Text of the determination
Case No: 246515 Determination Page 1 of 8
Case number: 246515
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
13 January 2012
Background
1. The Applicant and his wife are insured under a home building and contents
insurance policy that commenced on 1 December 2002 and was renewed
annually. The policy is current until 2 December 2011.
2. On 12 January 2011, the Applicant contacted the Financial Services Provider
(FSP) to report damage had occurred at the property as a result of water
inundation.
3. The Financial Services Provider (FSP) denied the claim on the ground that the
loss was as a result of water escaping and overflowing from the Bundamba
Creek. This falls within the policy‟s definition of “flood” and is excluded.
Summary of Applicant’ s Position
4. The Applicant is seeking cover under the policy for the damage caused to the
insured property which is estimated to be in excess of $50,000.
5. The issues raised by the Applicant‟s solicitor in his letter dated 28 September
2011 included:
The FSP‟s failure to discharge its obligations under section 35 of the
Insurance Contracts Act 1984 (the Act);
The FSP did not adequately investigate the claim and has relied upon a
generic hydrology report;
The Applicant‟s home was affected by multiple events. Before any riverine
flooding occurred, stormwater run-off and rain caused damage to the
property.
6. In a letter dated 21 October 2011, the Applicant‟s solicitor also stated damage
was caused by water inundating the property from a drain, or rather „pipe
backflow‟ flooding, prior to any overland flow. As such, this is covered by the
policy.
Determination
Case No: 246515 Determination Page 2 of 8
Summary of FS P’s Position
7. The FSP states:
Floodwater from the Bundamba Creek flowed southwards into MJ
Kinnane Park, where it promptly mixed with stormwater that had escaped
from the drain in the park;
The floodwater mixed with stormwater and flowed eastward where it
crossed David St, and flowed uphill into Christine St where it inundated
the Applicant‟s home;
It does not accept that stormwater alone crossed the streets and travelled
uphill to inundate the Applicant‟s home;
It is not required to accept a claim where damage is caused by a mixture
of floodwater (which is excluded under cover of the policy) and water
escaping from a drain.
The policy wording is clear and effective.
8. The FSP relies on the following policy provisions:
“ Home Building Insurance Policy
What we cover – insured events
You are covered for damage or loss to your home building occurring during
the period of cover and caused by the following events:
Yes
Storm and rainwater including stormwater run-off from areas surrounding the
site, or water escaping from any water main, drain, pipe, street gutter,
guttering or surface.
No
Damage or loss caused by flood. Flood means the inundation or covering of
normally dry land by water which:
escapes or overflows from, or
cannot enter, because it is full or has overflowed, or
is prevented from entering, because other water has already escaped or been
released from it,
the normal confines of any watercourse or lake, including any that may have
been modified by human intervention, or reservoir, canal, dam or stormwater
channel.
…
What we do not cover – general exclusions
You are not covered under any section of the policy for damage, loss, cost or
liability caused by or arising from or involving:
flood,
…
Home Contents Insurance Policy
Case No: 246515 Determination Page 3 of 8
What we cover – insured events
You are covered for damage or loss to your contents while they are in your home
or at the site, occurring during the period of cover, caused by the following
events:
Yes
Storm and rainwater including stormwater run-off from areas surrounding the
site, or water escaping from any water main, drain, pipe, street gutter, guttering
or surface.
No
Damage or loss caused by flood. Flood means the inundation or covering of
normally dry land by water which:
escapes or overflows from, or
cannot enter, because it is full or has overflowed, or
is prevented from entering, because other water has already escaped or been
released from it,
the normal confines of any watercourse or lake, including any that may have
been modified by human intervention, or reservoir, canal, dam or stormwater
channel.
…
What we do not cover – general exclusions
You are not covered under any section of the policy for damage, loss, cost
or liability caused by or arising from or involving:
flood ”
9. For the avoidance of doubt, the FSP has also confirmed that the policy covers
water which has escaped from a drain, even if the water escaping is sourced
from a nearby flooding watercourse, itself separated from the policyholder‟s
property on higher ground.
Issues
10. Whether the FSP has discharged its obligations under section 35 of the Act to
clearly inform the Applicant of the terms of its policy, and as such is entitled to
rely on its flood exclusion;
11. Whether the damage claimed by the Applicant was caused by flood as defined
by the policy.
