Home / Financial Firm (Unknown - Insurer) / Determination 246515

Determination 246515

Denial of home building claim for water inundation (flood exclusion)

FirmFinancial Firm (Unknown - Insurer)
Decided2012-01-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$50,000
SourceAFCA PDF

Summary

The applicant's home was inundated during the January 2011 Brisbane flood event, and the FSP refused the claim as flood damage. His solicitor argued the water came from drains and storm run-off. AFCA found the water was flood water overflowing from a watercourse and dismissed the complaint.

Water from a drain that combines with floodwater is properly categorised as flood for the policy exclusion, and the FSP discharged its onus on the balance of probabilities.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 246515 Determination Page 1 of 8 Case number: 246515 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 13 January 2012 Background 1. The Applicant and his wife are insured under a home building and contents insurance policy that commenced on 1 December 2002 and was renewed annually. The policy is current until 2 December 2011. 2. On 12 January 2011, the Applicant contacted the Financial Services Provider (FSP) to report damage had occurred at the property as a result of water inundation. 3. The Financial Services Provider (FSP) denied the claim on the ground that the loss was as a result of water escaping and overflowing from the Bundamba Creek. This falls within the policy‟s definition of “flood” and is excluded. Summary of Applicant’ s Position 4. The Applicant is seeking cover under the policy for the damage caused to the insured property which is estimated to be in excess of $50,000. 5. The issues raised by the Applicant‟s solicitor in his letter dated 28 September 2011 included:  The FSP‟s failure to discharge its obligations under section 35 of the Insurance Contracts Act 1984 (the Act);  The FSP did not adequately investigate the claim and has relied upon a generic hydrology report;  The Applicant‟s home was affected by multiple events. Before any riverine flooding occurred, stormwater run-off and rain caused damage to the property. 6. In a letter dated 21 October 2011, the Applicant‟s solicitor also stated damage was caused by water inundating the property from a drain, or rather „pipe backflow‟ flooding, prior to any overland flow. As such, this is covered by the policy. Determination Case No: 246515 Determination Page 2 of 8 Summary of FS P’s Position 7. The FSP states:  Floodwater from the Bundamba Creek flowed southwards into MJ Kinnane Park, where it promptly mixed with stormwater that had escaped from the drain in the park;  The floodwater mixed with stormwater and flowed eastward where it crossed David St, and flowed uphill into Christine St where it inundated the Applicant‟s home;  It does not accept that stormwater alone crossed the streets and travelled uphill to inundate the Applicant‟s home;  It is not required to accept a claim where damage is caused by a mixture of floodwater (which is excluded under cover of the policy) and water escaping from a drain.  The policy wording is clear and effective. 8. The FSP relies on the following policy provisions: “ Home Building Insurance Policy What we cover – insured events You are covered for damage or loss to your home building occurring during the period of cover and caused by the following events: Yes Storm and rainwater including stormwater run-off from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. No Damage or loss caused by flood. Flood means the inundation or covering of normally dry land by water which: escapes or overflows from, or cannot enter, because it is full or has overflowed, or is prevented from entering, because other water has already escaped or been released from it, the normal confines of any watercourse or lake, including any that may have been modified by human intervention, or reservoir, canal, dam or stormwater channel. … What we do not cover – general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: flood, … Home Contents Insurance Policy Case No: 246515 Determination Page 3 of 8 What we cover – insured events You are covered for damage or loss to your contents while they are in your home or at the site, occurring during the period of cover, caused by the following events: Yes Storm and rainwater including stormwater run-off from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. No Damage or loss caused by flood. Flood means the inundation or covering of normally dry land by water which: escapes or overflows from, or cannot enter, because it is full or has overflowed, or is prevented from entering, because other water has already escaped or been released from it, the normal confines of any watercourse or lake, including any that may have been modified by human intervention, or reservoir, canal, dam or stormwater channel. … What we do not cover – general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: flood ” 9. For the avoidance of doubt, the FSP has also confirmed that the policy covers water which has escaped from a drain, even if the water escaping is sourced from a nearby flooding watercourse, itself separated from the policyholder‟s property on higher ground. Issues 10. Whether the FSP has discharged its obligations under section 35 of the Act to clearly inform the Applicant of the terms of its policy, and as such is entitled to rely on its flood exclusion; 11. Whether the damage claimed by the Applicant was caused by flood as defined by the policy. Reasons for Decision 12. Due to the nature of the dispute, this matter has been referred to the Panel for a Determination in line with the Operational Guidelines to the Financial Ombudsman Service‟s Terms of Reference. Case No: 246515 Determination Page 4 of 8 13. The Panel consists of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. 