Home / Financial Firm (Unknown - Insurer) / Determination 246067
Determination 246067
Partial denial of shade sail support post replacement for faulty design and workmanship
Summary
The applicant's shade sail support posts were denied as faulty design and workmanship, and she complained about service delays. AFCA determined the FSP must indemnify the replacement posts with interest, but refused the service compensation and apology.
The FSP did not establish that the post failure was caused by faulty design or workmanship the applicant knew or should have known about, so the policy exclusion did not apply.
Issues
- Claim denial primary · upheld
“I determine that the FSP is obliged to indemnify the Applicant for the losses which she has sustained, including the replacement of the posts.”
- Delay secondary · not upheld
“I do not now consider it appropriate for an award of compensation under this heading.”
Subjects and remedies
pay claimpay interest
Text of the determination
Case No: 246067 Determination Page 1 of 6
Case number: 246067
General Insurance - Domestic Insurance - Home Building - Service - Delay in
Claim Handling - Faulty Design and Workmanship
1 March 2012
Background
1. The Applicant held a home building insurance policy with the Financial Services
Provider (FSP) which was current at the time of the loss.
2. It appears that the storm which had caused the damage had occurred on
approximately 1 January 2011.
3. Whilst the FSP accepted the claim for the sail shade, the FSP has denied the
claim for the cost of the shade supports. It suggests that these need to be
replaced due to a design fault and poor workmanship when the posts were
originally installed.
4. The Applicant disagreed with the FSP’s decision to deny this portion of her
claim.
5. The Applicant has also expressed concern about various matters affecting the
service provided by the FSP during the claims process.
6. When the matter was referred to this Service, it was the subject of a
Recommendation. On 2 December 2011, after carefully considering all of the
material and the various submissions made by the parties, a Case Manager
recommended that the FSP settle the Applicant’s claim based upon the lower
quotation of $11,207.59 less any sum already paid.
7. The Case Manager also recommended that the Applicant should be issued with
a formal written apology because of the service issues which she had
encountered throughout the claims process, and that the FSP pay the Applicant
$500 compensation.
8. Whilst the Applicant accepted this Recommendation, the FSP did not. When
rejecting the Recommendation, it made further submissions and attached
information provided by its contractors which was of particular relevance both to
the question of pre-existing problems with the sails and as to the service issues
about which the Applicant has made complaint.
Determination
Case No: 246067 Determination Page 2 of 6
Summary of Applicant’s Position
9. The Applicant says the sail shade was installed in 2008 and despite other
heavy storms the shade has never collected rainwater and failed.
10. The Applicant further says her property is in good condition and well
maintained.
11. The Applicant submits the FSP’s expert has incorrectly detailed the material
used for the shade and that the posts were not concreted into the ground.
12. In response to claims by the FSP that the Applicant had experienced previous
problems with the sails and that water had collected in them earlier, the FSP
has denied that she informed the contractors of the FSP of any such thing. She
emphatically denies that there has ever been a collection of water prior to this
incident.
13. On the question as to tension and the sail, the Applicant says “I did tell B & A
(representatives of the FSP) that the original sail company had checked the
tension of the sail (which I thought was a normal practice with a new sail), I did
not say the sail had been retens ioned “numerous times”. They only checked it
the once.”
14. On the question of stretching of the sail and the collection of water in the sail,
the Applicant says “I did not advise B that “when it rained the sails would
stretch”. B’s suggestion that I had “advised sails used to fill with water every
time it rained” is a complete fabrication. First there was only one sail, not
multiple sails, second I have never advised nor implied that the sail was in the
habit of stretching when it rained. It had not done so on any occasion before, let
alone “every time it rained”. The first time I had this problem is the subject of
this claim.”
Summary of FSP’s Position
15. The FSP says it is not liable to indemnify the Applicant for the original assembly
of the sail shade due to faulty design and worksmanship when it was first
installed.
16. The FSP relies on the following policy provision contained within the Product
Disclosure Statement (PDS) which the Applicant does not dispute receiving:
“We don’t cover loss, damage, injury or death arising from:
...
faulty design or workmanship that you knew about or should have reasonably known
about ”
17. When rejecting the Recommendation, the FSP supplied information that the
Applicant had informed an assessor that “she had the original sail company
attend her home to retension the sails on numerous times. The insured clearly
Case No: 246067 Determination Page 3 of 6
advised that when it rained the sails which stretched, therefore the sails would
have to be retens ioned”.
18. The FSP also supplied detailed information from its assessor as to her conduct
in the handling of the matter. These matters were relevant to the
recommendation that an apology should be offered, and that the Applicant
should be paid $500 by way of compensation.
Issue
19. Whether the FSP is entitled to parti ally deny the Applicant’s claim.
Reasons for Decision
20. I am satisfied a full exchange of information has taken place between the
parties and that each party has had the opportunity of addressing any issues
raised therein.
21. There is no dispute that a storm event took place which resulted in damage to
the Applicant’s sail shade. The FSP has partially admitted the claim as it is
clear that damage occurred as a result of a storm event such as is covered
under the policy.
22. But the question which has arisen is whether the FSP is liable to provide cover
for the replacement of the supporting posts. As to this aspect, the FSP argues
that the posts require replacing because they are a faulty design and
workmanship which has originated since the date of construction.
23. As to the subject, I note that the sails had apparently been in place for some 2
to 3 years.
24. In the area in which this Applicant lives, there would have been many
significant storms during that period of time. I would have thought that if the
FSP’s argument th at the posts require replacing due to faulty design, poor
workmanship etc., the problems would have developed much earlier.
25. The Applicant provided a report from expert (S) as to the cause of the damage.
S reported:
“As requested the following is a description of how your shade sail, support
posts, anchor points in your roof wand water damage to your ceilings has come
about.
