Home / Financial Firm (Unknown - Insurer) / Determination 245016

Determination 245016

Claim declined as flood damage, partly reversed for stormwater runoff

FirmFinancial Firm (Unknown - Insurer)
Decided2012-12-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer declined a home claim for water damage from the January 2011 Brisbane flood under the flood exclusion. The Panel found the ultimate inundation was flood, but accepted the lower part of the home was first damaged by stormwater runoff and ordered indemnity for that damage with interest.

The flood exclusion applied to the final inundation, but the insurer had not rebutted direct evidence of earlier rainwater runoff damage, which falls within the storm, rain or runoff cover.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 245016 Determination Page 1 of 11 Case number: 245016 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion/ condition 7 November, 2012 Background 1. The Applicant’s home (located in Goodna, Queensland) and contents were insured with the Financial Services Provider (FSP) under a home building and contents policy. 2. His property was damaged as a result of water inundating his home in January 2011. 3. A claim was lodged with the FSP who declined liability on the basis the damage was caused by flood which the policy excluded. 4. The Applicant believes he is entitled to indemnity because:  He was misled into believing he was covered for flood damage ;  He was not clearly informed of the flood exclusion; and  His property was initially damaged by events covered by the policy in any event. Summary of Applicant’s position 5. The Applicant is represented. For convenience, the Applicant and his representative will be referred to in this Determination jointly as the Applicant. 6. He was misled into believing he was covered for flood damage because:  He took out the policy through “QRI”.  QRI was acting as the FSP’s “undisclosed agent”.  He asked for a “good comprehensive policy”.  QRI informed him that he was getting “comprehensive” cover.  He understood “comprehensive” cover to mean that he was covered for every event. Determination Case No: 245016 Determination Page 2 of 11 7. As a result of QRI’s “silent misrepresentation”, he did not seek insurance elsewhere believing he was covered for flood damage. 8. He was not clearly informed that the policy excluded flood damage because:  The policy definition of “flood” is too broad and oppressive as it also excludes damage caused by floodwater combined with runoff and/or rainwater.  Policyholders would be confused because the Product Disclosure Statement (PDS) initially informs them that they are covered for rainwater and runoff, but later says that damage caused by rainwater or runoff combined with flood is not covered.  Determinations 41709 and 40607 support the view that the policy ’s flood exclusion was unclear, unusual, and oppressive. 9. His property was damaged by rain and/or storm water runoff before it became inundated by floodwaters. His account of the events that transpired are as follows:  There was heavy rain on 10 January 2011.  He first not iced “storm water” flowing underneath the property at about “midday”.  It was flowing down the hill from Woogaroo Street towards a stormwater channel which was located about 100 feet behind the home. The stormwater channel drains into Woogaroo Creek which ultimately connects to the Brisbane River.  It damaged antiques that were stored under the house as it was already too late to remove them.  He arrived home from work at about 12.30pm on 11 January 2011.  It was still raining at the time and the roundabout at Goodna had about 1.5metres of water.  He noticed water coming up from the backyard, but there was still water flowing under the house, damaging contents, a concrete slab and the carport in the backyard. 10. Photos show the erosion caused by water running under the home towards the creek. 11. The FSP has not established that his property was damaged by flood because:  It relies on general hydrology information.  Its site specific hydrology report (dated 11 July 2011) was obtained more than 5 months after the event. Determination 41709 supports the view that the site specific hydrology report should not be relied upon. Case No: 245016 Determination Page 3 of 11 12. Determination 238186 supports the view that the obtaining of site specific hydrology information post claim denial is inconsistent with an obligation to act with utmost good faith. 13. The Applicant refers to section 35 of the Insurance Contracts Act, 1984 (the Act) and the Corporations Act, 2001 . Summary of FSP’s position 14. It did not mislead the Applicant as to the nature of its relationship with QRI or into believing he was covered for flood damage because:  The policy documentation clearly states that QRI acts as the FSP’s agent in the matter.  The policy documentation and renewals clearly state that flood damage was not covered.  These documents have been sent to the Applicant. 15. The Applicant was clearly informed that flood damage was not covered by the policy because:  The flood exclusion in the current dispute is not similar to the provision considered in Determination 41709.  FOS has recently determined (Determination 235302) that its product disclosure statement (PDS) fulfilled the requirements of section 35 of the Act. 16. The Applicant’s property was damaged by flood because:  Its loss adjusters have concluded that the damage was caused by flood.  The findings of the Insurance Council of Australia’s hydrology report entitled “Flooding in the Brisbane River Catchment January 2011 Volume 3 – Flooding in Ipswich LGA” (ICA report) show that the damage was caused by flood. 