011, the Applicants lodged a claim under the policy due to
extensive water inundation following severe weather events in Queensland.
3. The FSP denied the claim on the basis the damage was due to “flood”.
4. Both the Applicants and the FSP have provided detailed submissions on the
relevant issues. For the sake of brevity, the Panel will summarise these
submissions given all of the material made available has been exchanged
with the other party.
Summary of Applica nts’ position
5. The Applicants are represented by legal representatives and for the sake of
simplicity reference to the Applicants includes reference to their solicitors.
6. The Applicants submit the following as alternative arguments in response to
the FSP’s d ecision:
a. They accept that the FSP’s policy states that “flood” is excluded but say
that the definitions for “Flood”, “Flash flood and stormwater run - off”, and
“Storm” are contradictory and confusing and that the FSP has therefore
failed to clearly inform them that “flood” was excluded as required
under Section 35 of the Insurance Contracts Act 1984 (the Act).
b. The damage was due to the insured event of “Flash flood and
stormwater run- off”. In particular, the inundation was due to heavy rain
that fell from 4am on 11 January 2011 which resulted in the Wivenhoe
Dam operators elevating their strategy to W4. This decision resulted in
massive discharges of water into the Brisbane River that ultimately
inundated her property.
Determination
Case No: 247135 Determination Page 2 of 12
c. The FSP is unable to discharge its onus in establishing the loss was
caused by “flood”.
7. The Applicants seek to be indemnified for their claim.
Summary of FSP’s position
8. In response to the Applicants’ arguments, the FSP has provided evidence
from an appropriately qualified individual to corroborate that a PDS was sent
to the Applicants prior to the claim. Further, it says that the policy structure
and layout in conjunction with this evidence enables it to rely on the
exclusion clause of “flood” pursuant to Section 35(2) of the Act.
9. The FSP relies on a number hydrology reports authored by SC and the
following policy provisions to deny the Applicants’ claim:
Page 3 of the Certificate of Insurance (COI)
“ What optional covers are included and not included
Home Contents
...
Flood and storm surge not included not included...”
Pages 10-12 of the PDS
“ Words / terms with special meanings
Word / term Meaning
...
Flood Rising water which enters your home as a result of it
running off or overflowing from any origin or cause.
This policy does not cover flood unless we have
agreed and it is shown on your certificate of insurance.
Flash flood and
stormwater run - off
A sudden flood caused by heavy rain that fell no more
than 24 hours prior to the flash flood or stormwater
run - off .
...
Storm A violent disturbance of the atmosphere associated
with strong winds including a cyclone, lightning, heavy
rain, hail or snow, but not continuous bad weather by
itself.
...”
Pages 17-18 of the PDS
“ Insured events you are covered for
Case No: 247135 Determination Page 3 of 12
Damage caused by weather...
What is covered What is not covered
Storm Loss or damage:
caused by rain, hail or snow
after it has reached the
ground...
...
Flash flood and stormwater run-off
A sudden flood caused by heavy rain
that fell no more than 24 hours prior to
the flash flood or stormwater run - off
Loss or damage caused:
by flood...
...”
Page 27 of the PDS
“ Your home
The most we will pay you for home claims
What is covered What is not covered
Flash flood and stormwater run-off
We will pay up to 50% of your home sum
insured or $25,000, whichever is higher.
...
...”
Page 32 of the PDS
“ Your contents
The most we will pay you for contents claims
What is covered What is not covered
... ...
Flash flood and stormwater run-off
We will pay up to 50% of your contents
sum insured or $25,000, whichever is
higher, but not exceeding your contents
sum insured.
...
...”
Page 48 of the PDS
“ Optional covers for extra peace of mind
The covers outlined in this section are optional and do not apply unless you
have asked for them and we agree to cover you. Additional premiums apply
for each cover. Your certificate of insurance will show which covers operate.
All optional covers are subject to the terms and conditions of this policy.”
Case No: 247135 Determination Page 4 of 12
Page 53 of the PDS
“ Optional covers for extra peace of mind
What is covered What is not covered
Flood and storm surge
This policy does not cover flood unless
we have agreed and it is shown on your
certificate of insurance.
Home and/or contents cover
We cover you for loss of or damage to
your home or contents caused by flood
or storm surge which happens during the
period of insurance at the property
address.
We will pay up to the:
home sum insured, if your home is
insured;
contents sum insured, if your
contents are insured for damage
caused by flood or storm surge,
We will pay for loss or damage in the
same way and in the same amounts as
we do under insured events cover.
