Whether the flood-related inundation of the home is covered as flash flood or excluded as flood
Text of the determination
Case No: 246850 Determination Page 1 of 12
Case number: 246850
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of Claim - Water Inundation - Flood vs Flash Flood
26 October 2012
Background
1. The Applicant insured her home and contents with the Financial Services
Provider (FSP). The relevant period of insurance operated for twelve months
beginning from 11 March 2010. During this period, the building was insured
up to a sum of $375,000 and the contents for $117,000.
2. On or about 11 January 2011, the Applicant‟s home in Bellbowrie was
subject to extensive water inundation following severe weather events in
Queensland. She lodged a claim.
3. The FSP denied the claim on the basis the damage was due to “flood”. The
Applicant, through her solicitors, has disputed this.
4. For the sake of simplicity, reference to the Applicant will include her legal
representatives.
5. Both the Applicant and the FSP have provided detailed submissions on the
relevant issues. For the sake of brevity, the Panel will only summarise these
submissions given all of the material made available has been exchanged
with the other party.
Summary of Applicant ’s position
6. The Applicant submits the following as alternative arguments in response to
the FSP‟s decision:
The FSP misled the Applicant as to the level of cover provided under
the policy. It had previously paid a claim in 2009 in similar
circumstances and this led her to believe that she would be covered for
the event.
The FSP‟s policy failed to clearly inform her that “flood” was excluded
as required under Section 35 of the Insurance Contracts Act 1984 (the
Act).
The water which inundated the property emerged from the local drains
and was properly classed as stormwater run-off, which is an insured
event.
Determination
Case No: 246850 Determination Page 2 of 12
Alternatively, the damage was due to “Flash flood”, which is also an
insured event. In particular, the inundation was due to heavy rain that
fell from 4am on 11 January 2011 which resulted in the Wivenhoe
Dam‟s operating engineers elevating their strategy to W4. This decision
resulted in massive discharges of water into the Brisbane River that
ultimately inundated her property.
Summary of FSP’s position
7. In response to the Applicant ‟ s arguments, the FSP submits the following:
It at no stage misled the Applicant as to the level of cover provided
under the policy.
There is no dispute that a PDS was sent to the Applicant prior to the
claim. Further, the policy structure and layout in conjunction with this
evidence enables it to rely on the exclusion clause of “flood” pursuant
to Section 35(2) of the Act.
The home was not subject to stormwater run-off or a flash flood.
8. The FSP relies on a number hydrology reports authored by SC and the
followin g policy provisions to deny the Applicant‟s claim :
Page 3 of the Certificate of Insurance (COI)
“ What optional covers are included and not included
Home Contents
...
Flood and storm surge not included not included...”
Pages 10-12 of the PDS
“ Words / terms with special meanings
Word / term Meaning
...
Flood Rising water which enters your home as a result of it
running off or overflowing from any origin or cause.
This policy does not cover flood unless we have
agreed and it is shown on your certificate of insurance.
Flash flood and
stormwater run - off
A sudden flood caused by heavy rain that fell no more
than 24 hours prior to the flash flood or stormwater
run - off.
...
Storm A violent disturbance of the atmosphere associated
with strong winds including a cyclone, lightening,
heavy rain, hail or snow, but not continuous bad
Case No: 246850 Determination Page 3 of 12
weather by itself.
...”
Pages 17-18 of the PDS
“ Insured events you are covered for
Damage caused by weather...
What is covered What is not covered
Storm Loss or damage:
caused by rain, hail or snow
after it has reached the
ground...
...
Flash flood and stormwater run-off
A sudden flood caused by heavy rain
that fell no more than 24 hours prior to
the flash flood or stormwater run - off
Loss or damage caused:
by flood...
...”
Page 27 of the PDS
“ Your home
The most we will pay you for home claims
What is covered What is not covered
Flash flood and stormwater run-off
We will pay up to 50% of your home sum
insured or $25,000, whichever is higher.
...
...”
Page 32 of the PDS
“ Your contents
The most we will pay you for contents claims
What is covered What is not covered
... ...
Flash flood and stormwater run-off
We will pay up to 50% of your contents
sum insured or $25,000, whichever is
higher, but not exceeding your contents
sum insured.
