Home / Financial Firm (Unknown - Insurer) / Determination 244668

Determination 244668

Withdrawal of accepted claim for collapsed boundary wall; section 46 ICA

FirmFinancial Firm (Unknown - Insurer)
Decided2011-11-15
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$5,335
Non-financial loss—
Amount claimed$25,000
SourceAFCA PDF

Summary

The FSP accepted a boundary wall collapse claim and a repair contract was signed, then declined the claim and withdrew a $5,335 offer. AFCA ordered indemnity of $5,335 for the wind-caused collapse only, excluding wider damage from gradual deterioration.

Wind was a proximate cause of the partial collapse within the storm cover, while the wider damage from gradual deterioration, earth movement and tree roots fell within the policy exclusions.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 244668 Determination Page 1 of 9 Case number: 244668 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim – Section 46 Insurance Contracts Act 1984 25 October 2011 Background 1. The Applicant held an Accidental Damage Home Insurance policy (the policy) with the Financial Services Provider (FSP). 2. A claim was lodged under the policy for damage to the external brick wall of the property arising from strong winds on 5 September 2010. 3. The FSP initially accepted the claim and authorised its preferred builder to undertake repairs to the damaged portion of the external brick wall (the wall). However, on further investigation and evidence submitted by its consultants the FSP reversed its decision to accept the claim and informed the Applicant that the claim was not one for acceptance. 4. The Applicant remains dissatisfied with the FSP‟s decision to decline the claim and is seeking indemnity in the estimated cost of repairs of between $20,000- $25,000. Summary of Applicant’s Position 5. The wall at the insured property partially collapsed due to strong winds on 5 September 2010. The wall had remained in place for over 35 years. 6. The Applicant lodged a claim under his policy with the FSP, which appointed an assessor to visit the property and carry out an assessment of the loss. 7. The FSP contacted the Applicant on two occasions to inform him that the claim had been accepted. A contract was received from the FSP‟s appointed builder which included the demolition of the remaining wall and rebuild o f the entire boundary wall. 8. The contract was signed and returned to the FSP with a cheque for the excess ($100) as a deposit, which the Applicant maintains was subsequently cashed. 9. The FSP subsequently appointed other consultants and on receiving additional reports in respect to the loss, the FSP moved away from its original decision to Determination Case No: 244668 Determination Page 2 of 9 accept the claim and informed the Applicant the claim would not be one for acceptance. 10. The Applicant contested the decision to decline the claim and raised the matter of a contract being entered into with the FSP‟s preferred builder and for which a deposit had also been paid. 11. The FSP on considering the App licant‟s complaint offered to cash settle the Applicant‟s claim in an amount equal to the original figure allocated by the FSP for the cost of repairs. At the time of informing the Applicant of this decision the FSP did not disclose the quantum of this amount it had originally allocated to the cost of repairs. 12. The Applicant received an offer from the FSP in the amount of $5,335. The Applicant is not prepared to accept this in settlement of his claim. Two independent quotes obtained by the Applicant to repair the damaged wall fall in the vicinity of $25,000. Demolition costs alone are estimated to be approximately $5,000. 13. The Applicant maintains that:  The wall was in place many years before the Applicant purchased the property 33 years prior to the loss.  The garden bed did have a second skin between it and the wall, as has been acknowledged in the consultants‟ reports .  The “imposed load of vegetation” noted in the report had been removed many years ago.  The boundary wall was not pushed over by defective design, it was demolished by strong winds on the date of loss, a day on which extremely strong winds were recorded. 14. T he Applicant remains dissatisfied with the FSP‟s attitude and management of the claim. Summary of FSP’s Position 15. The Applicant lodged a claim under the policy for the partial collapse of an external wall due to a windstorm. 16. The FSP instructed its preferr ed builder “J” to attend the insured property and submit a report on the damage and a quote for repairs. J formed the opinion that the loss was consistent with the Applicant‟s description and submitted a quote for repair in the amount of $5,335. 17. The Applicant was contacted and informed that the claim had been accepted. A contract in respect to the scope of repairs was provided to and signed by the Applicant, subject to the Applicant‟s contribution (excess) which he paid in the form of a cheque. Case No: 244668 Determination Page 3 of 9 18. On returning to the property to undertake the repairs, J discovered „structural‟ issues to a hidden retaining wall and requested the appointment of an engineer. 