We will not pay for loss or
damage to:
paths, driveways, paving,
retaining walls (whether or
not part of the home), tennis
cou rts or other playing
surfaces;
shade or sail cloth;
fabric awnings, swimming
pool and spa covers or
liners and the like;
glasshouse whether or not
constructed principally of
glass;
water in swimming pools or
spas...
...”
Issues
10. Whether the Applicants were “clearly informed” about what the policy did and
did not cover.
11. Whether the cause of the Applicants’ loss was covered under the policy.
Reasons for decision
12. Due to the nature of the dispute, the parties have been informed that the
matter has been referred to the Panel for Determination in line with the
Operational Guidelines to FOS’s Terms of Reference. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
13. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and a
representative with extensive experience in consumer claims.
14. It is appropriate to consider the issues under the various headings.
Case No: 247135 Determination Page 5 of 12
Consideration of "Flood" Definition in PDS
15. The Applicants have argued that the policy fails to clearly inform as to the
derogation from flood cover and the limitations on the extent of cover for
flash flood. There is no dispute that the Applicants had received the policy
documentation and Certificate of Insurance.
16. It is established law that in order to satisfy the requirement to clearly inform,
the language of section 35 (2) allows for a proposed insured to be clearly
informed by providing the relevant documentation in writing and that the
relevant exclusion and/or limitation in this case is clear and unambiguous
and presented in a manner which a person of average intelligence and
education is likely to have little difficulty in finding and understanding if that
person reads the policy in question.
17. The Panel has reviewed the FSP’s policy on a number of occasions. The
policy is indexed with relevant sections covering the insured events. The
policy sets out the definitions of storm and flash flood and stormwater run-
off. The policy clearly identifies that flood and storm surge is an optional
cover but otherwise flood is excluded from cover. The Certificate of
Insurance also clearly identifies that with respect to the Applicants’ policy
flood and storm surge is not covered.
18. Having considered the Applicants’ submissions and the FSP’s policy
documents, the Panel is satisfied that the FSP has met its obligations to
clearly inform the Applicants of the extent of the exclusions and limitations in
accordance with the requirements of the Act.
Water Inundation
The Evidence
19. The Applicants say that right outside their front gate there is a stormwater
drain which regularly backs up if there is a heavy storm.
20. In her 12 March 2012 submission, the female Applicant states that she left
the property at approximately 2-3am on Wednesday 12 January 2011 and at
that stage, water had started coming out of the stormwater drains. She
believes that it is likely her property was inundated shortly after she left the
property.
21. After the lodgement of the claim, the FSP appointed a loss adjuster (MY) to
investigate and report on the damage caused to the Applicants’ property.
The report stated that the Applicants’ home was inundated to a depth of
1730 mm.
22. Amongst the factual information, MY suggested that water first e ntered the
property at approximately 2pm on 11 January 2011. This does not accord
with the female Applicants’ statement or the report from the hydrologist. MY
also states that the loss was discovered on 11 January 2011, but has noted
that the date of loss was 12 January 2011, this is clearly incorrect.
Case No: 247135 Determination Page 6 of 12
23. MY stated that the Applicants’ property is located 100m from the Brisbane
River and considered that the cause of the loss was the river “breaking its
banks” and “the backup of the stormwater drainage which could discharge”
(sic).
24. Given the inconsistencies and lack of clarity the Panel is of the view that
MY’s report has little value and cannot be relied upon.
25. The FSP subsequently engaged a hydrologist, SC, to provide a report as to
the damage.
26. SC provided a statutory declaration dated 6 October 2011 to evaluate the
cause of the loss in the region surrounding and specifically affecting the
Applicants’ home. He found that:
A substantial amount of rain fell in the greater Brisbane area from 9
January 2011 and over the subsequent two days, which caused
significant inflows into the Wivenhoe Dam, which peaked on the evening
of 11 January 2011;
Rain also fell in the area of the Bremer River from 6am on 11 January
2011. This rain travelled along the Bremer River to the junction of the
Brisbane River and ultimately contributed about 15-25% of its peak flow;
A “small proportion” of the overall depth of the Brisbane River “may be
partially attributable to the rain that fell in the Bremer River catchment on
11 January 2011”, although the “overwhelming influence” was the rain
that had fallen in the previous days.