...
...”
Case No: 246850 Determination Page 4 of 12
Issues
9. Whether the FSP in any way misled the Applicant in respect of the level of
cover provided or misrepresented the policy to lead her to believe that she
was covered in the event of a flood.
10. Whether the Applicant was “clearly informed” about what the policy did and
did not cover.
11. Whether the cause of the Applicant‟s loss was covered under the policy.
Reasons for decision
12. Due to the nature of the dispute, the parties have been informed that the
matter has been referred to the Panel for Determination in line with the
Operational Guidelines to FOS‟s Terms of Reference. This dispute has not
been the subject of a FOS Recommenda tion and has proceeded directly to
Determination.
13. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and a
representative with extensive experience in consumer claims.
14. It is appropriate to consider the issues under the various headings.
Misrepresentation of Policy
15. The Applicant alleges that the FSP misled her over the level of cover
provided under the policy as it had previously provided cover for a similar
flooding event i n 2009 and she assumed that she would be similarly
indemnified for this event.
16. The only details provided of the previous claim suggest that the stormwater
drain in front of the Applicant‟s property “backed up” and water came into her
home through the shower and the toilet as well as entering the garage
through the driveway.
17. It is not in dispute that this claim was paid by the FSP.
18. The policy extends cover for both stormwater run-off and flash flooding. It
differentiates “flash flood” (which is covered) from “flood” (which is not) and
therefore the circumstances of each individual inundation event must be
considered.
19. The Panel is not of the opinion that the FSP is obliged to provide cover for
any potential claim as a result of paying an earlier claim with similar
circumstances. Each individual claim must be determined on its merits.
20. On this basis, the Panel is not of the view that the Applicant has been misled
in any way through the payment of the previous claim.
Case No: 246850 Determination Page 5 of 12
Consideration of ‘Flood’ Definition in PDS
21. The Applicant has not disputed receipt of the PDS document from the FSP.
It is further not in dispute that the Applicant received an annual COI.
22. The Applicant contends that the definition of flood is too broad, too difficult to
comprehend and that the FSP has not met its obligations under Section 35
of the Act to “clearly inform” her of what is and is not covered under the
policy.
23. The Applicant‟s solicitor has raised issue with the placing of definitions
throughout the policy and the difficulty a “reasonable person” would have in
evaluating it. The Panel is satisfied that the PDS should be read in its
entirety and that (should this be done) the interpretation of same should not
be difficult for a “reasonable person”.
24. The PDS has an index on the inside cover which highlights the areas of the
policy to which the policyholder might find information. Included in this is
“Words/terms with special meanings” on page 9, for which definitions of
relevant terms in the policy are provided. Flood is included on page 10,
together with the qualification that:
“... This policy does not cover flood unless we have agreed and it is shown on
your certificate of insurance. ”
25. In addition to this, page 53 directs the reader to “Flood and storm surge”,
which is explained under the bro ader definition of “Optional covers for extra
peace of mind”. This section explains that:
“... This policy does not cover flood unless we have agreed and it is shown on
your certificate of insurance. ”
26. It is not in dispute that no cover was optioned by the Applicant for “Flood and
storm surge” and therefore she was not covered for it under the policy. This
is reflected in the COI document.
27. A fair reading of Section 35(2) requires that the relevant exclusion or
limitation be in clearly and unambiguous language that a person of average
intelligence and education is likely to have little difficulty in finding and
understanding if that person reads the policy. Having reviewed the policy the
Panel is satisfied that the FSP has satisfactorily defined the events in the
policy as required under Section 35 of the Act and that it is entitled to rely
upon same in determining if the policy responds to the Applicant‟s loss.
Water Inundation
The Evidence
28. The Panel accepts that the FSP‟s policy does not extend cover to
circumstances where a loss is caused by a flood. The policy distinguishes
between flood, flash flood and stormwater run-off (the latter two of which are
Case No: 246850 Determination Page 6 of 12
covered). It extends cover to damage from sudden flood events “caused by
heavy rain that fell no more t han 24 hours prior” to the flash flood.