19. The FSP notes the scope of works contract signed by the Applicant and provided by J was subject to the disc laimer “ No allowances for any unseen works or works not mentioned in the above scope ”. 20. The FSP‟s appointed engineer and building consultants , “C” and “Z”, to the claim and they attended the insured property on 19 October 2010.The consultants undertook their assessment of the wall along the south side of the property and the previously concealed brick retaining wall in the back garden. The consultants formed the view that the damage was not the result of a single storm/wind event. Rather it was due to progressive degradation over the years because it was under designed and poorly constructed. 21. The Applicant contacted the FSP on 23 December 2010 and advised that he had obtained two independent quotes to undertake the repairs and both quotes were in the vicinity of $25,000. 22. The Applicant wrote to the FSP on 3 February 2011 and in making reference to Section 46 of the Insurance Contracts Act (1984), maintained that the FSP was prevented from declining the claim. 23. The FSP has considered whether the Applicant is afforded any protection under Section 46 of the Act. However, the FSP refers to Nelson v Hollard Insurance Co P/L [2010] NSWSC 199 and maintains this section does not assist the Applicant. 24. The FSP reviewed the claim but maintained the decision to decline the claim. However, in good faith the FSP offered to pay the Applicant $5,335 in line with the original quote of repairs submitted by J and the contract signed between the parties. 25. The quotes obtained by the Applicant include more than the part of the wall that actually collapsed. Neither builder has provided any alternative view to those of C and Z. The Applicant has failed to make available a written qualified opinion in support of his position. 26. In the event a claim is accepted the decision to repair, rebuild or pay an insured for that part of the building that actually sustained damage lies with the FSP. The FSP does not agree to repair the damage. 27. The FSP considers on the balance of probabilities, the two proximate causes for the loss are „gradual deterioration‟ and „faulty design‟. 28. The collapse due to wind of the wall which stood for 33 years would not have occurred unless there were pre-existing structural issues. 29. For a claim to be accepted it must be demonstrated that the cause of the loss is not excluded under the terms of the policy. Based on the consultants‟ reports the causes of the loss are excluded under the policy. Case No: 244668 Determination Page 4 of 9 30. The FSP has formally withdrawn its offer made in good faith to the Applicant to pay him $5,335 regardless of the fact the claim was not one for acceptance. 31. The policy does not cover the „gradual deterioration‟ of a „faulty design‟ or the actions of „tree roots‟ and „movement of earth‟. The FSP cons iders on the balance of probabilities, these are the proximate cause of the loss and that if the wall did not have these pre-existing issues it would not have collapsed. 32. The FSP relies on the following policy provisions: “Page 13 Storm, rainwater or wind We will cover your buildings or contents for loss or damage as a result of storm, rainwater or wind. … Page 32 Exclusions to your cover Any cover we provide is subject to the following exclusions. Accidental Damage cover, Additional cover and Strata Title Mortgagee Protection exclusions We will NOT cover any loss or damage as a result of, or caused by  Settling, shrinkage or any movement of earth  Erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear  …  Roots from trees, plants, shrubs or grass  …  A defect in an item, structural defects, or faulty workmanship or design … Page 51 How we settle a buildings claim 1 We will decide how we will settle your claim If your buildings suffer loss or damage, we will decide whether to  repair  rebuild, or  pay you the cost to repair or rebuild that part of your buildings that suffered loss or damage. If we do, we will  …  Only repair, rebuild or pay you for the part of parts of the building that actually sustained loss or damage, including damaged portions of fixed coverings to walls floors and ceilings only in the room, hall or passage where the damage occurred. ” Case No: 244668 Determination Page 5 of 9 Issues 33. Whether the FSP is entitled to decline indemnity to the Applicant for his loss under the policy. 34. Whether the FSP is entitled to withdraw its offer to cash settle the Applicant in line with the original scope of works approved and subject to a signed contract between the parties. Reasons for Decision 35. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. I have reviewed the submissions of the parties in relation to the terms and conditions of the policy and will only refer to the relevant submissions and materials raised. 36. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because due to the circumstances of the dispute, this dispute has not been the subject of a FOS Recomme ndation and has proceeded directly to Determination. I have reviewed the available evidence and am satisfied that it is not in dispute that:  The Applicant suffered a loss as a result of the partial collapse of the insured property‟s external brick boundary wall.  On the date of loss the insured property was exposed to strong winds. The FSP after undertaking the original assessment of the loss was satisfied that the damage claimed was due to the strong wind on the date of loss.  The insured property is covered for loss or damage arising from Storm, rainwater or wind. Wind was a contributing factor in the resultant partial collapse of the external boundary wall.  The Applicant‟s claim was originally accepted and a contract for repairs was signed between the parties.  The damaged wall was constructed and remained undamaged for approximately 35 years.  The external skin of the wall appeared to be in an overall good condition.  The Applicant would not reasonably have been aware of the issues identified and raised by the consultants with the construction of the wall.  The FSP although subsequently took the position that the claim was not one for acceptance, in good faith offered to pay the Applicant $5,335 in line with the original scope of works it had initially approved . Case No: 244668 Determination Page 6 of 9 The available evidence establishes that the partial collapse of the external boundary wall arose from or at the very least can be partially attributed to prevailing strong winds on the date of loss. I am satisfied the Applicant has established a prima facie claim in respect to the partial collapse of the wall. Therefore, the onus shifts to the FSP to establish it is not liable to provide indemnity to the Applicant under the policy. Cause of damage The FSP having originally accepted the claim proceeded to move away from this position and declined the claim on the basis of reports obtained from consultants C and Z. A number of concerns have been raised by the parties in the management of the claim, these have been discussed below. The FSP in maintaining its position that the claim was not one for acceptance has obtained and relies upon the reports submitted by consultants C and Z. I have reviewed both reports and note Z has relied upon C‟s report as he maintains that: “It would be pointless to reiterate the full extent of the joint inspection and wall assessment as they are accurately detailed in the attached [C‟s name] report dated 20 October 2010. The [C‟s name] report is clear and precise and reflects a comprehensive site analysis, technical content and an ethical determination. I concur fully with the [C‟s name] report and as such, preparation and presentation of an equally extensive report on my part would be superfluous.” I have considered the report submitted by C in its entirety and note that the report concludes that: “ Determination 1. We understand that the „brief‟ for our on -site inspection was to report the condition of the retaining wall behind the collapsed brick boundary fence. This inner skin of brickwork is not a retaining wall but seemingly a 110mm. thick brickwork installation and, as such, was not capable of retaining ground up to a height of 900mm. plus a garden bed on top. 2. The outer skin of brick boundary fence, 2.4 metres tall and unsecured, had no ability other than its own dead weight to resist forces applied by lateral wind. Rotational movement away from the vertical would rapidly increase the chances of the single skin wall becoming unstable and increasingly vulnerable to lateral wind forces and to gravity. 3. The construction of the south boundary brick fence was structurally defective, and the twin wall combination structurally flawed from conception. With the possible exception of the footings, no part of the present wall design can be re- used in any repair proposal.” The consultants have alleged that both the internal and external skins of the wall were defective and the twin wall combination is structurally flawed since original construction. The consultants in addition to indicating that there are present structural defects have also referred to other factors contributing to the loss, which are: Case No: 244668 Determination Page 7 of 9  Tree roots growing in between the skins of brickwork, separating the two abutting skins of the lower level brick work.  Compromise of stability of the walls over the last 10 years due to the introduction of the garden shelf immediately inside the boundary wall.  The inner skins rotating outwards from the visible settlement of the ground inside the wall between the pool surround and the planter box.  