The terrain data for the Applicants’ home suggested that it was unlikely
that the Applicants would have experienced significant stormwater or run-
off problems during the period;
Inundation from stormwater run- off requires “intense levels of rain” which
is sufficient to overcome the stormwater drainage system. Any such
run-off generally occurs during or very shortly after such an intense
period of rainfall;
A review of the rainwater gauge at Corinda High Alert Station,
approximately 4 km from the Applicants’ property and representative of
its rainfall in the expert’s opinion, revealed that 81 mm of rain fell
between 9 and 10 January 2011, with a further 47 mm falling on 11
January 2011 and the most intense rainfall on 11 January 2011 occurring
at approximately 11am. From 6pm on 11 January 2011 until 15 January
2011, a total of 2mm of rain was recorded;
The overall intensity of the rainfall was very low and unlikely to result in
run-off or stormwater inundation to the property;
The water level of the Brisbane River at 2pm on 11 January 2011 (the
time of the inundation of the Applicants’ property according to the MY
Case No: 247135 Determination Page 7 of 12
report) was well below the minimum level of the property as shown in the
Brisbane City Council Floodwise Report. As neither the rainfall intensity
nor the river water level at that time would have been sufficient to cause
inundation of the property, SC believes that the time of inundation
included in the MY report is incorrect;
By comparing the Brisbane River water level information to the height of
the Applicants’ property, SC says that the inundation of the property
would have occurred at about 3am on 12 January 2011.
Given the low intensity rainfall over the pe riod, any backflow from the
stormwater drains outside the front of the property would have been due
to the rising level of the Brisbane River rather than stormwater or other
local runoff.
27. Based on the evidence submitted the Panel concludes that on the bala nce of
probabilities that Applicants’ premises would not have been inundated by
stormwater runoff.
Releases from Wivenhoe Dam & Proximate Cause
28. Although flood is generally excluded under the FSP’s policy, cover is
provided for a particular type of flood, being flash flood. In order for a claim
to fall within the insured event of Flash flood and stormwater runoff, the
following elements must be established:
a. There was a sudden flood;
b. There was a heavy rain that occurred within 24 hours prior to that flood;
c. The sudden flood was caused by that heavy rain.
29. Therefore, the central issue for Determination in this dispute is whether the
inundation of the Applicants’ home on 12 January 2011 was due to flash
flood as defined within the terms of the policy, that is whether rain that fell no
more than 24 hours prior to the inundation of the Applicants’ property was
the proximate cause of the inundation.
30. On 21 May 2012 FOS issued a memorandum to all relevant stakeholders
advising that after considerable deliberation of all material available to it, the
Panel formed a view that the heavy rain occurring from approximately
4.00am on 11 January 2011 and in particular the heavy rain between
4.00am and 8.00am on 11 January 2011 was a proximate cause of the W4
strategy being invoked and therefore a proximate cause or trigger that led to
the flooding of many of the properties along the Brisbane River.
31. At that time, the Panel noted that in relation to the approach that each
dispute would depend upon the individual and unique factors relevant to the
dispute and in that regard the parties were invited to make further
submissions in relation to disputes before FOS.
Case No: 247135 Determination Page 8 of 12
32. In view of this, the FSP provided detailed further submissions to FOS on 18
June 2012 in relation to this dispute. Included with the submissions were the
following documents:
A Reference document for disputes relating to Queensland Floods (this
is a general reference document) relating to the various submissions
the FSP makes in relation to a number of issues. Not all issues raised
in the reference document appear in the current dispute;
Letter from the FSP’s hydrologist attaching a key information sheet for
the Applicants’ property;
Hydrologist report “Investigations of January 2011 inundation event –
Brisbane” dated March 2011;
Statement from hydrologist dated 7 June 2012.
33. The FSP has since provided revised Reference documents the latest dated
28 August 2012.
34. In summary the FSP argues that the proximate cause of the inundation of
the properties, that is the real or effective cause of the damage caused to the
properties downstream of the dam, is not simply the rain that occurred from
4.00am on 11 January 2011 but the combined effect of all of the rainfall and
not just the rain that had fallen from 4.00am on 11 January 2011 leading to
the implementation of the W4 strategy from 8.00am that day.
35. There is no dispute that heavy rain fell over the Wivenhoe Dam catchment
area and in fact parts of the Brisbane River from approximately 4.00am on
11 January 2011. It is not disputed that in addition to this there was heavy
rain over the Bremer River which influenced the level of the Brisbane River
and that rain commenced at approximately 6.00am on 11 January 2011.
36. The FSP’s hydrologist relied on data from SEQWater dated 2 March 2011
which confirms the rapid increase in releases from the Wivenhoe Dam from
8.00am on 11 January 2011. Examination of the SEQWater report identifies
the rapid increase in the inflows to the Wivenhoe Dam commencing from
about 4.00am, 11 January 2011. The report confirms the inflows into the
dam had been decreasing from as early as 8.00am from 10 January 2011
with steady decreases from approximately 3.00pm on 10 January 2011 to
2.00am on 11 January 2011.