17. The FSP has referred to a significant number of policy provisions in its submissions. However, most do not appear to be directly relevant to the issues that are in dispute. Considering the nature of its submissions, the following provisions appear to be relevant for consideration: “ Words with special meanings … “ flood ” means the inundation of normally dry land by water that has escaped or has been released from the normal confines of any natural watercourse, lake or lagoon whether or not altered or modified or of any reservoir, canal or dam. [Note: This policy does not cover loss, liability, injury or damage caused by or arising from flood to buildings and/or contents] … Case No: 245016 Determination Page 4 of 11 9. Storm, rainwater or run-off (Applicable whether you have buildings and/or contents cover) We will pay for loss or damage caused by storm, rainwater or run-off. “ storm ” means violent wind (including cyclones and tornadoes), thunderstorms and hail which may be accompanied by rain or snow. “ rainwater ” means rain falling naturally from the sky onto buildings and/or ground. “ run-off ” means rainwater that has collected on or has flowed across normally dry ground or has overflowed from swimming pool or spas. We will not pay for loss or damage: caused by: flood, or flood water combined with run-off and/or rainwater; “flood” means the inundation of normally dry land by water that has escaped or has been released from the normal confines of any natural watercourse, lake or lagoon whether or not altered or modified or of any reservoir, canal or dam. … When we will not pay a claim under your policy … Unless we state differently in your policy, we will not pay for: flood as defined…; any loss or damage which is not caused directly by any one of the insured events;” 18. The FSP also relies on the following information contained in its renewal notices: “ Cover Summary … This insurance is provided by [the FSP]. In arranging this insurance, [QRI] acts as agent for [the FSP] and not as your agent. … Please note Flood is not covered by this policy.” 19. The FSP refers to sections 14, 35, 69, and 77 of the Act. Issues 20. Whether the Applicant was misled into believing he was covered for flood damage. 21. Whether the Applicant was clearly informed he was not covered for flood damage. Case No: 245016 Determination Page 5 of 11 22. Whether the Applicant’s loss was caused by storm, rainwater, run -off, and/or flood (as defined in the policy). Reasons for decision Preliminaries 23. Due to the nature of the dispute, it has been directly referred to the Panel for Determination in accordance with the Operational Guidelines to the Financial Ombudsman Service’s (FOS) Terms of Reference. 24. The Panel consists of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 25. The Panel notes that the Applicant is legally represented and that the various statutory provisions referred to by the parties have been set out in their respective submissions. For the sake of brevity, the Panel will not repeat these provisions here. 26. On 30 October 2012 the Panel Chair Ombudsman attended on site where he met with the Applicant and a representative of the FSP. Unawareness of flood exclusion 27. The Applicant has not premised his claim (of being unaware of the flood exclusion) on the basis he did not receive a PDS or his renewal notices. He claims to be unaware of the flood exclusion because:  QRI allegedly informed him he had “comprehensive” cove r; which he understood to mean he was covered for any event.  The relevant policy terms were allegedly unclear. 28. Having carefully considered the matter, the Panel is unable to accept the Applicant’s propositions for the following reasons:  The Applicant has provided minimal information as to what occurred at policy inception. Apart from asserting that he had asked for “comprehensive” cover and was advised he was provided with such cover, he offered no further information as to what specifically transpired when he took out the policy.  As the Applicant alleges that a misrepresentation (which he relied on to his detriment) had occurred, he bears the onus of proving what specifically occurred at the time of the alleged misrepresentation. It is insufficient to merely offer vague and general information on the matter.  The Applicant has held his policy for many years and he does not deny receiving the PDS and the relevant renewal notices. These documents clearly state that he was not covered for flood damage. Case No: 245016 Determination Page 6 of 11  The poli cy’s definition of “flood” does not appear unusual. The definition is not uncommon or significantly dissimilar to how other insurers have ordinarily defined the term.  To the extent the “flood” definition was purportedly “broad” (which the Panel does not accept), the Service has previously determined that: - An insurer does not breach section 35 of the Act just because it may have adopted a broad definition of “flood”. - An insurer is entitled to specify what it wants (or does not want) to cover and in doing so, is entitled to say that certain terms used in its policy have specific meanings. - Section 35 of the Act regulates an insurer’s obligation to inform policyholders of its policy terms, not how it decides to define terms used in its policy. - Unless the specifi c meaning assigned to the term “flood” was inherently ambiguous in itself (which the Panel does not accept), the FSP would have fulfilled its section 35 obligation if it had informed the Applicant of the term and how it had defined it.  The Panel has determined on several occasions that Determination 41709 should be confined to the facts that were unique to that dispute. Having considered the material, the Panel finds the factual circumstances of this dispute materially different to that considered in Determination 41709. That Determination does not assist the Applicant’s cause.  