Text of the determination
Case No: 246151 Determination Page 1 of 8
Case Number: 246151
General Insurance – Home Building – Storm damage - Quantum
7 March 2012
Background
1. The Applicant insured his home building under an Accidental Damage Home
Building Insurance Policy for $450,000 with a $100 policy excess. The period of
insurance was 22 February 2010 to 22 February 2011.
2. On or about 5 December 2010, the Applicant‟s garage suffered storm damage.
Before repairs for the storm damage could be completed the property suffered
flood water inundation on or about 11 January 2011.
3. The Applicant obtained a quotation from a builder for the amount of $16,764,
including GST, to repair the storm damage to the garage.
4. On the advice of an external loss assessor but many months later, the Financial
Services Provider (FSP) appointed a consulting engineer to report on what
would have been storm damage and damage caused by the flood water
inundation.
5. The engineer reported that the builder‟s quotation for works was a reasonable
assessment of the costs associated with the total repairs required. However,
the engineer estimated the cost of repairs should be $10,710, including GST,
after deducting the following items:
Repair rotted timberwork and make good framing;
Water proofing and re-tiling of roof deck.
6. The FSP accepted t he engineer‟s estimate and cash settled the applicant for
the amount of $10,710 less the $100 policy excess.
7. The Applicant disputes the FSP decision in reducing the cost of repairs by
$6,054.
Summary of Applicant’s Position
8. The Applicant‟s property suffered damage in December 2010 arising from many
storms that swept through the Brisbane area. He arranged for emergency tarps
Determination
Case No: 246151 Determination Page 2 of 8
to be installed and obtained a quote from a builder to carry out repairs for the
amount of $16,764.
9. He states the FSP obtained two quotes for repairs and also had an engineer
submit a quote which the FSP accepted. However, the FSP has not explained
how it „averaged out‟ the multiple estimates to arrive at its payment amount of
$10,710. It has also not provided him with copies of the other two quotes.
10. The Applicant had to pay the amount of $16,764 because he could not wait
until July 2011 for repairs to be completed as the garage was still covered by
the tarpaulin.
11. The FSP has failed to mention that its external assessor provided a quotation
for repairs prior to the assessment by the engineer. The assessor assured the
Applicant that the quote the Applicant had received was reasonable and his
claim would be accepted.
12. The FSP‟s engineer‟s estimate of $10,710 exc luded waterproofing and retiling.
However, the FSP was aware that he had purchased the tiles himself and had
not made a claim on the FSP for these. The cost of the tiles was in excess of
$1,000. Further, his builder also did not include the cost of the tiles in his quote.
13. The FSP has stated that it is not responsible for the cost of waterproofing of the
tiles. He agrees with this. However, the FSP has not justified how the pouring of
the waterproof material over the roof of such a small area would cost $6,000.
14. The FSP has made reference to the cost of replacing various timber support
structures which had deteriorated. At no point did his builder‟s estimates or
quotations include the cost of replacement timbers.
15. The builder did not bill him for that work and therefore was not costed as a
separate issue. The FSP‟s engineer also did not provide an estimate for that
work. Further, the timber has simply been allowed to dry out and has been re-
sheeted over with plaster. There was no new timber involved in the repairs and
no new studs or noggins were inserted during the course of repairs.
16. The FSP has accepted the engineer‟s estimate of $10,710 to carry out repairs.
However, the FSP has not provided any copies of other quotes it obtained and
has not been open and reasonable about the whole matter.
17. In the FSP‟s letter dated 11 October 2011, it stated that repairs that would not
be covered included the lifting of roof tiles. However, in the engineer‟s scope of
works he stated:
„The following works would have been necess ary to repair the garage area:
...
Locate the cause of the water leak. This would most likely have required the
removal of the roof tiles unless the cause of the leak was found to be in the
box gutter.‟
Case No: 246151 Determination Page 3 of 8
18. There is no reference attached to that dot point to say that this cost should be
incurred by the Applicant but rather the cost of lifting the tiles and locating the
leak is borne by the FSP.
19. In reference to the „rotting timber‟, his builder did not quote for the replacement
of rotting timber nor did he make any corrections on the basis of older rotting
timber. The timber was simply allowed to dry out and has been re-sheeted with
plaster.
