Home / Financial Firm (Unknown - Insurer) / Determination 242752

Determination 242752

Water inundation claim denied as river flood

FirmFinancial Firm (Unknown - Insurer)
Decided2012-03-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants' home was inundated in January 2011 and the FSP denied the claim as river flood. AFCA determined the FSP must settle 20 percent of the loss from the initial storm or flash flood inundation, with interest, but the claim was otherwise excluded as river flood.

The FSP failed to prove on the balance of probabilities that the initial inundation was caused by river flood rather than an insured storm or flash flood event, so a fair apportionment under the Terms of Reference was applied.

Issues

Subjects and remedies

natural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 242752 Determination Page 1 of 8 Case number: 242752 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim (Flood) 22 February 2012 Background 1. The Applicants hold a home building insurance policy with the Financial Services Provider (FSP). 2. In January 2011, the Applicants‟ property was inundated with water following severe weather events in and around Brisbane. 3. The FSP assessed the claim and refused liability on the basis the loss was caused by river flood, which is an exclusion under the policy. 4. The Applicants disputed the decision on the basis the loss was caused by storm and/or flash flood, which is covered under the policy. Summary of Applicants ’ Position 5. The issues raised by the Applicants‟ legal representative in a letter dated 14 April 2011 to the FSP included:  The Applicants have not been clearly informed that flood was excluded by the policy.  The difficulty placed upon the policyholder in understanding the exact nature of cover is exacerbated by pages 29 and 30 of the Product Disclosure Statement (PDS) that outlines the insurance cover for damage caused by storm, rain or flash flood.  The definitions overlap with themselves and further, the flood definition creates an exclusion so wide as to render the coverage provided by storm, rain and flash flood meaningless.  The FSP did not adequately investigate the claim and is relying on a generic hydrology report. 6. The policy provides cover for storm or a flash flood. The Applicants have provided evidence which, they contend, confirms the damage to the building was the result of either a storm or flash flood as defined by the policy. As both occurrences are covered by the policy, the claim should be paid Determination Case No: 242752 Determination Page 2 of 8 Summary of FSP’s Position 7. The FSP states:  The Applicants‟ home was inundated by overflow from the Brisbane River as a result of the dam release flood wave from the Wivenhoe Dam and heavy rainfall in the preceding days;  Overflow from the Brisbane River comes within the policy definition of “river flood” and there is no cover under the policy in respect of river flood;  The PDS clearly informs the Applicants that flood is excluded from cover and therefore satisfies the statutory obligations under section 35 of the Insurance Contracts Act 1984 (the Act). 8. The FSP relies on the following policy provisions: “What you are not covered for There are certain times when this insurance may not provide cover. Some events we may not cover include:  Damage caused by the seas or river flood (see Section 1.12). … Definitions (The Meaning Of Some Words) … “flash flood” means what occurs when there are heavy, intense bursts of rainfall, usually during thunderstorms where so much water falls in a short time that it cannot get away quickly enough and collects and flows into your home. but does not include when rainwater on the site :  cannot run off into a water catchment system, because it is overflowing in flood; and  mixes with the flood water coming from the water catchment system and _then flows into your home. … “rain” means water that has fallen from the sky on to your building and the site but not water from flash flood . “river flood” means when water that is normally contained in a water catchment syste m increases because of rainfall or snow melt (whether in the immediate region or elsewhere) or is deliberately released by an authority, and the water overflows onto land that is not normally covered by water into your home. For example water may be deliberately released by an authority from a dam or reservoir. … INSURED EVENTS … 1.12 Storm, Rain Or Flash Flood … Case No: 242752 Determination Page 3 of 8 We will not pay for damage caused by:  the seas or tidal wave;  river flood ;  erosion or earth movement .” Issues 9. Whether the FSP was entitled to deny the cl aim on the basis the damage was caused by flood. Reasons for Decision 10. FOS has considered it is appropriate to expedite the dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is because of the issues in dispute and substantive quantum involved. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 11. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. 12. There has been an exchange of material between the parties. It therefore is not intended to recite details of the various reports in this Determination except where considered relevant. 13. The Panel Chair Ombudsman attended on site where he met with the Applicants and representatives of the FSP. 14. The Applicants‟ solicitor, in a letter dated 26 September 2011, made reference to two previous determinations to substantiate their clients‟ argumen t that the FSP failed to “clearly inform” them of the exclusion. One determination (Determination No 40607) discussed a definition which excluded “Flood water combined with run- off and/or rainwater” and was determined in the Applicant‟s favour. 15. However, it was noted by the Panel in Determination 40607 that there was an issue with information provided at the point of sale. Further, the Panel noted in that determination “ The member has not been able to provide any information as to whether or when the Product Disclosure Statement and/or policy were forw arded to the Applicant.” In the circumstances of this dispute, the Applicants have not disputed receiving the policy. 16. Determination 41709 discussed a flood definition that included rainwater mixing with water coming from a watercourse. In the current dispute though, the Panel notes that “rain water mixing with flood water coming from the water catchment system” is referenced as a limitation to the definition of “Flash flood”. Further, the FSP has denied this claim on the basis that river flood was the cause. Case No: 242752 Determination Page 4 of 8 17. In the circumstances of this dispute, it has not been argued by the Applicants‟ solicitor that a copy of the policy or PDS was not provided to the Applicants but rather it is argued:  The policy relied upon contains language that is unclear and ambiguous;  The overall framework of the policy is complex and confusing.  A person of average intelligence would have great difficulty in understanding whether damage caused by wet weather events would be covered by the policy. 18. The Applicants‟ solicitor has indicated this view is supported by the Applicants‟ understanding of cover based on the following commentary: “We found out from our neighbours that the house flooded in 1974, so we rang [FSP] about our cover, however their policy on flood cover was still unclear to me because of the varied definitions of flood. It seemed they didn’t cover all aspects of flood”. 19. As there is no actual signed statement it is unclear whether the phone call occurred prior to the loss. Altho ugh this comment may indicate the Applicants‟ confusion as to the extent of cover if the call occurred prior to the loss, then the Applicants were alerted that the policy did not cover all aspects of flood. If the phone call occurred after the loss there is no suggestion the Applicants were led to believe the policy covered river flood. 20. The Panel has also looked at the PDS. Whilst the wording of the PDS is quite broad, it is apparent from the reading of the documentation that it is indexed, has appropriate reference to the various definitions relied upon with respect to storm, flash flooding and flood and that it clearly identifies that it is not intended to cover river flood. 21. Further, it is the Applicants‟ responsibility to read the policy and relevant material to ensure they obtained the appropriate cover for their needs. There is no indication the Applicants sought clarification from the FSP regarding the aspects they found confusing and/or ambiguous. 22. As it has not been disputed the Applicants were provided with the PDS, the Panel accepts the FSP complied with section 35 the Act and is satisfied the Applicants‟ policy did not cover river flood. Storm Event 23. It is not in dispute that an extreme weather event took place in the region. The Applicants‟ solicitor has argued that the damage to the Applicants‟ property was the result of multiple events as water came out of drains in the street outside the Applicants‟ property and from the park, prior to the river breaking its bank. 24. The Applicants‟ solicitor has a rgued that the FSP has failed to discharge its onus to prove the damage was caused by an excluded event. The solicitor has advised: Case No: 242752 Determination Page 5 of 8  The FSP has a poor understanding of the „dam release flood wave‟ as it failed to consider information regarding the dam operators strategy from W3 to W4 and the subsequent increases from Wivenhoe Dam, at 0800 on 11 January 2011 in response to rainfall at 0400 that morning;  It takes approximately 22 hours for water from Wivenhoe Dam to reach Graceville;  Any „dam wave‟ would have hit Graceville at approximately 0600 on 12 January 2011 and any water at the Applicants‟ property prior to this time could not have been the result of „dam release flood wave‟.  