Whilst the Panel appreciates the concern raised (in Determination 40607) with respect to the FSP’s flood exclusion, it is of the view that such a concern could be more fairly addressed in the manner expressed in Determination 257702, which is as follows: “24. … Although the Panel acknowledges the concern raised in that Determination (with respect to a lack of distinction between concurrent and consecutive causes of a loss in the relevant exclusion), it is of the view that any perceived lack of clarity could be more fairly addressed by simply reading down the relevant exclusion so as to be consistent with the prevailing law. That is to say, to be consistent with the Wayne Tank principle. 25. The law, as it currently stands, does not require the FSP to advise the Applicants specifically of the impact of the Wayne Tank principle ( see Hams v CGU Insurance Limited [2002] NSWSC 273 ) or other relevant case law. In the Panel ’s opinion, the FSP’s attempt to inform policyholders of the impact of Wayne Tank (when it had no obligation to do so) should be commended and encouraged, rather than deterred and penalised.” 29. An FSP would generally satisfy its obligation (to clearly inform of any derogation from standard cover) by the provision of a PDS and relevant policy documentation. Case No: 245016 Determination Page 7 of 11 30. In this respect, the Panel has reviewed the FSP’s PDS and policy documentation and is satisfied that:  They were clearly indexed; and  The flood exclusion was not only clearly defined within the policy, but also referenced in the renewal notices. 31. In the circumstances the Panel accepts the FSP has met its obligation to clearly inform the Applicant of the flood exclusion. Proximate cause of damage 32. Turning to the cause of damage to his property, the Applicant essentially says that water from heavy rains on 10 and 11 January 2011 had been flowing through his property and underneath his home on both days, causing damage to a number of items that were stored or positioned there. These events occurred before his home was inundated by waters that can be regarded as flood water. 33. The FSP declined liability on the basis the damage was caused by flood (as defined in its policy). In doing so, it has relied on its loss adjuster’s report, the ICA report and the site specific hydrology report dated 11 July 2011. 34. However, the loss adjuster’s report only provides general information as to what may have ultimately occurred at the Applicant’s home. It offered no specific or reliable information as to timing or cause of the initial inundation of the home. 35. There is also nothing in the material to suggest that the loss adjuster was appropriately qualified to offer opinions on matters concerning hydrology. In saying this, the Panel is mindful of the comments made by the Commissioner in the Commission of Inquiry into the Queensland floods; that loss adjusters are rarely qualified to offer advice on matters concerning hydrology. 36. To the extent the loss adjuster’s report may assist, th e report purports to suggest that the upper level of the Applicant’s home was ultimately inundated to a height of 1 metre. Having said that, the report does not explain how it came to that conclusion. 37. The conclusions of the ICA report (referred to by the FSP) were also general in nature. It offers no specific information that assist in determining the timing and cause of the initial inundation of the Applicant’s home. To the extent the report may be of assistance, it suggests:  The Applicant’s area (ie. Good na) was likely to have been experiencing heavy rains on 10 and 11 January 2011.  The Applicant’s home was likely to have been ultimately inundated by waters that could appropriately be regarded as flood water. Case No: 245016 Determination Page 8 of 11 38. Having regard to the other available material as well as information in the public domain and the Panel Chair Ombudsman’s attendance on site , the Panel observes as follows:  There appears to be no specific rainfall data for the Applicant’s area (ie. for Goodna).  Bureau of Meteorology (BOM) records of rainfall activity at the Opossum Alert (3.8km from Goodna) shows that the area received: - 50.0mm of rain in the 24 hours to 9.00am on 10 January 2011. - 20.0mm of rain in the 24 hours to 9.00am on 11 January 2011. - 34.0mm of rain in the 24 hours to 9.00am on 12 January 2011.  BOM records of rainfall activity at the Carole Park Alert (6.1km from Goodna) shows that the area received: - 74.0mm of rain in the 24 hours to 9.00am on 10 January 2011. - 28.0mm of rain in the 24 hours to 9.00am on 11 January 2011. - 41.0mm of rain in the 24 hours to 9.00am on 12 January 2011.  BOM records of rainfall activity at the Bellbird Park Alert (6.8km from Goodna) shows that the area received: - 63.0mm of rain in the 24 hours to 9.00am on 10 January 2011. - 26.0mm of rain in the 24 hours to 9.00am on 11 January 2011. - 47.0mm of rain in the 24 hours to 9.00am on 12 January 2011.  Woogaroo Street is situated in front of the Applicant’s home . A railway line runs parallel with Woogaroo Street and both structures are on higher ground than the Applican t’s home .  The Applicant’s property slopes downwards from the front to its rear.  The main residence consists of two levels. The upper level is the actual living area while the lower level is used as a storage facility and also includes the laundry.  The Applicant had a number of contents stored in the lower level underneath the home and in two sheds located at the rear of the property. There is a garden shed, storing garden items to the side of the property and a larger shed for storage at the rear of the property.  