Home / Financial Firm (Unknown - Insurer) / Determination 242623

Determination 242623

Extent of hail damage to roofs and cash settlement of $8,508.50

FirmFinancial Firm (Unknown - Insurer)
Decided2013-06-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$22,850
SourceAFCA PDF

Summary

The applicant claimed $22,850 to replace hail-damaged roofs, while the FSP offered $8,508.50 after excluding maintenance and workmanship damage. AFCA found the $8,508.50 cash settlement appropriate and rejected the delay compensation claim.

Without contrary expert evidence, the building consultant report showing non-storm causes for much of the roof damage was preferred, so the policy exclusions applied.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 242623 Determination Page 1 of 8 Case number: 242623 General Insurance - Domestic Insurance - Home Building - Service - Dispute Over Extent of Storm Damage 28 June 2013 Background 1. The Applicant held a home and contents insurance policy with the Financial Services Provider (FSP) which was current at the time of the loss. 2. On 6 March 2010, the Applicant’s home was damaged as a result of a severe hail storm. The Applicant lodged a claim with the FSP for damage to his home (including the roofs of his house, pergola and garage) and various contents items. 3. The FSP accepted the Applicant’s claim and assessed the damage to his home and contents. After completing its investigations, the FSP cash settled the Applicant’s contents claim . However, the FSP denied certain parts of the Applicant’s claim for damage to the roofs of his house, pergola and garage based on reports from its consultants which found that some of the damage was not caused by the storm. 4. The FSP initially offered the Applicant a settlement of $3,263.04 for the roof damage. The FSP later determined that this was the incorrect amount and made a replacement offer of $8,508.50, reflecting a quote from the FSP’s builder for the cost of repairing the storm-related damage to the roofs. 5. The Applicant disputes the FSP’s denial of parts of his claim. The Applicant considers that the settlement offered by the FSP is insufficient to repair the storm-related damage to the roofs, based on quotes he has obtained from his own contractors. Summary of Applicant’s position 6. The Applicant says that the roofs of the home, pergola and garage were severely affected by the storm and require replacement. He considers that only a very limited portion of the damage to the roofs was caused by maintenance-related issues. Determination Case No: 242623 Determination Page 2 of 8 7. The Applicant says that he had been up on the roofs prior to the hail storm and observed that they were in an acceptable condition. He says that the roofs only began leaking following the storm and therefore it is reasonable to conclude that most of the damage was caused by the storm. 8. The Applicant seeks indemnity under the policy for $22,850, being the cost of replacing the roofs as quoted by his contractors, less $1,000 for the repair of damage which he accepts is maintenance-related and therefore excluded under the policy. 9. The Applicant considers that the FSP has unreasonably delayed the progress of his claim. Summary of FSP’s position 10. The FSP relies upon the expert opinions of its loss adjuster ( “ CL ” ), builder ( “ JL ”) and building consultant (“SE”) as the basis for its view as to what portion of the damage to the Applicant’s roofs was caused by the storm. 11. Based on its experts’ reports, t he FSP considers that a significant portion of the damage to the roofs was not caused by the storm but by factors such as wear and tear and faulty workmanship, and therefore falls within specific exclusions under the policy. The FSP considers that the amount of $8,508.50 offered to cash settle the repair costs represents an appropriate settlement in accordance with the terms of the policy. 12. In relation to the handling of the claim, the FSP notes that the assessment process was delayed due to factors including the Applicant being overseas and that he has on several occasions failed to contact the FSP to progress settlement of his claim. 13. The FSP relies on the following policy provisions: Pages 12-13 of the Product Disclosure Statement (PDS) “ Accidental Damage cover We will cover your buildings or contents for any accidental loss or damage. There are also a number of incidents we will cover under specific conditions – these are listed on the following pages. If you make a claim, you will need to pay any excesses that apply – you will only need to pay this amount once. Any cover we provide is subject to exclusions. ... Storm, rainwater or wind ... We will cover your buildings or contents for loss or damage as a result of storm, rainwater or wind. Case No: 242623 Determination Page 3 of 8 ... We will NOT cover water entering your buildings - ... - because of a structural defect, faulty design or faulty workmanship when your buildings were constructed... ” Page 32 of the PDS “ Exclusions to your cover Any cover we provide is subject to the following exclusions. ... We will NOT cover any loss or damage as a result of, or caused by ... erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear ... a defect in an item, structural defects, or faulty workmanship or design ... water entering your buildings - through an opening made for any building, renovation or repair work - because of a structural defect, faulty design or faulty workmanship when your buildings were constructed.” Issues 14. Whether the FSP’s cash settlement offer for the roof repairs rep resents an appropriate settlement of that part of the Applicant’s claim. 15. Whether the FSP has unreasonably delayed the Applicant’s claim. Reasons for decision 16. I am satisfied that a full exchange of relevant information has taken place between the respective parties and that each party has had the opportunity to address any issues raised therein. 