29. The Applicant confirms that she left her property at about 2-3am on 12
January 2011. The home had not been inundated at that time. She alleges
that the Brisbane River, which was in close proximity to her home, did no t
break its banks in their area, although:
“... the river broached further back stream where the banks are lower at the
end of [W] Road and up through the golf course approx one and a half
kilometres away. Our problems arose from the corner of [C] and [B] Roads
(large stormwater outlet) along [B] Road to the corner of [Ba] Street...
The water first came out of the storm water drains on [B] Road and then
entered my property through my back yard. I didn‟t see the water, however
[my] neighbour who lives behind me saw the water come from the storm water
drains on [B] Road.”
30. The Applicant‟s rear neighbour, CS, provided a statutory declaration
regarding the events:
“... I was at home on Wednesday 12 January 2011 until approximately 3.30am
when we evacuated.
... I saw water flow out of the underground car park drains and proceed across
the road to our house. Water was lapping at our garage door at around
3.30am...”
31. CS confirmed that both she and the Applicant‟s properties were on flat
ground. The properties were in different streets but backed onto each other.
32. After the lodgement of the claim, the FSP appointed a loss adjuster (MY) to
investigate and report on the damage caused to the Applicant ‟ s property.
The report estimated that there was about $69,700 worth of building damage
and $82,000 of contents damage. Amongst the factual information, MY
suggested that water first entered the property on 11 January 2011 and
peaked at 2.8m. He attributed the cause of the loss to “flood”.
33. The FSP subsequently engaged a hydrologist, SC, to provide a report as to
the damage.
34. SC provided a statutory declaration dated 20 July 2011 to evaluate the
cause of the loss in the region surrounding and specifically affecting the
Applicant ‟ s home. He found that:
a substantial amount of rain fell in the greater Brisbane area from 9
January 2011 and over the subsequent two days, which caused
significant inflows into the Wivenhoe Dam, which peaked on the
evening of 11 January 2011;
rain also fell in the area of the Bremer River from 6am on 11 Ja nuary
2011. This rain travelled along the Bremer River to the junction of the
Brisbane River and ultimately contributed about 15-25% of its peak
flow;
Case No: 246850 Determination Page 7 of 12
a “small proportion” of the overall depth of the Brisbane River “may be
partially attributable to the rain that fell in the Bremer River catchment
on 11 January 2011”, although the “overwhelming influence” was the
rain that had fallen in the previous days.
the terrain data for the Applicant‟s home suggested that it was unlikely
that the Applicant would have experienced significant stormwater or
run-off problems during the event that inundated the home;
inundation from stormwater run- off requires “intense levels of rain”
which is sufficient to overcome the stormwater drainage system. Any
such run-off generally occurs during or very shortly after such an
intense period of rainfall;
a review of the rainwater gauge at Wacol Alert, approximately 2.5km
from the Applicant ‟ s property and representative of its rainfall in the
expert‟s opinion, revealed that 87mm of rain fell over 9 and 10 January
2011, with a further 56mm falling on 11 January 2011. The majority of
the rainfall was in two bursts on 11 January 2011, being around 11am
and 4pm. After this time until 15 January 2011 there was only a further
1mm of rain;
the overall intensity of the rainfall was low and unlikely to result in run-
off or stormwater inundation to the property;
the water levels of the Brisbane River reached a level sufficient to
inundate the Applicant‟s property at about 5.00am on 12 January 2011;
the report from the Applicant was consistent with the events. The
Brisbane River first overflowed in the area into a gully to the northwest
of the Applicant‟s home;
stormwater run- off may have inundated the streets during “times of
intense rainfall”, although the rain “ceased at 4.00pm on 11 January
2011” and the property was not inundated at the time the Applicant left
10-11 hours later. If stormwater run-off were to inundate the home, it
would have occurred at around the time that the heavy falls were
recorded;
the Applicant‟s property was inundated by backflow from the Brisbane
River and not stormwater run-off or flash flooding (as defined in the
policy).
35. As a result of the report from SC, the FSP denied the claim on the basis that
it considered the cause of the loss to be flooding from the Brisbane River.