14. There has been an exchange of information between the parties and the Panel is satisfied that the parties have had the opportunity to respond to the issues raised. 15. The Applicant‟s solicitor has in a letter dated 28 September 2011, made reference to previous determinations in support of their client‟s dispute. In one determination (Determination No 40607) the Panel raised the issue with a definition of “flood”. The Applicant‟s solicitor has indicated that the policy definition is similar to this case. 16. The Panel does not concur that the definitions referred to are similar. Further, the Panel noted in Determination 40607 that there was an issue with information provided at the point of sale as “ The member has not been able to provide any information as to whether or when the Product Disclosure Statement and/or policy were for warded to the Appli cant.” 17. The Applicant‟s solicitor has referred to Determination 41709 which discussed a flood definition that included rainwater mixing with water coming from a watercourse. The Panel is uncertain as to how that determination is applicable in the context of the flood exclusion relied upon in this dispute as there is no reference to rainwater mixing with floodwater in the exclusion. 18. The solicitor has raised issue with the reports relied upon by the FSP in that they should not be considered as they do not assist the investigation of the claim. The solicitor has asked that the site specific hydrology report, dated six months after the event, not be relied upon due to the significant time that has passed. The solicitor referred to Determination 238186 to support this position. 19. However the Panel noted it was agreed between the parties that the FSP obtain a site specific report even though this was somewhat delayed. The Applicant‟s solicitor has been provided with the report and has had opportunity to dispute the findings of this report. The Panel sees no reason as to why this report should now not be considered. 20. In the circumstances of this dispute, it has not been argued by the Applicant‟s solicitor that a copy of the policy or PDS was not provided to the Applicant but rather it is argued:  The policy contains language that is unclear and ambiguous and the overall framework of the provision is complex and confusing;  A person of average intelligence would have great difficulty in understanding whether damage caused b y wet weather events would be covered by the policy. Case No: 246515 Determination Page 5 of 8 21. The Panel has considered the policy and is unsure as to what aspects of the policy the Applicant had difficulty understanding. The Panel is satisfied the flood definition is clear, the policy appropriately indexed and the exclusion for flood is found within the general exclusions. 22. Further, it is the Applicant‟s responsibility to read the policy and relevant material to ensure they have obtained the appropriate cover for their needs. There is no indication the Applicant sought clarification from the FSP as to the extent of cover following receipt of the PDS. 23. As it has not been disputed the Applicant was provided with the PDS, the Panel accepts the FSP complied with section 35 the Act and is satisfied the A pplicant‟s policy did not cover flood. Storm event 24. It is not in dispute that an extreme weather event took place. The Applicant‟s solicitor has argued that the damage to the Applicant‟s property was the result of water inundation from a drain prior to any flooding having occurred. 25. Alternatively, it is argued that multiple events of storm and rainwater occurred prior to any flood water. 26. The solicitor has been critical of the FSP‟s reliance on a generic hydrology report and that it should not be relied upon as it is not site specific. The solicitor has cited Determination 238186 to support this. 27. The FSP has stated only part of the information it relied upon is generic and that consideration needs to be given to the loss assessor‟s report, the interactive flood mapping and the recently obtained site specific hydrology report. 28. The hydrology report commissioned by the Insurance Council of Australia is an extensive report which covers the flooding in the Brisbane River catchment that occurred in January 2011. The report contains rainfall information and water gauge level information from the Brisbane River and Bundamba Creek River and therefore has some relevance. 29. Nevertheless, the FSP obtained a site specific report that was agreed to. The site specific report contained the following information which has not been disputed:  The house at the subject property was inundated to a peak depth of approximately 1.0 metre above floor level.  The floor level of the house is approximately 0.8m above the surrounding ground level. 