37. The Queensland Flood Commission of Inquiry report confirms that prior to
4.00am on 11 January 2011 and in fact prior to 8.00am of 11 January 2011
the dam releases were being managed at the W3 strategy. Whilst it is
accepted that the W3 strategy had led to an increase in the levels of the
Brisbane River, the W3 strategy was designed to avoid where possible
inundation of the properties below the Wivenhoe Dam by flooding from the
Brisbane River.
38. There is no dispute that there were two significant rainfall spikes with rain
that fell from 9 to 10 January 2011 being considered the first spike and rain
Case No: 247135 Determination Page 9 of 12
that commenced falli ng from approximately 4.00am on 11 January 2011
being the second spike.
39. There is no dispute that following the second spike that the W4 strategy was
adopted. The FSP has argued that the switch to strategy W4 was not the
natural and ordinary consequence of the rain that fell and in fact the move to
W4 strategy was not taken in accordance with the Wivenhoe Dam manual.
In the Panel’s view, the Queensland Flood Commission of Inquiry final report
does not find the adoption of W4 strategy at 8.00am on 11 January 2011
was inconsistent with the manual. Although there may be issues as to how
the Wivenhoe Dam had been managed prior to this time, there is nothing in
the material that has been provided to the Panel to suggest that the earlier
management of the Wivenhoe Dam influenced to any significant degree, the
adoption of the W4 release strategy at 8.00am on 11 January 2011.
40. The Insurance Council of Australia (ICA) hydrology report and the
information provided by the FSP’s hydrologist confirms that the increased
releases from the Wivenhoe Dam after the adoption of the W4 strategy led to
the development of a flood wave that ultimately caused the flooding of many
properties downstream of the Wivenhoe Dam.
41. In determining the proximate cause of the inundation it is necessary to look
at the effective or dominant cause of the inundation. The Panel agrees with
the FSP’s general submission that the proximate cause is a cause
determined by common sense evaluation of the relevant facts. In the event
that there are two or more proximate causes, one within the policy and the
other excluded, the policy does not respond. The proximate cause is not
determined by identifying the last event or final trigger but by determining
what is the dominant, effective, direct or efficient cause of the loss.
42. The FSP has maintained that the impact on the Wivenhoe Dam from the
rainfall that fell in the early hours of 11 January 2011 was only 29% while
71% of the volume of the inflow came from the rain that fell on 9 and 10
January 2011 or earlier. The FSP maintains that to find the rainfall which had
fallen from 4.00am on 11 January 2011 is the proximate cause is without
foundation as such an approach produces an entirely artificial outcome.
43. With due respect to the FSP’s argument the Panel disagrees. W hilst the
Panel accepts there has been a significant impact on the levels of the
Wivenhoe Dam by the rainfall that commenced falling on or about 9 January
2011 or earlier, the Panel is satisfied having regard to the information that
has been exchanged and the relevant legal principles, that the heavy rain
which commenced falling on or about 4.00am on 11 January 2011 was a
proximate or effective cause of the adoption of the W4 strategy.
44. The Panel accepts that the heavy rain that commenced falling around
4.00am on 11 January 2011 over the Wivenhoe Dam and Brisbane River
combined with the heavy rain that commenced falling over the Bremer River
at 6.00am that day was the cause of the inundation of the Applicants’
property.
Case No: 247135 Determination Page 10 of 12
The Applicants’ Inundation
45. The FSP’s hydrologist SC provided a summary “Key Conclusions Statement ”
on 7 June 2012 which provides a basis for determining the impact of the
river levels on the Applicants’ home.
46. SC’s statement indicates the effect of the W4 releases first reached the
vicinity of the Applicants’ property at 2.44pm on Tuesday 2011. He estimated
that the property was first inundated by the Brisbane River to the bench mark
level at 2.57am on 12 January 2011 and by 4am the same day, the property
was inundated up to 0.2m above the relevant benchmark level.
47. According to the Key Conclusions Statement, the minimum land of the
Applicants’ property was 6.3m AHD with the approximate benchmark level at
6.6m AHD. According to the Key Conclusions Statement W4 releases first
reached the vicinity o f the Applicants’ property at 2.44pm on Tuesday 11
January 2011 although the Statement does not indicate what is meant by the
vicinity. By 4am on 12 January 2011 the river level was approximately 6.8m
AHD which is approximately 0.2m above the benchmark level.
48. The Panel has some concern as to the calculation of these estimates and
accepts the possibility that these estimates may not be entirely accurate.
The Applicants have described leaving the property around 2-3am with water
coming up through the drains at that time. Given this is relatively consistent
with the hydrology information, the Panel most likely accept that the
Applicants’ property was first inundated above floor level at some stage prior
to 4am on 12 January 2011 and at 4am on 12 January 2011 was inundated
to a height of approximately 0.2m above floor level.