The water inundation at the Applicants‟ property commenced after 1900 on 11 January 2011 as noted by the FSP in its submission. This is almost 12 hours before the „dam wave‟ hit the Applicants‟ property;  The reports relied upon by the FSP have no evidentiary value in establishing the hydrology of the Applicants‟ property;  The FSP has failed to prove on the balance of probabilities the damage was caused by flood as opposed to an included event.  The event as described meets either definition of storm or flash flood. 25. In the alternative, the Applicants‟ solicitor has argued that the poli cy covers damage caused by „water or other liquid‟ , in that the policy covers damage caused by water or other liquid which suddenly escapes from a water pipe or main, road gutter or curbing. 26. The Applicants‟ solicitor has noted that a reasonable person‟s un derstanding of what would constitute a water main or pipe would include a storm water channel. As the damage was caused by water suddenly escaping from a water main or pipe, the claim should be paid. 27. The Applicants‟ solicitor has also argued that should th e Panel accept that inundation of water from the drains and flood are concurrent causes, the Wayne Tank principle does not apply due to the following:  Contra proferentem rule;  The principles that coverage provisions should be construed broadly and exclusions narrowly;  The desirability, at least where the policy is ambiguous, of giving effect of reasonable expectations that the FSP is not permitted to rely upon the exclusion. 28. The Applicants‟ solicitor cited a Canadian legal case in support of its po sition. However, the Panel is mindful that Australian courts have provided rulings on these issues and the law here is well established. In the Panel‟s view established Australian law on these matters takes precedence over a Canadian case. 29. Further, the Panel has given deliberation in past matters where there is disagreement between the parties as to whether storm or flash flood damage Case No: 242752 Determination Page 6 of 8 occurred prior to the arrival of flood waters and whether the Wayne Tank principle applies. 30. The Panel does not have the benefit of a site specific report but consideration has been given to the following „flood information‟ contained in the loss adjuster‟s report:  Habitable floor level was approximately 200mm above surrounding ground level;  The ground level of the house was approximately 3 metres above street level;  Water level in the house peaked at approximately 1,600mm;  The peak level occurred at 4am on 13 January 2011;  Water inundation to the property yard commenced at 11am on 12 January 2011;  Heaviest rainfall stopped on 11 January 2011; 31. However, the Panel Chair Ombudsman noted during the site visit that the rear corner of the ground floor of the house is in fact dug into the ground to a depth of 8 bricks, as evidence by the surrounding retaining wall. Thus, the ground level at the rear of the house is in fact higher than the floor level of the house in that area. The ground at that point also appears to slope upwards away from the house and towards the properties at the rear of the house. 32. The Panel is also aware the subject property is approximately 200 metres from the Brisbane River. 33. The Panel is aware of the Hydrological report obtained by the Insurance Council of Australia (ICA). The report is very extensive as it relates to an extreme weather event which caused flooding to the Brisbane region. In Volume 3 of the report ” – “Flooding in the Brisbane River Catchment” January 2011 the following information is available which needs to be considered:  Wivenhoe Dam release (9.3)  Large releases were made from Wivenhoe Dam over the period from 06:00 hours, possibly as early as 03:00 hours on 11 January 2011, until around 03:00 hours on 12 January 2011.  Releases from Wivenhoe Dam caused a flood wave in the Brisbane River. Water levels in the lower reaches of the Bremer River and its tributaries draining Ipswich City LGA were affected by backwater flooding and backwater effects from the Brisbane River.  It was concluded that the dam release flood from Wivenhoe Dam was the immediate cause of flooding along the reach of the Brisbane River downstream of the dam and along tributaries through the Ipswich City LGA. 34. According to the Applicants they evacuated the property at around 7pm on 11 January 2011. There is no indication water was in the house or yard at that Case No: 242752 Determination Page 7 of 8 time. The male Applicant returned the next day at approximately 10am and water was in the house and still rising. 