20. The Applicant contends that the FSP‟s engineer agreed that his builder
quotation was fair and reasonable. However, the FSP does not explain why
there is a $6,000 disparity between the engineer‟s estimate and the builder‟s
quotation.
21. The problem is that the professional estimate of costs does not concur with his
builder‟s quotation despite the engineer accepting that the builder‟s costs are
fair and reasonable.
22. The Applicant disputes the FSP accepting the $6,000 disparity without
explaining how the poring of the waterproofing and the physical laying of the
tiles provided would account for the $6,000.
Summary of FSP’s Positio n
23. The FSP believes that the insurance repair cost of $10,700 is based on the
opinion of its expert civil engineer and the disparity between it and the actual
repair cost is explained by various policy exclusions.
24. The Applicant‟s builder submitted a quotation dated 2 February 2011 that
stated:
„All labour and materials to stabilize sagging ceilings and effect repairs as required to
garage roof above residence:
...
4. Repair rotted timber work and make good framing as required.
5. Lift all roof tiles.
6. Waterproof roof area as required.
7. Relay new tiles to roof area. [Tiles To $30.00 sqr. Mtr.]
...‟
25. The FSP was unaware all of the repairs had been undertaken and determined
that an expert causation report was necessary for the following reasons:
The close proximity of the storm and flood events created a possibility of
some overlap in damage;
Case No: 246151 Determination Page 4 of 8
It was unclear how water had entered the garage roof – through the
gutters or through poorly maintained roof tiles.
26. The FSP engaged a civil engineer to investigate the damage and prepare a
causation report which included the following estimate of repairs which are
covered under the policy.
‘3.2 Estimate of Costs – Insurance Works Only
It is our opinion that the insurance repair cost to the garage should have been in the
vicinity below estimate; and only includes those works where the policy may respond.
Any repair cost for those parts that gave rise to the event have been excluded – i.e.
water proofing and re tiling.
Building preliminaries – Supervision, insurances Waste, final clean etc. $2,850.00
Temporary make safe and carpentry repair $1,500.00
Removal and reinstallation of garage door $200.00
Wall and ceiling sheeting replacement including cornice
and battens – 80 square metres @ $37/m2 $2,960.00
Painting Approximately 80 m2 @ $25/m2 $2,000.00
Electrical and other incidentals $1,200.00
Total - including builders margins and GST $10,710.00 ’
27. The above figures exclude the cost of supplying roof tiles over and water
proofing that may have been required.
28. The Applicant‟s builder‟s quote included repair to rotted timber work and make
good as required. It would be unlikely if the damage to the garage was solely
due to the single storm event of December 2010 that the timber work would
have rotted in this period.
29. Therefore, the FSP is of the opinion that if rotting to the timber work did occur
the water leak must have been present for a long period of time and gone
undetected.
30. The enginee r considered the builder‟s quotation was a reasonable assessment
of the costs associated with total repairs. However, the engineer stated that the
quote appeared to include costs payable by the applicant, that is, water
proofing and re tiling the deck roof.
31. The FSP submits the disparity in the two estimates can be attributed to:
1. The cost of water proofing the roof tiles (which is an improvement and
therefore not covered under the policy), and
Case No: 246151 Determination Page 5 of 8
2. The cost of replacing various timber support structures which had
deteriorated as a result of wear, tear or gradual deterioration which is
excluded from the cover provided by the policy.
32. Therefore, the reasonable cost of effecting repairs which are covered under the
policy is $10,710.00 as estimated by the engineer.
33. The Applicant has not provided any evidence to suggest that the difference in
the actual and insured repair costs can be attributed to anything other than the
policy exclusions.
34. The FSP relies on the following policy/contract provisions:
‘Section 2: Cover fo r your Home & Contents – Accidental Damage
What you are insured against, and what you are NOT
You are insured against accidental loss or damage (including the Specified Events
listed below) to your home, contents or both at the site during the period of insurance.
Property that belongs to your family or for which you or your family are legally
responsible will be treated as though it is your property.
Specified Events „Specified Events means loss or damage directly caused by the
following events (a) to (s):
...
(q) storm, tempest, rainwater, wind, hail, tornado, cyclone or hurricane, freeze or
weight of snow
...
How we will pay
Home
(a) At our option we:
...