There is a small creek that runs behind the Applicant’s home. This is the stormwater channel referred to by the Applicant in his evidence. Site Specific Hydrology Report dated 11 July, 2011 39. RA from hydrology company W attended at the site on 27 June 2011. RA detailed the Applicant’s version of events as:  The subject property was inundated above floor level sometime after 3.30pm on Tuesday 11 January 2011. At 3.30pm on Tuesday, water had inundated the rear yard and shed at the property. Case No: 245016 Determination Page 9 of 11  The high set timber house with a floor approximately 1m below the level of W street was inundated to a maximum depth of about 0.8m.  RA provides extensive details of the Applicant’s eye -witness account of water in the local area. 40. The report further details recorded rainfalls from the Wacol alert, located 3km north-east of the property and the Opossum alert located 4.3km (sic) south of the subject property. 41. RA describes the recorded rainfalls intensity as not being particularly severe for short durations and that peak stormwater runoff would have occurred 10- 30 minutes after the peak rainfall and that very little rainfall was recorded at the Wacol alert and the Opossum alert after 1600 hours on Tuesday, 11 January 2011. 42. RA then makes further commentary in respect to the location of the property including the height, the rainfall in the local area and concluded that the rainfall in the local catchment would not have resulted in inundation above the floor level of the house at the subject property. 43. RA concluded that the initial inundation above the floor level of the house at the subject property was caused by flood water from the Brisbane River backing up along the unnamed waterway that runs through the adjacent property to the north. 44. RA further concluded that initial inundation of the rear of the property and the garage may have resulted from rising water levels in the unnamed tributary following sustained rainfall in the local catchment. However, in RA’s view this did not contribute to inundation of the house above floor level. 45. The Panel notes that nowhere in this report does the hydrologist address the Applicant’s allegations in respect to stormwater runoff through the property. 46. In this regard the Panel notes the submissions from the Applicant’s representatives to the effect that there was a significant rain event in and around W Street Goodna which had an observed stormwater and rainwater runoff effect on the surrounding area which caused damage to the property. 47. When onsite, the Applicant described to the Panel Chair Ombudsman “a humungous amount of water flowing down from the front”. The Applicant detailed this water flow as occurring during 10 and 11 January 2011 and well prior to his departure from the home at about 3.20pm on 11January 2011. 48. On the basis of the material presented including the ICA report and the site specific hydrology report, the Panel accepts that ultimately the inundation at the Applicant’s property was as a result of water flows from the Brisbane River backing up the various creeks and tributaries in the area and this is properly categorised as flood within the terms of the policy. 49. The Panel is also satisfied that any inundation above the floor level of the home was as a result of the flood event described above. Case No: 245016 Determination Page 10 of 11 50. Having said that, while the Panel accepts that the ultimate inundation was as a result of flood, the Panel notes that the FSP has not addressed the submissions and evidence of the Applicant that initially the property was impacted by stormwater runoff. 51. There is nothing in the material that persuasively rebuts the Applicant’s direct evidence that he had personally observed water flowing through the lower sections of his property on 10 and 11 January 2011. 52. Considering these matters on the balance of probabilities, whilst the Panel accepts tha t the Applicant’s home was, at some stage, ultimately inundated by waters that could appropriately be regarded as flood for the purposes of the policy, the Panel also accepts that the lower sections of the Applicant’s home was likely to have been experiencing rainwater runoff on 10 and 11 January 2011, which includes the storage and laundry areas in the lower part of the house, the garden shed and the larger shed at the rear of the house. 53. In this respect, the available evidence suggests:  The Applicant’s are a was likely to have experienced heavy rains on 10 and 11 January 2011. - There is no persuasive rebuttal of the Applicant’s evidence on this issue. - BOM records of rainfall activity in nearby areas suggest there were heavy rains on these days. - The findings of the ICA report were consistent with a suggestion that there was likely to have been heavy rains on these days.  The topography surrounding the Applicant’s property is consistent with a suggestion that his property was at risk of runoff flow from the front of the property. 54. In the circumstances the Panel is satisfied that the Applicant would be entitled to indemnity in respect of the initial inundation from stormwater runoff. In assessing the level of initial inundation the Panel determines that a level of 150mm through the storage and laundry areas of the lower part of the house, as well as through the garden shed and the larger shed at the rear of the house would be fair and reasonable in the circumstances. 55. The parties are enjoined to work together to determine the extent of loss covered by the terms of this Determination. Determination 56. For these reasons, the Panel determines that the FSP is required to indemnify the Applicant for the loss/damage caused by rainwater running through his home on 10 and 11 January 2011 in accordance with paragraph 54 of the Determination above. Case No: 245016 Determination Page 11 of 11 57. In the event the FSP elects to settle any portion of the claim in cash, it is required to pay interest on such amount at the statutory rate from 15 March 2011, the date it first declined the claim, until the claim is settled.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.