Reasons for Decision
12. Due to the nature of the dispute, this matter has been referred to the Panel for
a Determination in line with the Operational Guidelines to the Financial
Ombudsman Service‟s Terms of Reference.
Case No: 246515 Determination Page 4 of 8
13. The Panel consists of an Ombudsman, a representative with extensive
experience in insurance industry matters and a representative with extensive
experience in consumer claims.
14. There has been an exchange of information between the parties and the Panel
is satisfied that the parties have had the opportunity to respond to the issues
raised.
15. The Applicant‟s solicitor has in a letter dated 28 September 2011, made
reference to previous determinations in support of their client‟s dispute. In one
determination (Determination No 40607) the Panel raised the issue with a
definition of “flood”. The Applicant‟s solicitor has indicated that the policy
definition is similar to this case.
16. The Panel does not concur that the definitions referred to are similar. Further,
the Panel noted in Determination 40607 that there was an issue with
information provided at the point of sale as “ The member has not been able to
provide any information as to whether or when the Product Disclosure
Statement and/or policy were for warded to the Appli cant.”
17. The Applicant‟s solicitor has referred to Determination 41709 which discussed a
flood definition that included rainwater mixing with water coming from a
watercourse. The Panel is uncertain as to how that determination is applicable
in the context of the flood exclusion relied upon in this dispute as there is no
reference to rainwater mixing with floodwater in the exclusion.
18. The solicitor has raised issue with the reports relied upon by the FSP in that
they should not be considered as they do not assist the investigation of the
claim. The solicitor has asked that the site specific hydrology report, dated six
months after the event, not be relied upon due to the significant time that has
passed. The solicitor referred to Determination 238186 to support this position.
19. However the Panel noted it was agreed between the parties that the FSP
obtain a site specific report even though this was somewhat delayed. The
Applicant‟s solicitor has been provided with the report and has had opportunity
to dispute the findings of this report. The Panel sees no reason as to why this
report should now not be considered.
20. In the circumstances of this dispute, it has not been argued by the Applicant‟s
solicitor that a copy of the policy or PDS was not provided to the Applicant but
rather it is argued:
The policy contains language that is unclear and ambiguous and the
overall framework of the provision is complex and confusing;
A person of average intelligence would have great difficulty in
understanding whether damage caused b y wet weather events would be
covered by the policy.
Case No: 246515 Determination Page 5 of 8
21. The Panel has considered the policy and is unsure as to what aspects of the
policy the Applicant had difficulty understanding. The Panel is satisfied the flood
definition is clear, the policy appropriately indexed and the exclusion for flood is
found within the general exclusions.
22. Further, it is the Applicant‟s responsibility to read the policy and relevant
material to ensure they have obtained the appropriate cover for their needs.
There is no indication the Applicant sought clarification from the FSP as to the
extent of cover following receipt of the PDS.
23. As it has not been disputed the Applicant was provided with the PDS, the Panel
accepts the FSP complied with section 35 the Act and is satisfied the
A pplicant‟s policy did not cover flood.
Storm event
24. It is not in dispute that an extreme weather event took place. The Applicant‟s
solicitor has argued that the damage to the Applicant‟s property was the result
of water inundation from a drain prior to any flooding having occurred.
25. Alternatively, it is argued that multiple events of storm and rainwater occurred
prior to any flood water.
26. The solicitor has been critical of the FSP‟s reliance on a generic hydrology
report and that it should not be relied upon as it is not site specific. The solicitor
has cited Determination 238186 to support this.
27. The FSP has stated only part of the information it relied upon is generic and
that consideration needs to be given to the loss assessor‟s report, the
interactive flood mapping and the recently obtained site specific hydrology
report.
28. The hydrology report commissioned by the Insurance Council of Australia is an
extensive report which covers the flooding in the Brisbane River catchment that
occurred in January 2011. The report contains rainfall information and water
gauge level information from the Brisbane River and Bundamba Creek River
and therefore has some relevance.
29. Nevertheless, the FSP obtained a site specific report that was agreed to. The
site specific report contained the following information which has not been
disputed:
The house at the subject property was inundated to a peak depth of
approximately 1.0 metre above floor level.
The floor level of the house is approximately 0.8m above the surrounding
ground level.
30. The Applicant provided the following information to the FSP‟s hydrologist (W):
It rained heavily on 11 January 2011.