Replace the home to a condition substantially the same as, but not better
than when new,
...
...
When you are not covered
...
Additional exclusions applying to this Policy
These additional exclusions apply to cover for your home, contents, additional
benefits and „Options you can choose for an additional premium‟.
...
(b) loss or damage resulting from or caused by:
wear, tear, rust, corrosion, depreciation or gradual deterioration
...‟
Case No: 246151 Determination Page 6 of 8
Issues
35. Whether the FSP has settled the Applicant‟s claim in accordance with the terms
and conditions of the policy of insurance in a fair and reasonable manner.
Reasons for Decision
36. There has been an exchange of material which the parties rely on. Each party
has had access to the material on which the other party bases its case. As a
consequence it is not necessary to go into all of this material in any great detail.
37. There is no dispute that the Applicant‟s garage suffered storm damage on or
about 5 December 2010. The Applicant eventually – after long delays by the
FSP - engaged a builder to repair the damage at a cost of $16,764.00 which
included relacing rotted timber and lifting all roof tiles, waterproofing the roof
and re-laying the tiles.
38. The FSP therefore – six months after the claim was lodged - engaged a
building engineer to inspect and report on the damage. Due to the possibility of
further damage occurring, the Applicant, by this time and after many complaints
to the FSP, had the builder complete the necessary repairs.
39. The engineer estimated that the cost of repairs covered by the policy of
insurance to be $10,710.00 including builder‟s margin and GST. The engineer
considered the cost of repairing rotted timber and re-tiling and waterproofing
the roof was not due to any storm damage.
40. Accordingly, the FSP cash settled the Applicant for the amount of $10,710 less
the $100 policy excess.
41. The dispute is in respect to whether or not the FSP is entitled to reduce the cost
of repairs paid by the Applicant, that is, $16,764.00, by $6,054.
42. In the engineer‟s report dated 20 June 2011 he stated:
„The quotation by [builder] includes “Item 4 – Repair rotted timberwork and
make good framing as required”. It would be unlikely if the damage to the
garage was solely due to the single storm event of December 2011 (should
have been 2010) that the timber work would have rotted in this period.
Therefore, it is our opinion that if rotting to the timberwork did occur that the
water leak must have been present for a long period of time and gone
undetected.
Deterioration was still visible to a section of the door framing timer located
above the tilt panel door.‟
43. Although the engineer recommended the FSP have the builder split up his
costs and submit them to the FSP, it appears the FSP did not make any
attempt to do so.
Case No: 246151 Determination Page 7 of 8
44. However, as these costs of the timber and roofing repairs are critical to this
dispute, FOS, through the Applicant, contacted the builder who supplied the
necessary costs.
45. The builder‟s correspondence received by FOS on 13 February 2012,
confirmed the following costs for:
Repair rotted timbers $1,771.00
Waterproofing and re-tiling garage roof $4,414.85
Total $6,185.83
The costs include 15% builder‟s margin and GST.
46. The FSP‟s engineer did not arrive at an estimated cost for these repairs but had
not considered them when arriving at the estimate of the cost of the storm
damage to the garage.
47. The engineer‟s cost estimate was $10,710, the Applicant‟s builder‟s cost was
$16,764, a variance of $6,054 which is very close to the engineer‟s variance
and favours the Applicant in the settlement of the claim.
48. I have carefully considered what I believe to be unreasonable delays on the
part of the FSP and as enumerated by the Applicant in his many complaints. I
have considered whether an award of compensation under Paragraph 9.3 b) (i)
of this Service‟s Terms of Reference is justified.
49. Paragraph 9.3 b) (i) is as follows:
“ 9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide
that the Financial Services Provider compensate the Applicant for
consequential financial loss or damage up to a maximum amount of
$3,000 per claim made in the Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide
that the Financial Services Provider compensate the Applicant for
non-financial loss but only where:
(i) an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with the
Applicant’s expectation of enjoyment or peace of mind
has occurred; or
…”
Case No: 246151 Determination Page 8 of 8
50. Ultimately I have decided that it is not appropriate to make such an award,
having regard only to the extreme pressure being experienced by insurers
following the Brisbane floods.
Determination
51. Accordingly, I determine that the FSP has settled the Applicant‟s claim in a fair
and reasonable manner and is not liable to make any further payments.