49. On this basis, damage caused by the inundation up to 0.2m above floor level
occurred within 24 hours of the rain which fell from 4am on 11 January 2011
and as such the FSP has required to indemnify the Applicants for such
damage.
50. The Panel notes that the peak level of inundation of 2.4m above benchmark
occurred well outside of the 24 hour flash flood period and therefore outside
the coverage provided by the policy. As such the FSP is not liable for
damage incurred by the inundation after 4.00am 12 January 2011 as this is
outside the relevant 24 hour period.
Quantum
51. The Renewal Certificate of Insurance provides a sum insured of $430,000
for the home with contents of $269,000. The Panel notes that damage
caused by flash flood is subject to the policy limit of 50% of the sum insured
or $25,000 (whichever is the greater) for each of the building and contents.
Pursuant to the policy cap, the FSP is liable up to an amount of $215,000 for
the damage to the building and $134,500 for the contents.
Case No: 247135 Determination Page 11 of 12
52. Given the time since the loss was sustained, the Panel accepts that the
parties may be unable to provide an exact estimate of the total loss
sustained, or a breakdown of that loss.
53. The Panel accepts that significant damage to contents would have occurred
as a result of inundation up to 0.2m above floor level and significant damage
to the building would have also have occurred. It is likely that inundation at
that level would have caused damage to the flooring, cupboards, appliances
both internal and external, electrical wiring, etc. It is however impossible to
assess the extent of this damage and the parties are asked to work
cooperatively together to establish the extent of the loss sustained to the
property and reach agreement as to the cost of the repairs to the home and
replacement of the various contents lost or damaged as a result of
inundation to a level of 0.2m above floor level.
54. Insofar as the FSP may have made payment of a compassionate sum to the
Applicants, FOS does not have jurisdiction to deal with this payment but
acknowledges that the FSP, given the terms on which the compassionate
payment was made, may be entitled to deduct this payment from any
settlement sum.
55. The Panel has also considered the issue of interest.
56. The FSP has argued that interest is only payable from the date from which it
was unreasonable to withhold payment. The FSP maintains that it is entitled
to a reasonable period to investigate and determine its position, and given
the complex nature of the flood disputes, the delays are not unreasonable.
Further complex situations require substantial periods of time for
independent bodies such as the Queensland Flood Commission of Inquiry
and FOS, to make conclusions on the issues in dispute.
57. The FSP maintains that it did not act unreasonably in this dispute and
therefore interest is not payable. Alternatively if some period of interest is to
be awarded it should be reduced to account for the substantial delays
through the course of the proce ss which were not the FSP’s fault.
58. Section 57 of the Insurance Contracts Act requires interest be paid when it
becomes “unreasonable for the insurer to have withheld payment”. An
examination of relevant case law indicates that most probably, interest will
be awarded from either when an insurer first emphatically denied liability or
disputed a matter, or from when in the normal course of events the claim
should have been paid if liability had not been disputed.
59. In this dispute the Panel accepts that the FSP was entitled to withhold
payment of the settlement monies until such time as it had properly
investigated the dispute and made its decision as to liability.
60. The FSP made its original decision to deny the claim after receiving relevant
assessment reports, hydrology reports and other information. The FSP was
aware of the terms of its policy and aware of the relevant provisions under
Case No: 247135 Determination Page 12 of 12
which liability might arise and chose to deny the claim having reviewed those
relevant provisions and the evidence available to it.
61. In the Panel’s view, at that point the FSP has made its decision on the claim
and it is appropriate that from that time interest be paid unless it can be
established that the Applicants had withheld information from the FSP that
would have led to an alteration of its decision.
62. Accordingly, the Panel determines that it is appropriate that the FSP in this
dispute pay interest from day upon which the FSP determined to deny
liability of the Applicants’ claim, until payment of the claim.
Determination
63. On the basis of the available information the Panel determines that the FSP
is to meet the cost of repairs incurred by the Applicants and the cost of the
replacement of items damaged as a result of the inundation of the property.
Any payment is subject to the limitations of the policy and agreement as to
the extent of loss attributable to flash flood throughout the Applicants’ home
to a level of approximately 0.2m above floor level.
64. In the event that the parties are unable to agree as to the extent of the loss
attributable to flash flood, the parties may make further submissions to the
Service and the Panel will determine the quantum of the claim.
65. Insofar as the FSP is to cash settle the claim, the FSP is to pay interest from
24 March 2011 (being the date of rejection of the claim) to date of payment
of the claim, in accordance with Section 57 of the Act.