17. As advised to the parties, the Service has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the Service’s Terms of Reference, due to the nature of the issues to be considered. This dispute has not been the subject of a Recommendation and has proceeded directly to Determination. Case No: 242623 Determination Page 4 of 8 18. There is an onus on an insured to establish on the balance of probabilities that a claim fits the definition of an insured event. This is known as a prima facie claim. Should this onus be discharged, it is then the responsibility of the insurer to establish, on the balance of probabilities, that an exclusion applies. Application of policy 19. The po licy provides cover for “any accidental damage”, with specific incident related cover for certain events, including “Storm, rainwater or wind”, subject to certain exclusions. 20. It is not in dispute that the Applicant’s property was damaged as a result of a h ail storm. To the extent that the Applicant’s property was damaged by this storm (or any other accidental event), I accept that the policy will respond, subject to any applicable exclusions. 21. However, the parties disagree as to what part of the damage to the roofs of the home, pergola and garage was caused by the storm. Cause of roof damage 22. The FSP has obtained several reports regarding the cause of damage to the roofs of the house, pergola and garage. Inspections by CL and JL 23. The FSP originally had the roofs inspected by its loss adjuster (CL). In his report dated 15 February 2011, CL noted: “The [Applicant] has had a roofer attend to provide a quotation for the resultant damage to their roof as a result of the hail storm and although the roof is water t ight the hail has caused extensive damage to the roofing tiles.” 24. On behalf of the FSP, CL subsequently engaged a builder (JL), to inspect the roofs and report on the cause of the damage. 25. In relation to the tiled roof of the main house, JL’s report dated 1 2 April 2011 stated that: there was one broken tile on the roof which was consistent with storm damage, and could be repaired for approximately $330; the cement work (bedding and pointing) on the roof required redoing, which was a maintenance issue and not consistent with storm damage; there were approximately 30 tiles which had chipped courses “which are of some age”, but would not allow water ingress and could be replaced as part of the rebedding and pointing; and the cost of rebedding and pointing the roof (including replacing the chipped tiles) would be approximately $3,355. Case No: 242623 Determination Page 5 of 8 26. In relation to the pergola roof (made of opaque laserlite), JL’s report stated that: the roof sheets were undamaged by the hail storm; and the roof screws had not been screwed down enough and the rubber washers were loose on the roof sheets – as the roof sheets were flat at the screw holes, this allowed water to run under the screws. 27. Based on the documents provided to the Service, it appears that JL did not report on the damage to the garage roof. SE inspection 28. After the Applicant disputed JL’s findings, the FSP arranged for a building consultant (SE) to inspect the roof damage and provide a further report. SE provided a report dated 24 October 2011, together with a scope of works for the repairs. 29. In relation to the roof of the main house, SE’s report stated that: there were approximately 60 damaged tiles, although the damage was generally not such as would lead to water ingress; the presence of dirt and debris on the majority of the damaged tiles indicated that much of the damage pre-dated the storm event. However, approximately 25% of the damaged tiles did not have any dirt or debris which indicated that the damage was more recent; approximately 90% of the damage was associated with the bottom right hand corner of the cover flange being cracked, broken or missing. This damage is not consistent with hail damage, which is random and indiscriminate, not localised to one corner of the tiles. Also, hail damage generally results in multiple fractures and breaks, or single large fractures and breaks. SE considered that, in some cases, the damage to the cover flange occurred because the tiler had failed to remove a “concrete dag” from the tiles during the installation pro cess. In other cases, the damage was likely to have been caused by pedestrian traffic; SE considered that the damage to the remaining 10% of the tiles was, on the balance of probabilities, consistent with hail damage. The damage to these tiles consisted of a large crack or partial localised fragmentation of a section of the tile; the bedding and pointing of the ridge capping tiles was in “extremely poor condition”, with various sections having wholly or partially dislodged. There was evidence of previous attempts to repair this area, which had been carried out in a manner not consistent with acceptable industry practice. The damage to the ridge capping tiles was, in SE’s opinion, caused by a failure to bed and point the tiles properly when the roof cover was installed, and was not storm related; and Case No: 242623 Determination Page 6 of 8 the metal roof of the home’s weatherboard extension appeared to have been in good condition prior to the storm but had sustained enough hail damage to warrant complete replacement. 30. In relation to the pergola ro of, SE’s report stated that: the metal ridge capping of the pergola roof had sustained enough hail damage to warrant replacement; and the laserlite roof sheeting did not show any evidence of hail damage but approximately 50% of the weather seals were not properly fastened and therefore did not provide effective weatherproofing. SE considered that either the screws had not been properly fastened when initially installed or they had come loose over time. SE considered that this was a maintenance related issue and had not occurred as a result of the storm. 