35. This evidence from the male Applicant challenges the FSP‟s loss adjuster‟s statement that water inundation to the property yard commenced at 11.00am on 12 January 2011. 36. Given the male Applicant‟s statement, the Panel accepts that the inundation commenced after 7pm or 8pm on 11 January 2011 and before 10am on 12 January 2011. 37. The Panel also notes the Applicants‟ statement at the site inspection that it was “perhaps still drizzling as they left on Tuesday night”. 38. Had flash flood been the single factor, the Panel would have expected the inundation to have occurred in the immediate hours after the most significant period of rain. The BOM records little rain after 6.00pm on 11 January 2011, with the heaviest rain on 11 January 2011 falling in the morning. 39. However, the Panel notes that the FSP has not provided a site specific hydrology report to clarify this issue and the FSP‟s basis for its denial, the loss adjuster‟s rep ort, omits the critical observation that the floor level at the rear of the house is some 8 bricks below the land level. Further, that the land at the rear of the house appears to slope upwards, away from the house. 40. In this case, the loss adjuster did not believe the policy provided liability as he postulated the damage arose as a result of inundation of water from the Brisbane River. 41. However, the loss adjuster, by failing to note the actual levels of the home, in respect to the land, has not addressed the possibility that the home was first inundated by run-off. In addition, there is no site specific hydrology report that addresses this issue. 42. The Panel has reviewed flood mapping and it is clear that the Graceville area was inundated by floodwater. The Pane l has also viewed aerial photographs of the area and notes that the location of the property was within the area of inundation from the Brisbane River. 43. The Panel notes the evidence that the home was inundated to a level of approximately 1.6 metres. The Panel accepts that river flood was responsible for this ultimate level of inundation. 44. However, the FSP has not denied that an insured event occurred but rather has denied the Applicants‟ claim on the basis that the loss was caused by river flood, which is specifically excluded under the policy. 45. In light of the above, particularly with reference to the omissions in the loss adjuster‟s report, the Panel determines the FSP has failed, on the balance of probabilities, to demonstrate the absence of an initial inundation courtesy the defined event of „storm, rain or flash - flood‟ in contradistinction to its hypothesis, that the entire inundation emanated from the excluded event of river flood. Case No: 242752 Determination Page 8 of 8 46. As such, the Panel is satisfied that the FSP should settle the Applican ts‟ claim insofar as the initial inundation is concerned. 47. The Panel accepts that it is an almost impossible task to determine what portion of the loss arose from this initial inundation; in such circumstances reliance must be placed upon clause 8.2 of the Terms of Reference to the Service namely, „to do what is fair in all the circumstances‟. Considering all matters, the Panel has determined that the FSP settle the Applicants‟ claim for 20% of the loss arising from water inundation. 48. For the sake of completeness the Panel notes it has also considered the Applicants‟ argument that as the water which inundated the property was discharged from a drain, this would give rise to a claim under „water or other liquid‟. 49. The FSP rejects this on the basis that the eve nt does not meet the definition of water which has „suddenly escaped‟. It also argues that the water was not drain water but was river water which had overflowed from the Brisbane River and therefore the proximate cause was floodwater, which is excluded from cover. 50. The Panel is inclined to the view that even though the water may have backflowed through the drains, the water was nevertheless floodwater from the Brisbane River. Under this scenario, it is well established Australian case law for the resultant waters to all be characterised as river flood, which attracts the policy exclusion. Determination 51. The Panel determines that the FSP is to settle the Applicants‟ claim for an amount equal to 2 0% of the Applicants‟ loss from water inundation. 52. The Panel further determines that the FSP is to pay interest on the settlement amount from the date of denial to the date of settlement at the rate specified by the Insurance Contracts Act.