Case No: 246515 Determination Page 6 of 8
Water pooled in the open stormwater drain located to the west of the
subject property.
The Applicant left the property late afternoon on 11 January 2011.
The Applicant saw water had started to inundate Christine Street near his
property and was steadily rising. Water had not entered his property at
this time.
31. W made the following findings:
The subject property is located approximately 340m south of Bundamba
Creek.
An open stormwater drain passes through parkland about 120m to the
west of the subject property and joins Bundamba Creek 350m north-west
of the subject property.
The open stormwater drain and Bundamba Creek have defined beds a nd
banks and both would be categorised as watercourses.
Located approximately 1.4km north-west of the subject property is
Bundamba (Hanlon St) Alert rainfall station.
The peak 1 hour rainfall intensity of 16.3mm/hr occurred at 1400 hours on
11 January 2011.
Peak stormwater run-off from the catchment of the nearby stormwater
drain would have occurred within 1 hour after the most intense rainfall.
No significant rainfall was recorded at the Bundamba (Hanlon St) Alert
rainfall station after 1700 hours on 11 Ja nuary 2011.
The recorded local rainfalls in the vicinity of the subject property were not
particularly severe for short durations (less than 1 year Average
Recurrence Interval for all durations).
Peak water levels in Bundamba Creek at Bundamba (Hanlon St) Alert
occurred at 1500 hours on 12 January 2011. Water levels at the subject
property would have peaked at the same time
Water observed backing up in the nearby stormwater drain on the
afternoon of 11 January 2011 was predominantly backwater from
Bundamba Creek (and indirectly from the Bremer River), not local
stormwater run-off.
32. W made the following conclusions:
Given the low intensity recorded at the subject property and the fact the
house was not inundated above the floor level late on 11 January 2011,
the property could not have been inundated by stormwater run-off.
The house at the subject property was inundated above floor level by
Bremer River floodwater which had flowed back up into Bundamba Creek
and the nearby stormwater drain, before overflowing to inundate
properties in Christine St.
Case No: 246515 Determination Page 7 of 8
33. The Applicant‟s solicitor disputes that the stormwater drain is a watercourse.
Further the policy does not define watercourse and the terms drain, stormwater
channel and watercourse have separate terms in the policy and should not be
substituted for the other.
34. It is argued that the damage was the result of stormwater inundation from the
drain and surrounding drains prior to flood water.
35. In response to this W advised:
“The water which inundated the property most certai nly originated from a
watercourse; the Bremer River. Note that during the January 2011 flood event,
the width of flooding of the parkland area at the end of Christine Street would
have been about 250 metres, which is much greater than the width of the
channel (about 10 metres). Hence, the vast majority of water that inundated the
property would have travelled from Bundamba Creek as overbank flow through
the parkland area surrounding the open channel, and not within the channel
banks.”
36. The policy defines “flood” to include water that escapes or is released from the
confines of a watercourse or stormwater channel.
37. Having reviewed all of the evidence in respect of the drain or water channel
contained within the parkland from where the water inundation occurred from,
the Panel is satisfied that drain referred to would constitute a watercourse
and/or stormwater channel.
38. However, even if this feature were classified as a drain, where water from a
drain combines with floodwater and then inundates a property, it is established
law that the combined water would be properly described as floodwater for the
purposes of the exclusion.
39. Having considered the evidence made available by the parties to this dispute,
the Panel is satisfied that, on the balance of probabilities, the insured property
was inundated by flood water overflowing from Bundamba Creek and backing
up in to the stormwater system. On the basis of established law, this water is
also properly categorised as flood water.
40. For the Applicant to be successful in this matter, he needs to show the damage
has been caused by an event covered by the policy. According to the terms of
the Applicant‟s policy, damage is covered only in circumstances where run -off
alone caused the damage. The Panel has considered whether the initial
inundation may have been run-off. There is no evidence to support this.
41. The policy does not cover loss or damage caused by flood. It follows that the
Applicant‟s claim does not succeed.
42. In the Panel‟s opinion, the evidence leads to the conclusion t hat on the balance
of probabilities the FSP has discharged the onus that rests with it to show the
cause for the damage was flood, which is not covered by the policy.
Case No: 246515 Determination Page 8 of 8
Determination
43. On the basis of the available information, the Panel determines that the FSP
was entitled to deny liability for the claim.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.