During the storm the wind has shaken your sail violently to the point where the
tension on the sail was compromised. This allowed water to collect in the sail,
creating enormous weight and strain on the support poles and the anchor points
through your roof. Consequently these gave way and exacerbated the problem
by allowing the sail to belly and collect even more water. The attachment points
in the roof have moved cracking the roof tiles allowing the water to fall through to
your ceiling.”
Case No: 246067 Determination Page 4 of 6
26. S also provided a quotation for the cost of replacing the sail and posts in the
sum of $11,207.59.
27. The Applicant obtained a further quotation and report from expert (SS). The
quotation amounted to $11,525.88 and the report detailed:
“Storms have shaken the sail & loosened the poles & footings in the ground
causing water to collect in the sail resulting in undue pressure to the structure.
Fitting a new sail to the existing poles will result in a repetition of the same
damage. Because of this I have allowed for new longer poles to be embedded
more securely.”
28. Faced with these opinions, the FSP appointed an expert to inspect the
structure. The expert “U” reported:
“SHADE SAIL HAS FAILED DUE TO POOR DESIGN, USE OF INFERIOR
TRUCK TARP AS SAIL FABRIC, AND BAD WORKMANSHIP.
NOT ENOUGH FALL HAS CAUSED TARP TO FILL WITH WATER STRETCH
BEYOND IT ELASTAC LIMIT MAKING IT UNUSABLE AND UNREPAIRABLE.
WEIGHT OF WATER HAS BENT ROOF FIXING POINTS WHICH ARE M20
TREADED ROD INSTEAD OF 75MM O.D. STEEL S.H.S. NO FLASHING
BOOTS HAVE BEEN USED TO SEAL RODS.
STEEL POSTS HAVE BEEN OVER LOADED BY THE LARGE AMOUNT OF
WATER HELD IN SAIL AN NEED RE FOOTING.
...
REPLACE WESTERN POST WITH MORE HEIGHT TO CREATE ENOUGH
FALL RE- FOOT TWO OTHER POSTS” (sic)
29. I interpret the reports from the various experts as establishing that, no doubt
with the benefit of hindsight, the original posts were not high enough to prevent
the collapse of the structure during an extreme storm event, however, I am
unable to reach the conclusion which is advanced by the FSP that this means
that the cause of the damage must, inevitably, be due to faulty design and
workmanship.
30. In any event, even if I considered that it had been established that there was
faulty design and workmanship, the entire history of the matter does not satisfy
me that the Applicant was reasonably aware of any such design faults or poor
workmanship.
31. When the FSP’s assessor has claimed that the sail had been the subject of “re -
tens ioning” numerous times, and that “the sails used to fill with water every time
it rained”, the Applicant has strenuously denied any such suggestion.
Importantly, she has advised that the sail had never stretched on any occasion
before, let alone every time it rained.
32. She is adamant that she had never seen the sail hold water before – “in spite of
the many storms, winds and showers that have been through here since it was
erected.”
Case No: 246067 Determination Page 5 of 6
33. Therefore, although I do not doubt that th e FSP’s assessor may have genuinely
believed that she was communicating information which had been given to her
by the Applicant, I am unable to accept that that information was correct.
34. I now turn to the Applicant’s claims in relation to inadequate servic e, and the
length of time to attend and address the issues.
35. In considering these matters, reference must be made to paragraph 9 of the
Terms of Reference for this Service. Paragraphs 9.2 and 9.3 are set out above:
9.2 Compensation for direct financial loss or damage
Subject to paragraph 9.7, FOS may decide that the Financial Services Provider
compensate the Applicant for direct financial loss or damage.
9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential
financial loss or damage up to a maximum amount of $3,000 per claim
made in the Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial
loss but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation
of enjoyment or peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual’s privacy rights –
injury has occurred to the Applicant’s feelings or humiliation has been
suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be
$3,000 per claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide
compensation for:
(i) consequential financial loss; or
(ii) non-financial loss,
In a Dispute arising as a result of a claim on a General Insurance Policy
that expressly excludes such liability.
d) The cap on liability in paragraph 9.3 a) does not in any way restrict FOS’s
ability to make an interest award under paragraph 9.5.
36. The Applicant is not suggesting that the delay has given rise to any direct
financial loss or damage, so that any compensation pursuant to paragraph 9.2
need not be considered.
37. The Applicant would, however, suggest that the delays of which she complains
should justify an award pursuant to 9.3.
38. It is important to note the wording of 9.3(b)(I).
39. As initially indicated by the Case Manager who noted that the FSP had not
countered the Applicant’s allegations of inadequate service, I should have
agreed with the Case Manager that this may be a matter appropriate for an
award of compensation under paragraph 9.3(b)(I).
Case No: 246067 Determination Page 6 of 6
40. However, in the material supplied by the assessor, some explanation is
provided for the chain of events which occurred. I do note that the Applicant
has not reported the matter until several weeks after the storm (although I note
that she suggests that she notified the FSP as soon as she became aware of
the damage).
41. Having taken into consideration the explanation which is provided by the FSP
and notwithstanding the comments by the Applicant, I do not now consider it
appropriate for an award of compensation under this heading.
42. Similarly, whilst the chain of events has caused significant concern to the
Applicant, I do not believe that the FSP has behaved so inappropriately as to
be required to apologise to her.
Determination
43. I determine that the FSP is obliged to indemnify the Applicant for the losses
which she has sustained, including the replacement of the posts.
44. As no challenge has been made to the sum of $11,207.59, being the lesser of
the quote provided by the Applicant, I determine that this sum be paid to the
Applicant together with interest upon such sum from 30 June 2011 until the
date of settlement.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.