Collapse of the wall would have been possible under self weight alone once the centre of gravity of the wall moved outside the 110mm width of the wall base. The Applicant does not agree with the FSP‟s position that the wall collapsed due to defective construction and points out that it has remained standing for over 33 years. It is the Applicant‟s position that the cause for the collapse was the strong winds on the day. I am satisfied that the consultants appointed by the FSP were qua lified to provide an opinion on the construction of the wall. However, the FSP and its appointed consultants have not reasonably established to my satisfaction that the construction of the boundary wall is defective. In order to do so, it would need to be shown that the measurements and methods used in the construction were not in line with the standards required at the time of construction. The FSP and or the consultants have not made available any evidence to establish what standards were in place at the time of construction and how the actual construction falls short of such standards. Therefore, on the basis of the available evidence, I am not satisfied it has been established that the proximate cause for the partial collapse of the external wall was due to defective construction methods. Notwithstanding, the above comment I do accept that the consultants have identified a number of concerns in respect to the condition, maintenance and construction of the external boundary wall which will require further consideration and rectification by the Applicant outside the scope of the policy. Extent of damage and cover under the policy 37. The policy is an “Accident Damage Home” policy which covers the Applicant‟s property for loss or damage arising from accidental loss or damage, including cover under specific conditions for a range of incidents and additional covers and legal liability. The policy defines accidental damage as: “damage to, loss or destruction of the buildings that make up your home, or your contents and valuable items, when it is caused by an unintentional act, or an unforseen and uncontrollable incident.” 38. The policy defines an “incident” as: “a single occurrence or a series of occurrences, including an accident or series of accidents arising out of one event.” Case No: 244668 Determination Page 8 of 9 39. On the basis of the provisions and definitions within the policy, I am satisfied that the scope of cover provided under the policy is limited to damage, loss or destruction of the insured property arising from a n unforeseen and uncontrollable event. 40. Therefore, in line with the policy, damage arising from an event of strong winds would be a loss covered under the policy. I am satisfied that the following matters need to be considered:  the FSP having assessed the loss was originally satisfied that the strong wind was capable of causing the partial collapse.  the FSP‟s decision that the partial collapse of the wall was due to factors excluded by the policy was made after multiple assessments and appointing suitably qualified consultants.  a contract to repair the damage resulting from the strong wind was entered into and for which the excess payment was accepted by the FSP.  what would be considered fair under all the circumstances. 41. I am satisfied that the FSP is obliged to provide indemnity to the Applicant for the loss arising from the partial collapse of the external boundary wall, in line with the original scope of works agreed upon between the parties. In addition, based on the available evidence I am satisfied that on the balance of probabilities, any further damage and or concerns identified beyond the collapsed portion of the wall are no t the result of the strong wind (the event). The additional damage has occurred over an extended period of time due to gradual deterioration, movement of earth and roots from trees and plants . 42. Therefore, I determine the extent of the FSP‟s obligation to provide indemnity to the Applicant is limited to a payment of $5,335 in line with the original quote obtained to repair the damage arising from the strong wind and covered under the policy. Section 46 Insurance Contracts Act 1984 43. The Applicant has relied on Section 46 of the Act to negate the effect of the policy exclusions. Given that I have determined that the allegations of underlying defect does not apply, I am satisfied that section 46 has no application to this matter. Determination 44. On the basis of the available information I determine that the FSP is obliged to honour its original offer to provide indemnity to the Applicant for the damage arising from the strong winds only. 45. The FSP is not obliged to provide indemnity to the Applicant for any additional damage or costs in relation to the repair or rectification of the remaining portion of the external boundary wall, not damage by the strong wind on the date of loss. Case No: 244668 Determination Page 9 of 9

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.