36. Since the matter has been referred to the Service, the Applicant has
suggested that the releases of water from the Wivenhoe Dam on 11 January
2011 were a significant factor in the increased water leve ls in the Brisbane
River and that this was a major influence in the inundation of the Applicant‟s
home. This is largely now agreed by the parties, although the dispute
centres on whether such an event is covered under the policy.
Case No: 246850 Determination Page 8 of 12
Releases from Wivenhoe Dam & Proximate Cause
37. On 21 May 2012 FOS issued a memorandum to all relevant stakeholders
advising that after considerable deliberation of all material available to it, the
Panel formed a view that the heavy rain occurring from approximately
4.00am on 11 January 2011 and in particular the heavy rain between
4.00am and 8.00am on 11 January 2011 was a proximate cause of the W4
strategy being invoked and therefore a proximate cause or trigger that led to
the flooding of many of the properties along the Brisbane River.
38. At that time, the Panel noted that in relation to the approach that each
dispute would depend upon the individual and unique factors relevant to the
dispute and in that regard the parties were invited to make further
submissions in relation to disputes before FOS.
39. In view of this, the FSP provided detailed further submissions to FOS in
relation to this dispute. Included with the submissions were the following
documents:
Reference documents for disputes relating to Queensland Floods (this
is a general reference document) relating to the various submissions
the FSP makes in relation to a number of issues. Not all issues raised
in the reference document appear in the current dispute;
Letter from the FSP‟s hydrologist attaching a key information sheet for
the Applicant‟s property;
Hydrologist report “Investigations of January 2011 inundation event –
Brisbane”;
A further statement from the hydrologist, SC.
40. The Panel has reviewed the reference documents. Insofar as the reference
documents relate to the current issues in dispute, those matters have been
considered.
41. In summary the FSP argues that the proximate cause of the inundation of
the properties, that is the real or effective cause of the damage caused to the
properties downstream of the dam, was the heavy rainfall that commenced
on 9 January 2011 (or earlier) and not simply the rain that occurred from
approximately 4.00am on 11 January 2011. The FSP maintains that on any
reasonable view, the damage sustained to the downstream properties was
the combined effect of all of the rainfall and not just the rain that had fallen
from approximately 4.00am on 11 January 2011 leading to the
implementation of the W4 strategy from 8.00am that day.
42. There is no dispute that heavy rain fell over the Wivenhoe Dam catchment
area and in fact parts of the Brisbane River from approximately 4.00am on
11 January 2011.
43. The FSP‟s hydrologist has relied on data from SEQWater dated 2 March
2011 which confirms the rapid increase in releases from the Wivenhoe Dam
from 8.00am on 11 January 2011. Examination of the SEQWater report
identifies the rapid increase in the inflows to the Wivenhoe Dam
Case No: 246850 Determination Page 9 of 12
commencing from about approximately 4.00am, 11 January 2011. The report
confirms the inflows into the dam had been decreasing from as early as
8.00am from 10 January 2011 with steady decreases from approximately
3.00pm on 10 January 2011 to 2.00am on 11 January 2011.
44. The Queensland Flood Commission of Inquiry report confirms that prior to
4.00am on 11 January 2011 and in fact prior to 8.00am of 11 January 2011
the dam releases were being managed at the W3 strategy. Whilst it is
accepted that the W3 strategy had led to an increase in the levels of the
Brisbane River, the W3 strategy was designed to avoid where possible
inundation of the properties below the Wivenhoe Dam by flooding from the
Brisbane River.
45. There is no dispute that there were two significant rainfall spikes with rain
that fell from 9 to 10 January 2011 being considered the first spike and rain
that commenced falling from approximately 4.00am on 11 January 2011
being the second spike.
46. There is no dispute that following the second spike that the W4 strategy was
adopted. The FSP has argued that the switch to strategy W4 was not the
natural and ordinary consequence of the rain that fell and in fact the move to
W4 strategy was not taken in accordance with the Wivenhoe Dam manual.
In the Panel‟s view, the Queensland Flood Commission of Inquiry‟s final
report does not find the adoption of W4 strategy at 8.00am on 11 January
2011 was inconsistent with the manual. Although there may be issues as to
how the Wivenhoe Dam had been managed prior to this time, there is
nothing in the material that has been provided to the Panel to suggest that
the earlier management of the Wivenhoe Dam influenced to any significant
degree, the adoption of the W4 release strategy at 8.00am on 11 January
2011.