31. In relation to the garage roof, SE observed that: galvanised flathead nails were affixed to the pan of each concealed fastened galvanised roof sheet and the junction of the supporting beam below. SE considered this to be defective building work which was not in accordance with the manufacturer’s instructions, as ro of sheets of this type are designed to be fastened with proprietary brackets and any penetration of the roof sheet (eg by nails) should be fully sealed and watertight. SE observed that as a result of the use of galvanised nails, moisture appeared to be congregating around the perimeter of the nails and leaking into the garage; water ponding on the south western corner of the roof coincided with a deformed section of the rib of one of the roof sheets and was consistent with damage caused by pedestrian traffic, not hail; and the metal roofing of the shed attached to the garage contained a single dent which was typical of that caused by hail impact. The adjacent polycarbonate sheet was buckled and the single fibreglass roof sheet was also torn in two places. SE considered that on the balance of probabilities the damage to these roof sheets was caused by hail. 32. SE also observed minor maintenance – related damage to the stormwater guttering, fascia and bargeboards. 33. SE provided a scope of works for repairs required to address the storm- related damage and a separate scope of works required to repair the damage resulting from other causes. The FSP obtained quotes from JL based on the two scopes of work. Analysis 34. The Applicant has questioned SE’s findings that part of t he damage to the roofs was not storm-related, on the basis that SE had not examined the roof prior to the storm and that the roof only began to leak following the storm. The Applicant also questioned the FSP’s conduct in initially relying on JL’s Case No: 242623 Determination Page 7 of 8 report, a nd later relying on SE’s report, in circumstances where there was a significant difference between the findings of the two consultants. 35. I accept that it can sometimes be difficult to accurately assess to what extent the observable damage to a roof is attributable to a particular weather event. In the absence of any independent evidence as to the condition of the roof prior to the relevant event, the assessor is necessarily limited to forming a view based on the state of the roof after the event. 36. I agree with the Applicant that there are inconsistencies between the conclusions reached by JL and SE. However, I note that SE was only engaged by the FSP to provide a report when the Applicant disputed JL’s findings. SE undertook an inspection of the roof damage and prepared a detailed report, which was ultimately more favourable to the Applicant than JL’s initial report, as SE identified significantly more storm -related damage. In these circumstances, I consider that the approach adopted by the FSP was appropriate. 37. In his report, SE separately describes each area of damage identified and analyses the likely causes thereof. SE’s report finds that many areas of damage which had not previously been accepted by the FSP were in fact storm-related, which was ultimately accepted by the FSP. Where SE concludes that particular damage was not storm-related, he offers cogent explanations for his conclusions and specifically identifies the factors which he considers caused or contributed to the relevant damage. 38. The Applicant has chosen not to obtain his own expert opinion, due to the expense involved. While this is understandable, in the absence of expert evidence to the contrary, I consider that SE’s report is highly persuasive and the FSP is entitled to rely on SE’s finding s in assessing the cause of the damage to the Applicant’s roofs. 39. The FSP has advised that its most recent offer of $8,508.50 to cash settle the Applicant for the cost of roofing repairs is based on JL’s quote which reflects SE’s scope of works for storm -related damage. On this basis, I consider that the FSP’s offer represents an appropriate settlement of that part of the Applicant’s claim in accordance with the terms of the policy. Delays in claim handling 40. The Applicant expressed dissatisfaction with the delays experienced in the handling of his claim, noting that it was first reported in March 2010 and remains unresolved. 41. I have reviewed the evidence provided by both parties and am of the view that, while the claim process has been ongoing for a significant period of time, the process was not unduly delayed by the FSP. 42. It was reasonable for the FSP to undertake a thorough review and assessment of the Applicant’s claim, particularly in circumstances where the Applicant disputed the findings of the original assessor. However, I accept Case No: 242623 Determination Page 8 of 8 that the Applicant was inconvenienced by the FSP’s decision to conduct multiple inspections, including a reinspection of damaged contents items due to its dissatisfaction with the initial report. 43. Nevertheless, the delay in the claim process is also attributable in part to factors such as the Applicant being overseas during the early part of the claims process, difficulties experienced by the FSP’s agents in contacting the Applicant by phone and the fact that the Applicant has gone for long periods without contacting the FSP to notify it that he was dissatisfied with its proposed resolution of his claim. 44. Without seeking to apportion blame for these delays, I am satisfied that both parties have contributed to the overall delay in r esolving the Applicant’s claim. Accordingly, I do not consider that the Applicant should be entitled to compensation from the FSP for the delays experienced. Determination 45. On the basis of the available information, I determine that: the cash settlement of $8,508.50 offered by the FSP for the roof repairs represents an appropriate settlement of that part of the Applicant’s claim; and the Applicant is not entitled to compensation from the FSP for delays experienced during the claim process.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.