30. The Applicant provided the following information to the FSP‟s hydrologist (W):  It rained heavily on 11 January 2011. Case No: 246515 Determination Page 6 of 8  Water pooled in the open stormwater drain located to the west of the subject property.  The Applicant left the property late afternoon on 11 January 2011.  The Applicant saw water had started to inundate Christine Street near his property and was steadily rising. Water had not entered his property at this time. 31. W made the following findings:  The subject property is located approximately 340m south of Bundamba Creek.  An open stormwater drain passes through parkland about 120m to the west of the subject property and joins Bundamba Creek 350m north-west of the subject property.  The open stormwater drain and Bundamba Creek have defined beds a nd banks and both would be categorised as watercourses.  Located approximately 1.4km north-west of the subject property is Bundamba (Hanlon St) Alert rainfall station.  The peak 1 hour rainfall intensity of 16.3mm/hr occurred at 1400 hours on 11 January 2011.  Peak stormwater run-off from the catchment of the nearby stormwater drain would have occurred within 1 hour after the most intense rainfall.  No significant rainfall was recorded at the Bundamba (Hanlon St) Alert rainfall station after 1700 hours on 11 Ja nuary 2011.  The recorded local rainfalls in the vicinity of the subject property were not particularly severe for short durations (less than 1 year Average Recurrence Interval for all durations).  Peak water levels in Bundamba Creek at Bundamba (Hanlon St) Alert occurred at 1500 hours on 12 January 2011. Water levels at the subject property would have peaked at the same time  Water observed backing up in the nearby stormwater drain on the afternoon of 11 January 2011 was predominantly backwater from Bundamba Creek (and indirectly from the Bremer River), not local stormwater run-off. 32. W made the following conclusions:  Given the low intensity recorded at the subject property and the fact the house was not inundated above the floor level late on 11 January 2011, the property could not have been inundated by stormwater run-off.  The house at the subject property was inundated above floor level by Bremer River floodwater which had flowed back up into Bundamba Creek and the nearby stormwater drain, before overflowing to inundate properties in Christine St. Case No: 246515 Determination Page 7 of 8 33. The Applicant‟s solicitor disputes that the stormwater drain is a watercourse. Further the policy does not define watercourse and the terms drain, stormwater channel and watercourse have separate terms in the policy and should not be substituted for the other. 34. It is argued that the damage was the result of stormwater inundation from the drain and surrounding drains prior to flood water. 35. In response to this W advised: “The water which inundated the property most certai nly originated from a watercourse; the Bremer River. Note that during the January 2011 flood event, the width of flooding of the parkland area at the end of Christine Street would have been about 250 metres, which is much greater than the width of the channel (about 10 metres). Hence, the vast majority of water that inundated the property would have travelled from Bundamba Creek as overbank flow through the parkland area surrounding the open channel, and not within the channel banks.” 36. The policy defines “flood” to include water that escapes or is released from the confines of a watercourse or stormwater channel. 37. Having reviewed all of the evidence in respect of the drain or water channel contained within the parkland from where the water inundation occurred from, the Panel is satisfied that drain referred to would constitute a watercourse and/or stormwater channel. 38. However, even if this feature were classified as a drain, where water from a drain combines with floodwater and then inundates a property, it is established law that the combined water would be properly described as floodwater for the purposes of the exclusion. 39. Having considered the evidence made available by the parties to this dispute, the Panel is satisfied that, on the balance of probabilities, the insured property was inundated by flood water overflowing from Bundamba Creek and backing up in to the stormwater system. On the basis of established law, this water is also properly categorised as flood water. 40. For the Applicant to be successful in this matter, he needs to show the damage has been caused by an event covered by the policy. According to the terms of the Applicant‟s policy, damage is covered only in circumstances where run -off alone caused the damage. The Panel has considered whether the initial inundation may have been run-off. There is no evidence to support this. 41. The policy does not cover loss or damage caused by flood. It follows that the Applicant‟s claim does not succeed. 42. In the Panel‟s opinion, the evidence leads to the conclusion t hat on the balance of probabilities the FSP has discharged the onus that rests with it to show the cause for the damage was flood, which is not covered by the policy. Case No: 246515 Determination Page 8 of 8 Determination 43. On the basis of the available information, the Panel determines that the FSP was entitled to deny liability for the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.