47. The ICA hydrology and the information provided by the FSP‟s hydrologist
confirms that the increased releases from the Wivenhoe Dam after the
adoption of the W4 strategy led to the development of a flood wave that
ultimately caused the flooding of many properties downstream of the
Wivenhoe Dam.
48. The question then arises as to what was the proximate cause of this
inundation. In determining the proximate cause of the inundation it is
necessary to look at the effective or dominant cause of the inundation. The
Panel agrees with the FSP‟s general submission that the proximate cause is
a cause determined by common sense evaluation of the relevant facts. In
the event that there are two or more proximate causes, one within the policy
and the other excluded, the policy does not respond. The proximate cause is
not determined by identifying the last event or final trigger but by determining
what is the dominant, effective, direct or efficient cause of the loss.
49. The FSP has maintained that the impact on the Wivenhoe Dam from the
rainfall that fell in the early hours of 11 January 2011 was only 29% while
71% of the volume of the inflow came from the rain that fell on 9 and 10
January 2011 or earlier.
Case No: 246850 Determination Page 10 of 12
50. Whilst the Panel accepts there has been a significant impact on the levels of
the Wivenhoe Dam by the rainfall that commenced falling on or about 9
January 2011 or earlier, the Panel is satisfied having regard to the
information that has been exchanged and the relevant legal principles, that
the heavy rain that commenced falling on or about 4.00am on 11 January
2011 was a proximate or effective cause of the adoption of the W4 strategy.
51. The Panel is also satisfied that whilst the level of the Brisbane River may
have been increasing under the W3 strategy, it was the heavy rainfall from
approximately 4.00am on 11 January 2011 that caused the need to adopt
the W4 strategy at 8.00am on the same day. In the Panel‟s view this rainfall
together with the heavy rainfall over the Brisbane River from approximately
4.00am that same day and the rainfall over the Bremer River from
approximately 6.00am that day caused the inundation of the Applicant‟s
property.
The Applicant’s Inundation
52. The FSP‟s poli cy allows for cover for flash flooding “ caused by heavy rain
that f ell no more than 24 hours prior” to the loss. Based on the Panel‟s
classification of the W4 event being a “flash flood”, the entry of water into the
Applicant‟s home must occur within 24 ho urs of the onset of rain
(approximately 4am on 11 January 2011).
53. SC‟s Key Conclusions statement of 7 June 2012 indicates the effect of the
W4 releases first reached the vicinity of the Applicant‟s property at 1.08pm
on 11 January 2011. He estimated that the approximate benchmark level
(represented by Slab on Ground) of the property to be RL 12.5m AHD and
that at 4.00am on 12 January 2011, the river, with the addition of the W4
wave reached a height of approximately 12.4m AHD, which is 0.1m below
the benchmark level. The benchmark level was reached at 4.22am on 11
January 2011 and the property ultimately inundated up to 2.1m above the
relevant benchmark level by 5.50pm on 12 January 2011.
54. The Applicant left her home between 2-3am and her rear neighbour
estimated that her home was inundated around 3.30am on 12 January 2011
(she did not specify at what time the Applicant‟s home was inundated or
whether the inundation was limited to the property or specifically involved the
home). SC‟s calculations place the tim ing of the inundation above
benchmark level at the Applicant‟s home to be 4.22am. SC did not attend the
property or conduct an inspection of the property. He did not speak with the
Applicant. His assessment was based amongst other things on aerial and
topographical data.
55. In light of the issues in dispute the Panel Chair Ombudsman (PCO)
conducted a site inspection on 4 October 2012 with the Applicant and a
representative of the FSP.
56. The FSP confirmed that while the FSP‟s assessor attended the property
SC‟s calculations as enumerated in his 7 June 2012 „Key Conclusions‟, were
arrived at without the benefit of either a site visit by the hydrologist or one of
Case No: 246850 Determination Page 11 of 12
his staff, or a conversation with the Applicant as to her knowledge of the
inundation event.
57. The Panel notes the minimum level of the property is 12.2m whilst the
benchmark is 12.5m. The benchmark was, according to SC, the right hand
rear corner of the house. The property slopes slightly away from the roadway
with the house set back from the roadway. The ho use is on a slab
approximately 50mm higher than ground level which is partof the lower
section of the property. It is difficult to accept the benchmark is 300mm
above the minimum level of the property in these circumstances.
58. The Applicant advised she left the property around 2.00am. There was no
inundation at that time. The neighbour observed water entering her garage
around 3.30am. Nobody actually observed when the Applicant‟s home was
first inundated.
59. The timing of the inundation is critical. The conclusions reached by SC have
the property inundated at 4.22am on 12 January 2011. This is approximately
24hours after the commencement of the heavy rainfall over the Wivenhoe
Dam. In the circumstances allowing for the fact that the timing of inundation
i s only an approximation, the Panel accepts that most likely the Applicant‟s
property was inundated close to 4.00am on 12 January 2011 and about
24hours after the commencement of the heavy rainfall.
60. Under the Terms of Reference the Panel is required in any dispute to do
what is fair in all the circumstances having regard to the relevant legal
principles, terms of the policy, good industry practice and prior
determinations, although not as binding precedents.
61. There is no evidence available as to the precise level of initial inundation.
The assessor‟s report refers to inundation including sewerage although
again does not identify if sewerage formed part of the initial inundation. The
Applicant does not know whether sewerage was part of the initial inundation.
I n the Panel‟s experience inundation from sewerage often accompanies the
initial flood water inundation.
62. Taking all the information into account and with the benefit of the site
inspection the Panel determines, on the balance of probabilities the
Applicant ‟s property was inundated above floor level to a height of 100mm
within 24 hours of the commencement of the heavy rainfall at approximately
4.00am 11 January 2011. Inundation above this height, would have occurred
outside the relevant 24 hour period and would be excluded under the policy
as flood.
63. The home and contents sums assured are respectively $375,000 and
$117,000, The flash flood monetary limits mean the FSP‟s potential
exposure is limited to a maximum of $187,500 and $58,500 respectively.
64. The extent of damage attributable to the initial inundation cannot be
assessed on the information available. It is likely that there would be
extensive damage to furnishings, appliances both indoor and outdoor as well
Case No: 246850 Determination Page 12 of 12
as to flooring , floor coverings , cupboards etc. Given this it is appropriate to
allow the FSP to obtain a scope of works to determine to damage sustained
from the initial inundation. As a consequence, the parties are encouraged to
work cooperatively to establish the quantum of loss arising from such an
inundation.
65. The Panel has also considered the question of interest.
66. The FSP has argued that interest is only payable from the date from which it
was unreasonable to withhold payment. The FSP maintains that it is entitled
to a reasonable period to investigate and determine its position, and given
the complex nature of the flood disputes, the delays are not unreasonable.
Further complex situations require substantial periods of time for
independent bodies such as the Queensland Flood Commission of Inquiry
and FOS, to make conclusions on the issues in dispute.
67. The FSP maintains that it did not act unreasonably in this dispute and
therefore interest is not payable. Alternatively if some period of interest is to
be awarded it should be reduced to account for the substantial delays
through the course of the process which were not the FSP‟s fault.
68. Section 57 of the Insurance Contracts Act requires interest be paid when it
becomes “unreasonable for the insurer to have withheld payment”. An
examination of relevant case law indicates that most probably, interest will
be awarded from either when an insurer first emphatically denied liability or
disputed a matter, or from when in the normal course of events the claim
should have been paid if liability had not been disputed.
69. Whilst the Panel would normally award interest from the time the FSP made
its decision to deny a claim, in this dispute given the timing of the inundation
and the requirement that the FSP obtain a current scope of works as to the
extent of the insured loss the Panel is satisfied that interest is not payable
should the FSP seek to cash settle the loss. In so far as the FSP paid the
Applicant an amount of $12,500 from its compassionate fund this payment
does not fall within the Panels jurisdiction.
Determination
70. On the basis of the available evidence, the Panel accepts that the FSP is
liable for the Applicant‟s loss pursuant to the policy terms surrounding its
flash flood provision up to a height of 100mm within the property.